Nisarg
Nisarg
Nisarg
An Internship Report on
AMADIUS REALITY
Submitted by
Diploma Engineering
In
[SUMMER 2024]
i
FACULTY OF ENGINEERING & TECHNOLOGY
MONARK UNIVERSITY
Vahelal, Ahmedabad
CERTIFICATE
This is to certify that the Internship report submitted has been carried out by
PANDYA NISARG JAYESHKUMAR (22021302020005) at AMADIUS REALITY under
my guidance in partial fulfilment in 6th Semester for the Diploma Engineering in Civil
Engineering of Monark University, Vahelal during the academic year 2023-24.
ii
CERTIFICATE OF COMPANY/INDUSTRY
iii
FACULTY OF ENGINEERING & TECHNOLOGY,
MONARK UNIVERSITY
Vahelal, Ahmedabad.
DECLARATION
I hereby declare that the Internship report submitted along with the Internship entitled
HIMALAYA’S LANDMARK PROJECT submitted in partial fulfilment for the degree of the
of Diploma Engineering in Civil Engineering to Monark University, Vahelal, is a bonafide
record of original project work carried out by me, at AMADIUS REALTY under the
supervision of HITENDRA PATEL and that no part of this report has been directly copied
from any students’ reports or taken from any other source, without providing due reference.
Sign of Student :
iv
Acknowledgement
I would like to express my sincere gratitude to the guide, Prof. Jaydip Jadia, for his
invaluable guidance, support, and encouragement throughout the process. His expertise,
patience, and feedback have been instrumental in shaping my ideas and guiding me towards
the completion of this Internship.
I would also like to extend my appreciation to the faculty members of the Civil Department
as well as H.O.D of Civil Department, Prof. Jaydip Jadia, for their valuable insights and
feedback on my Internship. Their critiques, suggestions, and encouragement have helped me
to develop a deeper understanding of the subject matter.
In addition, I would like to thank my Family and Friends for their unwavering support and
encouragement throughout this journey. Their love, motivation, and belief in me have been
the driving force behind my academic success.
Once again, I express my deepest gratitude to all those members who have contributed to the
successful completion of this thesis and progress.
v
ABSTRACT
vi
Content
Certificate..................................................................................................................... 3
Acknowledgement........................................................................................................ 4
Abstract......................................................................................................................... 5
Chapter 1: Introduction
1. About the company................................................................................................... 7
2. Aim and Objectives of the organization................................................................... 7
3. Statement of the Project............................................................................................ 8
vii
Chapter 3: Overall Experience
1. Technical
Experience.............................................................................................. 46
2. Personal
Experience................................................................................................ 46
viii
CHAPTER – 1
INTRODUCTION
ABOUT THE COMPANY:-
MISSION STATEMENT
To create product and services that makes the difference, to serve the
society with par excellence, to the ability and passion to work wisely.
VALUE STATEMENT
Leadership: Ability to guide others without force into a direction.
Collaboration: To work jointly with others or together.
ix
STATEMENT OF THE PROJECT
HIMALAYA FALAKNUMA
x
CHAPTER – 2
SKILL LEARNED AND PROCESS OF
BUILDING CONSTRUCTION PHASES
COMPONENTS OF BUILDING:-
SUB STRUCTURE – Foundation is a part of the sub structure. It is
constructed according to soil quality at that site. Sub structure is a
load bearing structure.
If soil have good bearing capacity than we use shallow foundation in
construction and if the baring capacity of soil is not good or suitable
than we use deep foundation at the site.
SUPER STRUCTURE – Super structure is a part of structure that is
above plinth level (P.L). Following are the important part of super
structure,
Floor
Roof
Lintel
Parapet
Sun shade
Doors & Windows
During this internship period I have worked on RCC part of the
structure at site. The structure is load bearing type. Here various
learning points like
Drawing
Planning
Formwork
Arrangement of reinforcement, Production of concrete
xi
PRODUCTION OF CONCRETE:-
CONCRETE =
CEMENT+SAND+WATER+AGGREGATE+ADMIXTURE
Admixture is used for increase strength of concrete.
