Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
1 KINFRA IECC 666 0% 12-Aug-24 01-Mar-27 0
1.2 Design stage 112 0% 12-Aug-24 14-Jan-25 554 14-Jan-25, 1.2 Des
A1090 Receipt of all Client DeliverablesReceipt of all Client Deliverables
1 0% 12-Aug-24 12-Aug-24 79 A1040
A1100 Concept Design Submission 14 0% 12-Aug-24 29-Aug-24 0 A1040
A1120 Soil Test & Report Submissio n 14 0% 13-Aug-24 30-Aug-24 613 A1090
A1110 Concept Design Approval 10 0% 23-Aug-24 05-Sep-24 61 A1100
A1150 Submission of Architectural Drawings 21 0% 06-Sep-24 04-Oct-24 61 A1090, A1110
A1130 Submission of Final Estimate 12 0% 02-Oct-24 17-Oct-24 613 A1120
A1160 Approval Of Architectural Drawings 8 0% 04-Oct-24 15-Oct-24 61 A1150
A1140 Approval of Final Estimate 5 0% 17-Oct-24 23-Oct-24 613 A1130
A1170 Submission Of Structural Drawings upto Plinth 17 0% 18-Oct-24 11-Nov-24 61 A1160
Submission Of Structural Drawings upto Plinth
A1180 Approval Of Structural Drawings upto Plinth 16 0% 30-Oct-24 20-Nov-24 61 A1170Approval Of Structural Drawings upto Plinth
A1190 Submission Of Structural Drawings - Super Structure 49 0% 30-Oct-24 06-Jan-25 554 A1180 Submission Of Structura
A1200 Approval of Of Structural Drawings - Super Structure 14 0% 26-Dec-24 14-Jan-25 554 A1190 Approval of Of Struc
1.3 Procurement Stage 48 0% 16-Oct-24 20-Dec-24 571 20-Dec-24, 1.3 Procurement Sta
1.3.1 Material Approval 48 0% 16-Oct-24 20-Dec-24 571 20-Dec-24, 1.3.1 Material Appro
1.3.1.4 Civil and structural materials 19 0% 16-Oct-24 11-Nov-24 600 11-Nov-24, 1.3.1.4 Civil and structural materials
A1210 Submission of all Civil Bulk Materials 5 0% 16-Oct-24 22-Oct-24 Submission
571 A1160of all Civil Bulk Materials
A1220 Approval of all Civil Bulk Materials 5 0% 18-Oct-24 24-Oct-24 Approval
612 A1210
of all Civil Bulk Materials
A1230 Submission of all Civil Finishing Materials 14 0% 18-Oct-24 06-Nov-24 600 Submission
A1210 of all Civil Finishing Materials
A1250 Submission of all Facade Materials 14 0% 18-Oct-24 06-Nov-24 603 Submission
A1210 of all Facade Materials
A1270 Submission of all Truss Work Materials 14 0% 18-Oct-24 06-Nov-24 603 Submission
A1210 of all Truss Work Materials
A1240 Approval of all Civil Finishing Materials 7 0% 01-Nov-24 11-Nov-24 600 A1230
Approval of all Civil Finishing Materials
A1260 Approval of all Facade Materials 7 0% 01-Nov-24 11-Nov-24 600 A1230
Approval of all Facade Materials
A1280 Approval of all Truss Work Materials 7 0% 01-Nov-24 11-Nov-24 600 A1230
Approval of all Truss Work Materials
1.3.1.2 MEP Materials 43 0% 23-Oct-24 20-Dec-24 571 20-Dec-24, 1.3.1.2 MEP Materia
