MS Slab
MS Slab
1.0 Introduction
2.0 Objective
The objective of this Method Statement is to provide a detailed procedure on how the
Works or part thereof are to be carried out in compliance with the Contract, and to
carry-out the Works safely, quality workmanship and in a timely manner.
3.0 Scope
This Method Statement (Methodology) shall apply for the repairs of the following
structural elements but are not limited to:
a. Suspended slabs
b. Beams
c. Piles with steel casing (monotube piles)
d. Pile caps
e. Fender beams/blocks
4.0 Responsibility
Generally, on turn-over of the Work Area (Site Possession) by ATI the Contractor’s
Survey Team together with assigned Safety Group shall:
a. pre-establish the limits of the Site Possession area [Four (4) corners, minimum)]
and thereafter,
b. completely secure the Work Area
Generally, in all cases and stages of the repair Works, the provision of complete
enclosure using concrete barriers, installation of safety signage’s, directional/traffic
signage’s and related items to safely secure the area particularly to all workers and
equipment thereat should be the priority step of the work to be carried out. (refer to MS-
Lifting….)
Set-out in-situ the location and establish the limits of construction of the elements to be
repaired, complete with visible markings (use white coloured paint), and reference
gridlines. Limits of construction of slabs may be taken from the underside from a
given reference and transferred on slab deck whereupon markings be established.
a. Workers all set with complete PPE’s appropriate to the activity, including
environmental protection, i.e. noise and dust control
c. Demolish slab to the required limits using hand-held jack hammer, pneumatic type
or AC operated or any appropriate equivalent. Start the demolition approximately at
mid-section such that a pilot hole is formed, so that location of existing steel
reinforcement is seen, where good steel reinforcement is to be maintained and
where to cut deteriorated ones that need to be replaced. Slab may be broken into
small chunks.
d. Dispose offsite concrete slab chunks /other debris resulting from the demolition
work.
A.2 False works, form setting, placement of steel reinforcement, and inspection.
UNDERDECK REPAIR
In General work:
Concrete placement
For Beam, Pile Cap and Fender Block. Concrete mix is conveyed to a
mixing bowl of box. The box is position on the floater before putting the
concrete mix. Concrete crew will fill the box manually until it has reached
the required volume. The floater with mixing box is then led to the location
where concrete placement is done and manually poured through the aid
of pail.
a. Removed the existing corroded monotube steel of the existing piles to the
extent as prescribed by the Project-supervision team.
b. Roughen the surface all around the existing pile after the removal of the
existing monotube steel using chipping hammer or other acceptable means.
c. Apply zinc-rich epoxy paint to all existing reinforcement.
d. Install the reinforcement bars (rebar) after fixing the bottom plate support,
provide concrete spacer block for maintaining space between rebar and
monotube piles.
e. After completion of the rebar works, installation and fixing the steel forms
shall commence. Fabricated circular steel forms longitudinally divided into
two parts will be fixed and firmly be connected by flange and bolts. Bottom
and side connections of the steel forms shall be sealed with inner tube cut
from used tire. Provide concrete spacer blocks for maintaining the required
concrete cover.
f. Fabricated steel forms, fabricated vertical rebar shall be transported under
the deck using fabricated floater/pontoon.
g. Remove/stripping off forms when concrete achieved the compressive
strength design for stripping.
h. This procedure shall be done repeatedly to all piles scheduled for
encapsulation-cast in situ.
i. Apply protective coating to all exposed concrete surface.
a. All loose concrete shall be chipped off separately from sound concrete.
b. Apply zinc-rich epoxy paint to all existing exposed reinforcements.
c. All sound concrete shall be patch with structural concrete repair mortar.
d. Apply protective coating to all exposed concrete surface.
C. Repair of Pile Cap