Design Guidelines For Foundation of WTG
Design Guidelines For Foundation of WTG
PAGINA - PAGE
Engineering 2 di/of 50
TABLE OF CONTENT
1. INTRODUCTION ...................................................................................................4
2. DEFINITIONS AND ACRONYMS ......................................................................4
3. REFERENCES ......................................................................................................4
4. UNITS OF MEASURE ..........................................................................................4
5. GEOTECHNICAL STUDIES ................................................................................5
5.1. Geological report........................................................................................5
5.2. Geotechnical investigation plan...........................................................5
5.2.1. Site tests ................................................................................................. 6
5.2.2. Laboratory tests ..................................................................................... 8
5.3. Soil classification and geotechnical characteristics.........................8
5.4. Pile design ................................................................................................9
6. MATERIALS .......................................................................................................10
6.1. Material safety factors .........................................................................10
6.2. Concrete .................................................................................................10
6.2.1. Cement ...................................................................................................10
6.2.2. Admixtures .............................................................................................10
6.2.3. Aggregates .............................................................................................11
6.2.4. Environmental conditions .....................................................................11
6.2.5. Slump classes ........................................................................................11
6.3. Reinforcing Steel ..................................................................................12
6.4. Anchor bolts and embedded ring.......................................................12
6.5. Grout .......................................................................................................12
6.6. Backfilling soil .......................................................................................13
7. LOADS ...............................................................................................................13
7.1. Wind load ...............................................................................................14
7.1.1. Design Load Cases as per IEC-EN 61400 ............................................14
7.1.2. Reference Wind Speed ..........................................................................17
7.2. Seismic action .......................................................................................17
7.3. Load combinations ...............................................................................17
8. FOUNDATION LAYOUT ...................................................................................19
8.1. Forecasted quantities for direct foundations ..................................19
8.2. Shape of shallow foundation ..............................................................19
8.3. Deep foundations layout .....................................................................20
8.4. Reinforcement layout ..........................................................................20
8.5. Conduits for cables ...............................................................................22
8.6. Anchor bolt cage ...................................................................................24
9. DESIGN CHECKS ..............................................................................................25
CODICE – CODE
PAGINA - PAGE
Engineering 3 di/of 50
ANNEXES
PAGINA - PAGE
Engineering 4 di/of 50
1. INTRODUCTION
The document provides the guidelines for the design and the construction of the foundations for Wind
Turbine Generators.
The requirements and guidelines reported in this document shall be considered as a minimum standard
to be satisfied. At the same time, local codes shall be taken into consideration and the most stringent
requirements would govern the design.
In order to overcome a lack of quality in the procedures of testing and placing different materials, the
EN, ACI, ASTM or BS code requirements are here shown and shall be applied where local codes are not
sufficiently clear to establish an acceptable level of design and quality of the work execution.
Minimum analysis to be performed, suggested criteria for the geotechnical and structural checks are
reported and shall be considered when dealing with the common design. Specific consideration on the
optimized design is also reported, summarizing the results of previous studies and underlining the
advantages of circular shape.
Finally, work execution procedures and report/drawing layouts are described. The scope is to ensure a
quality product and correct execution of works based on the experience gained in similar projects
3. REFERENCES
For National and International standards and codes, for reference books and reports see Annex A.
This design criteria specification is referred to wind farm plants to be designed and built in different
regions. The codes herein considered aim to cover the international requirements well known and used
in common practice (European and American Codes have been considered and widely mentioned in the
text). Additional local codes shall be considered during the design, the execution and the testing of the
foundation. Their requirements shall be followed if they are more stringent than those stated in this
document.
4. UNITS OF MEASURE
All the documents, reports and drawings shall use the following unit of measure:
• force kN
CODICE – CODE
PAGINA - PAGE
Engineering 5 di/of 50
• moment kNm
• mass density kg/m3
• weight density kN/m3
• stress, pressure, strength and stiffness MPa (N/mm2)
• coefficient of permeability m/s
• coefficient of consolidation m/s2
• temperature °C (Celsius)
Other quantities, not explicitly mentioned here, shall be expressed in accordance with the international
system of units (SI).
5. GEOTECHNICAL STUDIES
The foundations of WTG fall in Category 2 as defined in EN 1997-1, since the expected dimensions,
loads and soil conditions can be considered conventional. Foundation may fall in Category 3 (see
reference) if unusual ground properties are encountered, or applied loads are exceptional, or the area is
highly seismic, or in other similar circumstances. Efforts to be made in conducting the geotechnical
investigation are proportional to the category level.