Actual Level of Effort Remaining Work Page 1 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 2 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A1290 Submission of all PHE Items 14 0% 23-Oct-24 11-Nov-24 571 A1210
Submission of all PHE Items
A1310 Submission of all Electrical Items 14 0% 25-Oct-24 13-Nov-24 577 A1290
Submission of all Electrical Items
A1300 Approval of all PHE Items 7 0% 06-Nov-24 14-Nov-24 571 A1290
Approval of all PHE Items
A1320 Approval of all Electrical Items 7 0% 08-Nov-24 18-Nov-24 595 A1310
Approval of all Electrical Items
A1340 Approval of all ELV Items 7 0% 13-Nov-24 21-Nov-24 592 A1310Approval of all ELV Items
A1330 Submission of all ELV Items 21 0% 14-Nov-24 12-Dec-24 577 A1310 Submission of all ELV Items
A1350 Submission of all FPS Items 21 0% 15-Nov-24 13-Dec-24 571 A1300 Submission of all FPS Items
A1370 Submission of all HVAC Items 21 0% 15-Nov-24 13-Dec-24 571 A1350 Submission of all HVAC Items
A1360 Approval of all FPS Items 7 0% 12-Dec-24 20-Dec-24 571 A1350 Approval of all FPS Items
A1380 Approval of all HVAC Items 7 0% 12-Dec-24 20-Dec-24 571 A1370 Approval of all HVAC Items
1.4 Construction Stage 666 0% 12-Aug-24 01-Mar-27 0
Actual Level of Effort Remaining Work Page 3 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cutting/Filling
Retaining Wall
Masonry Works
Soffit Finishes
Actual Level of Effort Remaining Work Page 4 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A1540 Internal Wall Finis hes 75 0% 16-Jan-26 30-Apr-26 47 A1530
A1550 Floor Finishes 75 0% 13-Mar-26 25-Jun-26 152 A1540
A1560 Joineries 30 0% 19-Jun-26 30-Jul-26 152 A1550
1.4.2.4 Final Fixtures & Finishes 263 0% 23-Dec-25 24-Dec-26 47
1.4.2.4.1 Civil Works 193 0% 31-Mar-26 24-Dec-26 47
A1570 External Wall Fin ishes 75 0% 31-Mar-26 13-Jul-26 47 A1520, A1530
A1600 Internal Paininting 75 0% 10-Apr-26 23-Jul-26 47 A1540
A1580 OH Tanks 35 0% 05-May-26 22-Jun-26 173 A1570
A1590 Waterproofin g Works 7 0% 23-Jun-26 01-Jul-26 173 A1580
A1610 External Painting 60 0% 14-Jul-26 05-Oct-26 47 A1570
A1620 Interior Furnishing Works 80 0% 04-Sep-26 24-Dec-26 47 A1600
A1630 Internal Painting Final Coat 35 0% 06-Nov-26 24-Dec-26 47 A1700
A1660 External Painting Final Coat 35 0% 06-Nov-26 24-Dec-26 47 A1700
1.4.2.4.2 MEP Works 263 0% 23-Dec-25 24-Dec-26 47
A1670 Plumbing First Fix 30 0% 23-Dec-25 02-Feb-26 250 A1520
A1690 Electrical First Fix 30 0% 03-Feb-26 16-Mar-26 250 A1670
A1680 Plumbing Final Fixures 45 0% 24-Jul-26 24-Sep-26 112 A1600
A1700 Electrical Final Fix 75 0% 24-Jul-26 05-Nov-26 47 A1600
A1730 HVAC Works 90 0% 24-Jul-26 26-Nov-26 67 A1600
