SECTION-1 (GENERAL)

1 66kV GIS Mehrauli Road, Gurugram.


1.1 The scope of this Project is to establish 66kV Gas Insulated Substation (GIS) at
Mehrauli Road, Gurugram with complete automation and civil work
configuration. The intent of this specification covers the following:
1.2 The specification includes the design, engineering, manufacture, fabrication,
testing at manufacturers works, delivery, unloading at site, storage, erection,
testing and commissioning at site of the complete 66kV switchyard in the Yard
of existing 66kV AIS Mehrauli Road, Gurugram including:
 Indoor 66kV SF6 gas insulated metal enclosed switchgear (GIS)
(Annexure-A1).
 4 No. 25/31.5MVA, 66/11kV Power Transformers (Transformers to be
provided by HVPNL).
 1 No. 200KVA 11/0.433kV LT Transformer,
 11kV VCB Panels, 11kV Automated Switched Capacitor banks, Fire
Extinguishers, Testing equipment’s, associated civil works including soil
investigation, including disposal of sewerage/industrial waste water &
removal of malba/sludge, internal roads, drains, necessary buildings
etc., 66kV XLPE copper Power Cables, 11kV XLPE Aluminium Power
Cables, Indoor & outdoor End Termination Boxes, Substation
Automation with Relay & Protection and other electrical and mechanical
auxiliary systems on turnkey basis. Bidder shall also ensure GIS
compatibility for line feeder and provide the ancillary equipment
required for the same. For connecting 66kV GIS with primary of
transformers, bidder will use XLPE copper Power Cables along with
cable termination for both end and flexible conductor, structures etc. as
per GELO. For connecting 11kV side of 66/11kV Transformer bidder
will use 11kV XLPE Aluminium Power Cables and as per GELO drawing
no. HGD-3C/616.
1.3 The supply will include all supporting structures, auxiliary equipment’s,
mechanical linkages, SF6 gas piping, auxiliary circuits wiring, interlocking
devices, current and voltage transformers, cable end boxes and SF6 bus ducts.

1.4 Support structure required for installation and commissioning of above


equipment’s shall be provided by the bidder/manufacturer.

1.5 It is the intent of this specification to describe primary features, materials,


and design & performance requirements and to establish minimum standards
for the work.

1.6 The specification is not intended to specify the complete details of various
practices of manufactures/ bidders. But to specify the requirements with
regard to performance, durability and satisfactory operation under the
specified site conditions.

1.7 Whenever a material or article is specified or described by the name of a


particular brand, manufacturer or trade mark, the specific item shall be
understood as establishing type, function and quality desired. Products of
other manufactures may also be considered, provided sufficient information is
furnished so as to enable the purchaser to determine that the products are
equivalent to those named.
1.8
Supply will include computer with UPS and printer.

1.9 Any deviation or variation from the scope requirement and/or intent of this
specification shall be clearly mentioned under Deviation Schedule of the Bid
Proposal Sheets irrespective of the fact that such deviation/variation may be
standard practice or a possible interpretation of the specification by the bidder.
Except for the deviation/variations which are accepted by the purchaser before
the award of the contract, it will be the responsibility of the bidder to fully
meet the intent and the requirements of the specification within the quoted
price. No other departure from the specification except for the declared
deviation indicated by the bidder in his proposal shall be considered. The
interpretation of the purchaser in respect of the scope, details and services to
be performed by the bidder shall be binding, unless specifically clarified
otherwise by the purchaser in writing before the award of contract.

1
1.10 The drawings enclosed with the specification are preliminary drawings for
bidding purpose only and subject to changes that may be necessary during
detailed engineering after award, keeping the basic parameters as specified.

1.11 Scope of Work

1.11.1 Design, Engineering, manufacture, testing, supply on CIP basis,


transportation to site including port and custom clearance if required,
insurance, storage, testing and commissioning of following items:-

a) Indoor 66kV SF6 gas insulated metal enclosed switchgear (GIS).


b) 4x25/31.5 MVA, 66/11 kV T/Fs along with all accessories and
mandatory spares (Transformers to be provided by HVPNL).
c) All type of Neutral CT’s, Surge Arrestors with their terminal connector
along with mandatory spares.
d) Lightning protection.
e) Complete Sub-Station automation including Hardware & Software for
66kV and 11kV.
f) Complete 66kV C&R Panels and 11 kV VCB Panels with SEMs on each
T/F I/C VCB Panel.
g) Associated mechanical & electrical auxiliaries & EOT cranes &
mechanical operated crane etc.
h) 1.1kV grade power & Armoured (FRLS) control copper cables along with
complete accessories for switchgear, metering and protection
equipment’s.
i) Substation structures for sub-station towers & beams and equipment
structures.
j) Insulator strings, hardware clamps and connectors, junction box, copper
lug, glands & PVC ferrules for control cabling, fiber cleats, aluminum
clamps, bolts, nuts, washers etc. for fixing control cables in trenches,
galvanized iron trays & clamps, ACSR conductor, GS earth wire, spares.
Cables supporting angles/channels, buried cable trenches & outdoor
trenches with channels with trench covers.
k) Boltless C-Type Wedge connector & equipment interconnections shall be
suitable for Single Zebra/AAC Tarantulla Conductor.
l) Complete lighting and illumination of the switchyard, GIS cum Control
room Building, receptacles etc. as per technical specification/BOM.
m) Air Conditioning system as per specification in Section-6, Chapter-12 &
Ventilation system for GIS hall-AHU. The requirement of ventilation
system shall be as per Annexure V and separate room for air handling
unit to be provided adjacent/inside (as per space availability) GIS hall
however their design will be in scope of bidder as per requirement.
n) i) The building should accommodate 66kV GIS hall and control room.
ii) The entry of power cable should be made independently transformer
wise, to be provided in multilayer type trays for proper/easy
maintenance purpose.
iii) The detailed design/drawing of building for proposed substation will
be submitted by firm for approval.

o) Grounding system of the substation i.e. complete Earth mat lying will be
designed/quoted for soil resistivity of 50m. In case soil resistivity is more
than 50m then the earth mat will be designed for actual soil resistivity.
The payment of extra material to be used for earth mat shall be made on
pro rata basis & equipotential mat beneath the floor of GIS building as per
IEEE/tech. specification/IS./IEC etc.
p) Complete fire - fighting equipment.
q) One set of 220V 100 AH DC battery (San Tubular) with battery charger
(SMPS) & DCDB along with associated accessories.
r) 415V LT ACDB 300A along with associated accessories.
s) 1X200 KVA 11/0.4 kV station T/Fs for auxiliary supplies.
t) Providing 4 No. 9000KVAR 12.65 kV Automatically Switched Capacitor
Bank along with allied equipment.
u) Cable support structure for 66kV XLPE cable for each bay shall be of
2
Galvanized steel and shall be designed along with civil foundation by the
successful bidder after award of the contract.
v) The supply, installation, erection, testing and commissioning of PLCC
equipment (if required) for both end will be in scope of bidder. The shifting of
Wave Trap/CVT/protection coupler/PLCC terminal etc. if required for
matching purpose will be in scope of bidder.
o) Special Equipment’s for testing and maintenance along with mandatory
spares.
w) Recommended spare parts, maintenance tools and other equipment
necessary for maintenance purposes for fifteen years of trouble free service
other than those specified as mandatory spares.

x) Any other equipment/material required to complete the specified scope.