PAGINA - PAGE
Engineering 6 di/of 50
available geological data shall be done and the main characteristics shall be reported in the
investigation plan.
PAGINA - PAGE
Engineering 7 di/of 50
PAGINA - PAGE
Engineering 8 di/of 50
During the final investigation, the complete investigation (geophysical tests, direct investigations, with
the collection of samples, and penetrometer tests) shall be performed for each WTG foundation.
PAGINA - PAGE
Engineering 9 di/of 50
PAGINA - PAGE
Engineering 10 di/of 50
designed for the foundations; positions where soil has the lowest mechanical characteristics shall be
tested. At least two trial pile tests shall be performed in a site. The Axial test can be executed only after
the concrete has reached its design strength and shall be carried on until the predicted pile ultimate
load or significant settlements are reached.
6. MATERIALS
The properties of construction material shall be shown on the calculation report and on the construction
drawings. The following sections are listing the minimum properties of materials and the minimum
safety factors to be applied.
obtain the design values: gC = 1,5 for concrete; gs = 1,15 for reinforcing steel and gs = 1,25 for anchor
6.2. Concrete
The characteristic cylindrical compressive strength, according to EN 196-1/EN 206-1/ASTM C39 of
concrete at 28 days shall normally be:
fck
[N/mm2]
12 fill and lean concrete
25 cast in situ piles
30 pedestal, raft
Table 3 minimum concrete strength
Before starting the execution of works, the proposed composition of concrete mix shall be tested, in
order to verify the design strength and other requirements. If local regulations are not available, the
requirements of EN 12390-1 and EN 12390-2 (or of ASTM C31 and ASTM C192) shall be followed for
the preparation, shape and curing of the samples. EN 12390-3 describes the procedures for the
strength evaluation. Equivalent standards, such as ASTM C39 may be used.
6.2.1. Cement
Cement shall be as defined in EN 197-1. Additional constituents may be present if particular
performances are required.
6.2.2. Admixtures
Admixtures may be used to improve the concrete performances. Usually admixtures are added to
accelerate or delay the setting and to improve the workability or the durability of concrete. The
admixture shall comply with UNI EN 934-2 / ASTM C494
Fly ash (conforming to EN 450 / ASTM C618) and silica fume (conforming to EN 13263 / ASTM C1240)
may be used if high strength concrete is necessary or particularly adverse environmental conditions are
expected.
CODICE – CODE
PAGINA - PAGE
Engineering 11 di/of 50
6.2.3. Aggregates
Aggregates to be used for concrete shall be in compliance with UNI EN 12620 and tested according to
EN 933-1. Due to the high concentration of reinforcing bars and steel inserts, the maximum allowable
diameter of aggregates should generally be 20-25mm. The designer shall evaluate the concentration of
reinforcement bars and determine the maximum diameter in order to avoid segregation of concrete.
In order to avoid concrete segregation in congested areas, the suitable space between bars, conduits,
connections etc. shall be properly evaluated during the design phase. Particular care shall be taken in
evaluating the maximum aggregate diameter for the pedestal and the areas around the connection.
Once the value of h has been measured, five classes can be defined as per UNI EN 206-1:
CODICE – CODE
PAGINA - PAGE
Engineering 12 di/of 50
Class h (mm)
S1 10<h<40
S2 50<h<90
S3 100<h<150
S4 160<h<210
S5 h>210
Table 4 Slump classes
The slump class shall be stated on construction drawings and checked before starting the concrete
pouring activities at site. Generally class S3 is required but a higher class may be required by the
designer if particular circumstances are foreseen. For example, a higher slump class shall be required
for more congested area, such as the bottom part of the raft, where the bottom reinforcement and the
vertical bars may require a more fluid concrete (see Figure 3); lower slump classes are adequate for the
raft sloped portion.
6.5. Grout
High strength non-shrinking grout shall be used for the connection of the steel plate of the tower to the
reinforced concrete foundation.
The grout compressive strength shall be at least 80 N/mm2 tested as per EN 196-1. Adequate bonding
to concrete shall be assured and tested in accordance to EN 1542; the grout shall have high fatigue
resistance (due to the presence of dynamic actions) and shall be suitable for the thickness to be filled
and the expected temperatures during the execution of work and operating life. Cementitious or epoxy
grouts may be used (such as Basf Masterflow).
