CR El Kitabi
CR El Kitabi
CR El Kitabi
E-LINECR MANUAL
Akcaburgaz Mahallesi,
3114. Sokak, No:10 34522
Esenyurt - Istanbul
Tel: +90 (212) 866 20 00
Fax: +90 (212) 886 24 20
MENTAL MAN
ON
V IR
AG
s
E
ISO
A N D EN
MENT SYSTE
14001
AL
E 344805
M
QU S
www.eaeelectric.com
E-LINECR
INDEX
Introduction 2
Project Design 6
Equipment Used 12
Electrical site-tests 23
Declaration 26
Certificates 27
Product Overview 28
CRMANUAL
Introduction
Dear Customer,
EAE Elektrik A.S. Products are designed to provide the maximum benefit in efficiency and
service. Our products are manufactured in accordance with IEC standards and EAE is
quality assured to ISO 9001 standards in their modern production plants in Istanbul .
The components that you have purchased are manufactured by a completely environment
conscious, that is ISO 14001 certified.
These instructions should be read carefully and acted upon before taking delivery of
equipment on site.
Handling, installation and operation of busbar systems should be carried out only by
skilled, trained and authorized personnel using all associated equipment such as rubber
gloves, helmet, safety glasses or face shields and flash resistant clothing in accordance
with established safety practices.
2
CRMANUAL
Unloading, Handling and Storage of Products
Unloading:
§ Forklift is the most reliable and easiest method for the unloading of the products from the container or
the truck arriving at the worksite.
§ Utmost care is required to be exercised to ensure avoidance of any harm that can be sustained by the
products during the unloading process.
Storage:
§ From the packing list check the number of pallets received, the number, dimensions and the condition
of the busbar lengths. Advise any discrepancies immediately to the local EAE representative.
§ All products should be stored in a dry environment. The casting materials for the joint must be stored
at a temperature between 5 °C and 25 °C and not exposed to direct sunlight
Handling:
§ Do not handle the materials using steel ropes or hooks. As shown in the castresin busbar should be
lifted using lifting straps placed at each end of the busbar length.
§ Short modules may be lifted using a single strap providing that the piece is balanced.
§ A wooden spacer should be used every 1.5m when storing the lengths placed on top of each other.
§ Do not stack more than 5 modules on each other horizontally.
3
CRMANUAL
Handling and Lifting
1500 mm 1500 mm
4
CRMANUAL
Handling and Hanging
Introduction:
This installation manual includes the details of safe and quick handling and installation of cast resin
busbar product. It shall be read carefully before starting the procedures on the product and relevant
steps shall be followed.
Things To Do:
1- Read the info note on the pallet; lift and handle the the product as shown in "Figure 1" taking the pallet
weight into consideration.
2- Product shall be hanged and lifted as shown in "Figure 2" while it is handled. (Figure 2)
3- Resin and hardener shall be stored as shown in Figure 3.
4- Busbar route shall be marked before starting the installation.
5- Installation shall start from a single point (preferably panel) and shall be completed with the last
module.
6- Do not perform casting before performing megger test on the joint and observing infinite resistance
as the result of the test.
7- Do not apply expired joint casting agent.
5
CRMANUAL
Project Design
A A
m n.=25cm
m n.=25cm
m n.
400
m n.
25cm
Rated Current 630 800 1000 1250 1600 2000 2500 2250 2500 - 3000 3200 3600 4000 5000
CRA - Al (A)
Conductor Busbar Code 06 08 10 12 16 20 25 23 27 - 30 33 36 40 50
Rated Current 800 1000 1250 1600 2000 2500 - 3000 3200 3600 4000 - 5000 - 6300
CRC - Cu (A)
Conductor Busbar Code 08 10 12 16 20 25 - 30 32 36 40 - 50 - 63
A (mm) 90 105 130 160 210 250 300 310 340 370 410 430 490 590 730
6
CRMANUAL
Horizontal & Vertical Cast Resin Busbar Applications
500 CEILING
BEAM
100
200
WALL
PE
BUSBAR RUNNING ON FLATWISE L3
L2
PE L3 L2 L1 N APPLICATION L1
N
WALL
500
HOLE
PE L3 L2 L1 N
200 BUSBAR-2 BUSBAR
WALL
200
500
350 (min.)