1.11.2 Civil Works

a) Foundation for sub-station main gantry/steel structures and equipment’s as


per approved drawings. For breaker the design/drawing of foundation shall be
submitted by successful bidder for approval before execution.
b) Foundation for 4 No. 25/31.5MVA transformer including associated radiator.
Complete in all respects as per approved T/F, substation transformer, 4 Nos.
9MVAR 11kV Capacitor Bank along with allied equipment’s complete as per
technical specifications. The successful bidder shall submit foundation design
& drawings as per approved equipment drawing for approval before execution.
c) Foundation for lighting poles, junction box, panels & control cubicles of
equipment’s (wherever required) without any extra cost to HVPNL.
d) RCC outdoor cable trenches along with RCC covers, cable racks, trench
culverts crossings the road, drainage system including drainage pipes,
manholes with RCC covers whenever required, installation of pump, cable etc.
complete. The design/drawings shall be evolved by the successful bidder and
got approved from HVPNL before execution.
e) Laying of concrete roads leading to switch yard, switch house & GIS buildings
(as applicable) from HUDA/PWD/village road including earth filling for road
and berms, if required and PCC in front, rear or side (as applicable) of the
switch house building for parking etc. The above shall be as per
GELO/CLO/site requirement.
f) Provision of two pipe(s) culverts of suitable dia. as per technical specifications
on approach road leading to switch yard & switch house/GIS building from
HUDA/PWD/village road (as per site requirement).
g) Fencing & Boundary wall for the S/Stn. along with main entrance gates as per
drawing attached.
h) Site surfacing including leveling, dressing, compaction, laying of lean
concrete/PCC in areas under scope of contract/wherever required in the
switchyard area as per site requirement.
i) The removal of weed growth/ tree cutting shall be responsibility of the
contractor. Contractor may note that purchaser shall not pay any
compensation for any loss or damage to the properties or for tree cutting due
to contractor’s works.
j) Construction of Control room building & GIS building: the successful bidder
has to develop architectural & structural/foundation drawings and shall
submit the same to HVPNL before execution. Both the building shall include
indoor cable trenches, all services such as lighting, sanitary, drainage, RW
pipes, collection tank, soakage pit, etc. Collection tank & soakage pit shall be
required if HUDA’s sewerage system is not in place. The architectural & the
structural design for Control room building above plinth level shall however be
kept same as per approved drawings.
k) The GIS halls dimensions and functional details given in GELO are tentative
since the detailed engineering is in scope of successful bidder.
l) Cutting/Filling of earth to required depth including leveling, dressing,
compaction etc. in S/Stn. including switchyard and roads wherever required
to achieve required formation level as decided by employer.
m) Construction of one no. rain harvesting system (rechargeable bore/well) for
entire sub-station including control room/GIS buildings and yard for
collection of water from switch house/GIS buildings and yard. The
disposal/drainage scheme for draining rain water shall include open drains,
RCC pipes, inspection chambers, manholes, RCC covers where ever required,

3
settlement tank, sum pit-cum-pump chamber with pump motor, GI Suction
delivery pipes, electric control panels, cables etc. complete in all respects. The
bidder shall evolve design and drawing for rechargeable well, settlement tank,
sump pit-cum-pump chamber and drainage scheme and got the same
approved before execution.
n) All civil works associated with construction of buildings, indoor/outdoor
equipment/tower foundations, erection of EOT crane, indoor/outdoor cable
trenches, drains, services, anti-fire wall, rechargeable well, sump pit-cum
pump chamber, settlement tank, septic tanks etc. are in the scope of
successful bidder.
1.11.3 The Switchgear shall be complete with all necessary terminal boxes, SF6 gas
filling, interconnecting power and control wiring, pressure switches,
grounding connections, gas monitoring equipment and piping, support
structures etc.
1.11.4 The work to be done under this specification comprises the provision of all
labour, plant, equipment and material and the performance of all work
necessary for the complete installation and commissioning of switchyard on
turnkey basis. It is hereby required that the contractor should provide all
apparatus, appliances, material and labour etc. not specifically mentioned or
included, but are necessary to complete the entire work or any portion of the
work in compliance with the requirements implied in this specification is
deemed to be included in the scope of contractor.
1.11.5 The contractor shall be fully responsible for:-
i) Complete project management
ii) Design and engineering of entire work of GIS Substation including supply of
complete documentation i.e. design drawings, design memorandums, O&M
manuals for all works which shall be identified at the time of contract.
iii) Insulation coordination including studies for selection of metal oxide surge
arrestors, parameters, location for complete switchyard. The specifications
and quantity provided elsewhere are indicative only. The final quantities shall
be worked out during detailed engineering of insulation coordination.
iv) The quality of all materials and workmanship of the complete work.
v) The Contractor shall be responsible for detailed design and engineering of
overall system, sub-systems, elements, system facilities, equipment’s,
auxiliary services, etc. It shall include proper definition and execution of all
interfaces with systems, equipment, material and services of purchaser for
proper and correct design, performance and operation of the project.
vi) Contractor shall provide complete engineering data, drawings, reports,
manuals, etc. for purchaser’s review, approval and records.
vii) The scope shall also include the design and engineering as per details
elaborated elsewhere in this specification.
viii) The Contractor shall carry out earth resistivity measurements at the
substation site(s) (based on four electrode method).
ix) For all structural works, the contractor shall prepare all fabrication drawings.
x) The Contractor shall be responsible for design, engineering, manufacture,
testing & inspection at manufacturer’s works, supply transportation,
insurance, delivery at site, unloading, storage, in plant transportation at site,
complete erection & supervision, site testing & inspection, and successful
commissioning of all equipment and material listed at ‘Bill of Quantities’
enclosed as Annexure-A1 to E1 of this section, detailed elsewhere in
specification and as shown on the tender drawings. Any item though not
specifically mentioned, but is required to complete the project works in all
respects for its safe, reliable, efficient and trouble free operation shall also be
taken to be included, and the same shall be supplied and erected by the
Contractor without extra cost unless it is explicitly excluded elsewhere in the
specifications.
xi) All consumables, wastages and damages shall be to the account of contractor.
xii) The contractor shall construct, erect and install all equipment and material
required for completion of substation(s) covered under the project. He shall be
responsible for provision of all labor, tools and tackles and supervisory staff
for safe, reliable, proper and correct erection of all equipment required for
successful completion of the substation(s).
xiii) The tools and plant shall include, but not limited to, special hoisting
equipment, cranes, slings, consumables and all other articles and supplies as
required.
xiv) The contractor shall ensure periodic cleaning of work site and removal of all
waste material, packaging material, surplus earth and left-over and their
proper disposal.
xv) The contractor has to employ suitable manpower and supervision personnel.
The contractor is solely and fully responsible for the safety of personnel and