CODICE – CODE
PAGINA - PAGE
Engineering 13 di/of 50
The designer shall define (and report on the construction drawings) the minimum grout resistance to be
reached before tensioning the anchor bolts
Where a proper protection to the erosion and the stability of the backfilling can be assured over the
whole service life of the plant, its contribution to the foundation stability may be considered, only if
approved by EGP. The unfavorable effects of the backfill placed above the existing grade shall always be
considered.
The designer shall define and properly report on the construction drawings the design limits and the
tests to be performed (site and laboratory tests) to verify those limits.
7. LOADS
In order to define the actions on the WTG and transmitted to its foundation, all the relevant site
parameters shall be identified.
The main action here considered is the wind load (see section 7.1). The wind velocity may be averaged
CODICE – CODE
PAGINA - PAGE
Engineering 14 di/of 50
in different ways according to the applied code. The reference value, to which the WTG is designed, is
defined as the maximum speed averaged over 10 minutes with a recurrence period of 50 years
expected at the hub height [IEC-EN 61400, latest edition].
The site parameters to define the snow and earthquake loads must be identified as well. The presence
of ground water shall be adequately investigated and, where necessary, the buoyancy effects shall be
taken into account.
PAGINA - PAGE
Engineering 15 di/of 50
PAGINA - PAGE
Engineering 16 di/of 50
PAGINA - PAGE
Engineering 17 di/of 50
PAGINA - PAGE
Engineering 18 di/of 50
Load factors for wind loads reported in the IEC shall be considered a minimum requirement. The
designer is responsible to verify if more stringent requirements found in the local codes are applicable
for the WTG foundation design. In any case, the designer shall consider the load combinations in
accordance with the suggestion of [AWEA-ASCE Recommended Practice for Compliance of Large Land-
based Wind Turbine Support Structures]:
the document deals with the American codes ASCE 7 and ACI 318, but the same assumptions can be
extended to other local codes.
The calculation report shall also include the seismic load combinations. The seismic loads shall be given
as per section 7.2. The relevant load combinations shall follow the recommendations given in section
11.6 of IEC-EN-61400 shall be followed. The seismic load shall be combined with an operational wind
load equal to the higher of:
a) loads during normal power production by averaging over lifetime;
b) loads during emergency shutdown for a wind speed selected so that the loads prior to the
shutdown are equal to those obtained as per a)
Furthermore, IEC-EN-61400 states that the load factor to be used for all load components shall be 1.0.
The combination of design seismic loads and factored extreme wind loads shall not be performed.
Serviceability Limit State checks shall be performed using the Normal Operational Loads and Fatigue
loads reported in the documentation provided by the WTG manufacturer.
CODICE – CODE
PAGINA - PAGE
Engineering 19 di/of 50
8. FOUNDATION LAYOUT
PAGINA - PAGE
Engineering 20 di/of 50
Based on previous experience, amax should be limited to 25% for the feasibility of concrete pouring.
The pedestal is higher on fine and coarse soils, Figure 8, while a more economical design leads to lower
values for foundation on rocks, Figure 7.
PAGINA - PAGE
Engineering 21 di/of 50
PAGINA - PAGE
Engineering 22 di/of 50
To facilitate the pouring of concrete, the use of multiple layers of bars (bundles bars), as per ACI 318
and EN 1992-1, is suggested; additionally the radial reinforcements may have different lengths and
may be bent in a staggered way. See the figure below for example.
Construction phases shall be considered in the drawings: to allow the proper pouring of concrete,
adequate space for a flexible pressure hose (150÷200 mm of diameter) shall be left in between the
reinforcing bars, at least at the locations highlighted in Figure 12.
PAGINA - PAGE
Engineering 23 di/of 50
PAGINA - PAGE
Engineering 24 di/of 50
a) b) c)
Figure 17 a) tensile behavior of concrete; b) compressive behavior of concrete;
c) symmetric behavior of steel
• the inclusion of reinforcement bars in the FEM is not generally required, but steel bars and steel
inserts shall be properly modeled if the simplified model (without reinforcing bars) will not
reproduce the stress path in a proper way, at least in the area around the conduits path.
