Facts of Living
Facts of Living
Facts of Living
Facts of living
Facts of living 1
The Building
The Building
in detail
The building is typical of MSR developments throughout For the residential levels the building is divided into
the UK and for the purposes of this study is located in a number of 2 person (approx 50m2) and 4 person
outer London. The building is of a rectangular plan form (approx 65m2) flats, serviced from zones at each end of
of approx 17m by 60m with a nominal height of 18m, the building, where the stairs and lifts are located. It has
and a gross floor area of 6060m . 2
a fire resistance of 60 minutes, and is not sprinkler
It consists of: protected. These levels are clad in an insulated render,
below-ground car parking with regularly spaced individual windows making up a
ground floor retail outlets quarter of the façade. For the residential floors the ratio
five residential storeys of habitable space to gross floor area is 0.85:1
Access to the below ground car park is provided by The roof construction is designed to take the same
an access ramp that runs along the rear of the whole loads as all other floors, but does not support any
building. The column spacing, dictated by the layout additional roof structures.
of the car park, is continued throughout the building
Minor pipework in this building is passed underneath or
removing the need for an expensive transfer structure.
through the beams or floor. Provision for lighting units,
The retail floor level is generally open plan (it can be
fire protection, ceiling depths and an allowance for
divided into shop units as required by the developer)
deflections are included in the depth of the floor zone.
and has a glazed façade to the street. The retail level is
not sprinkler protected and has been designed to have
a fire resistance of 60 minutes.
Structural systems
Four structural systems for this Building are detailed in this publication. They are:
• composite beam and slab • Slimdek® • ASB with pre-cast hollow core units • reinforced concrete flat slab
2 Facts of living
The Building
= 70mm raised floor = 70mm raised floor = 70mm raised floor = 70mm raised floor
+ 135mm slab + 300mm slab + 250mm concrete slab + 250mm concrete slab
+ 260mm beam + 88mm ceiling + 88mm ceiling + 70mm ceiling
+ 88mm ceiling = 458mm ≈ 460mm = 408mm ≈ 410mm = 408mm ≈ 410mm
= 553mm ≈ 550mm
Ceiling Ceiling
Ceiling
Ceiling
2.5m
2.5m
2.5m
16.5m
2.5m
2.5m
3.1m
20.4m
Facts of living 3
Study Methods
Study methods
The study considered four different structural forms.
These forms were chosen, as they typified the Construction programme assumptions
structural options currently in use in MSR buildings. MACE undertook the programming for all options. It is
The complete set of results appears in the new Steel assumed that the programming and plant resources for
Construction Institute publication SCI-P-338 'Cost each option are consistent - so that they do not favour
Comparison of multi-storey residential buildings', but any form of construction. The key interfaces between
for the purpose of brevity only the highlights for each preceding and following trades are assumed to be well
option have been detailed in this summary version. maintained.
Fire protection
For effective fire protection, it is assumed that an
intumescent coating is used for the beams, bracing
and columns in the basement, while a board system
is used (where required) for the columns and beams
above ground level. Asymmetric Slimflor® Beams
(ASBs) are partially encased in concrete and do
not require any additional protection for 60 minutes
fire resistance.
4 Facts of living
Study Methods
steel decking, have also been accurately costed. North East -12
North West -12
The itemised rates for the various concrete Northern Ireland -28
The composite unit rates used for other elements in the West Midlands -11
buildings have been compiled from Davis Langdon's Yorkshire and Humberside -14
Facts of living 5
Cost Effective Construction
Cost-effective
construction
The study showed that steel-based systems offer the
fastest and lowest cost construction options available
for MSR buildings.
Cost-effective steel Time-related savings
For the MSR building in the study, the results showed Faster construction has additional benefits. It results
that the composite beam and slab system was the in savings in the cost of site management and on-site
lowest cost option, followed by Slimdek and ASB+PC
®
activities. It reduces the cost of finance, since a shorter
construction systems. The concrete option proved to construction period reduces the time during which
be the most expensive solution. interest has to be paid. This effect is an integral part
of the cost comparison study.
