Project Management Question Bank Cluster 09
Project Management Question Bank Cluster 09
1. Assembling project team and assigning their responsibilities are done during which phase of a
project management?
a. Initiation
b. Planning
c. Execution
d. Closure
4. A process that involves continuously improving and detailing a plan as more detail become
available is termed as
a. project analysis
b. project enhancing
c. progressive deliberation
d. progressive elaboration
1
8. The scope of the work is defined in which phase of the project management?
a. Initiating
b. Planning
c. Executing
d. Closing
9. How the project work will be carried out, monitored, and controlled? These questions are ed in
which phase of the project management?
a. Initiating
b. Planning
c. Executing
d. Closing
10. The review of the successes and the mistakes is normally held during _____ phase.
a. initiation
b. planning
c. execution
d. closure
11. A ____ is a set of activities which are networked in an order and aimed towards achieving the
goals of a project.
a. Project
b. Process
c. Project management
d. Project cycle
2
16. Following are the phases of Project Management Life Cycle. Arrange them in correct order
1.Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery
a. 3-2-1-4
b. 1-2-3-4
c. 2-3-1-4
d. 4-3-2-1
20. Resource requirement in project becomes constant while the project is in its _____ progress stage.
a. 40 to 55%
b. 55 to 70%
c. 70 to 80%
d. 80 to 95%
21. The probability of completing the project can be estimated based upon the ____ .
a. Uniform distribution curve
b. Normal distribution curve.
c. U-shaped distribution curve
d. None of the above
22. In the initial stage of the project the probability of completing the project is ___ .
a. Zero
b. High
c. Low
d. Any of the above
23. The entire process of a project may be considered to be made up on number of sub process placed
in different stage called the
a. Technical key resources
3
b. Work key structure
c. Work Breakdown Structure (WBS).
d. None of the above
24. Tool used for comparison of the proposed project to complete projects of a similar nature whose
costs are known.
a. Algorithmic model
b. Expert judgment
c. Top down
d. Analogy
25. Each component of the software product is separately estimated and the results aggregated to
produce an estimate for the overall job.
a. Algorithmic model
b. Expert judgment
c. Bottom-up
d. Top down
28. Devising and maintaining a workable scheme to accomplish the business need” is
a. Initiating process
b. Planning process
c. Executing process
d. Controlling process
4
31. Which of these is not one of the constraints of a project?
a. Scope
b. Resources
c. Team
d. Budget
32. Which of the following is not correct about initial phase of a project?
a. The cost associated at the beginning of the project is highest.
b. Stakeholders have maximum influence during this phase
c. The highest uncertainty is at this stage of the project.
d. All the above statements are correct.
33. The project you are managing has nine stakeholders. How many channels of communications are
there between these stakeholders?
a. 9
b. 8
c. 45
d. 36
35. A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can
BEST describe the difference of $5,000?
a. Cost Variance
b. Management Overhead
c. Management Contingency Reserve
d. Schedule Variance
37. Andrew has joined as the Project Manager of a project. One of the project documents available to
Andrew lists down all the risks in a hierarchical fashion. What is this document called?
a. Risk Management Plan.
b. List of risks.
5
c. Monte Carlo diagram.
d. Risk Breakdown Structure.
38. During which stage of Risk planning are risks prioritized based on probability and impact?
a. Identify Risks
b. Plan Risk responses
c. Perform Qualitative risk analysis
d. Perform Quantitative risk analysis s
40. Which of the following does NOT generate changes to the Project documents?
a. Define Activities
b. Sequence Activities
c. Estimate Activity Resources
d. Estimate Activity Durations
41. is a set of activities which are networked in an order and aimed towards achieving the goals of
project?
a. Project
b. Process
c. Project management
d. Project cycle
42. Resources refers to
a. Manpower
b. Machinery
c. Materials
d. All of the above
6
c. Formulation and planning various activities
d. All of the above
46. Following are the phases of Project Management Life Cycle. Arrange them in correct order
1.Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery
a. 3-2-1-4
b. 1-2-3-4
c. 2-3-1-4
d. 4-3-2-1
50. Resource requirement in project becomes constant while the project is in its _____ progress stage.
a. 40 to 55%
b. 55 to 70%
c. 70 to 80%
d. 80 to 95%
51. The probability of completing the project can be estimated based upon the ____ .
a. Uniform distribution curve
b. Normal distribution curve.
c. U-shaped distribution curve
d. None of the above
7
52. In the initial stage of the project the probability of completing the project is ___ .
a. Zero
b. High
c. Low
d. Any of the above
53. The entire process of a project may be considered to be made up on number of sub process placed
in different stage called the
a. Technical key resources
b. Work key structure
c. Work Breakdown Structure (WBS).
d. None of the above
54. Tool used for comparison of the proposed project to complete projects of a similar nature whose
costs are known.
a. Algorithmic model
b. Expert judgment
c. Top down
d. Analogy
55. Each component of the software product is separately estimated and the results aggregated to
produce an estimate for the overall job.
a. Algorithmic model
b. Expert judgment
c. Bottom-up
d. Top down
58. “Devising and maintaining a workable scheme to accomplish the business need” is
a. Initiating process
b. Planning process
8
c. Executing process
d. Controlling process
9
66. Completion of a CPM network diagram activity is commonly known
a. Connector
b. Event
c. Node
d. All the above.
67. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times
for the three activities are 12, 15, and 10, then the earliest start time for Y will be
a. 10
b. 15
c. 12
d. Cannot be determined
68. Activities P, Q and R instantly follow activity M, and their current start times are 12, 19, and 10.
Therefore, the latest finish time for activity M is
a. 11
b. 10
c. 18
d. Cannot be determined
71. A project has three independent critical paths A, B and C. To reduce the project length, we have
to shorten
a. The activities of A
b. The activities of B
c. The activities of C
d. The activities of A, B, and C simultaneously.
10
d. All the above.
73. Referring the figure state which one of the following statements, is correct:
a. The initial node of activity b is 2
b. The final node of activity b is 3
c. The initial nodes of activities b and c are the same
d. All the above.
77. The technique for establishing and maintaining priorities among the various jobs of a project, is
known
a. Event flow scheduling technique
b. Critical ratio scheduling
c. Slotting technique for scheduling
d. Short interval scheduling.
78. The PM distributed a document to the stakeholders, which described the software to be
developed, the functionality, the users it would serve and the installation timeline. The document
was an example of:
a. Product scope
b. Project scope
c. A combination of project and product scope
d. It was not complete enough to be either a product or a project scope document
79. Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name of
this identifier?
11
a. Product ID number
b. Code of accounts
c. Quality inspection identifier
d. Project activity code
80. When developing a project's scope statement, which of the following should not be included?
a. Project justification.
b. Cost/benefit analysis
c. Project deliverables
d. Measurable objectives
82. Which of the option is not a notable challenge while scheduling a project?
a. Deadlines exist.
b. Independent activities.
c. Too many workers may be required.
d. Costly delay
12
c. Node
d. All the above.
87. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times
for the three activities are 12, 15, and 10, then the earliest start time for Y will be
a. 10
b. 15
c. 12
d. Cannot be determined
88. Activities P, Q and R instantly follow activity M, and their current start times are 12, 19, and 10.
Therefore, the latest finish time for activity M is
a. 11
b. 10
c. 18
d. Cannot be determined
13
c. avoids delays which are very common in bar charts
d. All the above.
99. The artificial activity which indicates that an activity following it, cannot be started unless the
preceding activity is complete, is known as
a. event
b. free float
c. dummy
d. constant.
14
c. does not consume time
d. all the above.
102. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start
and latest finish time, then the following relation holds good
a. EF = ES + D
b. LS = LF? D
c. LF = LS + D
d. all the above.
103. The difference between the time available to do a job and the time required to do the job,
is known as
a. event
b. float
c. duration
d. constraint.
104. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
a. LST-EST
b. LFT- EFT
c. TL-EFT
d. all the above.
106. The time by which activity completion time can be delayed without affecting the start of
succeeding activities, is known as
a. duration
b. total flat
c. free float
d. interfering float.
107. For completion of a project, the critical path of the network represents
a. minimum time
b. maximum time
c. maximum cost
15
d. minimum cost.
110. Pick up the correct network for the activities of pouring concrete, erection of form work,
removal of form work and curing of concrete from the following:
a. Pouring of Concrete,2. Erection of form work,3. Curing of concrete,4. Removal of form
work
b. Erection of form work ,2. Pouring of concrete3. Curing of concrete,4. Removal of form
work
c. Removal of form work 2. Erection of form work3. Pouring of concrete,4. Curing of
concrete
d. Pouring of concrete2. Curing of concrete 3. Erection of form work 4. Removal of form
work.
111. In a certain project an activity C can only be started when activities A and B have been
completed, which have no bearing on each other and can be started independently. The correct
network for the activities, is
a. Activities A and B can be started independently
b. Activity C can be started only on completion of activity A
c. Activity D can be started only on completion of activity
d. all the above
112. In a project logic, four activities M, N, 0 and P are to be completed before starting
activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr.
respectively, the earliest event occurrence time for the activity
a. 1200 hr.
b. 1400 hr.
c. 1500 hr.
d. 1700 hr.