PAGINA - PAGE
Engineering 25 di/of 50
9. DESIGN CHECKS
PAGINA - PAGE
Engineering 26 di/of 50
(1 − υ 2 ) M
tan(θ ) = Iθ
E B2L
where B and L are the foundation dimensions (for a circle B=L); M is the overturning moment for
Operational Loads in the plane of B, Iθ can be evaluated using the following Table 11, ν and E are the
Poisson ratio and the deformation modulus.
Table 11 Definition of Iθ
In the executive design phase, the same approach may be used only to verify the results of more
complex calculations, the evaluation of short and long term behavior of the foundation shall be
accurately investigated and reported.
For long term analyses in cohesive soils, settlements must be checked considering the working life of
the WTG and the loads expected to act for a significant period (i.e. design load cases defined as
operational loads or normal production loads by the manufacturer). In case of non uniform or complex
stratigraphy, FEM analysis may be required.
8Gdyn R
Kt =
(2 − υ )
8Gdyn R 3
Kr =
3(1 − υ )
The above values are valid for circular foundations with radius R or octagonal foundation whose
CODICE – CODE
PAGINA - PAGE
Engineering 27 di/of 50
PAGINA - PAGE
Engineering 28 di/of 50
Figure 19 Dynamic Shear Modulus/ Measured Shear Modulus from shear wave velocity
vs Shear Deformation
Shear wave velocities may be easily investigate from the ground surface through Multychannel Analysis
of Surface Waves (MASW) or seismic refraction tests, or performing Down Hole or Cross Hole tests
inside the boreholes.
Even if the investigation may reach high depth, only the values related to the shallower layers shall be
taken into account, the measured wave velocities shall be averaged from the foundation plan up to a
depth where the soil pressure is 60% to 70% of the pressure applied at the foundation level (about 1,5
time the foundation radius). Figure 20 shows the pressure isobars for a uniformly loaded circular area.
9.2.3. Sliding
Horizontal actions transmitted from the WTG to the foundation imply the evaluation of the soil shear
resistance. Both undrained and drained conditions shall be considered. For drained condition the soil
resistance Rd is obtained by multiplying the total vertical design loads Nd by tan δ (design structure-
CODICE – CODE
PAGINA - PAGE
Engineering 29 di/of 50
ground friction angle; if not directly determined, its value can be set as 2/3 of the soil friction angle φ).
Rd = N d tan(δ )
(note that the design value of the friction angle is reduced by the partial safety factor).
For undrained soil conditions, the soil resistance is equal to the product of the base area under
compression multiplied by the undrained shear strength
Ru = Ac cu
materials safety factors shall be taken in accordance with the applicable codes.
9.2.4. Overturning
The factored stabilizing moment due to WTG selfweight, concrete and backfilling dead loads shall be
greater than the factored moment due to the horizontal actions.
Favorable effects of backfill weight should be accounted for only if their permanent presence is
positively assured (i.e. only the backfill below the original ground level can be considered, see section
6.6). The stabilizing moment due to passive earth pressure shall be neglected.
(
qult = 5.14 1 + sc' + d c' − ic' − bc' − g c' + q)
Where:
⎛ φ⎞
N q = eπ tan(φ ) tan 2 ⎜ 45 + ⎟
⎝ 2⎠
N c = ( N q − 1) cot(φ )
N γ = 2( N q + 1) tan(φ )
values for index of shape (s), depth (d), load inclination (i), soil inclination (g) and foundation base
inclination (b) may be found in the reference document. Where alternative methods (such as Mayerhof
or Hansen approach) are used, similar equations would be adopted, while the value of each index shall
be referred to the chosen method.
CODICE – CODE
PAGINA - PAGE
Engineering 30 di/of 50
be = 2( R − e)
2
⎛ b ⎞
l e = 2 R 1 − ⎜1 − e ⎟
⎝ 2R ⎠
where e is the eccentricity due to the total bending moment and to the vertical load and R is the radius.