A1710 ELV Works 75 0% 14-Aug-26 26-Nov-26 67 A1600
A1720 ELV Works 75 0% 14-Aug-26 26-Nov-26 67 A1600
A1740 External Services & Connections 65 0% 25-Sep-26 24-Dec-26 47 A1610
1.4.3 Convention centre 661 0% 12-Aug-24 22-Feb-27 5
1.4.3.1 Foundation Works 148 0% 14-Feb-25 09-Sep-25 384
A1750 Piling Works 60 0% 14-Feb-25 08-May-25 5 A1420
A1760 Pile Load Test 3 0% 24-Mar-25 26-Mar-25 503 A1750
A1770 Pile Cap 45 0% 30-Apr-25 01-Jul-25 5 A1750
A1780 Plinth Beam 45 0% 08-Jul-25 08-Sep-25 5 A1770
A1790 PCC 7 0% 01-Sep-25 09-Sep-25 384 A1780
1.4.3.2 Structural Works 237 0% 29-Jul-25 24-Jun-26 178
1.4.3.2.1 Ground Floor 75 0% 29-Jul-25 10-Nov-25 5
A1800 RCC Verticals 45 0% 29-Jul-25 29-Sep-25 5 A1780
A1810 RCC Horizontals 60 0% 19-Aug-25 10-Nov-25 5 A1800
1.4.3.2.2 First Floor 75 0% 21-Oct-25 02-Feb-26 178
Actual Level of Effort Remaining Work Page 5 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 6 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A1820 RCC Verticals 45 0% 21-Oct-25 22-Dec-25 178 A1810
A1830 RCC Horizontals 60 0% 11-Nov-25 02-Feb-26 178 A1820
1.4.3.2.3 Second Floor 60 0% 16-Dec-25 09-Mar-26 178
A1640 RCC Verticals 30 0% 16-Dec-25 26-Jan-26 178 A1830
A1650 RCC Horizontals 45 0% 06-Jan-26 09-Mar-26 178 A1640
1.4.3.2.4 Terrace Floor 18 0% 02-Mar-26 25-Mar-26 178
A1850 RCC Horizontals 18 0% 02-Mar-26 25-Mar-26 178 A1840
A1840 RCC Verticals 12 0% 10-Mar-26 25-Mar-26 178 A1650
1.4.3.2.5 Structural Steel Works 65 0% 26-Mar-26 24-Jun-26 178
A1860 Erection of Steel Support system 30 0% 26-Mar-26 06-May-26 178 A1850
A1870 Installation of Roofing Sheets 20 0% 07-May-26 03-Jun-26 178 A1860
A1880 Flashing, Rainwater Gutter,Louvers,Glass 15 0% 04-Jun-26 24-Jun-26 178 A1870
1.4.3.4 Finishing Works 206 0% 25-Nov-25 08-Sep-26 124
1.4.3.4.1 Ground Floor 106 0% 25-Nov-25 21-Apr-26 224
A1890 Masonary Works 42 0% 25-Nov-25 21-Jan-26 5 A1810
A1900 Plumbing First Fix 25 0% 18-Dec-25 21-Jan-26 288 A1890
A1910 Electrical First Fix 25 0% 18-Dec-25 21-Jan-26 288 A1900
A1920 Soffit Finishes 26 0% 06-Jan-26 10-Feb-26 224 A1890
A1950 Joineries 26 0% 20-Jan-26 24-Feb-26 264 A1920
A1930 Internal Wall Finis hes 30 0% 03-Feb-26 16-Mar-26 224 A1920
A1940 Floor Finishes 36 0% 03-Mar-26 21-Apr-26 224 A1930
1.4.3.4.2 First Floor 102 0% 05-Feb-26 26-Jun-26 176
A3210 Masonary Works 42 0% 05-Feb-26 03-Apr-26 5 A1890
A3240 Soffit Finishes 26 0% 27-Feb-26 03-Apr-26 176 A3210
A3220 Plumbing First Fix 25 0% 02-Mar-26 03-Apr-26 206 A3210
A3250 Internal Wall Finis hes 30 0% 27-Mar-26 07-May-26 176 A3240
A3230 Electrical First Fix 25 0% 13-Apr-26 15-May-26 206 A3220