4
materials. Any damages to the existing facilities shall be made good by the
contractor at no extra cost to the purchaser. The contractor shall coordinate
with site personnel for arranging shut down for interconnection with the
existing systems, if required.
xvi) The contractor shall be responsible for the overall management and
supervision of works. He shall experiences, skilled, knowledgeable and
competent personnel for all phase of the project, so as to provide the
purchaser with a high quality system.
xvii) The contractor’s supervisory personnel shall provide operation and
maintenance assistance during the warranty period.
xviii) A Project execution schedule called Master Network (MNW) in the form of
PERT chart/network shall be prepared by the contractor for purchaser’s
approval. The MNW shall identify milestones of key event for each work/
component in the areas of engineering, procurement, manufacturer, dispatch,
erection and commissioning. It shall indicate interfaces and inputs required to
be given by Purchaser.
xix) The scope includes testing and commissioning of all equipment, subsystems
and systems of the project and putting them into successful commercial
operation. The scope shall include but not limited to the requirements
given elsewhere in the specification.
xx) The contractor shall be responsible to provide all necessary testing and
commissioning personnel, tools and plant, testing equipment, etc. All
expenses for carrying out the routine tests as specified in relevant standard
shall be to contractor’s account. However the expenses w.r.t.
purchaser/purchaser’s representative for witnessing these tests which
contractor shall take into account shall be as follows:-
a) For Inspections/tests to be carried out for equipment offered from within
purchaser’s country.
All tour expenses shall be borne by purchaser.
b) For inspections/tests to be carried out for equipment offered from
outside purchaser’s country:-
It is envisaged that inspection/testing of all such equipment shall be
witnessed. Each inspection shall be carried out by a team of 3 to 4 engineers
nominated by the purchaser. Their To & Fro travel expenditure from
purchaser’s country to the place of inspection/testing shall be borne by the
bidder including all boarding and lodging charges.
xxi) The contractor shall identify all interface issues with purchaser and other
agencies, and shall be responsible for such interfacing, coordination and
exchange of all necessary information.
a) The approach road up to the GIS substation area shall be provided by the
Purchaser. All internal roads (if any) shall have to be constructed by the
contractor.
b) Bidder will solely be responsible for obtaining statuary clearances for
providing temporary connections for construction of power and water. The
contractor shall arrange for necessary meters etc. and shall pay applicable
energy and water charges as per applicable rates to the concerned authorities.
xxii) Contractor shall make his own necessary arrangements for the following and
for those listed anywhere else in this specification.
a) Construction power supply at all work areas.
b) Provision of water supply arrangement.
c) Construction office and store (open and covered)
d) Construction workshop and material/field testing laboratory
e) Boarding & lodging arrangement for their personnel.
f) Fire protection and security arrangements during construction
stage.
g) Any other requirements of the Haryana Government and as per
the purchaser’s rules, regulations and practices.
h) the contractor shall make his own necessary arrangements like
diesel generator sets, water etc., at his own cost so that progress
of work is not affected and Employer shall in no case be
responsible for any delay in works because of non-availability of
power, water etc.
i) Provide labour license as per Govt. Rules.

1.11.6 SF6 gas filling & evacuating plant with gas cylinders shall be supplied by the
bidder as per Bid Price Schedules and shall be utilized by the bidder for
commissioning. The contractor would be required to hand over the same in
good working condition with enough gas for one charging of complete system
with 20% extra gas as indicated in mandatory spares of relevant Bid Price
Schedule.
5
1.11.7 EOT crane shall be provided in 66KV GIS building for GIS equipment handling
during installation, commissioning and maintenance etc. Crane lifting capacity
shall be adequate to handle the heaviest package of GIS but shall not be less
than 5 tonnes for 66kV System. The crane shall also be provided with speed
drive mechanism.
1.11.8 Supply, erection, testing and commissioning of all items of work required to
make the 66kV bays fully functional.
1.11.9 Bidder shall submit along with the bid and also during detailed engineering
the computation and calculation for enclosure loss and details about the
measures taken to reduce losses so as to limit the temperature rise of
enclosure as per the requirement of clause 4.37 of section: GIS.

2.0 Mandatory Maintenance Equipment


The Bidder shall include in his scope mandatory maintenance equipment’s as
specified. The prices of these shall be indicated in respective schedules. These
would be considered in bid evaluation.
A List of mandatory maintenance equipment is given at Annexure E-1, of this
section. The Owner reserves the right to buy any or all of these. The Bidder
shall furnish the itemized and total prices for this equipment in the offer.
In Compliance with the requirements of Bid documents, the prices for
mandatory maintenance equipment must be given separately, and shall be
used for bid evaluation purposes. All mandatory maintenance equipment shall
be delivered at site.
3.0 Commissioning spares
The bidder shall supply spares, which he expects to consume during
installation, testing and commissioning of system. The quantity of these spares
shall be decided based on his previous experience, such that site works shall
not be hampered due to non-availability of these spares. Bidder shall submit a
complete list of such spares along with the bid, the cost of which shall be
deemed to have been included in the lump sum proposal price of the package.
The unused commissioning spares may be left at the site for use by the
purchaser, if so agreed at a cost to be negotiated.
No mandatory or recommended spares will be used during the commissioning
of the equipment/plant before take over by the purchaser.
4.0 Recommended spares.
In addition to the mandatory maintenance equipment, the bidder shall also
provide a list of recommended spares giving unit prices and total prices for 5
years of normal operation of equipment in the relevant schedule of the BPS.
The Purchaser reserves the right to buy any or all the recommended spares.
The recommended spares parts shall be delivered at the site(s). The list of
recommended spares to be furnished by the bidder should also contain the
following:

a) Population of each item installed along with reference drawing number.


b) Service life expectancy of each item.
c) Offer validity period.
4.1 Price of recommended spares will not be used for evaluation of bids. The price
of these spares will remain valid for a period of not less than 120 days after
the date on which the validity of main bid expires. The prices of any
recommended spares shall be subject to review by the purchaser and shall be
finalized after mutual discussions.

5.0
Tools & Tackles
The Bidder shall also supply at each substation site one set of all special tool
and tackles, etc. which are required by the purchaser’s maintenance staff to
maintain the works successfully at no extra cost. The list of such tools and
tackles shall be enclosed with the offer.