The loaded area is equal to
⎡ ⎛e⎞ ⎤
Aeff = 2 ⎢ R 2 arccos⎜ ⎟ − e R 2 − e 2 ⎥
⎣ ⎝R⎠ ⎦
equivalent to the area of a rectangle with the following dimensions:
le
leff = Aeff
be
leff
beff = be
le
In case of foundations close to a slope, the global stability shall be checked for both the upward and
downward slope around the WTG platform. As defined in section 5.2 the mechanical properties of the
area will be defined in the geotechnical studies and a consequent soil profile section must be defined
along the slope under investigation. The use of a proper 2D slope stability method (such as Bishop,
Janbu or Morgenstern and Price methods) is necessary. The output of the analysis shall report the
safety factors for the different sliding surfaces and highlight the one with the smallest safety factor (as
per the figures reported below):
CODICE – CODE
PAGINA - PAGE
Engineering 31 di/of 50
PAGINA - PAGE
Engineering 32 di/of 50
• the whole surface shall be reacting under unfactored Operational Loads (0% gapping).
9.2.7. Piles
The design shall define the forces acting on piles. The system soil-pile shall be checked against the
axial, transversal or tensile failure. Tip and lateral (friction) forces shall generally be accounted
separately, since different safety factors may be prescribed by codes.
When considering the pile check for transversal forces, the resistance is related to the mechanism of
failure. It depends on the soil parameters, but also on the piles and pile cap geometry, i.e. it shall be
assessed if the pile head rotation can be considered fully restrained or not.
Uplift forces on piles shall be limited. For Operational Loads no tension is allowed on piles since cyclic
loadings would damage concrete. Tensile uplift forces may be allowed for the Extreme Loads and the
piles resistance shall be adequately checked considering the lateral (friction) resistance only.
As
ρ= is the ratio between the flexural (radial) reinforcement and the unitary area;
bu d
As is the area of the flexural reinforcement in tension (in mm2), for a unitary arclength bu;
d is the effective depth of the section considered (in mm);
• where the design concrete shear resistance is exceeded, the whole external shear shall be
resisted by steel shear reinforcement without considering any concrete contribution.
CODICE – CODE
PAGINA - PAGE
Engineering 33 di/of 50
The design concrete shear resistance (Vcd) per unitary width shall be calculated applying the partial
factors on material (g) and/or on member resistance (Φ) in accordance with the applicable local codes:
Vck v ck
Vcd = = bu d
γ γ
Or
PAGINA - PAGE
Engineering 34 di/of 50
PAGINA - PAGE
Engineering 35 di/of 50
Besides the Ultimate Limit State checks, also Serviceability Limit State checks shall be performed, as
required in the applicable codes. As a minimum check, the Designer shall verify that the maximum
crack width under Serviceability loads is below 0,3 mm. Operational Loads, as given in the WTG
manufacturer loads, shall be considered as Serviceability loads (if not clearly reported by the Loads
documentation, the Designer may use the same loads used for the 0% gapping, see section 9.2.6).
If the designer perform a design by using a 3-dimensional elements, the results obtained shall always
be compared with the usual 2D FEM model (based on shell/plate elements, as described above).
Eventual stress reductions achieved in the 3-D FEM may be considered in the structural checks by the
Designer only if approved by EGP.
In any case the stresses reached in the raft shall never lead to its plasticization in any section, since the
foundation shall always remain be in the elastic range, even in Ultimate Limit States.
PAGINA - PAGE
Engineering 36 di/of 50
1⎛ a⎞
T = ⎜ 1 − 0 .7 ⎟ F
4⎝ h⎠
CODICE – CODE
PAGINA - PAGE
Engineering 37 di/of 50
4M d Nd
F= +
πD 2
b πDb
where Db is the anchor cage diameter. The pretension force shall be added to the external actions.
Horizontal radial and circular bars shall be provided in order to resist the tensile force. The use of these
bars will ensure a cage around the concrete and will confine it to resist the high compression stresses
that will arise. Figure 28 shows radial “U-shaped” or “C-shaped” bars placed close to both the flanges.
PAGINA - PAGE
Engineering 38 di/of 50
top of concrete. Unless more stringent requirements are stated in the applicable codes, the surface
inclination shall be assumed 45°, see Figure 29.
The design tensile resistance of concrete shall be checked against the design stress obtained by dividing
the tensile force by the rupture area. When the concrete resistance is overcome, the entire pull-out
force shall be resisted by adequate reinforcement, see [AWEA-ASCE Recommended Practice for
Compliance of Large Land-based Wind Turbine Support Structures].
45
Figure 29 Anchor bolt with embedded bottom flange and rupture cone
Such reinforcement shall be properly anchored to the bottom bars layer of the foundation. It is
preferable to have several bars positioned around the bolts in order to distribute the pull-out tensile
stresses over a wider area (see Figure 26).