113. If the total float and duration of an activity are 5 and 10 days respectively, the particular
activity can be
16
a. started 5 days later
b. completed 5 days later
c. performed at slower rate in 15 days
d. all the above.
115. Critical path lies along the activities having total float
a. positive
b. negative
c. zero
d. same.
117. The time which results in the least possible construction cost of an activity, is known
a. normal time
b. slow time
c. crash time
d. standard time.
118. The technique for establishing and maintaining priorities among the various jobs of a
project is known
a. Event flow scheduling technique
b. Critical ratio scheduling
c. Slotting technique for scheduling
d. Short interval scheduling.
17
d. none of these.
120. If a is the optimistic time, b is the pessimistic time and m is most likely time of an
activity, the expected time of the activity, is
a. a + m + b
b. a + 2rn + b
c. a + 4m + b
d. a + 5m +b
124. Under which category of Project Selection models is the "Payback period" categorized?
a. Non-Numeric project selection model
b. Theoretical Project selection model
c. Numeric project selection model
d. Classical Project selection model
125. A document that formally authorizes the existence of a project and provides the project
manager with the authority to apply organizational resources to project activities is:
a. Project Plan
b. Project Report
c. Project Budget
d. Project Charter
18
126. Under which category of Project Selection models is the "Sacred Cow" categorized?
a. Non-Numeric project selection model
b. Theoretical Project selection model
c. Numeric project selection model
d. Classical Project selection model
128. Which of the following is the correct sequence of Project Team building activities
a. Forming, Norming, Storming, Performing
b. Forming, Storming, Performing Norming
c. Forming, Performing, Storming, Norming
d. Forming, Storming, Norming, Performing
129. Which are the decisions at the GATE in Stage Gate Process?
a. Go, Kill, Hold, Recycle
b. Go, Start, Process, Recycle
c. Hold, Process, Inspect, Recycle
d. Hold, Kill, Inspect, Recycle
130. Which of the following is a Project Management Knowledge area as defined by Project
Management Institute (PMI)?
a. Project Financial Management
b. Project Personnel Management
c. Project Integration Management
d. Project Purchasing Management
19
133. The activity "Acquire project team" is a part of:
a. Closing Process Group
b. Monitoring and Control Process Group
c. Executing Process Group
d. Planning Process Group
136. Which of the following activity is included in the “Project Integration Management”?
a. Develop project charter
b. Plan Scope Management
c. Define Scope
d. Collect requirements
137. Which of the following activity is included in the “Project Scope Management”?
a. Develop project charter
b. Collect Requirements
c. Define Activities
d. Sequence Activities
138. Which of the following activity is included in the “Project Time Management”?
a. Develop project charter
b. Collect Requirements
c. Define Activities
d. Determine Budget
139. Which of the following activity is included in the “Project Cost Management”?
a. Develop project charter
b. Collect Requirements
c. Define Activities
d. Determine Budget
20
140. The activity "Create Work Breakdown Structure (WBS)" is a part of:
a. Project Scope Management
b. Project Cost Management
c. Project Time Management
d. Project Scope Management
141. In the process to develop the Project Charter, under which category “Enterprise
Environmental Factors” are considered?
a. Inputs
b. Tools and Techniques
c. Outputs
d. Objectives
143. The abbreviation "PERT" used in Project Network Analysis stands for:
a. Project Examination and Rectification Technique
b. Projects Evaluation for Rapid Testing
c. Project Evaluation and Review Technique
d. Programmed Examination and Recognition Technique
144. Any Task or Operation which consumes resources like man hours, time, capital, machine
hours etc. is called as:
a. Event
b. Activity
c. Process
d. Program
145. An Event which represents the start of Multiple Activities is called as:
a. Simple Event
b. Burst Event
c. Merge Event
d. Critical Event
146. An Activity which must be completed before the start of Another activity is called as:
a. Predecessor Activity
21
b. Successor Activity
c. Dependent Activity
d. Follower Activity
a. Predecessor Activity
b. Successor Activity
c. Dependent Activity
d. Follower Activity
148. Observing the Given Project Network Diagram, Select the correct Statement.
149. 8. In the Given Project Network Diagram, Identify the Successor Activity for Activity C :
22
a. Activity B
b. Activity A
c. Activity D
d. Activity F
153. The maximum possible time taken by an activity for completion is called as:
a. Optimistic Time
b. Pessimistic Time
c. Most Likely Time
d. Expected Time
23
c. More than Optimistic Time but Less than Pessimistic Time
d. Equal to the Expected Time
156. For a certain activity, the time estimates in days are: Optimistic Time=2, Most Likely
Time=5 and Pessimistic Time=8. Determine the Expected Time for activity.