Training of purchaser’s Personnel


6.0 (a) Training at Manufacturer’s works:
The successful bidder shall arrange for training of 2 persons of the employer
at the manufacturer’s works of GIS for 5 working days in Design,
manufacturing and testing of GIS being supplied. The traveling, lodging,
boarding & visa arrangement including all expenses shall be made by the
successful bidder for the above training.
(b) Training at Site:
The successful bidder shall arrange for training of 5 persons including
operating field staff of Employer for five working days at each GIS sub-station
in operation and maintenance of GIS. The expenses for training including
6
traveling, lodging, boarding of the trainer shall be borne by the successful
bidder.
The detailed design shall be submitted for approval by the employer, during
7.0 detailed engineering.
SCHEDULE OF QUANTITIES
The detailed description of various items/equipment and civil works are
indicated at Annexure – I to V & Schedule A1, B1, C1, D1, E1. The bill of
quantity of major equipment is also indicated and wherever the quantities are
not indicated the bidder is required to compute the quantity. Bidder is
required to indicate unit rate and total price of the items under a particular
head in bid proposal sheets. Bidder should include all such items in the bid
proposal sheets, which may not be specifically mentioned but are essential for
the execution of the contract.

SOIL DATA
8.0 The earth resistivity for 66KV GIS Mehrauli Road, Gurugram, shall be
ascertained by the bidder himself.

Physical and Other Parameters


9.0 Location of the Substations
9.1 The location of the substations is in Gurugram.

Meteorological data
9.2 The meteorological data of the substation is indicated at Annexure-III.
However, for design purpose, ambient temperature should be considered as
50° C.

Basic Reference Drawings


For 66/11kV voltage level, Double bus-switching scheme (GIS) layout
10.0 arrangement shall be used. The Single line diagram and layout arrangements
are attached with bidding documents Annexure-IV, which shall be further
engineered by the bidder. The dimensions of GIS rooms are indicative; Bidder
may increase the dimensions of building as per requirement (with the
provision of service bay).

DRAWING
11.0 1. The bidder shall maintain inter equipment distances, bay length, bay
width etc. in accordance with the enclosed general/electrical layouts of
the substation, while doing so the bidder will ensure that the statutory
electrical clearances required for substation are maintained.
(Annexure-IV).
2. The drawing enclosed gives the basic scheme, layout of substation,
substation buildings, associated service etc. In case of any discrepancy
between the drawing and text of specification the bidder is advised to
get these clarified before submission of bid. No claim what-so-ever on
this score shall be entertained after award of contract.
3. The bidder shall adopt HVPNL design of galvanized steel structure for
tower, beam and equipment supporting structures for 66/11kV S/Stn.

In case of any discrepancy between the drawings and text of specification, the
requirements of text shall prevail in general. However, the Bidder is advised to
get these clarified from Employer.
In case of any discrepancy between Section-GTR and individual sections for
various equipment’s, requirement of individual equipment section shall
prevail.

7
12.0 Specific Requirement

The bidder shall be responsible for safety of human and equipment during the
working. It will be the responsibility of the Contractor to co-ordinate and
obtain Electrical Inspector’s clearance before commissioning. Any additional
items, modification due to observation of such statutory authorities shall be
provided by the Contractor at no extra cost to the Employer.

Notes:
13.0
a) The bidder or his authorized representative should visit the site of works
and its surroundings to obtain himself at his responsibility and expenses,
all information regarding general site characteristics, accessibility,
infrastructure details and factual position in respect of scope of work viz-a-
viz GELO drg. attached with the bid document. Any alteration/addition
envisage in the document must be got clarified before submission of the
bid.
b) No extra payment shall be made on account of any change in the layout
drgs. required for providing DSLP as per Rezavig method.

8
ANNEXURE-I
66kV SUB-STATION

Sr. Name of Scope of Work Scheme


No. S/Stn.
1 66KV GIS The specification includes the design, engineering, Double
Mehrauli manufacture, fabrication, testing at manufacturers bus bar
Road, works, delivery, unloading at site, storage, erection, (66 kV,
Gurugram testing and commissioning at site of the complete 66kV with Bus
switchyard in the yard of existing 66kV AIS Mehrauli coupler)
Road Gurugram including:
 Indoor 66kV SF6 gas insulated metal enclosed
switchgear (GIS).
 4 No. 25/31.5MVA, 66/11kV Power
Transformers (Transformers to be provided by
HVPNL).
 One No. 200KVA 11/0.433kV LT Transformer,
11kV VCB Panels, 11kV Automated Switched Capacitor
banks, Fire Extinguishers, Testing equipment’s,
associated civil works including soil investigation,
including disposal of sewerage/industrial waste water &
removal of malba/sludge, internal roads, drains,
necessary buildings etc., 66kV XLPE copper Power
Cables, 11kV XLPE Aluminium Power Cables, Indoor &
outdoor End Termination Boxes, Substation
Automation with Relay & Protection and other electrical
and mechanical auxiliary systems on turnkey basis.
Bidder shall also ensure GIS compatibility for line
feeder and provide the ancillary equipment required for
the same. For connecting 66kV GIS with primary of
transformers, bidder will use XLPE copper Power Cables
along with cable termination for both end and flexible
conductor, structures etc. as per GELO. For connecting
11kV side of 66/11kV Transformer bidder will use 11kV
XLPE Aluminium Power Cables and as per GELO
drawing no. HGD-3C/616.
For detailed BOQ refer Annexures A1, B1, C1, D1, D2 and E1.

9
ANNEXURE-II

LOCATION OF SUB-STATIONS

Sr. No. Name of Substation Nearest Rail Head

1. 66KV GIS Mehrauli Road, Gurugram, Gurugram


Rewari.

10
ANNEXURE-III

METEOROLOGICAL DATA

1.1 Equipment to be supplied against this specification shall be suitable for


satisfactory continuous operation under the following tropical conditions:

i) Location
In the state of Haryana

ii) Max. Ambient air temp. (deg. C) 50

iii) Min ambient air temp. (deg. C) -2.5

iv) Daily average air temp. (deg. C) 35

v) Average no. of Thunder storm days per 45


Annum

vi) Maximum Relative Humidity (%) 100

vii) Minimum Relative Humidity (%) 26

viii) Average annual rain fall (mm) 900

ix) Max. wind pressure (kg/sq m) 195

x) Max. altitude above mean sea level (meters) 1000


xi) Isoceraunic level (days/year) 45

xii) Seismic level 0.3 g


(horizontal acceleration)
xiii) Average no. of rainy days per Annum 120

NOTE: Moderately hot and humid tropical climate conductive to rust and
fungus growth. The climate conditions are also prone to wide variations in
ambient condition. Smoke is also present in the atmosphere. Heavy
lightening also occurs during June to October.

