Real Time Project Using ETAP-Combined Cycle Plant
Real Time Project Using ETAP-Combined Cycle Plant
Mail id:[email protected]
Real Time projects using ETAP for the combined cycle power plant
pg. 1
Subbiahkannan
Mail id:[email protected]
pg. 2
Subbiahkannan
Mail id:[email protected]
3.)What is Efficiency?
Energy can neither be created nor be destroyed it can convert the one form
energy into other form of energy
Efficiency always defined as the output/Input
Note:-
The above two terminology are conflicted because the energy can
neither be created nor be destroyed.
Then output is always equal to input because the energy always not
destroyed
Efficiency can be defined in better way
Efficiency = useful input/output
Because input is always equal to output
We call some losses that losses also some output we are not utilizing it
pg. 3
Subbiahkannan
Mail id:[email protected]
4.)What about the efficiency of Open cycle plant & combine cycle gas turbine
plant?
In open cycle plant, the exhaust gas is wasted that is not used
In combine cycle plant, waste some amount of heat that can be extracted &
convert into electricity
Then obviously efficiency is more & you will be able to increase the efficiency
of Gas turbine plant from 45% to 60% in the combine cycle plant
5.)Case study of Combine cycle plant(Introduction)
pg. 4
Subbiahkannan
Mail id:[email protected]
Now we are going to see why we are using the NGTR and how to choose the
power factor of 0.85 and which regulation they are go with p.f. of 0.85 why not
0.9 or 0.95 p.f. used these are the question you may ask?
pg. 5
Subbiahkannan
Mail id:[email protected]
Note:-
It is the Non-Generator Circuit Breaker scheme
Unit Auxiliary Transformer rating:
Here you are having the unit auxiliary transformer & its capacity is 16MVA and
voltage rating is 15.75/6.9kV
In the unit auxiliary transformer also, you are having the NGR which limits the
fault current of 300A
Why not they are not using the solid ground system instead they are go with
Resistance ground system
Unit auxiliary transformer for supply the auxiliary loads for our gas turbines
pg. 6
Subbiahkannan
Mail id:[email protected]
pg. 7
Subbiahkannan
Mail id:[email protected]
It also important to identify where do we need the on load tap changer is need &
where off load tap changer is sufficient
What is the tap range we need to select for the transformer all those things we
need the Load flow analysis
Load flow analysis is essential for any combine cycle plant at the initial
stage along the engineering stage & as built stage itself
Short circuit study:
How to select the short circuit rating of MV switchgear
How to select the short circuit rating of LV switchgear
Generator step up transformer impedance
Unit Auxiliary transformer impedance
Station Auxiliary transformer impedance
Generator circuit breaker rating
Motor Acceleration/Motor starting study:
Combine cycle plant uses the natural gas Compressor.
if you have the gas plant then compressor needs the largest capacity of motor
you need
Note:-
Boiler feed pump might be the largest motor in the thermal power plant
Transient stability study:
To perform and check what is the critical clearing time
Relay co-ordination study:
To give the protection setting
Arc flash studies
To ensure that what is the personal protective equipment is needed
Why Arc flash study is needed like you may need the live maintenance on your
switchgears then you need arc flash study
pg. 8
Subbiahkannan
Mail id:[email protected]
You may need the Harmonic Analysis, if your system consists of Variable
frequency drives for the medium voltage motors
It is the optional & it is required only when considerable VFD’s are used
The above studies are come under the steady state and electromechanical transients
In addition to that since this system is connected to 400kV, then definitely you need the
Insulation co-ordination study for 400kV
Temporary over voltage,
slow front over voltage
switching over voltage
transformer energization
Lightning over voltage is need when your outgoing feeders are
transmission lines
If it is the Gas Insulated substation then you need the very fast front
overvoltage
8.)Why high-capacity Generator should not solidly grounded & why they are
connected to NGTR
pg. 9
Subbiahkannan
Mail id:[email protected]
So, it is important and limit the SLG current much less than what is the stator
core saturation or damage value
Hence typically the High-capacity generator are limited SLG fault current to 5A
& limiting the SLG fault current into 5A in 15.75kV generator need the huge
rating of NGR it is practically not possible to have the high neutral grounding
resistor value
This is the reason why we go with one transformer with step down
voltage from 15.75kV to 0.24kV and you are connecting the small
resistance which limits the SLG fault current
since the resistance value is connected to the huge value on the other
side that limit the SLG fault current to a very small value typically 5A
Note:
Please try to understand 600A at 240V of the LV side of it & not the HV side
pg. 10
Subbiahkannan
Mail id:[email protected]
pg. 11
Subbiahkannan
Mail id:[email protected]
pg. 12
Subbiahkannan
Mail id:[email protected]
Answer:-
These 6.174A is the SLG fault current that is going to have the very short time
Whereas 50kVA,3A is the continuous current you might be aware the
transformer can withstand through fault current for 2sec
So, like these NGT can withstand much higher current than the current of 6A
what is going to flow during the SLG current because the duration is restricted to
very few milliseconds or seconds
pg. 13
Subbiahkannan
Mail id:[email protected]
Answer:
Here the generator is rated at 40deg Celsius and here step-up transformer is
rated at 50deg Celsius
So, whenever you select the transformer for the combine cycle plant or gas
plant please be remember
Collect the generator capability curve at the different temperatures
from the OEM
Collect the capability curve for generator step up transformer at
various temperatures from the OEM
Then decide the transformer rating
I am repeating once,
Collect the rating Vs different temperature of the generator OEM
Collect the rating Vs different temperature of the transformer OEM
Then you select the ideal one.