Additionally, the resistance of the bottom embedded flange shall be checked: adequate dimensions and
thickness shall be provided. The concrete area above the embedded flange shall be checked against
concrete crushing and splitting (as described above for the area below the tower flange).
PAGINA - PAGE
Engineering 39 di/of 50
Nevertheless, in case embedded steel rings, as shown in Figure 30, are used by the WTG manufacturer
to connect the tower to the foundation, the following is required:
• shear studs on both the internal and external surface of the ring (as per Figure 30);
• holes at the top of the ring to allow the radial reinforcement to be properly anchored in the
central area, additional intermediate holes would be preferable.
The foundation designer shall satisfy the following requirements:
• the steel ring shall be embedded at least up to the 60-70% of the total foundation height, the
following scheme having the ring inside the pedestal is not acceptable;
PAGINA - PAGE
Engineering 40 di/of 50
⎛ f ⎞
f cd , fat = k1β cc (t 0 ) f cd ⎜1 − ck ⎟
⎝ 250 ⎠
where k1 can be kept equal to 0.85 unless lower values are found in applicable codes, βcc may be lower
than 1 if loads are applied before the complete curing of concrete, fcd and fck are the design and
characteristic cylinder compressive strength of concrete (safety factor for concrete shall not be less than
1.50).
An adequate concrete resistance to fatigue stresses is ensured if
σ c ,max σ c ,min
≤ 0.5 + 0.45 ≤ 0.9
f cd , fat f cd , fat
where σ c , max and σ c ,min are respectively the maximum and the minimum achieved stress values
In a similar way steel stresses shall be checked. The maximum stress range for steel ( Δσ max ) under
the relevant load cases shall be checked against the characteristic fatigue strength.
Δσ Rsk
γ F , fat Δσ max ≤
γ s , fat
Δσ Rsk shall be defined in accordance with the applicable code for the considered number of cycles. If
local standards are not available, the S-N curves, as reported in EN-1992 should be used, see the
following Figure 33:
CODICE – CODE
PAGINA - PAGE
Engineering 41 di/of 50
Safety factor for loads (gF,fat) and for materials (gs,fat) shall be found in the applicable codes.
When the WTG manufacturer supplies the fatigue loads in multiple cycles, the analysis shall be
performed using a cumulative damage approach. The cyclic actions on the WTG may be grouped in
several steps, each one with a mean value and a range. The “Rain flow” procedure described in
[Guidelines for Design of Wind Turbines (DNV/Risø)] is a widely recognized method to define those
values and the corresponding estimated number of cycles. The number of cycles (ni) defined by the
WTG manufacturer for a certain step shall be compared to the number of cycles causing the element
failure for the corresponding stress level (Ni). Summing the ratio of the two values for all the i blocks,
an evaluation of the cumulative damage ratio D is calculated:
ni
∑N i
=D
i
Values of D must be lower than 1.0; more restrictive values may be found in applicable codes.
The report produced by the designer shall include all the design assumptions and the features of the
software used for the calculation. Commonly used software, such as SAP2000 by Computer and
Structures, are preferable. The designer shall provide, together with the calculation report, suitable files
to evidence and verify the design results. Original input and output files of the used software shall be
provided to EGP (FEM models, both structural and geotechnical).
The following data shall be summarized and clearly reported by the designer:
• all safety factors required by the applicable codes and adopted in the calculation (see Table 13 as
an example);
CODICE – CODE
PAGINA - PAGE
Engineering 42 di/of 50
PAGINA - PAGE
Engineering 43 di/of 50
PAGINA - PAGE
Engineering 44 di/of 50
PAGINA - PAGE
Engineering 45 di/of 50
PAGINA - PAGE
Engineering 46 di/of 50
Drainage system
Proper drainage mechanism for surface water shall be defined and properly reported on construction
drawings. All the details of the drainage system to be implemented in order to assure a dry working
area during the construction shall be reported in the drawings.
For foundations laying on clayey soils, a drainage system to be placed at the base of the foundation is
also recommended. Construction drawings shall report all the details.
Compaction of backfill
The compaction of backfill shall be started only after the concrete of the WTG foundation has reached
an adequate ageing but not less than 7 days. The use of small compactors is preferable to avoid
damages in the early stages of concrete strengthening. The backfill shall be placed in layers, whose
maximum thickness shall be 30cm. Compaction requirements (as stated in the construction drawings)
shall be checked at each layer.