HOLE
200
BUSBAR
WALL
BUSBAR-1 BUSBAR-2
200 CENTRE LINE
PE PE OF JOINT
L3 L3
L2 L2
L1 L1
N N
7
CRMANUAL
Suspension Components
SUPPORTS
CR-UT HANGER SET FOR EDGEWISE APPLICATION (STANDARD APPLICATION)
Conductor
CRA - Al CRC - Cu Cross
Order
Conductor Conductor L A
Section Code
Rated Busbar Rated Busbar (mm) (mm)
Current Code Current Code
630 06 800 08 6x40 300 90 3025348
800 08 1000 10 6x55 300 105 3025348
1000 10 1250 12 6x80 300 130 3025348
1250 12 1600 16 6x110 350 160 3025348
1600 16 2000 20 6x160 400 210 3025348
2000 20 2500 25 6x200 400 250 3025348
2500 25 - - 6x250 450 300 3025348
A
43 65
4
L
65
4
L
*Flatwise Application is supplied for only on special conditions. Please call us for non-standard dimensions.
8
CRMANUAL
Suspension Components
SUPPORTS
CR HANGER SET WITH BRACKETS FOR CR HANGER SET WITH BRACKETS FOR
EDGEWISE APPLICATION EDGEWISE APPLICATION
(Standard Application) (Non-Standard Application)
5 5
50 50 50 50
L L
UAS-K5 Supports
Description L Order Code
(mm)
L
UAS-K5 Support (1) 200 3005324
L
UAS-K5 Support (2) 250 3005323
50 UAS-K5 Support (3) 300 3005322
5 50 UAS-K5 Support (4) 350 3005321
Threaded Rod UAS-K5 Support (5) 400 3005320
UAS-K5 Support (6) 500 3005319
UAS-K5 Support (7) 600 3005318
UAS-K5 Support (8) 700 3005317
Extension Unit UAS-K5 Support (9) 1100 3005316
Connection Units
Description L Order Code
(mm)
9
CRMANUAL ORDER CODE
LENGTH L (mm)
Suspension Components
SUPPORTS
IDT
IDY
IDT
IDT
10
CRMANUAL ORDER CODE
LENGTH L (mm)
Suspension Components
SUPPORTS
UPY
Steel
Dowel T
L
Threaded
Rod
65
UPY 43
UPY
11
CRMANUAL
Equipment Used
1 2 3 4
Fabric Crane Ropes Torque Wrench Hot Air Blower Spirit Level
5 6 7 8
9 10 11 12
13 14 15 16
12
CRMANUAL
Horizontal Edgewise Mounting Application
1 2
Stretch and head plastic at the tip of the busbar Tip parts exposed on the busbar are required to be
shall be removed. cleaned with a clean and dry piece of cloth. After the
completion of the cleaning process, it is aligned with
It is alinged with the block joint and mounted on the
stationary busbar.Block joint bolt shall be slightly
tightened for not to falling
3 4 mm
250
Second busbar is brought into alignment with the Coupled busbars and block joint shall be put into
block joint. The block joint shall be loosened, and the final form by looking at the alignments there of.
second busbar shall be mounted on the stationary Torqued with the torque wrench by setting to 83 Nm.
busbar. Bolt clearance is removed tightened slightly.
5 6
MW
Megger test shall be conducted among the entire Inner surfaces of molds (surfaces subject to casting
phases. process) shall be cleaned with a clean and dry piece
of cloth.
13
CRMANUAL
Horizontal Edgewise Mounting Application
7 8
mm
70
Block joint moulds shall be brought on the coupled Alloy shall be casted uninterruptedly from the same
busbars and affixed accordingly. Block joint moulds spot.
shall be secured on the trays with bolts with a (Please refer to page 22 for alloy preparation guide.)
distance of 70 mm from the tip of the busbar.
9 10
Vibration is provided by means of plastic hammer. For each juncture, brushing for 2 minutes shall be
performed once in every 10-15 minutes throughout
1 hour.
x
11 12
After the curing of the material (6-12 hours), casting Megger test should not be conducted for a
mold shall be removed, and the sharpness of the minimum of 12 hours after the casting process.
part shall be smoothed accordingly.
(Note: Varies depending on the seasonal conditions
and temperature. Cold weather is disadvantageous.)