A3260 Floor Finishes 36 0% 24-Apr-26 12-Jun-26 176 A3250
A3270 Joineries 26 0% 22-May-26 26-Jun-26 176 A3260
1.4.3.4.3 Second floor 102 0% 20-Apr-26 08-Sep-26 124
A3280 Masonary Works 42 0% 20-Apr-26 16-Jun-26 5 A3210
A3310 Soffit Finishes 26 0% 12-May-26 16-Jun-26 5 A3280
A3290 Plumbing First Fix 25 0% 13-May-26 16-Jun-26 154 A3280
A3320 Internal Wall Finis hes 30 0% 09-Jun-26 20-Jul-26 5 A3310
Actual Level of Effort Remaining Work Page 7 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RCC Verticals
RCC Horizontals
09-Mar-26, 1.4
RCC Verticals
RCC Horizonta
Masonary Works
Plumbing First Fix
Electrical First Fix
Soffit Finishes
Joineries
Actual Level of Effort Remaining Work Page 8 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A3300 Electrical First Fix 25 0% 24-Jun-26 28-Jul-26 154 A3290
A3330 Floor Finishes 36 0% 07-Jul-26 25-Aug-26 124 A3320
A3340 Joineries 26 0% 04-Aug-26 08-Sep-26 124 A3330
1.4.3.4.4 Terrace Floor 53 0% 17-Jun-26 28-Aug-26 131
A2950 Masonary Works 6 0% 17-Jun-26 24-Jun-26 21 A3280
A2960 Internal Wall Finis hes 6 0% 13-Jul-26 20-Jul-26 5 A2950, A3320
A2970 Floor Finishes 2 0% 26-Aug-26 27-Aug-26 131 A2960, A3330
A2980 Joineries 1 0% 28-Aug-26 28-Aug-26 131 A2970
1.4.3.5 Final Fixtures & Finishes 661 0% 12-Aug-24 22-Feb-27 5
1.4.3.5.1 Civil Works 661 0% 12-Aug-24 22-Feb-27 5
A3020 Internal Painting 44 0% 12-Aug-24 10-Oct-24 577
A3030 Interior Furnishing Works 120 0% 12-Aug-24 24-Jan-25 546 Interior Furnish
A3050 Internal Painting Final Coat 35 0% 12-Aug-24 27-Sep-24 631
A3200 External Painting Final Coat 35 0% 12-Aug-24 27-Sep-24 631
A2990 External Wall Fin ishes 75 0% 21-Jul-26 02-Nov-26 5 A2950, A3280, A1890, A3210, A2960
A3000 OH Tanks 28 0% 03-Nov-26 10-Dec-26 57 A2990
A3010 Waterproofin g Works 7 0% 03-Nov-26 11-Nov-26 78 A2990
A3040 External Painting 80 0% 03-Nov-26 22-Feb-27 5 A2990
1.4.3.5.2 MEP Works 604 0% 20-Sep-24 13-Jan-27 33
A3060 Plumbing Final Fixures 60 0% 20-Sep-24 12-Dec-24 577 A3020 Plumbing Final Fixures
A3070 Electrical Final Fixures 60 0% 20-Sep-24 12-Dec-24 577 A3020 Electrical Final Fixures
A3090 FPS Works 73 0% 15-Sep-26 24-Dec-26 47 A3320
A3100 HVAC Works 85 0% 16-Sep-26 12-Jan-27 34 A3320
A3080 ELV Works 76 0% 30-Sep-26 13-Jan-27 33 A3320
A3110 External Services & Connections 45 0% 10-Nov-26 11-Jan-27 35 A2990
1.4.7 Cafeteria 120 0% 14-Aug-26 28-Jan-27 22
1.4.7.1 Foundation Works 25 0% 14-Aug-26 17-Sep-26 117
A2660 Excavation 2 0% 14-Aug-26 17-Aug-26 0 A1420
A2670 Footings 3 0% 18-Aug-26 20-Aug-26 22 A2660
A2680 Plinth Beam 19 0% 21-Aug-26 16-Sep-26 22 A2670
