VisiLean Constraints Log User Guide
VisiLean Constraints Log User Guide
VISILEAN USER-GUIDE
CONSTRAINT MANAGEMENT
VisiLean Ltd. | Confidential and proprietary
VisiLean Ltd. | Confidential and proprietary 2
INTRODUCTION
VisiLean offers a dedicated section for Managing your Constraints on the Project
Constraints are any issues/challenges that will potentially hinder you and your teams from executing
a job on-site for when it is planned. Constraints can be recorded in multiple ways on VisiLean:
• Constraints can also be raised for Tasks in-progress that have hit an issue on-site that
needs resolution
• Constraints raised for work-in-progress must be cleared in order for the Task to be completed at the job-
site successfully.
NOTE:
• Property Panel can be accessed from any of the views – Gantt, Scheduler, Table View.
• Dashboard drill-down will allow you to view, edit, and raise Constraints
• Property Panel will also allow you to raise Constraints, as well as view and edit them
• But these will be only Constraints linked to the selected Task
1. Click on a Task 2
2. Click on Constraints button 1
3. Fill out the Constraint Form
4 5
4. Scheduler view will show icon for Tasks with Constraints
5. You can View the Constraint from the Property Panel
3
Note:
• You will not see the “Task” section when raising a
Constraint from the Property Panel.
• It will link to the Selected Task directly.
• If you wish to link the Constraint to more Tasks, “Edit”
the Constraint and add more Tasks to link.
Constraints created from importing BIM360 Issues can be visualized, edited, and actioned as well.
NOTE:
• Selecting any parameters WILL NOT APPLY the Filters - NEED TO CLICK “APPLY”
• Advanced Options – Will allow you to select from the following dates:
• Creation Date
• Commitment Date
• Completion Date Advanced Options
NOTE:
• Upload Attachment first from “Select File” and then click on “Upload File”
• Only Project Admins have the option to Delete a constraint
The detailed review section of the Constraints Log offers all the important information related to the Constraint.
Summary Bar
Details Card
Note:
• You can Edit/Change any of the information added to the
Constraint from this section at any point, except for: 5
• The Target Date
• The Author and Creation Date
6
VisiLean Ltd. | Confidential and proprietary 14
EDIT CONSTRAINTS – WEB APP
Process for Updating Assigned Constraints
1. Click on “Commit”
2. Commitment Date - Select the Date by which you, as
3
the Owner, are committing to resolve this Constraint
3. The Status will auto-change to “Committed”
4. Click on “Save”
Note:
• Repeat the same process for Closing a Constraint 1
• Completion Date – The date on which the Constraint
has been closed 2
• Status will auto change to “Closed”
1 3
3
4
Task Listing – Task Card – Click on Chat Icon Click on Attachment – Create Constraint -
Access your Task Top-right Corner Click on Constraints Fill the Form
OR
• Access Task listing from the Dashboard
• Click on any Task
• Task Card will show “Constraints” folder
• Clicking on that will show Linked Constraints
• Click on Constraint to Edit/Update
EDIT CONSTRAINTS 1
3
Q: Can the responsible person be anyone from the project, irrespective of their organization in VisiLean?
ANS: Yes, you can assign the Constraint to anyone on the project on VisiLean.
Q: Can the Start and Completion of Tasks be restricted if there are Open Constraints linked to it?
ANS: Yes, you can restrict the Start and Completion of Tasks affected by Open Constraints from Project “Settings” – “Parameters”.
Q: Can one revert the status by removing the commitment date or the completion date of the constraint?
ANS: No, but the Owner of the Constraint has the option to change the commitment date and completion date.