Rapid construction
The speed of construction of steel structures was Additionally the rapid completion of a building also
highlighted by the study. For both steel and concrete, brings an earlier return on investment as the building
the erection of the structure is a relatively small can be occupied sooner, helping to offset the cost of
proportion of the overall programme time – but steel borrowing or allowing finance for the next phase of a
was shown to be the faster option. development. These more intangible benefits are not
calculated in the study
For MSR building, the steel structural systems could
Time related savings
be erected in ten or eleven weeks, compared with
Structural form Frame after Completion
the twelve weeks required for a reinforced concrete completion of frame and
of basement floors Overall
system. In addition, erection of concrete frame (weeks) (weeks) (weeks)
structures begins later than the steel alternatives, since Composite beam and slab 10 22 69
a ground-bearing slab must be constructed prior to Slimdek® 9 21 68
6 Facts of living
Cost Effective Construction
Additional measurements
The tables below compare the finished structural For example, the weight of steel is only a crude
dimensions and steel weights of each of the measurement of efficiency - and does not take into
construction systems. These findings illustrate some of account the reduced costs of fire protection and
the merits of the different systems, but should not be cladding and the ease of service installation.
considered in isolation.
Additional measurements
Structural form Beam and Overall Building Area fire Basic steel Total steel weight
slab depth floor zone height protection frame per floor area
weight per
(m2/m2 floor area
(mm) (mm) (m) floor area) (kg/m2) (kg/m2)
Composite beam and slab 395 550 18.9 0.64 48.7 68.0
Slimdek® 300 460 18.3 0.24 46.3 73.4
ASB + PC 250 410 18.0 0.25 41.9 46.9
Reinforced concrete flat slab 300 410 18.0
Facts of living 7
The Value of Steel
The value
of steel
Steel offers considerable advantages over concrete,
making it the first choice material for large building
construction in any location.
Minimal disruption Built-in quality
Steel construction can dramatically reduce the impact Off-site fabrication improves the quality of the
of building activities on the surrounding area. This is building frame, since the majority of work is carried
particularly important in inner city locations or sites out under closely controlled factory conditions -
close to residential areas. Steel construction minimises unaffected by on-site trades or the weather. All steel
noise and dust, shortens the construction period and frames are prefabricated, providing the potential for
reduces the amount of waste generated. Deliveries can a “right-first-time” build, which minimises time and
even be timed to suit local traffic conditions and keep disruption on site.
disruption in the area to a minimum.
Steel does not suffer from creep or shrinkage and,
Flexible solution when properly protected, does not rot or decay.
Steel construction generates an inherently flexible
solution. All internal walls can be repositioned allowing Environmental benefits
buildings to be adapted repeatedly to suit the changing Steel offers a clean, efficient and rapid construction
needs of their occupants. method, which reduces the impact of building
activities on the environment. The small amount of
waste produced is generally recycled, and all steel is
potentially reusable. Today, around 40 per cent of steel
is produced from recycled material
8 Facts of living
Slimdek®
ASB+PC unit
Facts of living 9
Appendix One
Appendix one
Design parameters and assumptions
Structural design
The building is designed for an imposed load of The car park arrangement dictates the structural grid
1.5kN/m2 in the residential apartments, 2.5kN/m2 in that is adopted in order to avoid the use of an
residential communal areas such as walkways and expensive transfer structure. This is based on a 3-car
4.0kN/m2 in the retail ground floor area. Additional bay (7.5m wide) along the facade, and columns at 4.8,
loads of 1 kN/m for partitions and 0.7kN/m for
2 2
6.7 and 5.0m respectively across the building.
the ceiling, services and raised floor are common
for all areas. Fire protection
Fire protection is taken as board for columns, internal
The deflection limits are taken as defined in BS 5950 beams and bracing members above ground, but an
Part 1. The total deflections of the beams or slabs of all intumescent coating protects the steelwork in the
options are limited to a maximum of span/200. Edge basement. In Slimdek® the ASB beams are partially
beam deflections are limited to a maximum of span/500 encased in concrete, and do not require protection for
under imposed and cladding loads. In practice, this building.
deflections will be much less than these limits, owing to
the stiffness of the connections. Acoustic performance
The building is designed to meet the acoustic
S355 steel (to BS EN 10 025) is used for the columns requirements of Part 'E' of the Building Regulations
whereas S275 steel is used for the UB and UC beams, (2003) and uses robust details wherever possible.
which are generally controlled by serviceability criteria. Post Completion Testing would be needed where
ASB sections are always S355. Normal weight concrete no appropriate Robust Detail is available.
is used throughout the building for all options.