A2690 PCC 7 0% 09-Sep-26 17-Sep-26 117 A2680
1.4.7.2 Structural Works 29 0% 17-Sep-26 27-Oct-26 89
1.4.7.2.1 Ground Floor 25 0% 17-Sep-26 21-Oct-26 22
A2770 RCC Vericals 10 0% 17-Sep-26 30-Sep-26 22 A2680
Actual Level of Effort Remaining Work Page 9 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 10 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A2780 RCC Horizontals 15 0% 01-Oct-26 21-Oct-26 22 A2770
1.4.7.2.2 Structural Steel Works 4 0% 22-Oct-26 27-Oct-26 89
A2790 Erection of Steel Truss 2 0% 22-Oct-26 23-Oct-26 89 A2780
A2800 Roofing Sheets 2 0% 26-Oct-26 27-Oct-26 89 A2790
1.4.7.3 Finishing Work 16 0% 01-Dec-26 22-Dec-26 49
1.4.7.3.1 Ground Floor 16 0% 01-Dec-26 22-Dec-26 49
A2700 Masonary Works 6 0% 01-Dec-26 08-Dec-26 22 A2780
A2710 Plumbing First Fix 2 0% 07-Dec-26 08-Dec-26 22 A2700
A2720 Electrical First Fix 2 0% 07-Dec-26 08-Dec-26 22 A2710
A2730 Soffit Finishes 3 0% 09-Dec-26 11-Dec-26 22 A2720
A2740 Internal Wall Finis hes 2 0% 14-Dec-26 15-Dec-26 22 A2730
A2750 Floor Finishes 2 0% 16-Dec-26 17-Dec-26 49 A2740
A2760 Joineries 3 0% 18-Dec-26 22-Dec-26 49 A2750
1.4.7.4 Final Fixtures & Finishes 32 0% 16-Dec-26 28-Jan-27 22
A2630 External Wall Fin ishes 7 0% 16-Dec-26 24-Dec-26 22 A2740
A3150 Electrical Final Fixures 7 0% 16-Dec-26 24-Dec-26 42 A2740
A2640 Waterproofin g Works 7 0% 25-Dec-26 04-Jan-27 22 A2630
A3170 Interior Final Coat Painting 5 0% 25-Dec-26 31-Dec-26 42 A3150
A3180 Exterior Final Coat Painting 5 0% 25-Dec-26 31-Dec-26 42 A3150
A3190 Exterior services & Connections 5 0% 25-Dec-26 31-Dec-26 42 A3150
A2650 Internal Painting 8 0% 05-Jan-27 14-Jan-27 22 A2640
A3120 Interior Works 5 0% 15-Jan-27 21-Jan-27 22 A2650
A3130 External Painting 5 0% 15-Jan-27 21-Jan-27 27 A2650
A3140 Plumbing Final Fixures 5 0% 15-Jan-27 21-Jan-27 27 A2650
A3160 ELV Works 5 0% 22-Jan-27 28-Jan-27 22 A3120
1.4.4 Electrical Room 80 0% 14-Aug-26 03-Dec-26 62
1.4.4.1 Foundation Works 25 0% 14-Aug-26 17-Sep-26 62
A2580 Excavation 2 0% 14-Aug-26 17-Aug-26 0 A2660
A2590 Footings 3 0% 18-Aug-26 20-Aug-26 62 A2580
A2600 Plinth Beam 19 0% 21-Aug-26 16-Sep-26 62 A2590
A2610 PCC 7 0% 09-Sep-26 17-Sep-26 62 A2600
1.4.4.2 Structural Works 15 0% 18-Sep-26 08-Oct-26 102
1.4.4.2.1 Ground Floor 15 0% 18-Sep-26 08-Oct-26 102
A2570 RCC Verticals 10 0% 18-Sep-26 01-Oct-26 107 A2610
Actual Level of Effort Remaining Work Page 11 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 12 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A2620 RCC Horizontals 15 0% 18-Sep-26 08-Oct-26 62 A2610
1.4.4.3 Finishing Work 20 0% 09-Oct-26 05-Nov-26 82