11
ANNEXURE-IV

Sr. No. Name of Substation GELO DRAWING NO

1. 66KV GIS Mehrauli Road, Gurugram HGD-3C/616

12
ANNEXTURE-V
VENTILATION SYSTEM FOR GIS HALL

Each GIS hall shall have an independent ventilation system. Each


ventilation system shall consist of two 100% capacity systems, one
operating and one stand-by.
To ensure that the air being supplied to the GIS hall is free from dust
particles, a minimum two stage dust filtration process shall be supplied.
This shall consist of at least the following:
1) Pre Filters: To remove dust particles down to 10 micron in size with at
least 95% efficiency.
2) Fine Filters: To remove dust particles down to 5 microns in size with at
least 99% efficiency.
All the filters shall be panel type. Easy access should be available to the
filters for replacement/ cleaning.
The ventilation of the GIS hall shall be of a positive pressure type with
minimum 4 air changes per hour. The pressure inside the GIS hall shall
be maintained 5 mm of Water above the atmospheric pressure. Fresh
outdoor air shall be filtered before being blown into the GIS hall by the air
fans to avoid dust accumulation on components present in the GIS hall.
Each GIS hall shall be provided with motorized exhaust dampers with
local control.

13
EQUIPMENTS/MATERIALS TO BE SUPPLIED AND ERECTED FOR
66KV GIS Mehrauli Road, Gurugram
Annexure-A1

The 72.5kV SF6 Gas Insulated Switchgear (along with AHU with room) for three
phase system shall have double bus bar arrangement with 10 bays (4 No.
25/31.5MVA Transformer, 1 No. bus-coupler and 5 nos. feeder bays. Space for
future bays shall be kept in GIS hall for adding 2 no. future bays and jointing plugs
required for connecting GIS of different makes. The SF6 Gas Insulated Switchgear
rated for 66kV, 3-phase, 50Hz, 31.5kA fault level shall be of the indoor metal-enclosed
type, comprising of following items.
Unit Qty
1 72.5kV, 1250A, single 3– or three 1–, SF6 gas Set 2
insulated, metal enclosed bus bars arrangement,
consisting of 1250A single 3– or three 1– SF6 gas
insulated switchgears, each Bus Bar comprising of :-
i) Bus bar enclosures running through the length of the
switchgear to interconnect each of the circuit breaker
bay modules in double main bus system.
ii) Three, 2-core, single phase or single 3- voltage
transformers/ PTs.
iii) 1250A, One 3– or three 1–, single pole, group
operated isolator/disconnector and one, 3– or three
1–, single pole, group operated earthing switch with
manual and motor driven operating mechanisms.
iv) 1250A, One high speed fault make 3– or three 1–,
single pole, group operated earthing switches,
complete with manual and motor driven operating
mechanisms.
v) Each GIS compartment with gas monitoring device,
pressure switch etc. as required.
vi) Terminal boxes/ Local Control Cubicle.
vii) Interconnecting wiring/ piping.
viii) Grounding, support structures and platforms.
2 72.5kV, 800A, single 3– or three 1–, Bus coupler Set 1
bay module, consisting of 800A single 3– or three
1 – SF6 gas insulated switchgears, comprising of:
i) 800A, One 3– or three 1–, SF6 gas insulated circuit
breaker, complete with operating mechanism.
ii) Three,3-core,single phase current transformers (600-
300-150/1-1-1A)
iii) Two sets of isolator/disconnector switches each of
800A, One 3– or three 1–, single pole, group operated
isolator/disconnector switches each with 3– or three 1-
, single pole, group operated earthing switch and
complete with manual and motor driven operating
mechanisms.
iv) Each GIS compartment with gas monitoring device,
pressure switch etc. as required.
v) Terminal boxes/ Local Control Cubicle.
vi) Interconnecting wiring/ piping.
vii) Grounding, support structures and platforms.
3 72.5kV, 800A, single 3– or three 1–, Transmission SET 5
line feeder circuit breaker bay modules, consisting
of 800A single 3– or three 1– SF6 gas insulated
switchgears, each comprising of:-
i) 800A, One 3 –  or three 1 –, SF6 gas insulated circuit
breaker, complete with operating mechanism for
outgoing feeder.
ii) Three, 66kV LAs (LAs should not be provided in GIS)
and Voltage detectors /sensors (Output shall be taken
to LCC)
iii) Three, 3-core, single phase current transformers (600-
300-150/1-1-1A)
iv) 800A, One 3– or three 1–, single pole, group operated
isolator/disconnector without earthing switch,
complete with manual and motor driven operating
14
mechanisms.
v) 800A, One 3– or three 1–, single pole, group operated
isolator/disconnector with one, 3– or three 1–,
single pole, group operated earthing switch, complete
with manual and motor driven operating mechanisms.
vi) 800A, One 3– or three 1–, single pole, group operated
isolator/disconnector with one normal and one high
speed fault make 3– or three 1–, single pole, group
operated earthing switches, complete with manual and
motor driven operating mechanisms.
vii) Each GIS compartment with gas monitoring device,
pressure switch etc. as required.
viii) Terminal boxes/ Local Control Cubicle.
ix) Interconnecting wiring/ piping.
x) Grounding, support structures and platforms.
4. 72.5kV, 400A, single 3– or three 1–, Transformer Set 4
feeder circuit breaker bay modules, consisting of
400A single 3 –  or three 1 – SF6 gas insulated
switchgears, for 66/11kV transformer, each
comprising of: -
i) One 3– or three 1–, SF6 gas insulated circuit
breaker, complete with operating mechanism for
incomer bay from 66/11kV transformer.
ii) Three, 3-core, single phase current transformers (300-
150/0.577-1-1A).
iii) 400A, One 3– or three 1–, single pole, group operated
isolator/disconnector without earthing switch,
complete with manual and motor driven operating
mechanisms.
iv) 400A, One 3– or three 1–, single pole, group operated
isolator/disconnector with one, 3– or three 1–,
single pole, group operated earthing switch, complete
with manual and motor driven operating mechanisms.
v) 400A, One 3– or three 1–, single pole, group operated
isolator/disconnector with two earthing switches
each comprising of one 3– or three 1-, single pole,
group operated earthing switches complete with manual
and motor driven operating mechanisms.
vi) Each GIS compartment with gas monitoring device,
pressure switch etc. as required.
vii) Local Control Cubicle.
viii) Interconnecting wiring/ piping.
ix) Grounding, support structures and platforms.
5 66kV XLPE copper Cable 1C 400mm2 (including one Mtr. 1056
no. spare cable per Transformer bay) coated with fire (Appox.)
retardant Paint for connecting 66kV side of 66/11kV
transformer with GIS with termination kit for both end
for all four cables.
Total No. of 66kV Termination Kits (T/F=4 x
Cables/TF=4 x 2 = 32 Nos.)
6 66kV XLPE Aluminum Cable 1C 1200mm2 (including Mtr. 4400
one no. spare cable per line bay) coated with fire (Appox.)
retardant Paint for connecting 66kV line with GIS with
termination kit for both end for all four cables.
Total No. of 66kV Termination Kits (Line Bay= 5 x
Cables/Line=4 x 4 = 80 Nos.)
7 Ventilation System (AHU) to accommodate in designated No. 1
room in GIS Hall as per Annexure-V as it is already an
integral part of the ventilation system.