Separating walls
The natural frequency limit is taken as 4Hz with a Separating walls are double layer light steel wall
response factor in accordance with BS6472 (250mm width and 8 kg/m2 steel weight per unit wall
The 2002 Building Regulations also require that all area) with 2 layers of fire resisting plasterboard per side
buildings possess `robustness' through provision of and 75mm mineral wool batts between the studs.
tying action. This necessitates the placement of
additional reinforcement across the beams in the Partition walls
pre-cast concrete options. Partition walls are a single layer light steel wall
(125mm width and 3 kg/m2 steel weight per unit
The steel options for both buildings are designed as wall area) comprising one layer of 12mm plasterboard
braced against wind load, with bracing accommodated on both sides.
within the core area. In the concrete option, reinforced
concrete shear walls are used. These 'core' positions External walls
are selected to offer the required escape routes and External walls consist of an insulated render (on
zones for vertical services. Their size is sufficient to 100mm EPS insulation) attached to 10mm CPB ,
accommodate lifts, stairways and any vertical ducts screw-fixed to single layer light steel wall (125mm
and pipes. width and 5 kg/m2 steel weight per unit wall area) with
two layers of 12mm fire resisting plasterboard on the
inside, 100mm mineral wool batts and a 15mm cavity.
Wall thickness is 250mm overall.
10 Facts of living
Appendix One
Roof
The roof is a flat roof built as the floor construction but
with a built-up layered roofing system laid to falls.
Car parking
The below-ground car parking is considered as
being common to all schemes, the only variant
being the use of steel or concrete columns.
A total of 38 car parking spaces are to be provided
beneath the building.
Staircases
The staircases are generally precast concrete with
powder coated balustrades and hardwood handrails.
Windows
Windows in the building are opening, aluminium,
polyester powder-coated, double-glazed units.
The windows are to be 2100mm high. Double glazed
doors are provided to access the balcony areas.
External doors
The type of external door specified changes with
location but all are solid security doors.
Sanitary/kitchen fittings
The sanitary and kitchen fittings are proprietary
products tailored to suit the type of accommodation.
Internal doors
The internal doors are veneered, solid core
within a hardwood frame and have stainless
steel ironmongery.
Facts of living 11
Appendix Two
Appendix two
The cost rates for some of the major elements used for the frame and floor costings in the study are
included here for information but do not necessarily reflect current competitive pricing.
12 Facts of living
Support for the construction industry from
Corus Construction and Industrial
Guidance on the design and use of structural sections and plates.
Corus provides free advice to the construction industry You can contact us as follows:
covering all aspects of the design, specification and Technical Hotline
use of its range of construction products. +44 (0)1724 405060
Facsimile
Corus Construction and Industrial manufactures +44 (0)1724 404224
structural sections and plates for building and civil Literature Line
engineering applications. Advice is provided by our +44 (0)1724 404400
team of qualified engineers with extensive experience Email
in the design and construction of buildings and [email protected]
bridges. Specialist advice on fire engineering, durability www.corusconstruction.com
and sustainability is also available. Our regional
network of engineers covers the whole of the UK and Corus Construction & Industrial
Ireland and is supported by a dedicated design team Technical Sales and Marketing
based at our manufacturing centre in Scunthorpe. PO Box 1
Brigg Road
General enquiries on other products and systems Scunthorpe
manufactured by Corus will be routed to our North Lincolnshire
Construction Centre who will direct you to the DN16 1BP
appropriate source of market and product expertise.
Copyright 2004
Corus
MRW:4000 UK:08/2004