00 31-May-18
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Soil Improvement Vibro Replacement (Stone Columns) Pre-
SAIC-A-1013 15-Jul-18 CIVIL-
Installation (Survey) and Installation Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Major Plant facilities will be referenced to a local plant grid which in turn is SAES-A-100
A2
tied into the UTM coordinate system. Sec. 4.3
Land elevations are referenced to Mean Sea Level (MSL) vertical datum SAES-A-100
A4
for all. Sec. 5.2
ACI 117
Tolerance for deviation of location shall be 1/24 of diameter but not more
A6 Sec. 3.2.2.1
than 3 in (75 mm).
ACI 117
B1 Tolerances for the depth of Stone Columns shall be - 2 in. & + 6 in.
Sec. 5.2.1
Working Levels (W.L.) have been established before any Soil SAES-A-100/ IFC
B5
Improvement Works are commenced. Drawings
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-100 - Survey Coordinates, Datum's and Data Formats, 19 February 2018
2- Approved Method Statement for Soil Improvement
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: