The Comprehensive Study On Water Resources Development and Management in Bali Province
The Comprehensive Study On Water Resources Development and Management in Bali Province
The following drilling core data indicates an old valley covered by welded tuff beneath the recent
valley.
Basement of welded tuff layer rises gradually on both banks.
Completely weathered tuff breccia beneath the welded tuff was observed in the drilling core
DA-1(existing hole) and DA-6 on the left bank, and DA-8 and DA-10 on the right bank.
Old river deposits beneath the welded tuff were observed in the drilling core DA-2(exisiting
hole), DA-7 of riverbed and DA-4(existing hole) on right bank. The surface of the old river
deposits were approximately 240 m in elevation.
94 m
06.2
m EL.=4
834 DA-8 0 m
399.
EL.= L=10
DA-6 0 m
L=10
410 0
10
5
20
10
30
15
40
20
50 N Value
25 Lu
m >200
803
10 20 30 40 50 N Value
400 0 5 10 15 20 25 Lu
372. d) 213
EL.= bjecte 56
DA-1 0 m (su
390 L=10
30
39
380
27 Lu Crest Level 371 m 26
0 5 10 15 20
370 7m
8.44 4m
.=33 4.89
9 EL .=33
360 DA- 0 m 0 EL
L=10 DA-1 0 m 50
50 L=10
350
10 20 30 40 50 N Value
340 0 5 10 15 20 25 Lu 10 20 30 40 50 N Value
0 5 10 15 20 25 Lu
330 55 378
28 124 ?
50
320 59
50
6m
310 28 1.01
EL.= 100
DA-7 0 m
100
300 L=10
290 50
10 20 30 40 50 N Value 50
5 10 15 20 25 Lu
280
100 2.5 E-4 cm/s
270
260
250
Volcanic ash
240
Tuffaceous tuff breccia 100
100
50
230
220
Welded tuff Ground water
table
210
Tuff breccia
80
200
190
Surface of old
180 valley
170
160
250.00 (m)
38 1 PAA 8 PD1
BM2LA1 23 25 4 6 8 PA2 17 9 PD5 C72 PD2
19 17 15 4A 12 10 2A 1 40 37 27 0-1A2 20 DA9 10 PD12 PD10 PD5 C81 C79 C71 C74 C76 BM4-A4
NOMER 7A 6A 5A 20 18 16 14 13 11 9 8 7 5A 4 6 32 A DA6 P1 41 39 36 P1 2122 24 26 28 PA1 3 5 A2 7 9 A2-2 1819
1 23
4 5P7A 1112 DA-7 DA-10 PD13 PD11 A3 PD9 PD8 PD7 C82 C80 C78 DA8 CS71
CS73
C73 C75 C77 PD4 C77
418.540
417.448
416.301
413.638
413.049
412.838
411.972
411.228
410.391
410.453
409.520
406.791
405.756
404.105
403.393
402.131
400.292
398.233
397.631
393.306
391.932
390.404
391.645
393.951
395.358
397.292
399.834
403.804
403.118
402.860
402.427
401.462
400.440
400.055
400.525
399.627
397.289
395.417
394.813
393.846
393.026
391.611
390.998
391.996
391.464
390.910
390.244
388.819
387.092
385.636
384.019
382.589
381.297
380.391
380.654
379.836
378.475
378.065
370.305
366.777
365.749
363.571
362.848
362.559
360.743
358.601
355.916
354.737
349.888
346.258
338.447
336.507
335.178
333.470
332.042
330.393
281.016
279.092
279.001
334.894
355.980
355.944
367.697
371.551
371.322
376.360
384.951
393.498
395.749
397.561
400.159
400.815
403.753
404.106
404.122
406.294
406.129
405.934
407.697
407.577
407.050
408.029
409.777
409.465
410.629
410.717
410.534
413.038
412.863
414.769
ELEVASI
7.099
1.538
0.870
4.581
1.204
5.164
2.067
1.612
2.772
2.511
1.914
4.893
2.494
3.274
3.483
4.982
1.945
2.634
2.105
4.727
1.319
4.847
7.769
4.390
2.049
4.686
0.379
1.209
3.139
2.686
2.387
1.900
2.970
0.645
5.024
1.237
3.813
1.424
4.009
5.342
2.062
2.093
1.557
4.998
0.933
5.983
0.780
5.256
3.823
1.013
1.041
7.751
3.489
2.327
3.162
3.135
0.258
2.239
2.092
1.613
3.161
4.933
3.283
2.795
1.676
1.671
0.664
0.968
2.000
5.453
5.907
9.050
9.665
3.195
6.088
2.279
3.754
2.693
0.423
2.570
8.997
6.994
0.565
1.155
1.546
3.515
1.581
9.964
0.915
2.837
9.037
3.874
JARAK 47.075 20.877 7.374 11.442 16.680 11.384 20.314 34.994 14.600 40.632 14.301 13.946 10.343 11.336 15.972 17.439 14.679
410 0
10
5
20
10
30
15
40
20
50 N Value
25 Lu
m >200
803
10 20 30 40 50 N Value
400 0 5 10 15 20 25 Lu
372. cted) 213
EL.= (subje 56
DA-1 0 m
390 L=10
30
39
380
27 Lu Crest Level 371 m 26
0 5 10 15 20
370 m
38 .447 4m
EL .=3 89
.= 334.