14
CRMANUAL
Resin Application on Horizontal Edgewise During Assembly
Horizontal Application
After the entire adjustments are made, megger test and dielectric test shall be
conducted on the busbar system coupled and absence of any stray voltage shall be
ensured accordingly. Material prepared in buckets shall be casted on juncture area.
Material casting shall be ensured not to have any clearance at all. After the
completion of casting process, the material shall be ensured to be placed tightly by
slightly hammering the block joint moulds.
After the block joint mould is filled up to the upper level, the surface is required to
be levelled out with a brush.
For the purpose of expediting the air outlet after the completion of the casting
process, vibration rendering process shall be applied on the mold for 8-10
minutes by a plastic hammer.
Casting surface shall be brushed once in every 10-15 minutes and air bubbles
forming shall be removed and the surface shall be smoothed accordingly.
To remove the block joint mould, it shall be waited for curing process of 6-12
hours and the complete stiffening to be completed.
In case of a requirement of more than 1 dose of application in the application of
the juncture resin, it shall be performed successively without waiting for the
application of the 2nd and the 3rd doses.
Note: Material for each joint shall be prepared separately and this
prepared material shall be poured within 15 minutes.
15
CRMANUAL
Horizontal Mounting Application
1 2
Stretch and head plastic at the tip of the busbar Tip parts exposed on the busbar are required to be
shall be removed. cleaned with a clean and dry piece of cloth. After the
completion of the cleaning process, it is aligned with
the block joint tray and mounted on the stationary
busbar. Block joint bolt shall be slightly tightened for
not to falling.
3 4 mm
250
Second busbar is brought into alignment with the Coupled busbars and block joint shall be put into
block joint. The block joint shall be loosened, and the final form by looking at the alignments thereof.
second busbar shall be mounted on the stationary Torqued with the torque wrench by setting to 83 Nm.
busbar. Bolt clearance is removed tightened slightly.
5 6
MW
Megger test shall be conducted among the entire Inner surfaces of molds (surfaces subject to casting
phases. process) shall be cleaned with a clean and dry piece
of cloth.
16
CRMANUAL
Horizontal Mounting Application
7 8
mm
70
Block joint molds shall be brought on the coupled Alloy shall be casted uninterruptedly from the same
trays and affixed accordingly. Juncture molds shall spot.
be secured on the trays with bolts with a distance of (Please refer to page 22 for alloy preparation guide.)
70 mm from the tip of the busbar.
9 10
Vibration is provided by means of plastic hammer. For each juncture, brushing for 2 minutes shall be
performed once in every 10-15 minutes throughout
1 hour.
x
11 12
After the curing of the material (6-12 hours), casting Megger test should not be conducted for a
mold shall be removed, and the sharpness of the minimum of 12 hours after the casting process.
part shall be smoothed accordingly.
(Note: Varies depending on the seasonal conditions
and temperature. Cold weather is disadvantageous.)
17
CRMANUAL
Resin Application Horizontal During Assembly
Horizontal Application
After the entire adjustments are made, megger test and dielectric test shall be
conducted on the busbar system coupled and absence of any stray voltage shall be
ensured accordingly. Material prepared in buckets shall be casted on juncture area.
Material casting shall be ensured not to have any clearance at all. After the
completion of casting process, the material shall be ensured to be placed tightly by
slightly hammering the block joint moulds.
After the block joint mould is filled up to the upper level, the surface is required to
be levelled out with a brush.
For the purpose of expediting the air outlet after the completion of the casting
process, vibration rendering process shall be applied on the mold for 8-10
minutes by a plastic hammer.
Casting surface shall be brushed once in every 10-15 minutes and air bubbles
forming shall be removed and the surface shall be smoothed accordingly.
To remove the juncture mold, it shall be waited for curing process of 6-12 hours
and the complete stiffening to be completed.
In case of a requirement of more than 1 dose of application in the application of
the juncture resin, it shall be performed successively without waiting for the
application of the 2nd and the 3rd doses.
Note: Material for each joint shall be prepared separately and this
prepared material shall be poured within 15 minutes.