1.4.4.3.1 Ground Floor 20 0% 09-Oct-26 05-Nov-26 82
A2360 Masonary Works 6 0% 09-Oct-26 16-Oct-26 62 A2620
A2510 Plumbing First Fix 2 0% 19-Oct-26 20-Oct-26 62 A2360
A2520 Electrical First Fix 2 0% 21-Oct-26 22-Oct-26 62 A2510
A2530 Soffit Finishes 3 0% 23-Oct-26 27-Oct-26 62 A2520
A2540 Internal Wall Finis hes 2 0% 28-Oct-26 29-Oct-26 62 A2530
A2550 Floor Finishes 2 0% 30-Oct-26 02-Nov-26 82 A2540
A2560 Joineries 3 0% 03-Nov-26 05-Nov-26 82 A2550
1.4.4.4 Final Fixtures & Finishes 25 0% 30-Oct-26 03-Dec-26 62
A2430 External Wall Fin ishes 5 0% 30-Oct-26 05-Nov-26 62 A2540
A2440 Waterproofin g Works 7 0% 06-Nov-26 16-Nov-26 62 A2430
A2450 Internal Painting 4 0% 17-Nov-26 20-Nov-26 62 A2440
A2460 Plumbing Final Final Fixures 2 0% 23-Nov-26 24-Nov-26 69 A2450
A2470 Electrical Final Fixures 2 0% 23-Nov-26 24-Nov-26 69 A2450
A2480 Interior Works 3 0% 23-Nov-26 25-Nov-26 68 A2450
A2490 External Painting 4 0% 23-Nov-26 26-Nov-26 62 A2450
A2500 Final Coat Paint - Int & Ext 5 0% 27-Nov-26 03-Dec-26 62 A2490
1.4.5 Pump/Utility Room 98 0% 18-Aug-26 31-Dec-26 42
1.4.5.1 Foundation Works 25 0% 18-Aug-26 21-Sep-26 115
A2390 Excavation 2 0% 18-Aug-26 19-Aug-26 0 A2580
A2400 Footings 3 0% 20-Aug-26 24-Aug-26 0 A2390
A2410 Plinth Beam 19 0% 25-Aug-26 18-Sep-26 0 A2400
A2420 PCC 7 0% 11-Sep-26 21-Sep-26 115 A2410
1.4.5.2 Structural Works 15 0% 21-Sep-26 09-Oct-26 0
1.4.5.2.1 Ground Floor 15 0% 21-Sep-26 09-Oct-26 0
A2370 RCC Verticals 10 0% 21-Sep-26 02-Oct-26 0 A2410
A2380 RCC Horizontals 5 0% 05-Oct-26 09-Oct-26 0 A2370
1.4.5.3 Finishing Work 16 0% 19-Nov-26 10-Dec-26 57
1.4.5.3.1 Ground Floor 16 0% 19-Nov-26 10-Dec-26 57
A2290 Masonary Works 6 0% 19-Nov-26 26-Nov-26 42 A2380
A2300 Plumbing First Fix 2 0% 25-Nov-26 26-Nov-26 42 A2290
A2310 Electrical First Fix 2 0% 25-Nov-26 26-Nov-26 42 A2300
Actual Level of Effort Remaining Work Page 13 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 14 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A2320 Soffit Finishes 3 0% 27-Nov-26 01-Dec-26 42 A2310
A2330 Internal Wall Finis hes 2 0% 02-Dec-26 03-Dec-26 42 A2320
A2340 Floor Finishes 2 0% 04-Dec-26 07-Dec-26 57 A2330
A2350 Joineries 3 0% 08-Dec-26 10-Dec-26 57 A2340
1.4.5.4 Final Fixtures & Finishes 20 0% 04-Dec-26 31-Dec-26 42
A2250 External Wall Fin ishes 5 0% 04-Dec-26 10-Dec-26 42 A2330
A2260 Waterproofin g Works 7 0% 11-Dec-26 21-Dec-26 42 A2250
A2270 Internal Painting 4 0% 22-Dec-26 25-Dec-26 42 A2260
A2280 External Painting 4 0% 28-Dec-26 31-Dec-26 42 A2270
1.4.6 External Works 140 0% 18-Aug-26 01-Mar-27 0
1.4.6.1 Drain 62 0% 12-Oct-26 05-Jan-27 39