360 DA-9 0 m 0 EL
L=10 DA-1 0 m 50
L=10
350 50
10 20 30 40 50 N Value
340 0 5 10 15 20 25 Lu 10 20 30 40 50 N Value
0 5 10 15 20 25 Lu
330 55 378
28 124
50 ?
320 59
50
6m
310 28 1.01
EL.= 100
DA -7 0 m
100
300 L=10
290 50
10 20 30 40 50 N Value 50
5 10 15 20 25 Lu
280
100 2.5 E-4 cm/s
270
260 D class
250
240
CL class (partly D class) 100
100
50
230 CM class
220 Groundwater
CH class table
210
80
200
190
Surface of old
180 valley
170
160
250.00 (m)
38 1 PAA 8 PD1
BM2LA1 23 25 27 4 6 8 PA2 17 9 PD5 C72 PD2
19 17 15 4A 12 10 2A 1 40 37 0-1A 2 20 DA9 10 PD12 PD10 PD5 C81 C79 C71 C74 C76 BM4-A4
NOMER 7A 6A 5A 20 18 16 14 13 11 9 8 7 5A 4 6 3 2 A DA6 P1 41 39 36 P1 2122 24 26 28 PA1 3 5 A2 7 9 A2-2 18 19
1 23
4 5P7A 1112 DA-7 DA-10 PD13 PD11 A3 PD9 PD8 PD7 C82 C80 C78 DA8 CS71
CS73
C73 C75 C77 PD4 C77
418.540
417.448
416.301
413.638
413.049
412.838
411.972
411.228
410.391
410.453
409.520
406.791
405.756
404.105
403.393
402.131
400.292
398.233
397.631
393.306
391.932
390.404
391.645
393.951
395.358
397.292
399.834
403.804
403.118
402.860
402.427
401.462
400.440
400.055
400.525
399.627
397.289
395.417
394.813
393.846
393.026
391.611
390.998
391.996
391.464
390.910
390.244
388.819
387.092
385.636
384.019
382.589
381.297
380.391
380.654
379.836
378.475
378.065
370.305
366.777
365.749
363.571
362.848
362.559
360.743
358.601
355.916
354.737
349.888
346.258
338.447
336.507
335.178
333.470
332.042
330.393
281.016
279.092
279.001
334.894
355.980
355.944
367.697
371.551
371.322
376.360
384.951
393.498
395.749
397.561
400.159
400.815
403.753
404.106
404.122
406.294
406.129
405.934
407.697
407.577
407.050
408.029
409.777
409.465
410.629
410.717
410.534
413.038
412.863
414.769
ELEVASI
7.099
1.538
0.870
4.581
1.204
5.164
2.067
1.612
2.772
2.511
1.914
4.893
2.494
3.274
3.483
4.982
1.945
2.634
2.105
4.727
1.319
4.847
7.769
4.390
2.049
4.686
0.379
1.209
3.139
2.686
2.387
1.900
2.970
0.645
5.024
1.237
3.813
1.424
4.009
5.342
2.062
2.093
1.557
4.998
0.933
5.983
0.780
5.256
3.823
1.013
1.041
7.751
3.489
2.327
3.162
3.135
0.258
2.239
2.092
1.613
3.161
4.933
3.283
2.795
1.676
1.671
0.664
0.968
2.000
5.453
5.907
9.050
9.665
3.195
6.088
2.279
3.754
2.693
0.423
2.570
8.997
6.994
0.565
1.155
1.546
3.515
1.581
9.964
0.915
2.837
9.037
3.874
JARAK 47.075 20.877 7.374 11.442 16.680 11.384 20.314 34.994 14.600 40.632 14.301 13.946 10.343 11.336 15.972 17.439 14.679
The bed rocks distributed around the proposed dam site shows intermediate characteristic between
volcanic rocks and volcanic sedimentary rocks according to the past experience in Japan.