Concrete is made by tilting type of machine mixture. Concrete work
is an important for strength of structure that’s why it done by suitable
method and technology.
xiii
CEMENT:-
OPC (Ordinary Portland Cement) Used in All types of construction
like slab, beam, stair, lift, etc.
PPC (Portland Pozzolna Cement) Used in Plaster.
AGGREGATE
Neat cement is very rarely used
in construction works since its
liable to shrink too much and
becomes cracks on setting.
Moreover it will be costly to use
neat cement therefore cement is
mixed with some strong & hard
materials. They also reduce cost
of concrete.
Two types of aggregate used in
concrete
1. Fine Aggregate
2. Coarse Aggregate
Size = 10 mm or 20 mm
xiv
CONCRETE CUBE TEST:-
The concrete cube test is performed for the purpose of determining
the compressive strength of a concrete element. The cubes used for
this test have a dimension of 150 x 150 x 150 mm as long as the
largest aggregate does not exceed 20 mm. Generally speaking, the
cubes are cured for and tested at 7 and 28 days, although certain
projects might require curing and testing times of 3, 5, 7, 14, or more
days. The results from the compressive strength test are used to
determine the strength of the concrete. If the test results are
inconclusive or show that your concrete isn’t curing as quickly as it
should, you risk not being able to advance your project as soon as you
would like to. Grade of the concrete are measures in terms of M
values.
M stands for mix .that is basically concrete mix consisting cement,
sand, aggregate and water. And value after M I defined the
compressive strength in N/mm2 after 28 days.
Mix Ratio cement in Sand in Water in Compressive
(M) kgs kgs liters strength
After 28 days
(N/mm2 )
5 1:5:10 141 785 70.5 5
xv
STEPS FOLLOW FOR COMPRESSIVE CUBE TESTS:-
After well dried weight of cube is checking, its not be less than 8.1 kg.
xvi
DRAWING:-
In the drawing I see the plan of the site.
xvii
LINE DIAGRAM WITH INTERNAL ELEVATION
xviii
FLOOR PLAN
PLANNING:-
It is the process of modelling and analysis of any RCC framed
structure. In this part a rough sketch is drawn over the architectural
drawing depicting the various components that can be designed by the
structural engineer.
xix
It also involved the thought on forces that will be imposed over the
structure and their calculations.
BLOCK MASONRY:-
Masonry is an assembly of bricks, blocks or stone held together with
mortar. The common material used in masonry are Brick, Stone,
Concrete block.
xx
Concrete block masonry is widely used for high rise building
structure. The most common application of block masonry is walls for
building.
Block Size:
1.
100mm×200mm×600mm
2.
150mm×200mm×600mm
3.
200mm×200mm×600mm
4.
230mm×200mm×600mm
Quantity
1 truck = 25m^3
For ex. 100×200×600
Block volume=0.012
Approx.
2100 block in 1
truck
GROUN
D
LEVEL
xxi
PLINTH LEVEL
SEAL LEVEL
LINTEL LEVEL
SLAB LEVEL
COPING:-
xxii
Coping means covering the top of the wall with a layer of stone,
Block, brick with concrete. Coping keep the building safe from
seepage of water during rainfall and earthquake conditions.
Window’s lower face
Seal level = 1m
Generally M15 grade concrete used in coping.
M30 OR M40
xxiii
• REBARING
Insert the steel bars in concrete structure.
Size =75-100 mm
Chemical
(Foslo company)
Chicken mesh
It strengthens the
plaster against forces.
Mainly to avoid the
xxiv
crack formed due to insufficient gap filling between RCC
column and block joint.
Material - fibre
MICRO CONCRETE:-
Micro concrete is a cement based coating which can be applied thinly
(approx. 2-3 mm) to a range of different surfaces including tile and
wood. It provides the look and feel of concrete at a fraction of the cost
and weight of real concrete.
It’s similar to another material called micro cement.
It is durable and can be applied easily to surfaces internally and
externally.
It is also a waterproof material and therefore it makes for an ideal
covering option for bathrooms and splash backs in kitchen.
Ratio of water cement is 1:8.
Uses of Micro concrete:
Pre-packaged mix
Reduced water requirements
Fast drying
xxv
SCAFFOLDING:-
The scaffolding is a temporary structure on the outside of a building
to support platforms. Used by workers while constructing, plastering
etc. This temporary formwork is useful in building construction,
demolition, maintenance and repair works. Scaffolding is erected
either on one or both sides of the wall. The height of the scaffolding
can be adjusted with the progress of the work.