Note: 66kV XLPE Aluminium cable 1200mm2 (4 single core cable for each circuit including one
no. spare cable) from each line (i.e. from Tower where conductor is terminated) will be
terminated in the GIS through Line CVTs as shown in GELO and the GIS should be suitable for
termination of the same. The above line cable & line termination kits are in the scope of the
substation bidder & will be supply/erected by the substation bidder. The substation bidder and
GIS panel manufacturer should be present during the termination of line cable to the GIS and
they will ensure/certify the safe/correct termination of the cable to the GIS.

15
66KV GIS Mehrauli Road, Gurugram

ANNEXURE-B1
BILL OF QUANTITIES
Sr. No. DESCRIPTION UNIT Qty.
1. 25/31.5MVA, 66/11 kV Power Transformer along with No. 4
10% extra oil (Transformers to be provided by HVPNL).
2. 220V 100 AH San Tubular Battery. Set 1
3. 66 kV Surge Arrestor. (For Power Transformers) No. 12
66kv Surge Arrestor (Polymer Type), (For incoming lines No. 15
to be installed at Tower where line conductor is
terminated)
4. 11kV Surge Arrestor No. 12
5. 66 kV NCT For 66/11kV T/F (300-200-250/1 A) (To be No. 4
provided by HVPNL)
6. 11 kV NCT For 66/11T/F (1800-900/5 A) (To be No. 4
provided by HVPNL)
7. 66kV C&R Panels with SAS
i Line Protection & Circuit breaker Panel (without auto Set 5
reclose).
ii T/F Protection & Circuit breaker Panel (without auto Set 4
reclose).
iii Bus Coupler Protection & Circuit breaker Panel (without Set 1
auto reclose).
8. 11 kV 15 Panel Board (2000A) with one SEM on each T/F Set 4
I/C Panel (including one no. bus sectionalizer panel).
9. 11 kV Power Cable XLPE 1C x1000mm2 coated with fire Mtr. 2400
retardant paint for T/F to 11kV incomer with termination
kit for both ends (4 runs per phase for each transformer
allocating them 2 runs per phase for each 11kV I/C).
10. 11 kV Power Cable XLPE 3C x 400sq mm coated with Mtr. 200
fire retardant Paint for Capacitor Bank with termination
kit for both ends.
11. 11 kV Power Cable XLPE 3C x 50 sq. mm coated with Mtr. 50
fire retardant Paint for station T/F with termination kit
for both ends.
12. 9000KVAR 12.65 kV Capacitor Bank with 11 kV L&E, Set 4
RVTs and 11KV LA, reactor as per technical specification.
13. 220 V 20/30A SMPS Battery charger. Set 1

14. 220 V 100 AH D.C.D.B. Set 1

15. 415 V LT AC Distribution Board 300 A. No. 1

16. 11/0.4 kV Station T/F 200 KVA. No. 1

17. EOT-Crane as per clause 1.11.7 Section-1 and Clause No. 1


29.0 of GIS Specification.

18. 1.1 kV Copper Control Cable armoured (FRLS) for 66kV Lot Lot
bays & 11kV side of sizes 7CX4mm2, 2CX4mm2,
4CX4mm2, 2CX6mm2, 16CX2.5mm2, 10CX2.5mm2,
7CX2.5mm2, 3CX2.5mm2 etc. including junction box (as
per Section-5 of copper control cable specification and
Section-7 of Switchyard Erection).
19. 650/1100 Volts 3.5 core 240 mm2 aluminium power Lot Lot
cable (FRLS) from Aux. T/F to ACDB.
20. 650/1100 Volt 3.5 core 70 mm2 aluminium cable (FRLS) Lot Lot
for oil filtration set.
21. 650/1100 Volt 4 core 16 mm2 armoured (FRLS) copper Lot Lot

16
power cable for MLDB etc. and other cable required as
per contract for 66kV bays.
22. Grounding system of the substation. Earthing Mat Mtr. 3114.5
Material. The earth mat will be designed/quoted for soil sq
resistivity of 50m. In case soil resistivity is more than
50m then the earth mat will be designed for actual soil
resistivity. The payment of extra material to be used for
earth mat shall be made on pro rata basis. The
approximate area of earth mat to be laid is given in the
corresponding columns of the substations. However, item
will remain a Lot item (calculations may be made
considering fault/shock duration of 1 sec).
23. Computer system

a. Computer system (SFF) with Intel core i5, 9th No 1


generation processor, 8GB RAM, 1 TB HDD, 19.5”
Display with UPS.
b. Mono chrome Multifunctional printer, A-4, 25PPM, No 1
Wi-Fi.
24. Fire Fighting equipment’s as per section-6

a) 22.5 Kg Capacity FE CO2 type, Trolley Mounted No 4


b) 25 Kg Capacity FE DCP type, Trolley Mounted No 4
c) DCP 10 Kg Capacity, Wall mounted No 4
d) FE CO2 6.5 Kg Capacity, Wall mounted No 4
e) DCP 5 Kg Capacity, Wall mounted No 4
f) Foam Type 9 Litre Capacity, Wall mounted No 4
g) Water CO2 9 Litre Wall mounted No 2
h) Fire Buckets (12 Nos. with stand in one set) Set 4
25. Complete lightning of control room building, switch yard area, road and
street as per section-7 of the specification.
a) Supply and installation of 2 fittings of 240W LED lamps Set 12
with all accessories for Complete lighting of outdoor
Switch yard area as per clause 16.0 of section 7 of the
specifications.
b) Supply and installation of 35W LED tube on tubular steel No. 12
poles along with the boundary wall at a distance of 30
meter as per as per clause 16.0 of section 7 of the
specification
c) Complete lighting of road and street by providing 90W No. 17
LED lamps on tubular steel poles at a distance of
15meter along the roads and streets as per as per clause
16.0 of section 7 of the specification.
d) Supply and installation of post top lantern 40W LED No. 4
Lamps with all complete accessories at the entrance
gate of sub-station.
e) Supply and installation of 40W LED Lamps with all No. 12
complete accessories on corners of control room
building.
26. High wall type split AC unit of 2 Ton capacity for SCADA No. 4
room & C&R Panel room (as per technical specification).
27. Complete Substation automation system of 66/11kV Lot Lot
substations including hardware (along with transducers)
along with associated equipment for the bays (bay as
defined in the technical specification, section- sub-
station automation system) as per technical specification
Name of 66kv Bay Present Future
66kv T/F Bay 4 2 Future Line

17
66kv Line Bay 5 or T/F Bay
66kv Bus Coupler 1
Note: signals from protection relays in 11kV incomer
would also be wired to substation automation system
(SAS)
28. Time synchronization equipment. No. 1
29. Testing of IUM System at NABL accredited lab Lot Lot

30. Anti-Fire wall No. 3

31. 66kV CVT No. 15

Note: The quantities given are approx. and for evaluation purpose, however, the
payment shall be made as per actual on the basis of unit price. Any item required to
complete the scope of work & successful commissioning of substation/bay as defined
in Section-1, however not specifically mentioned in BOQ shall be provided by the
bidder without any additional cost implication, if any clarification is required for any
such items shall be obtained before the submission of bids.