18
CRMANUAL
Vertical Mounting Application
1 2
Stretch and head plastic at the tip of the busbar Tip parts exposed on the busbar are required to be
shall be removed. cleaned with a clean and dry piece of cloth. After the
completion of the cleaning process, it is aligned with
the block joint tray and mounted on the stationary
busbar. Block joint bolt shall be slightly tightened for
not to falling.
3 4
mm
250
Second busbar is brought into alignment with the Coupled busbars and block joint shall be put into
block joint. The block joint shall be loosened, and the final form by looking at the alignments there of.
second busbar shall be mounted on the stationary Torqued with the torque wrench by setting to 83 Nm.
busbar. Bolt clearance is removed tightened slightly.
5 6
MW
Megger test shall be conducted among the entire Inner surfaces of molds (surfaces subject to casting
phases. process) shall be cleaned with a clean and dry piece
of cloth.
19
CRMANUAL
Vertical Mounting Application
7 8
The support sheet delivered to assist that the block The alloy shall be casted uninterruptedly from the
joint mold maintains its position shall be affixed. sheet that are delivered to assist the casting process
Block joint molds shall be brought on the support from the same spot.
sheet and secured by means of bolts in a manner (Please refer to page 22 for alloy preparation guide.)
that the gaskets shall be at the bottom.
9 10
Vibration is provided by means of plastic hammer. For each juncture, brushing for 2 minutes shall be
performed once in every 10-15 minutes throughout
1 hour.
x
11 12
After the curing of the material (6-12 hours), casting Megger test should not be conducted for a
mold shall be removed, and the sharpness of the minimum of 12 hours after the casting process.
part shall be smoothed accordingly.
(Note: Varies depending on the seasonal conditions
and temperature. Cold weather is disadvantageous.)
20
CRMANUAL
Resin Application Vertical During Assembly
Vertical Application
After the entire adjustments are made, megger test and dielectric test shall be
conducted on the busbar system coupled and absence of any stray voltage shall be
ensured accordingly. Material prepared in buckets shall be casted on juncture area.
Material casting shall be ensured not to have any clearance at all. After the
completion of casting process, the material shall be ensured to be placed tightly by
slightly hammering the block joint moulds.
After the block joint mould is filled up to the upper level, the surface is required to
be levelled out with a brush.
For the purpose of expediting the air outlet after the completion of the casting
process, vibration rendering process shall be applied on the mold for 8-10
minutes by a plastic hammer.
Casting surface shall be brushed once in every 10-15 minutes and air bubbles
forming shall be removed and the surface shall be smoothed accordingly.
To remove the block joint mould, it shall be waited for curing process of 6-12
hours and the complete stiffening to be completed.
In case of a requirement of more than 1 dose of application in the application of
the juncture resin, it shall be performed successively without waiting for the
application of the 2nd and the 3rd doses.
Note: Utmost care should be exercised for the alignments in vertical
applications. Otherwise, clearances
may form on the upper part to risk the
juncture accordingly.
21
CRMANUAL
Preparation of Joint Casting Material
Megger test is definitely required to be conducted prior to
the casting process.
< 5°C STOP
Resin (A), Hardener (B) and fillers; must be stored at least
< 35°C STOP
one day over (> 20 °C ).
MW
Ambient temperature of job side must be 5°C < T amb <40°C
< 1MW OK T(°C)
< 1MW NOT OK
350 mm
150 mm + 100 mm
1 2 A 3
A
B
Filler removed from the plastic bucket. Resin and hardener are mixed in plastic bucket.
4 5
Mix resin and hardener thoroughly with stirrer Add fillers and mix until homogeneous; at least 5
at least 1 minute. minutes.
Then application must be done within 15 minutes.
22
CRMANUAL
Electrical site-tests
Cu
rre
Vo nt p
lta rob
ge e (-)
pro
Vol be
ta (-)
Cu ge
rre pro
nt p be
rob (+)
e (+)
Rmax ≤ 1,5 mΩ
Remarks
W tnesses
Name Company Date S gnature
24
CRMANUAL
EAE Electrical Site Test Report
Line Insulation Resistance Test Report
Results
PE L3 L2 L1 N
Before Casting After Casting
N - L1 = .............................................. / .............................................. MΩ
N - PE = .............................................. / .............................................. MΩ
L1 - L2 = .............................................. / .............................................. MΩ
L1 - L3 = .............................................. / .............................................. MΩ
L1 - PE = .............................................. / .............................................. MΩ
L2 - L3 = .............................................. / .............................................. MΩ
L2 - PE = .............................................. / .............................................. MΩ
L3 - PE = .............................................. / .............................................. MΩ
Remarks
W tnesses
Name Company Date S gnature
25
CRMANUAL
Declaration
CE DECLARATION OF CONFORMITY
Product Group E-Line CR Busbar Energy Distribution System
The objects of the declaration described below is in conformity with the relevant Union harmonisation
legislation. This declaration of conformity is issued under the sole responsibility of the manufacturer.
