Description Amount
1 Dismelting and cleaning 10,000.00
2 Civil 234,625.00
3 Floor Finish 5,596,050.00
4 Ceiling Work 1,389,750.00
5 Glass & board partition 50,000.00
6 Paint 106,970.00
7 Wall paneling 435,350.00
8 Furniture 3,729,000.00
9 Sanitary 540,150.00
10 Electric 915,491.00
11 Miscellaneous 295,235.00
Total Amount 13,302,621.00
Design & Consultancy Fee 1,995,393.15
Grand Total 15,298,014.15
IN WORD :
Without VAT & AIT
Terms & Condition :
Mode of Payment:
1. 50% with the work order
2. 35% payment after 50% of work progress.
3. 15% within 7 days after job completion.
Duration of work:
a.110 days from the date of work order depanding on the payment schedule, political &
environmental situation.
Support:
* Electricity support during the work will be provided by Client.
* For quick delivery, permission for whole night work will be arranged by Client.
Client service and warranty:
* 12 months free repair in any sort of wooden and paint related default (caused due to
quality of the job).
* 24 months free warrenty for Electric Item.
OTHERS:
1.Any additional item will be a subject of extra bill.
2. For any support, a valid work order from the client is a mandatory requirement.
3. All payments will be made via A/C payee cheque in favor of ‘DOT 5 PVT. LTD’
4. 10% Wastage will be added with final measurement.
Regards,
________________
Md. Mahfuj Khan
Managing Director
DOT 5 PVT. LTD
SL No Description Quantity Unit Rate Amount
Dismantling Work :
1 Site cleaning and mobilization preparation :
Preparation of electricity connection, water connection and general
site cleaning. Client will show source and contractor will have arrange
necessary facilities including pipe, cable, etc to get the connection. 1 Job 5,000.00 5,000.00
Total 10,000.00
SL No Description Quantity Unit Rate Amount
CIVIL WORK :
5" Brick Work :
5" thick brick wall with 1st class bricks in 1:4 cement
mortar (sand F.M. 1:5) including screening and washing of sand,
racking out joints, shorting, cleaning and soaking the bricks at
1 least for 24 hours before use and necessary scaffolding, proper 650 sft 145.00 94,250.00
curing including supply of all materials etc. all complete as per
direction of Project consultant.
Plaster Work :
Minimum 1/2" thick cement plaster (1:6) to brick wall both
inner surfaces, finishing the corners and edges including
washing / screening of sand, cleaning the surface, necessary
2 scaffolding, curing at least for 3 days including supply of 550 sft 30.00 16,500.00
materials, all complete as per direction of Project consultant.
Total 234,625.00
SL No Description Quantity Unit Rate Amount
Floor Tiles Work :
1 Rustic Tiles floor(Foreign Made):Size:24"X 24"
Supply, fitting and fixing of floor Tiles size 24''x 24'' (made by
China / equivalent) placing over wall with required cement
mortar (proportion 1:4 and average thickness 3/4"), racking out
the joint & filling with same color putty including cutting and 3685.00 sft 340.00 1,252,900.00
leveling of the wall etc. all complete as per direction of Project
Consultant.
11 Artificial grass:
Supply, fitting, fixing of artificial grass and necessary all 2575 sft 250 643,750.00
hardware.
Total 5,596,050.00
SL No Description
Quantity Unit Rate Amount
CEILING WORK :
DECORATIVE VENEER BOARD LOUVER
Supply, fitting, fixing of 12 mm veneer board louver
suspended from existing R.C.C slab of the building at the desired
1 level height made of 1/2" teak veneer board over frame work of 2" X 350 Sft 650.00 227,500.00
1" best quality Garjon wood .all complete as per design, direction &
full satisfaction of the Engineer in charge.
Total 1,389,750.00
SL No Description Quantity Unit Rate Amount
FLUSH DOOR
Total 50,000.00
SL No Description Quantity Unit Rate Amount
PAINT WORK :
Plastic Painting :
Plastic emulsion paint of approved best
quality and color delivered , applying to wall and
ceiling in two coats over a coat of brand specified
primer or sealer elapsing specified time for
1 drying/recoating including cleaning drying, making free 550 Sft 35.00 19,250.00
from dirt, grease, wax, removing all chalked & scaled
materials, fungus, mending good the surface defects,
sand papering the surface and necessary scaffolding,
spreading by brush/ roller/spray etc. all complete as
per direction of Project consultant.
3D wall paneling
Supply, fitting, fixing of 3D board wall pasting & other
1 accessories all complete as per design, direction & full 320.00 sft 280.00 89600.00
satisfaction of the Engineer in charge.
Total 435350.00
SL No Description Quantity Unit Rate Amount
FURNITURE WORK
SANITARY WORK :
Toilet paper holder :Supplying, fitting and 3.00 pcs 650.00 1,950.00
fixing cp toilet paper holder of 150 x 150 x 126
mm size including making holes in walls and
6 mending good the damages with cement mortar
(1:4) etc. all complete as per direction of the
engineer-in-charge.
Lighting work
SL No Description Quantity Unit Rate Amount
LED PANEL LIGHT (24"X24"):
Supply, fitting & fixing of 24"X24" 40w led panel light
1 & necessary all hardware with 1 years warranty. 1.00 Pcs
Brand: Chaina
Pendent Light:
Supply, fitting & fixing of Imported
15 Pendent Light and other necessary accessories 1.00 Pcs 12500.00 12500.00
etc. Made in China or Equivalent
SPHARE LIGHT
Supply, fitting & fixing 14" dia Sphare
21 light with approved quality etc all complete up to 0.00 PC 1500.00 0.00
testing & comissioning as per direction and full
satisfaction of Engineer in charge.
Frosted Paper :
Supply & pasting of Imported 200 micron thick frosted sticker
over glass 4' wide in position made in Thailand (equivalent) origin
4 with design cutting etc. all complete as per direction of Project 1 Sft 40.00 40.00
consultant.