PAGINA - PAGE
Engineering 47 di/of 50
Steel bar supply must be in accordance with the local codes in force. In general each batch must be
tagged and well identified in terms of production data and material characteristics.
Steel bars shall be stored in such a way that corrosion and deformation are prevented. Preferably bars
shall be divided and kept separated for type and diameter. Besides all the requirements for the
certification of the steel manufacturers and the inspections required by applicable codes, additional
tests may be required by EGP for the bars stored on site.
Concrete pouring
Concrete shall be poured just after mixing. The time for transportation after concrete mixing shall be
kept as low as possible (less than one hour).
Concrete shall be preferably poured in subsequent fresh layers. When this is not possible, the hardened
surface shall be properly roughened and all loose parts removed, bonding agents on top of the
hardened concrete should be used. Forms shall be clean and the reinforcing bars shall be rust free. A
proper placement of concrete shall avoid segregation of aggregates and displacement of steel bars and
CODICE – CODE
PAGINA - PAGE
Engineering 48 di/of 50
forms. The use of hose for concrete pumping shall be considered, to avoid free drop from more than
1.5m. Adequate space between the steel reinforcement shall be provided during the design phase (see
Figure 12) and shall be verified at site before starting the concreting. Immediately after placing, the
concrete shall be properly compacted by means of vibrators. The use of membrane-forming compounds
to prevent the loss of moisture during the early stage of curing of concrete may conform to ASTM C309.
Execution of grouting
The indication of the grout manufacturer shall be followed for a proper grout preparation. During the
first grouting execution, if necessary, the supervision of grout manufacturer technicians may be
required in order to validate the procedures and properly train the contractor workers. In case of
adverse climatic conditions the construction contractor shall issue dedicated documentation to EGP
describing the execution procedures and the precautions to the taken at site for handling of materials,
preparation and pouring of grout.
At least six (6) grout samples shall be taken during the pouring of the grout. Three (3) samples shall be
used in order to define the grout resistance before the anchor bolt tensioning. Tests results shall be
CODICE – CODE
PAGINA - PAGE
Engineering 49 di/of 50
issued to EGP. In case of deviation of the grout properties at the age of tests from the properties
defined by the manufacturer at the same age, the anchor bolts tensioning shall not be started (even if
the minimum required resistance for bolt tensioning has been reached).
Execution of piles
Bored cast in situ piles shall preferably be used for the foundation of wind turbine generators.
Segregation of aggregates shall be avoided in pumping concrete, through a flexible pressure hose
placed down to the bottom of the hole. In case of loose soil materials, a permanent case shall be put in
place. The reinforcement arrangement shall be such that all possible interferences during pouring are
avoided.
The portion of concrete in excess from the cut-off level shall be removed, avoiding all possible damage
to rebars and properly exposing them. The lean concrete layer for the piles cap shall be laid down as
soon as possible in order to prevent soil to impair the connection. All loose material shall be removed
before starting the concreting of the pile cap.
Tests on piles
The design resistance of piles shall be checked during the geotechnical characterization in order to have
a proper design. After the execution the following tests will be performed for:
• axial compression load (according to ASTM D1143)
and, if required:
• axial tensile load (according to ASTM D3689);
• lateral load (according to ASTM D 3966).
Based on the number of executed piles and on the soil heterogeneity, the number of tests shall be
defined. The following minimum requirements shall be respected:
• 1 pile test if N≤20
• 2 pile tests if 21<N≤50
• 3 pile tests if 51<N≤100
• 4 pile tests if 101<N≤200
• 5 pile tests if 201<N≤500
A lower number of tests on executed piles may be performed if trial piles have been previously tested.
During the construction phase, the quality of the execution shall be verified by means of non destructive
tests. Cross-hole tests or sonic tests are here suggested. Cross hole tests are performed in pipes
previously installed inside the reinforced concrete piles. The pipes shall be arranged at 120°C, properly
sealed at the junctions and closed at their lower end; they shall be fixed to the reinforcement in order
to keep their mutual distance constant along the pile length.
Cross hole tests shall be performed in compliance with standard ASTM D 6760.
CODICE – CODE
PAGINA - PAGE
Engineering 50 di/of 50