18
66KV GIS Mehrauli Road, Gurugram
ANNEXURE–C1

Sr. DESCRIPTION UNIT Quantity


No
1 66 kV bolted type single suspension string No. 12
assembly with 6 numbers ANTI FOG type disc
insulators (E&M strength 9000 kg) per string with
all hardware accessories including ball & socket
connections and suspension clamp set suitable for
Zebra Conductor. Alternatively the bidder may quote
silicon polymer composite insulator string in place
of Disc Insulators
2 Bolted type 11kV Single tension string assembly No. 24
with 3 numbers Anti FOG type disc insulators
(E&M strength 9000 kg) per string with all
hardware accessories including ball & socket
connections and tension clamp sets suitable for
Twin tarantulla Conductor. Alternatively the bidder
may quote silicon polymer composite insulator
string in place of Disc Insulators
3 Boltless C-Type Wedge connectors matching with Lot Lot
conductor size.
4 Spacers suitable for Twin Tarantulla conductor Lot Lot
5 Copper lugs glands, PVC ferrules for control L/S L/S
cabling.
6 Fibre cleats, Aluminium clamps, bolts, nuts, L/S L/S
washers etc for fixing control cables in trenches
7 Galvanized iron perforated tray with side coupler L/S L/S
plate bolts, nuts, washers and clamps etc. of size
75x25x2 mm, 150x25x2mm, 100x25x2mm etc. &
G.I. Conduits of 50mm/100mm dia from
equipment to main trench as per Section-7,
Switchyard erection.
Painted lattice type steel trays of adequate size as L/S L/S
per site requirement for laying control and power
cables from panels to GIS & Transformers and for
11kV Outgoing cables & other cables identified as
per site requirement confirming to Section-7 & 9.
8 Twin Tarantulla Conductor (approx.) Mtr. 216
9 Zebra Conductor (approx.) Mtr. 108
10 7/3.15 Earth wire. Lot Lot
11 U-bolt 20mm dia. Lot Lot

The quantities given in Annexure C-I is approx. and for evaluation purpose,
however, the payment shall be made as per actual on the basis of unit
price/Lot.

19
ANNEXURE D1
66KV GIS Mehrauli Road, Gurugram

Schedules of items for associated steel structure works to be quoted for each
substation as applicable. The bidder is required to estimate the quantities and
furnish the unit rate for each item/ works and the total price for each item in the bid
proposal sheets. The list may not be exhaustive, and the bidder may modify/ append
the same as required.
Sr. DESCRIPTION UNIT Quantity
No
Item for associated structure work
‘Lattice type steel structure for 66KV GIS Mehrauli Road, Gurugram.
Supply of material, preparation of fabrication drawing, galvanizing and
delivery of lattice type steel structure for tower and beams for 66/11kV
switchyard fabricated from steel conforming to IS: 2062 including nuts-
bolts gusset plates foundation bolts and other accessories as per drawings
supplied by the owner.
1. Main S/Stn. Tower and beam
i Tower type CT-4 No. 5
ii Tower type CT-5 No. 0
iii Beam type CB-6 No. 4
iv Tower type DT-2 No. 4
v Tower type DT-3 No. 4
vi Beam type DB-2X No. 4
2. Equipment Supporting Structure
i 66 kV NCT & 11kV NCT combined No. 4
structure Drg. No. HTD/ST-149
ii 66 kV Surge Arrestor Drg. No. HTD/ST- No. 12
89R
iii 11 kV NCT Drg. No. HTD/ST-88 (if No. 4
required)
iv 66kV Cable support structure of No. 56
galvanized iron along with foundation to
be designed by bidder as per site
requirement/size of cable

Note: The quantity given above are as approximate in case of variation of quantities at
the time of detailed engineering, actual quantities shall be payable as per quoted price.

20
ANNEXURE D2
66KV GIS Mehrauli Road, Gurugram

Schedules of items to be dismantled at 66KV AIS Mehrauli Road for construction of


new 66KV GIS Mehrauli Road. The bidder is required to estimate the quantities and
furnish the unit rate for each item/ works and the total price for each item in the bid
proposal sheets. The list may not be exhaustive, and the bidder may modify/ append
the same as required.
Sr. DESCRIPTION UNIT Quantity
No.
1st Phase 2nd Phase Total
1) 66kV Tower Type CT-4 No. 3 2 5
2) 66kV Tower Type CT-5 No. 3 2 5
3) 66kV Beam Type CB-6 No. 5 2 7
4) 66kV Tower Type CT-6 No. 2 - 2
5) 66kV Tower Type CT-8 No. 4 - 4
6) 66kV Beam Type CB-7 No. 4 - 4
7) 33kV Tower Type DT-3 No. 2 - 2
8) 33kV Beam Type DB-2X No. 1 - 1
9) 66kV Isolator with structure No. 2 - 2
10) 66KV SF6 Breaker No. 1 8 9
11) 66kV CT with Structure No. 3 9 12
12) 66kV LA with Structure No. 3 9 12
13) 66/11kV Transformer with No. 1 3 4
MK
14) 11KV Combined CT/PT Unit No. 1 3 4
with Structure
15) 66kV Line MKs No. - 7 7
16) 66kV L&E No. - 5 5
17) 11kV Capacitor 3MVAR with No. - 3 3
Structure
18) 66kV CT No. - 15 15
19) 66kV LA No. - 15 15
20) 66kV Isolator No. - 16 16
21) 11kV Capacitor 3MVAR APFC No. - 1 1
22) ACSR Conductor, Hardware LOT
fittings etc.

Note: The quantity given above are as approximate in case of variation of quantities at
the time of detailed engineering, actual quantities shall be payable as per quoted price.

The shifting/transportation of dismantled equipment & structures to DD Store/Site


Store (i.e. as per directions of TS wing) shall be in scope of bidder.

21
ANNEXURE-E1
MAINTENANCE EQUIPMENT & MANDATORY SPARES AT 66KV GIS Mehrauli Road,
Gurugram

MAINTENANCE EQUIPMENT
Sr. No. Description Unit Quantity
i. Portable circuit breaker operation analyzer. Set 1

ii. Digital Micro-Ohm meter for contact resistance Set 1


measurement Ranges (0-100 ohm)
(0-1 milliohm)
(0-10 milliohm).
iii. Dew Point meter Set 1
iv. Portable partial discharge monitoring system for Set 1
GIS.
v. SF-6 Gas filling and evacuating plant Set 1
vi. SF-6 Gas leak detector (Portable) Set 1
vii. Tools for gas handling Set 1
viii. LT DC Leakage detector from control cabinets and No. 1
LT cables

Spares (Mandatory)

Sr. Description Unit Quantity


No.