A2220 Earthworks 26 0% 12-Oct-26 16-Nov-26 0 A2380
A2230 RCC Drains 30 0% 17-Nov-26 28-Dec-26 39 A2220
A2240 Precast Cover Slab 6 0% 29-Dec-26 05-Jan-27 39 A2230
1.4.6.2 UG Tank 63 0% 12-Oct-26 06-Jan-27 38
A2170 Earthworks 26 0% 12-Oct-26 16-Nov-26 0 A2220
A2180 Base Slab 10 0% 17-Nov-26 30-Nov-26 38 A2170
A2190 RCC Wall 15 0% 01-Dec-26 21-Dec-26 38 A2180
A2200 Internal Finishes 6 0% 22-Dec-26 29-Dec-26 38 A2190
A2210 Cover Slab 6 0% 30-Dec-26 06-Jan-27 38 A2200
1.4.6.3 STP 97 0% 12-Oct-26 23-Feb-27 4
A2130 Earthworks 12 0% 12-Oct-26 27-Oct-26 0 A2170
A2140 Substructure 20 0% 28-Oct-26 24-Nov-26 4 A2130
A2150 Super structure - steel 45 0% 25-Nov-26 26-Jan-27 4 A2140
A2160 Equipments Installations & Connections 20 0% 27-Jan-27 23-Feb-27 4 A2150
1.4.6.4 Security Cabin 88 0% 12-Oct-26 10-Feb-27 13
A2090 Earthworks 3 0% 12-Oct-26 14-Oct-26 0 A2130
A2100 Substructure 15 0% 15-Oct-26 04-Nov-26 13 A2090
A2110 Super structure 40 0% 05-Nov-26 30-Dec-26 13 A2100
A2120 Finishes including Electrical Works 30 0% 31-Dec-26 10-Feb-27 13 A2110
1.4.6.5 Compound Wall 101 0% 12-Oct-26 01-Mar-27 0
A2050 Earthworks 12 0% 12-Oct-26 27-Oct-26 0 A2090
A2060 Foundation 26 0% 28-Oct-26 02-Dec-26 0 A2050
A2070 Wall Construction 36 0% 03-Dec-26 21-Jan-27 0 A2060
Actual Level of Effort Remaining Work Page 15 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 16 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Activity ID Resource Activity Name Original Duration Schedule % Start Finish Total Float Predecessors Qtr 1, 2025
IDs Complete
Jan
A2080 Finishes 27 0% 22-Jan-27 01-Mar-27 0 A2070
1.4.6.6 Landscaping Works 140 0% 18-Aug-26 01-Mar-27 0
A2030 HardScaping 140 0% 18-Aug-26 01-Mar-27 0 A2080
A2040 SoftScaping 80 0% 10-Nov-26 01-Mar-27 0 A2080
1.4.8 Testing & Commisioning 20 0% 20-Oct-26 16-Nov-26 75
A1980 Lift 20 0% 20-Oct-26 16-Nov-26 75 A2220
A1990 Electrical Items Including DG 20 0% 20-Oct-26 16-Nov-26 75 A2220
A2000 ELV Items 20 0% 20-Oct-26 16-Nov-26 75 A2220
A2010 FPS Items 20 0% 20-Oct-26 16-Nov-26 75 A2220
A2020 HVAC Items 20 0% 20-Oct-26 16-Nov-26 75 A2220
1.4.9 Handover 30 0% 06-Oct-26 16-Nov-26 75
A1960 Snagging & Desnagging 30 0% 06-Oct-26* 16-Nov-26 75 A2220
A1970 AsBuilt drawings 30 0% 06-Oct-26 16-Nov-26 75 A2220
1.5 Project Completion 0 0% 0
Actual Level of Effort Remaining Work Page 17 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
KINFRA IECC Classic Schedule Layout 16-May-24 10:35
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Actual Level of Effort Remaining Work Page 18 of 18 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation