Quiz 5
Quiz 5
Quiz 5
2] What is the primary difference between the test plan, the test design
specification, and the test procedure specification?
a) The test plan describes one or more levels of testing, the test design
specification identifies the associated high-level test cases and a test
procedure specification describes the actions for executing a test.
b) The test plan is for managers, the test design specification is for
programmers and the test procedure specification is for testers who are
automating tests.
c) The test plan is the least thorough, the test procedure specification is the
most thorough and the test design specification is midway between the two.
d) The test plan is finished in the first third of the project, the test design
specification is finished in the middle third of the project and the test
procedure specification is finished in the last third of the project.
a) Test tasks
b) Environmental needs
c) Exit criteria
d) Test team training
4] Consider the following exit criteria which might be found in a test plan:
Which of the following statements is true about whether these exit criteria belong
in an acceptance test plan?
5] During test execution, the test manager describes the following situation to the
project team: ‘90% of the test cases have been run. 20% of the test cases have
identified defects. 127 defects have been found. 112 defects have been fixed and
have passed confirmation testing. Of the remaining 15 defects, project
a) Traceability
b) Confirmation testing
c) Configuration control
d) Test documentation management
7] A product risk analysis meeting is held during the project planning period. Which
of the following determines the level of risk?
8] You are writing a test plan using the IEEE 829 template and are currently
completing the Risks and Contingencies section. Which of the following is most
likely to be listed as a project risk?
9] You and the project stakeholders develop a list of product risks and project risks
during the planning stage of a project. What else should you do with those lists of
risks during test planning?
a) Determine the extent of testing required for the product risks and the
mitigation and contingency actions required for the project risks.
b) Obtain the resources needed to completely cover each product risk with
tests and transfer responsibility for the project risks to the project
manager.
c) Execute sufficient tests for the product risks, based on the likelihood and
impact of each product risk and execute mitigation actions for all project
risks.
d) No further risk management action is required at the test planning stage
10] In an incident report, the tester makes the following statement, At this point, I
expect to receive an error message explaining the rejection of this invalid input
and asking me to enter a valid input. Instead the system accepts the input,
displays an hourglass for between one and five seconds and finally terminates
abnormally, giving the message, "Unexpected data type: 15. Click to continue." '
This statement is likely to be found in which of the following sections of an IEEE
829 standard incident report?
a) Summary
b) Impact
c) Item pass/fail criteria
d) Incident description
a) A bug report
b) A defect report
c) An incident report
d) A test summary report
5 Replace customer's first name with exactly the same first name 6 Close the
customer record and close the database
a) Tests 1 and 4
b) Tests 2 and 3
c) Tests 5 and 6
d) Tests 3 and 5
13] In an incident report, the tester makes the following statement, 'At this point,
I expect to receive an error message explaining the rejection of this invalid input
and asking me to enter a valid input. Instead the system accepts the input,
a) Summary
b) Impact
c) Item pass/fail criteria
d) Incident description
14] What test roles (or parts in the testing process) is a developer most likely to
perform?
a) i and ii.
b) i and iv.
c) ii and iii.
d) iii and iv.
15] A new system is about to be developed. Which of the following functions has
the highest level of risk?
1. B
2. A
3. C
4. D
5. B
6. C
7. B
8. A
9. A
10. D
11. C
12. D
13. D
14. A
15. A
16. C