Types of
scaffolding
Single
scaffolding
Double
scaffolding
Ladder
scaffolding
Cantilever
scaffolding
Steel scaffolding
Timber
scaffolding
Suspended
scaffolding
In this site
steel
scaffolding
is used.
Mostly steel
material are
used
because of
high strength and durability.
xxvi
Therefore workers can use it to transport heavy equipment and
supplies.
Its initial cost is more, but it can be used for longer period.
PLASTERING:-
Plastering is the process of
covering rough walls and uneven
surfaces in the construction of
concrete structures. Purpose of
protect wall and other concrete
element against the atmospheric effect.
In plaster cement, sand and water is used.
Cement is PPC.
Thickness: 12mm-20mm
Clean the surface with water and is kept wet till applying plaster.
Preliminary coat is applied on the surface to fill up hollow portion
of masonry.
First coat of plastering is called “chhant”.
Thickness of first coat is 9-10mm.
Second coat is applied after 6hrs and thickness of this coat is 10
mm.
xxvii
The final setting coat should not be applied until the previous coat
is almost dry.
Cement plaster and cement mortar ratio 1:3 or 1:4 for plastering on
RCC.
Complete plaster is allowed to rest for 1 day and watered for at
least 7 days.
PLASTERING TOOLS
• TROWEL (લેલુ)
• METAL FLOAT(પતરું)
280mm×130mm
• WOODEN FLOAT
Used for the finishing coat of plaster
• ALUMINIUM
CHANNEL
(plaster પટ્ટી)
Size = 1.5m, 2m
• RIGHT
ANGLED
SCALE
• MEASURING
TAPE
BULL
(THIYA):-
Plastering thickness
is marked by bull.
Wall lines & right angles are consider while fixing the bull marks.
xxviii
DEFECTS IN PLASTER
Cracking
Efflorescence
Falling out of plaster
Blowing of plaster
FORMWORK:-
Formwork is also called SHUTTERING.
Formwork is a temporary mould to provide support to fresh concrete
when placed in structure until concrete is hardened.
It provides supports to horizontal, vertical, and inclined surfaces or
also provides supports to cast concrete according to required shape &
size.
Generally three types of formwork is used
xxix
1. Steel formwork
Steel formwork give smooth surfaces and are suitable for big
project.
Easy to assemble
2. Wooden planks formwork
Generally wooden planks formwork is used by contractors because
this formwork is cheap and easily available but this type of
shuttering effects the strength of concrete.
3. Temporary brick masonry formwork
xxx
SLAB SHUTTERING:-
Slab shuttering is support the weight of concrete during the curing
process and when the concrete slab is positioned on permanent
supports.
Bases are required that are made from wood or metal.
The horizontal joints create a flat surface where timber, plywood,
steel sheets can be used as a base onto which the concrete is poured.
Generally 28 days are required before removing formwork.
After 7-9 days removing the slab supports. In this time curing process
is continued.
Process of removing shuttering is called “Deshuttering”.
xxxi
• ONE WAY SLAB
Long length/Short length ≥ 2
Bending of slab takes place in shorter direction
Thickness is more so used steel is also more
• TWO WAY SLAB
Long length/Short length < 2
Bending of slab takes place in both direction
Thickness is less so used steel is also less
• FARMA
Size: 1×3 ft., 1.5×3 ft., 2×3 ft.
• VERTICAL SUPPORT
500mm, 1000mm,
2000mm
xxxii
• LEDGER
1200mm
• BOX PIPE
20ft.
100mm×100mm
• TATA BOX
1500mm, 2000mm
50mm
• SPAN
8ft length
(ખોલીએ ત્યારે)15ft maximum
L
IFT WALL SHUTTERING (પડદી)
xxxiii
Casting also known as poured in place is a concreting technique
which is undertaken in the concrete component’s finished portion.
Casting is the preferred choice for concrete slabs and foundations, as
well as components such as beams, columns, walls, roofs and so on.
Casting of concrete can allow for greater flexibility and adaptability,
it can be difficult to control the mix particularly if weather conditions
are not favourable. Cast-in place concrete will also require a strength
test and time for curing.