a. 5 days
b. 4 days
c. 6 days
d. 8 days
157. For a certain activity, the time estimates in days are: Optimistic Time=1, Most Likely
Time=1 and Pessimistic Time=1. Which of the following statement is correct?
a. Variance=1
b. Variance=2
c. Variance=0
d. Variance=3
158. For a certain activity, Earliest Start Time(EST)=20, Earliest Finish Time (EFT)=45, latest
Start Time (LST)= 20 and Latest Finish Time (LFT)= 45. Determine the value of TOTAL Float.
a. Total Float=20
b. Total Float=45
c. Total Float=25
d. Total Float=00
159. Which of the following is the Appropriate criterion to select any project?
a. Net Present Value (NPV) should be positive
b. Net Present Value (NPV) should be negative
c. Benefit Cost Ratio (BCR) should be less than One
d. Net Benefit Cost Ratio (NBCR) should be less than Zero
160. The demand for disposable plastic tubes for a general hospital is 300 units and 350 units
for September and October month respectively. Using 200 units as the forecasted demand for
September Month, calculate the forecasted demand for October month. Consider the value of
Smoothing constant=0.7
a. 270 units
b. 300 units
c. 350 units
24
d. 200 units
161. A ____ is a set of activities which are networked in an order and aimed towards
achieving the goals of a project.
a. Project
b. Process
c. Project management
d. Project cycle
166. Following are the phases of Project Management Life Cycle. Arrange them in correct
order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery
a. 3-2-1-4
b. 1-2-3-4
c. 2-3-1-4
25
d. 4-3-2-1
170. Resource requirement in project becomes constant while the project is in its _____
progress stage.
a. 40 to 55%
b. 55 to 70%
c. 70 to 80%
d. 80 to 95%
171. The probability of completing the project can be estimated based upon the ____ .
a. Uniform distribution curve
b. Normal distribution curve.
c. U-shaped distribution curve
d. None of the above
172. In the initial stage of the project the probability of completing the project is ___ .
a. Zero
b. High
c. Low
d. Any of the above
26
173. The entire process of a project may be considered to be made up on number of sub
process placed in different stage called the
a. Technical key resources
b. Work key structure
c. Work Breakdown Structure (WBS).
d. None of the above
174. Tool used for comparison of the proposed project to complete projects of a similar nature
whose costs are known.
a. Algorithmic model
b. Expert judgment
c. Top down
d. Analogy
175. Each component of the software product is separately estimated and the results
aggregated to produce an estimate for the overall job.
a. Algorithmic model
b. Expert judgment
c. Bottom-up
d. Top down
176. Following is (are) the component(s) of risk management
a. Risk Assessment
b. Risk Control
c. Risk Ranking
d. All of the above
178. “Devising and maintaining a workable scheme to accomplish the business need” is
a. Initiating process
b. Planning process
c. Executing process
d. Controlling process
27
c. Project scope
d. All of the above
181. The span of time within which the investment made for the project will be recovered by
the net returns of the project is known as
a. Period of return
b. Payback period
c. Span of return
d. None of the above
184. The values of the future net incomes discounted by the cost of capital are called
a. Average capital cost
b. Discounted capital cost
c. Net capital cost
d. Net present values
28
d. None of the above
186. The internal Rate of Return (IRR) criterion for project acceptance, under theoretically
infinite funds is: accept all projects which have
a. IRR equal to the cost of capital
b. IRR greater than the cost of capital
c. IRR less than the cost of capital
d. None of the above
189. Where capital availability is unlimited and the projects are not mutually exclusive, for the
same cost of capital, following criterion is used
a. Net present value
b. Internal Rate of Return
c. Profitability Index
d. Any of the above
191. With limited finance and a number of project proposals at hand, select that package of
projects which has
a. The maximum net present value
b. Internal rate of return is greater than cost of capital
29
c. Profitability index is greater than unity
d. Any of the above
196. Which from the following represents the correct project cycle?
a. Planning→Initiating→Executing→Closing
b. Planning→Executing→Initiating→Closing
c. Initiating→Planning→Executing→Closing
d. Initiating→Executing→Planning→Closing
197. The strategy used to correct resource over-allocations by balancing demand for resources
and the available supply is known as
a. resource assignment
b. resource leveling
c. resource splitting
d. resource scheduling
198. A horizontal bar chart that shows project tasks against a calendar is called
30
a. Milestone
b. Goal
c. Gantt chart
d. PERT chart
199. The statistical tool that depicts a project’s tasks and the relationships between those tasks
is known as
a. Milestone
b. Goal
c. Gantt chart
d. PERT chart
200. According to Olivier Mesly, the 4 P’s critical for the success of a project are:
a. plan, processes, people, policy
b. plan, processes, people, power
c. plan, processes, potential, policy
d. plan, processes, potential, power
------------------
31