Scheduling Through Week 21AI
Scheduling Through Week 21AI
All trademarks / copyrights of other companies are respected and are properties of those companies.”
Primavera Risk Analysis
• It is Friday 13th July 2023 - do not worry that this is in the past, all
the things you will learn will still be totally relevant. And because
this project has already finished, we can tell you that the project
came in early, well within budget and everyone got a huge pay
rise - so your typical project really !!!
Primavera Risk Analysis
• File | New
• Choose the "New Plan" template and click Open.
• Plan | Plan Information.
• Enter 'Garden Landscaping' in the Plan Title.
• Click on the Dates tab.
• Change the Plan Start Date to 15/07/23.
• Change the Data Date to 15/07/23.
• Click on OK to exit the dialog box.
Entering tasks
• 1. Move the mouse to the end of the "Buy fence materials" task bar
- you must move the mouse past the duration symbol until it
changes to F-?
• 2. Click and drag the F-? mouse pointer to the start of the "Dig
post holes" task bar. The mouse pointer should change to F-S.
• Any tasks that are then assigned the resource LABORER will not be
able to take place on the weekends.
• The cost of a resource is accrued every time a unit of resource is used by a task. The number
of resource units used by a task depends on the loading of the resource, the number of
resource units assigned and the task duration.
• Examples
• How cost is accrued for a task with a normal loading
• In this tutorial we will be assigning one unit of the resource LABORER to the task 'Put up posts'.
• As the resource LABORER has a normal loading, one unit of the resource will be used every
day.
• 'Put up posts' has a duration of 3 days. Therefore it will use 3 units of the resource LABORER. So
at a cost of $30 per unit the total cost will be $90.
• How cost is accrued for a task with a spread loading
• In our tutorial we will be assigning one unit of the resource PAINT to the task 'buy paint'.
• As the resource PAINT has a spread loading only one unit is used regardless of the task
duration.
• 'Buy paint' will therefore use one unit of the resource paint. So at a cost of $30 per unit the
total cost will be $30.
Assigning a cost to a resource
• Follow the steps below to enter the costs for the resources in Mr. House's project.
• Select the cell under Cost that corresponds to the resource you wish to add a cost
to.
• Type in the costs shown below.
• FENCE=$100
• FISH=$20
• LABORER=$30
• PAINT=$30
• SAND=$20
• SLABS=$100
• Assigning a supply to a resource
• The supply defines how many units of resource are available at any one time.
• The materials have an infinite supply because Mr. House can go to the shops and
buy more. On the other hand the supply of laborers is limited because Mr. House
only knows two laborers that he can employ for the project.
• Follow the steps below to change the supply
of LABORER to 2
Assigning a cost to a • Select the cell under Supply that corresponds
to the supply of the LABORER.
resource
• Type in a value of 2.
• The resource setup should now look like this:
. Assigning resources to tasks
• 1. The plan does not finish on time when the resources are leveled. Remember the
Best Gardens competition is on the 28th July!
• Mr. House tries to kill two birds with one stone. He wants to see the effect of taking
the laborer off the 'line pond' task and doing it himself.
• Remove the LABORER resource assigned to 'Line pond' by following the steps below
• Select the task 'Line pond'.
• In the Task Details click on the Resources tab
• Click on the LABORER.
• Press delete key on the keyboard.
• Now the plan is adjusted a quick look at the totals line tells you that the
estimated project cost is now $840 and therefore just within the project
budget.
• But before we can start cheering we need to see if the project now
finishes on time when the resources are leveled
• Reset the tasks back to their earliest starts and level the plan
• Plan | Level Resources.
• The option Reset all the tasks to their early start dates should be already
checked - if not check it now. This ensures that the results of our
previous resource level are reset before we level again.
• Click Level Now button.
• Your plan should now look like this:
Printing
• If you click on the 80% date in the right hand vertical axis a line is
drawn that hits the curve and then goes vertically down to the
same date.
• Find the approximate position of the 80% date on the horizontal axis.
• You will notice that the majority of the hits are to the left of this date. In
fact 80% of the hits are to the left and 20% are to the right. So during the
analysis 80% of the finish dates were on or before the 20th May and 20%
of the finish dates were after the 20th May. You can therefore say there
is an 80% chance of the finish date being on or before the 20th May.
• So if this was your project plan you would now have some very useful
information about the date you are likely to finish your project.
• One of the things that makes a project risky is the number of tasks that run in
parallel. With tasks in parallel it only takes one to be late and the project is late
but all the parallel tasks must be early for the plan to be early.
Criticality Index
• Format | Columns.
• In Grouped Fields tab locate and select the column ‘Risk Output –
Criticality Index’ under Risk Outputs.
• Add it to the Right Columns tab by selecting the Right Columns tab and
pressing the > button.
• Use the Up and Down buttons to move your new column to the desired
location and click OK.
•
• You will notice it has been filled with values that vary from 0% to 100%
(before the analysis they were all 0%).
• The Criticality Index tells you how often a task was on the critical path
during the risk analysis. The reason tasks can sometimes be on the
critical path and sometimes not is because during the risk analysis the
task durations vary and this can alter the critical path. You will have
seen the critical path change if you watched the tasks during the step
through analysis.
Criticality Index
• The interesting thing about the criticality index is that it helps you identify those
tasks that are most likely to be critical during the project.
• To make a bit more sense of this report we will sort the tasks by criticality.
• View | Sort...
• Select 'Criticality'
• Click Apply.
• Click Close.
• The tasks should now be sorted in order of criticality. Tasks with the same
criticality are sorted by start date.
• The tasks that have 100% criticality are most likely to be on the critical path
during the project and they therefore should be given the most attention.
• Edit | Undo sort.
This will undo the sort by criticality you have just applied. There are multiple
levels of undo and redo should you need them.
•
Thank You!
All trademarks / copyrights of other companies are respected and are properties of those companies.”