SLAB CASTING
PROCESS
1. Shuttering
2. Clear cover
3. Reinforcement
4. Electrical wiring
5. Casting
6. Vibrating
7. Curing
xxxiv
COLUMN SHUTTERING:-
Column is a supporting
pillar or a structural
element which transfer the
upcoming load its self-
weight to the hard soil
foundation.
Two end and two side both
are joined by the yokes and
bolts.
STANDARD
BALANCE
TATA BOX
1500mm, 2000mm
50mm
TYROID
CLAMP
VERTICAL
SUPPORT
BOX PIPE
20ft
Size = 100mm×100mm
COLUMN CASTING:-
Height = 9ft
xxxv
M40 Grade concrete
0.4 cm concrete used in column casting.
• TYROID
Steel is used because it bonds well with
concrete.
Dia. = 10-15mm
xxxvi
BEAM BOTTOM:-
Beam is a structural member constructed to transfer the load, Primary
purpose of beam is transfer the load from slab to the columns or
foundation.
Reinforced concrete beams are commonly used in construction as it
provide extra tensile strength and proves to be economical.
Fixed beam – Both ends fixed
xxxvii
Plumb bob, Measurement, Column dimensions, Level of Beam
bottom
• Lapping
Lapping means overlapping of two bars side by side.
Required for two different bars are overlapped and get a constant line
of bar.
Length of the steel bar = 12m.
• Lapping length = 52D , Where D is Dia. of steel bar
Both bars are of same dia.
STAIRCASE:-
FLIGHT – The inclined slab of staircase is called flight.
MID LANDING – It is level platform at the top or bottom of a flight
between the floors.
RISER - Vertical distance between two tread.
Not be more than 200 mm.
xxxix
Size=150 mm
TREAD - Horizontal distance between two riser.
Size=300 mm
WAY SLAB - The slab below steps in the staircase.
STAIR CASTING
6mm Dia. Bars at 150mm
12mm Dia. Bars at 150mm
M30 grade concrete used.
QUANTITY
Way slab length = 3.35m
2m Width
Way Slab Thickness = 200 mm
0.2×2×3.35=1.34
Riser=150mm
Tread=300mm
½ ×0.15×0.3×2×10=0.45
Total= 1.34+0.45 = 1.79cm
xli
SR. NO. STRUCTURAL MEMBER TIME
1. BEAM SIDES 2-3 DAYS
2. WALL 2-3 DAYS
3. COLUMNS 2 DAYS
4. SLAB (SIDES) 2-3 DAYS
5. SLAB 7-9 DAYS
6. BEAM 7-9 DAYS
7. WATER TANK 2 DAYS
TIME OF REMOVAL OF FORMWORK (DESHUTTERING)
EFFECTIVE COVER:-
Effective cover is the distance measured from the face of the member
to the centre of area (centroid) of the main reinforcement. This is the
dimension mostly used for design calculation.
xlii
COLUMN - 40 mm
SHEAR WALL - 25 mm
BEAMS - 25 mm
SLABS - 15 mm
STAIRCASE - 15 mm
RETAINING WALL - 20 /25 mm
WATER RETAINING STRUCTURES - 20 /30 mm
STEEL:-
Information about steel used during construction
STEEL GRADE: FE 415, FE 500 & FE 500D
Diameter of bars uses: 8mm, 10mm, 12mm, 16mm, 20mm, 25mm, 50mm.
Fe 500 grade of steel have yield strength of 500 N/ mm2.
Due to elongation of the steed due to bending the length of the steel is
increase and the steel length is became the longer than required .So,
After calculating the bar bending schedule of the particular shape and
finding required actual of the steel. We cut the steel according to
length suggest by bar bending schedule and bend the steel according
the given in structural plan and layout of the steel.
xliv
VIBRATING OF THE CONCRETE:-
Vibration means quickly moving up and down about a point of
equilibrium.
It is used for concrete compaction.
It consolidates freshly poured concrete to remove the trapped air and
excess water.
It is to settle the concrete firmly in the place of form-work.
TYPES OF VIBRATORS:
Internal Vibrator – In this vibrating concrete from within the
formwork.