These engineering properties were estimated based on limited data of laboratory tests and
observations of outcrops at the site. The above rock classification and engineering properties will
be revised in the course of the geological investigation.
In-situ rock tests will be necessary to determine engineering properties in the detailed design study.
Additional investigation including core drillings is necessary for the detail design of proposed dam
and its foundation treatment.
(3) Permeability
Based on the survey results, permeability coefficient of the bedrocks shows the order of 10-5 to 10-4
cm/s (2-10 Lu) except for the surface weathered zone (within about 20 m in depth) and some parts
of welded tuff layer.
Ground water level of the right bank is approximately EL 340 m (about 25 m lower than HWL).
Spring water from the confined aquifer in welded tuff layer was observed at drilling hole DA-7. Old
river deposits are covered by welded tuff.
Additional investigation including core drillings shall be curried out for the design of foundation
treatment.
4m
6.29
.=40
34 m 8 EL
DA- 0 m
399.8
EL.= L=10
DA-6 0 m
L=10
410 0
10
5
20
10
30
15
40
20
50 N Value
25 Lu
10 20 30 40 50 N Value
3m >200
0 5 10 15 20 25 Lu 2.80
400 .=37 bjected) 213
1 EL 56
DA- 0 m (su
390 L=10
30
39
380
27 Lu Crest Level 371 m 26
0 5 10 15 20
370 47 m
38.4 894
m
EL.=3 .= 334.
360 DA-9 0 m 0 EL
L=10 DA-1 0 m 50
50 L=10
350
10 20 30 40 50 N Value
340 0 5 10 15 20 25 Lu 10 20 30 40 50 N Value
0 5 10 15 20 25 Lu
330 55 378
28 124
50 ?
320 59
50
16 m
310 81.0
EL.=2 100
DA-7 0 m
100
300 L=10
290
50</= Lu 50
10 20 30 40 50 N Value 50
5 10 15 20 25 Lu
280
20</= Lu <50 100 2.5 E-4 cm/s
270
260
10</= Lu <20
250
5</= Lu <10
240 100
100
230
2</= Lu <5 50
220
Lu <2 Groundwater
210 table
80
200
190
Surface of old
180 valley
170
160
250.00 (m)
38 1 PAA 8 PD1
4 6 8 PA2 17 9 PD5 C72 PD2
19 17 15 4A 12 10 2A 1 40 37
BM2LA1 23 25 27 0-1A2 20 DA9 10 PD12 PD10 PD5 C81 C79 C71 C74 C76 BM4-A4
NOMER 7A 6A 5A 20 18 16 14 13 11 9 8 7 5A 4 6 3 2 A DA6 P1 41 39 36 P1 2122 24 26 28 PA1 3 5 A2 7 9 A2-2 1819
1 23
4 5P7A 1112 DA-7 DA-10 PD13 PD11 A3 PD9 PD8 PD7 C82 C80 C78 DA8 CS71
CS73
C73 C75 C77 PD4 C77
418.540
417.448
416.301
413.638
413.049
412.838
411.972
411.228
410.391
410.453
409.520
406.791
405.756
404.105
403.393
402.131
400.292
398.233
397.631
393.306
391.932
390.404
391.645
393.951
395.358
397.292
399.834
403.804
403.118
402.860
402.427
401.462
400.440
400.055
400.525
399.627
397.289
395.417
394.813
393.846
393.026
391.611
390.998
391.996
391.464
390.910
390.244
388.819
387.092
385.636
384.019
382.589
381.297
380.391
380.654
379.836
378.475
378.065
370.305
366.777
365.749
363.571
362.848
362.559
360.743
358.601
355.916
354.737
349.888
346.258
338.447
336.507
335.178
333.470
332.042
330.393
281.016
279.092
279.001
334.894
355.980
355.944
367.697
371.551
371.322
376.360
384.951
393.498
395.749
397.561
400.159
400.815
403.753
404.106
404.122
406.294
406.129
405.934
407.697
407.577
407.050
408.029
409.777
409.465
410.629
410.717
410.534
413.038
412.863
414.769
ELEVASI
7.099
1.538
0.870
4.581
1.204
5.164
2.067
1.612
2.772
2.511
1.914
4.893
2.494
3.274
3.483
4.982
1.945
2.634
2.105
4.727
1.319
4.847
7.769
4.390
2.049
4.686
0.379
1.209
3.139
2.686
2.387
1.900
2.970
0.645
5.024
1.237
3.813
1.424
4.009
5.342
2.062
2.093
1.557
4.998
0.933
5.983
0.780
5.256
3.823
1.013
1.041
7.751
3.489
2.327
3.162
3.135
0.258
2.239
2.092
1.613
3.161
4.933
3.283
2.795
1.676
1.671
0.664
0.968
2.000
5.453
5.907
9.050
9.665
3.195
6.088
2.279
3.754
2.693
0.423
2.570
8.997
6.994
0.565
1.155
1.546
3.515
1.581
9.964
0.915
2.837
9.037
3.874
JARAK 47.075 20.877 7.374 11.442 16.680 11.384 20.314 34.994 14.600 40.632 14.301 13.946 10.343 11.336 15.972 17.439 14.679
The Siap River, a main turbidity of the Ayung River, flows together at approximately 400 m
upstream of the proposed dam site. The reservoir area forms a V-shaped and relatively straight
valley extending N-S.