1 General
1.1 Complete GIS modules, along with enclosure, all
active parts such as conductor, conductor joints, Set 1
shields, end covers etc. for each type of
Bus Bar Sections (including Bus Bar
Interconnection Modules)
Bus Ducts Sections (including
Compensators/expansion joints/bellows)
Bends
SF6/Air Bushing.
Oil/SF6 Bushing
Cable Termination kit

1.2 SF6 gas Pressure Relief Device assembly of each Set 1


type
1.3 SF6 Pressure gauge cum switch /Density Set 5
monitors and pressure switch as applicable, of
each type
1.4 Coupling device for pressure gauge cum switch for Set 2
connecting Gas handling plant of each type
1.5 Rubber Gaskets, “O” Rings and Seals for SF6 gas Set 5
for GIS enclosures of each type
1.6 Molecular filter for SF6 gas with filter bags (10 % Set 1
of total weight)
1.7 Control Valves for SF6 gas of each type Set 3
1.8 SF6 gas (20 % of total gas quantity) Lot 1
1.9 Pipe length (Copper or Steel as applicable) for SF6 Set 2
Circuit of each type (if applicable)
1.10 Locking device to keep the Dis-connectors Set 2
(Isolators) and Earthing/Fast Earthing switches in
close or open position in case of removal of the
driving Mechanism
1.11 UHF PD Sensors of each type along with BNC Nos. 5
Connector

22
1.12 Support Insulators (gas through) of each type Nos. 10
(complete with metal ring etc.)
1.13 Gas Barriers of each type (complete with metal Nos. 10
ring etc.)
1.14 SF6 to air bushing of each type complete in all No. 2
respect
2 SF6 CIRCUIT BREAKER:
2.1 Complete Circuit Breaker (Three Phase) with Set 1
interrupter, main circuit, enclosure and
Marshalling Box with operating mechanism to
enable one to one replacement of applicable
type of CB by spare. (if applicable)
2.3 Fixed, moving and arcing contacts including Set 1
insulating nozzles of each type (for Main
Chamber & PIR Chamber as applicable)
2.4 Trip coil assembly with resistor as applicable Set 3
2.5 Closing coil assembly with resistor as Set 3
applicable
2.6 Relays, Power contactors, push buttons, timers Set 1
& MCBs etc. of each type
2.7 Auxiliary switch assembly of each type Set 3
2.8 Operation Counter Set 3
2.9 Windoscope / Observing window of each type Set 2
2.11 For Hydraulic Operated Mechanism, if applicable
2.11.1 Hydraulic operating mechanism with drive Set 3
motor of each type
2. Ferrules, joints and couplings of each type Set 3
11.2
2. Hydraulic filter of each type Set 3
11.3
2. Hose pipe of each type Set 3
11.4
2. N2 Accumulator of each type Set 3
11.5
2. Valves of each type Set 3
11.6
2. Pipe length (copper & steel) of each size & type Set 3
11.7
2. Pressure switches of each type Set 3
11.8
2. Pressure gauge with coupling device of each Set 3
11.9 type
2.11.1 Hydraulic oil (20% of total Oil quantity) Set 1
0
2.11.1 Pressure Relief Device of each type Set 3
1
2.12 For Spring Operated Mechanism, if applicable
2.12.1 Complete Spring Operating Mechanism Set 3
including charging
mechanism etc. of each type
2.12.2 Spring Charging Motor Nos. 2
2.13 For Hydraulic-Spring Operated Mechanism, if applicable
2.13.1 Complete Hydraulic-Spring Operating Set 3
Mechanism including charging mechanism etc.
of each type
2.13.2 Spring Charging Motor Nos. 2
2.13.3 Pressure switches of each type Set 3
2.13.4 Pressure gauge with coupling device of each Set 3
type

23
3 Disconnector Switches/Earthing Switches:
3.1 Complete set of 3-phase dis-connector of each Set 1
type including main
circuit, enclosure, driving mechanism and
support Insulator etc. to enable complete one to
one replacement of all applicable type of
Isolator by spare
3.2 Complete set of 3-phase Maintenance Earthing Set 1
switch of each type, including main circuit,
enclosure, driving mechanism and
support Insulator etc. to enable complete one to
one
replacement of all applicable type of Earth
Switch by spare
3.3 Complete set of 3-phase Fast Earthing switch of Set 1
each type,
including main circuit, enclosure, driving
mechanism and support Insulator etc. to
enable complete one to one replacement of all
applicable type of Earth Switch by spare (if
applicable)
3.4 Copper contact fingers & corona shield for dis- Set 1
connector male &
female contact–for one complete (3-phase) dis-
connector of each type
3.5 Copper contact fingers & corona shield for Set 1
Maintenance Earthing
switch male & female contacts, for one
complete (3- phase) earthing switch of each
type
3.6 Copper contact fingers & corona shield for Fast Set 1
Earthing switch
male & female contacts, for one complete (3-
phase) earthing switch of each type (if
applicable)
3.7 Open/Close contactor assembly, timers, key interlock,
interlocking coils, relays, push buttons, indicating lamps,
Power contactors, resistors, fuses, MCBs & drive control cards
etc. one of each type for one complete MOM box
3.7.1 For Disconnector Set 2
3.7.2 For Maintenance Earth switch Set 2
3.7.3 For Fast Earthing Switch (if applicable) Set 2
3.8 Limit switches and Aux. Switches for one complete MOM Box
3.8.1 For Disconnector Set 2
3.8.2 For Maintenance earth switch Set 2
3.8.3 For Fast Earthing Switch (if applicable) Set 2
3.9 Drive Mechanism of each type
3.9.1 For Disconnector Set 2

3.9.2 For Maintenance earth switch Set 2


3.9.3 For Fast Earthing Switch (if applicable) Set 2
3.10 Motor for Drive Mechanism of each type
3.10.1 For Disconnector Set 3
3.10.2 For Maintenance earth switch Set 3
3.10.3 For Fast Earthing Switch (if applicable) Set 3
4 CURRENT TRANSFORMER
4.1 Complete CT of each type and rating as Nos. 2
supplied with enclosure
and primary conductors to enable one to one

24
replacement of all applicable type/rating of CT
by spare

5 Voltage Transformer
5.1 Complete PT of each type with enclosure to No. 1
enable one to one
replacement of all applicable type/rating of VT
by spare (if applicable)
6 SURGE ARRESTOR
6.1 Complete Gas insulated Surge arrester of each No. 1
type and ratings
with enclosure and insulator (if applicable)
6.2 Surge counter/ monitor of each type (if No. 2
applicable)
7 Local Control Cubicle (LCC)

7.1 Aux. relays, Contactors, Push Buttons, Set 5


Switches, Lamps,
Annunciation Windows, MCB, Fuses, Timers,
Terminal Blocks etc. of each type & rating

Note:
1. Any equipment which is not supplied as main equipment, mandatory spare for
that is not envisaged.
2. Any equipment specified in Technical Specification with different types (including
different current ratings), if the contractor has supplied higher rating equipment
against such different types of equipment, mandatory spare for higher rating only
shall be acceptable.
3. All the rubber spare parts shall be vacuum impregnate.

25