External Vibrator – In this vibrating the formwork from the outside.
Form Vibrator
Surface Vibrator
xlv
CURING OF THE CONCRETE:-
Curing of Concrete is a method by which the concrete is protected
against loss of moisture required for hydration and kept within the
recommended temperature range.
Curing will increase the strength and decrease the permeability of
hardened concrete.
Curing is also helps in mitigating thermal and plastic cracks, which
can severely impact durability of structures.
A curing practice involves keeping the concrete damp or moist until
the hydration of concrete is complete and strength is attained.
Curing of concrete should begin soon after initial setting time of
concrete or formwork/shuttering is removed and must continue for a
reasonable period of time as per the specified standards, for the
concrete to achieve its desired strength and durability.
WHAT PROPERTY ARE IMPROVED BY CURING:-
xlvi
Higher serviceability performance by increasing abrasion
resistance
Improved microstructure by developing better hydrate gels and
solid mass.
METHODS OF CURING:
Water Curing
xlvii
Core cutting:-
Core cutting is a method used for creating holes in concrete for pipes,
wires, etc.
First locate the rebar and mark the position on concrete surface after
that do a core-cut by adjusting location (main bars not cut)
xlviii
jacketing:-
Strengthening of column
Load carrying by column is increased (Adding 13th and 14th floor in
building)
Jacketing is modification of existing structure to make them more
resistant. In this process concrete added around the column. It
improve shear strength of column.
Formwork is installed around the
existing column and proper support is
provided then column casting is
occurred. And then curing.
CHEMICAL
NITOBOND
xlix
FLOORING:-
The purpose of a floor is to provide a level surface capable of
supporting the occupants of a building, furniture, equipment and
sometimes internal partitions.
To perform this function and in addition the situation of the floor in
the building and the nature of the building itself, the floor must satisfy
following requirements:
Adequate strength and stability
Adequate fire resistance
Sound insulation
Damp resistance
Thermal insulation
While select the material for
flooring smoothness, Hardness,
maintenance of provided material
are considered.
l
TILED FLOORING:
Tiled flooring is constructed form
square, hexagonal, or others shapes made
up of clay, cement concrete or tiles.
These are commonly used in residential
flooring, offices, hospitals, schools.
Over the concrete base a 25 to 30 mm
thick layer of lime mortar ratio 1:3 is
spread to serve as a bedding.
Before laying the tiles it is cured for 12
to 24 hours, near cement slurry is spread
over the bedding mortar and the tiles are
laid flat over it.
• Base concrete
75-100mm thick
Concrete ratio = 1:3:6
• Wearing surface
40mm thick
Concrete ratio = 1:2:4
li
WATER PROOFING:-
Waterproofing is the process of making structure
waterproof. So that is not affected by water.
Usually extensive waterproofing measures are added to a building at
the time of construction, to provide moisture control from the start.
lii
PROCESS OF WATERPROOFING
• Cleaning
• At sunken portions Apply 1st layer of chemical
Chemical = DR. Fixit LW+ 302
• Fill the blanks (ગાબડા)
• VATA
• Apply 2nd layer of chemical
It’s applied after 4 hrs of 1st layer is dry.
• Water leakage checking
If it is happened repeat this process.
• Water pipes fitting to proper level & slope.
Thickness of layer = 20 mm
Ratio of Cement and sand 1:4
• Finished the surface level
After plumbing work filled the voids Using wastage blocks to the
surface level with 25mm PCC.
liii
CHAPTER – 3
OVERALL EXPERIENCE
TECHNICAL EXPERIENCE:-
During the internship I learn the detailed experience about how the
building constructed.
I learn how to read the plan and what information give us in the detail
of the building plans their layout plan, centre line plans ,column
schedule .
I learned that besides the knowledge the good engineer must have the
Personal Experience:-
This internship is an excellent opportunity for me go to the ground
level and experience the things that we would have never giving
through going straight into a job.
Personally I experience that simultaneously of the practical
knowledge and also studying of college is best to implement and
develop the mind and personality as civil engineer.
This internship is lifetime memorable for me. And the experience that
I personally gained is very huge. And personally I thank u to the
engineers which shear the information and teach me.
Interaction with workers and local public was also a great experience.
lv