Standard :
EN 61439-6
Low-voltage switchgear and controlgear assemblies - Part 6: Busbar trunking
systems
IEC 61439-6
Low-voltage switchgear and controlgear assemblies - Part 6: Busbar trunking
systems (busways)
CE - Directive
2014/35/EU “The Low Voltage Directive”
Emre GÜRLEYEN
26
CRMANUAL
Certificates
27
CRMANUAL
Product Overview
28
PRODUCT TYPES
CABLE TRAYS
INDOOR SOLUTIONS
SUPPORT SYSTEMS
Please visit our website for the updated version of our catalogues.
www.eaeelectric.com
IRAQ
OMAN
SUDAN
CHILE
PERU
KENYA
LEBANON
GHANA
SUDANCHILE
YEMEN CHILEALGERIA PERU
OMAN TURKMENISTAN TURKEY
INDIA MADAGASKAR
SRI LANKA LATVIA
ETHIOPIA
FRANCE TAIWAN
GHANA UKRAINE
JAN VIETNAM
KONGO
CAMEROON ESTONIA FINLAND KUWAIT
UM IRELAND
BANGLADESH KUWAIT
THAILAND QATAR
UZBEKISTAN SYRIA ALGERIA CHINA
AR SYRIA GHANA THAILAND QATAR CAMEROON DENMARK
ONIA TANZANIA MADAGASKAR
MOROCCO
KENYA
PAKISTAN ROMANIA QATA
BELGIUM AUSTRIA GERMANY KENYA
SINGAPORE TANZANIA
TAN CZECH REP. ETHIOPIA PERU EQ. GUINEA TURKEY OMAN VIETNAM LATVIA MACED
MEN PERU SYRIA NETHERLANDS SINGAPORE AUSTRIAIRAQ LIBYA
OMAN AZERBAIJAN
TANZANIA MACEDONIA MADAGASKAR TUNISIA AZERB
POLAND TURKMENISTAN
KAZAKHSTAN NIGERIA LUXEMBOURG RWANDA GREECE SYRIA CROATIA SOUTH KOREA SWIT
ND TURKEY MAURITIUS GREECE THAILAND SYRIA
TES MYANMAR SPAINIRELAND SERBIA OMAN
SLOVENIA
KOREA UZBEK
EGYPT FRANCE ETHIOPIA CAMEROON PAKISTAN
VIETNAM
SPAIN EGYPT VIETNAM SUDANMADAGASKAR NETHERLANDS
TURKEY NIGERIAITALYRUSSIA U.KINGDOM TAIWAN
BAHRAIN SWITZERLAND U. A. EMIRATES BULGARIA SOUTH AFRICA QATAR TURKEY GREECE PAKISTAN D
ULGARIA GHANATURKMENISTAN
GREECE SRI LANKA
CYPRUSBELARUS AZERBAIJAN
MYANMAR NIGERIARUSSIA
VIETNAM NORWAY SERBIANORWAY SPAIN FRANCE DENMARK M
NIGERIA POLAND U. A. EMIRATES
NA VIETNAMSOUTH KOREA
ANDS
TURKEY ICELAND
HUNGARY CAMEROON YEMEN U.
VIETNAM SWITZERLAND
A. EMIRATES CHILE
TURKMENISTAN
LUXEMBOURG
YEMEN
LITHUANIA
SUDAN SWITZERLAND U. A. EMIRATES MALTA SU
MACEDONIA TANZANIA MADAGASKA
MACEDON
ANMAR SAUDI ARABIA YEMEN BRASIL BELGIUM POLAND BELGIUM U.KINGDOM TURKMENISTAN CZECH REP. AZERBAIJAN DENMARK
OVENIA RUSSIAYE