Gantt Scurve

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT : Carlos Tiu Center for Technology Innovation and Research

LOCATION: Adamson University

Duration DECEMBER JANUARY FEBRUARY MARCH APRIL


Item Description Amount % Weight
(weeks)
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18

A GENERAL REQUIREMENTS
Facilities for the Engineer 11,000,000.00 1.35 18 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
Other general requirements 18,000,000.00 2.20 18 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12

SUBTOTAL 29,000,000.00

B REMOVAL AND DEMOLITION WORKS


Removal of existing water line 1,000,000.00 0.12 1 0.12

SUBTOTAL 1,000,000.00

C SITE DEVELOPMENT

Earthworks 25,000,000 3.06 1 3.060


Subbase and base course 10,000,000.00 1.22 1 1.22
Surface Courses 15,000,000.00 1.84 1 1.84
Drainage and slope protection structures 5,000,000.00 0.61 1 0.61
Miscellaneous structures 10,000,000.00 1.22 1 1.22
Lanscaping works 5,000,000.00 0.61 1 0.61
Exterior Electrical Works 2,000,000.00 0.24 1 0.24

SUBTOTAL 72,000,000.00

D ALL BUILDINGS STRUCTURES

STRUCTURAL WORKS 265,000,000

Footing 55,000,000.00 6.73 3 2.24 2.24 2.24


Column 50,000,000.00 6.12 2 3.06 3.06
Slab 75,000,000.00 9.18 4 2.29 2.29 2.29 2.29
Stairs 55,000,000.00 6.73 2 3.37 3.37
Handrails 30,000,000 3.67 2 1.84 1.84
ARCHITECTURAL WORKS 254,000,000

Tiles 70,000,000.00 8.57 1 8.57


Metal frame ceiling 40,000,000.00 4.90 1 4.90
Windows 45,000,000.00 5.51 1 5.51
Doors 40,000,000.00 4.90 1 4.90
Ceiling 40,000,000.00 4.90 1 4.90
Painting 19,000,000.00 2.33 1 2.33

PLUMBING AND SANITARY WORKS 60,000,000

Water meter and plumbing fixtures 10,000,000.00 1.22 1 1.22


Pipe installation 10,000,000.00 1.22 1 1.22
Cistern tank and cold water lines 10,000,000.00 1.22 1 1.22
Sewer line works 10,000,000.00 1.22 1 1.22
Septic vault 10,000,000.00 1.22 1 1.22
Storm drainage 5,000,000.00 0.61 1 0.61
Downspout 2,500,000.00 0.31 1 0.31
Catch basin 2,500,000.00 0.31 1 0.31

MECHANICAL WORKS 84,000,000

Airconditioning 60,000,000.00 7.34 1 7.344


Exhaust fan 24,000,000.00 2.94 1 2.938

ELECTRICAL WORKS 52,000,000

Installation of sockets 2,000,000.00 0.24 1 0.24


Network cabling of wires 15,000,000.00 1.84 1 1.84
Panelboard with main & branch breakers 15,000,000.00 1.84 1 1.84
Conduits, boxes and fittings 5,000,000.00 0.61 1 0.61
CCTV system 15,000,000.00 1.84 1 1.84

SUBTOTAL 715,000,000.00

GRAND TOTAL 817,000,000.00 100.00


PROJECT ACCOMPLISHMENT
WEEKLY 0.20 0.32 5.95 3.26 2.44 2.44 2.44 3.26 3.26 5.86 5.86 4.33 4.33 22.72 8.77 7.54 10.48 6.56
WEEKLY CUMMULATIVE 0.20 0.52 6.47 9.72 12.17 14.61 17.05 20.30 23.56 29.42 35.28 39.61 43.93 66.65 75.42 82.96 93.44 100.00

You might also like