if you draw the graph between the generator rating & transformer rating
pg. 14
Subbiahkannan
Mail id:[email protected]
When we say the rating of Generator & step-up transformerSLD may confuse
SLDsays that the Generator step up transformer(230MVA) may be in-
adequately size by looking at the generator(240MVA) but it is good enough
Because 50deg Celsius,230MVAthese trafo will be much more than the
240MVA at 40deg Celsius
13.)What is the purpose of On-load tap changer in generator step-up
transformer?
Option:
a.)To regulate the grid voltage
b.)To regulate the generator terminal voltage
c.)To extract the maximum reactive power capability from the generator
Answer: B & C
b.)To regulate the generator terminal voltage
c.)To extract the maximum reactive power capability from the generator
pg. 15
Subbiahkannan
Mail id:[email protected]
For the given system with 100% grid voltage, real power injected to grid is 49.5
MW and, the reactive power absorbed from grid is 7.35 MVAr
At PCC leading power factor of 98.92% is observed.
The generator terminal voltage (Vg) is maintained at 100% and the loss in
Generator transformer (GT) at 0% tap having impedance of 12.5% is 0.07 MW
and 3.14 MVAr.
At 100% grid voltage, generator absorbs reactive power of 4.03 MVAr
I repeat my statement,
In generator step up transformer HV winding no-load voltage is as same as the
grid voltage
pg. 16
Subbiahkannan
Mail id:[email protected]
During the normal grid voltage, the generator starts absorbing the reactive power
from the grid, leads to the leading power factor these may impact the penalty
from the utility
If you don’t have the OLTC, then you don’t able to extract the reactive power
capability of these generator to the grid
In some of the plants, it is important to understand as the individual power
producer you will be having two benefits
pg. 17
Subbiahkannan
Mail id:[email protected]
Result of LFA:
These generators neither generate the real power nor generate the reactive power
I have given all the information & I have given all this data but un-fortunately it
is not generating any real power or reactive power why?
“Capacity is something different and what now generating is different ”
pg. 18
Subbiahkannan
Mail id:[email protected]
pg. 19
Subbiahkannan
Mail id:[email protected]
If you see the case-1 in which generator is generating 4.95MVAr and in case-2
the generator generates the 112.5MVAr
If you see the case-1 you extract the reactive power of 14.2MVAr from the
grid and in case-2 you inject the reactive power of 87.8MVAr to the grid
pg. 20
Subbiahkannan
Mail id:[email protected]
What is Qmax:
In the thermal unit,
Then Qmax, it is the maximum reactive power generate by the generator
should be 0.60*Pmax
For ex:-
if we have 100MW thermal unit, then which can able to generate at-least
60MVAr
What is Qmin:
In the thermal unit,
Then Qmin, it is the maximum reactive power absorb by the generator
should be (-)0.30*Pmax
For ex:-
if we have 100MW thermal unit, then which can able to absorb at-least 30MVAr
Depends on the generator and the grid code
Like every country which provide some regulations for the nuclear unit, thermal
unit, wind/solar for renewable they will provide some Qmin and Qmax value
based on that you have to give the generator power factor
pg. 21
Subbiahkannan
Mail id:[email protected]
So, in our case 0.85 power factor at the time only we can maintain the above
grid regulations
Each & every grid code has their own requirements of what is the reactive power
must be supported
Typically, 0.95 power factor for renewables.
Whereas 0.85,0.9.0.95 depends on the thermal, hydro, nuclear etc.,
pg. 22