Actual
Actual
Actual
Submitted by:
JOVELITO D. REYES
JDRC CONSTRUCTION AND SUPPLIES
General Manager
1st Quarter
cd cd cd cd
10 10 0.06
3 3 0.01
90 90 90 90 360 0.08
3 3 6 0.03
7 7 0.09
7 7 0.03
30 10 40 7.26
5 5 0.02
10 5 15 0.27
10 15 25 0.43
15 20 35 3.10
23 30 53 2.40
20 30 50 9.75
0 30 30 30 90 -
25 25 0.70
20 20 1.01
90 90 90 90 360 0.005
90 90 90 90 360 0.006
25.26
2nd Quarter 3rd Quarter 4th Quarter Total
0.06 -
0.01 -
0.08 0.08 0.07 0.31 0.00
0.03 0.06 - 0.00
0.09 -
0.03 0.03
1.81 9.07 0.00
0.02 0.00
0.08 0.35 0.04
0.11 0.54 - 0.00
0.70 -
5.53 5.53 5.53 17.60 - 0.00
15
25
0.23
0.50
1,610.00
14,490.00
3,622,500.00
0.15 0.08
0.50 0.50
1,050.00 560.00
9,450.00 5,040.00
2,362,500.00 1,260,000.00
Back-up for first period
Item Description
Qty unit
1 l.s
Qty unit
4 each
Qty unit
0.25 lot
Qty unit
0.5 l.s
Qty unit
7.2 km
Qty unit
1 l.s
Total = 3.90
Width = 6.00 m
Length = 5,630.52 m
Total 33,783.12 sq.m
Length = 4,500.00 m
Width = 6.00 m
Thickness = 0.15 m
No. of Units = 1.00
Total 4,050.00 cu.m
Road way
Length = 3,000.00 m
Width = 6.00 m
Thickness = 0.15 m
No. of Units = 1.00
2,700.00 cu.m
Shoulder
Length = - m
Width = 0.50 m
Thickness = 0.13 m
No. of Units = 2.00
- cu.m
Length = 2,500.00 m
Width = 2.50 m
Total 6,250.00 sq.m
Paveshoulder
Length = - m
Width = 0.50 m
Thickness = 0.15 m
No. of Units = 2.00
Total - cu.m
Station No.
Qty unit
25.00 unit
88.00
IN - HOUSE
DETAIL ESTIMATE
Project : Road Concreting Sitio Sayawan to Barangay Tambobong Boundary; Barangay Salaysay, Marilog District
Part C: EARTHWORKS
101(1) Clearing and Grubbing
1.00 Backhoe @ 2,300.00 per hr x
(Capacity: (2000 sq.m / day)
1.00 Dump Truck @ 1,000.00 per hr x
1.00 Chainsaw or Equivalent 1,000.00 per day x
1.00 Supervisor 700.00 per day x
8.00 Laborers 350.00 per day x
150k UNIT
1.00 Backhoe unit rental 1,800.00 per hr x
Fuel 1,200.00 per hr x
Labor Cost
1.00 P.E. 900.00 per day x
1.00 foreman 700.00 per day x
2.00 skilled 470.00 per day x
2.00 labor 400.00 per day x
1.00 warehouse man 400.00 per day x
1.00 flagman 350.00 per day x
Equipment:
Capacity: 70.00 cu.m per hr
100,000.00
cu.m
720,000.00 3,120,000.00
unit cost = 72.73 per cu.m
= 3,365,400.00
unit cost = 78.45 per cu.m
= 12,500.00
= 1,760.00 cu.m
2,000.00 = 96,000.00
1,800.00 = 86,400.00
Item Description
Qty unit
1 l.s
Qty unit
4 each
Qty unit
0.45 lot
Qty unit
0.4 l.s
Qty unit
6.48 km
Qty unit
0.9 l.s
Total = #REF!
Width = 6.00 m
Length = 5,630.52 m
Total 33,783.12 sq.m
Length = 5,253.96 m
Width = 6.00 m
Thickness = 0.15 m
No. of Units = 1.00
Total 4,728.56 cu.m
Road way
Length = 4,350.00 m
Width = 6.00 m
Thickness = 0.15 m
No. of Units = 1.00
3,915.00 cu.m
Shoulder
Length = 3,189.00 m
Width = 0.50 m
Thickness = 0.13 m
No. of Units = 2.00
414.57 cu.m
Length = 630.52 m
Width = 5.00 m
Total 3,152.60 cu.m
Paveshoulder
Length = 1,261.04 m
Width = 0.50 m
Thickness = 0.15 m
No. of Units = 2.00
Total 189.16 cu.m
Station No.
0+552.72 14.00 pc
1+035.06 13.00 pc
1+134.33 10.00 pc
1+424.89 10.00 pc
Qty unit
10.5 each
b.) Bollards
Qty unit
35 unit
22
30
31
31
30
31
30
31
31
29
31
30
3
360
90
Project : Road Concreting Sitio Sayawan to Barangay Tambobong Boundary; Barangay Salaysay, Marilog District
142,206,518.80
142,500,000.00
293,481.20
60
ITEMIZED QUANTITIES AND COST OF REVISION FOR VARIATION ORDER NO.1
Republic of the Philippines
OFFICE OF THE CITY ENGINEER
CONTRACTOR: JDRC CONSTRUCTION AND SUPPLIES
City of Davao
Project : Road Concreting Sitio Sayawan to Barangay Tambobong Boundary; Barangay Salaysay, Marilog District
COST AND QUANTITIES WITHIN LIMITS OF THIS VARIATION REVISED QUANTITIES OF THIS APPROVED VARIATION ORDER
1/EXTRA WORK ORDER 1 NO. 1
B. Labor Cost
B. Equipment Cost
B. Labor Cost
B. Equipment Cost