Suspicious
landslide
Direction of the
cave
Dam axis
Results of aerial photograph inspection and ground mapping are summarized as follows:
There are no obvious landslides in the planned reservoir. However, a suspicious landslide
was observed in the proposed disposal site at the right bank approximately 500 m upstream
of the proposed dam site.
No suspicious slopes, which have potential of large-scale rock mass failure, are detected.
No thick unconsolidated deposits including residual soil, talus deposits and volcanic ash in
the proposed Ayung dam reservoir are observed.
Although pumiceous tuff breccia forming small gully on the both bank about 40-50 m above
the riverbed seems to be erosive and collapse-prone, it is indeed well cemented and relatively
stable. The SPT values performed in drilling holes at the dam site are 30-50 and over even
in highly weathered sections. However, rapid rise or declination of reservoir water level can
trigger slope failure. In long-term bank erosion might be caused by surface wave of the
reservoir.
According to the results of aerial photograph inspection and ground mapping, there are no obvious
landslides in the planned reservoir. However, geological study including core drillings and stability
analysis for suspicios land slide at the right bank shall be recommended in detail design phase.
nsion
Water
at
Level
Design flood -
Surcharge level 0.075
Design seismic coefficient
Full reservoir 0.15
Empty 0.075
Concrete 2.30t/m3
Other Conditions Unit weight Water 1.00t/m3
Sediment in water 1.10t/m3
Coefficient of sediment 0.50
pressure
Wind wave 1.0m
Wave height
Seismic wave 0.6m
Shear strength
F τ0
Friction coefficient f CM0.84 CH 1.00 160tf/m2
Horizontal shear strength τ0 CM0.84 80tf/m2
CL 0.57 40tf/m2
Location of foundation Downstream of 4.5 m from upper surface
drain well
Based on the stability analysis, basic dimension of Ayung dam which minimizes dam volume is
shown as follows:
Downstream Slope 1 : 0.80
Height of Fillet 10 m
Upstream Slope of Fillet 1 : 0.4
Dam Crest Elevation EL.371.00m
1:0.8
Dam height 66.0m
1:0.4
EL.305.00m
Figure-III-3.9 Basic Dimension of Dam
Required shear stresses in the dam body of each elevation are as shown in Table-III-3.8.
Table-III-3.8 Required Shear Stress
Elevation Upstream Edge Downstream Edge Required Shear Strength
(m) (tf/m2) (tf/m2) (tf/m2)
(5) Spillway
Since Ayung Dam does not have flood control function, spillway with capacity of 1,270m3/sec
discharge has to be installed in more than normal water level 366m in elevation. Taking into
consideration with dam operation and maintenance, type of spillway for Ayung Dam shall be
designed as toe guide wall type with no gates. Relations between overflow depth and width of
overflow section to discharge 1,270m3/sec are calculated applying the following formula, and the
results are summarized in Table-III-3.9.
Q = CBH 3 2 (3.1)
where, Q: Discharge (m3)
C: Discharge Coefficient (= 2.0)
B: Overflow Width (m)
H: Overflow Depth (m)
Considering the river width and spillway width, overflow depth of spillway shall be adopted as
3.0m. Dam top elevation shall be 371m in elevation by adding normal water level 366m in
elevation, overflow depth 3.0m, bridge clearance of 1.5m and bridge beam height of 0.5m.
(6) Artificial Concrete Plug
Base rock of Ayung Dam has the strength of CM class rocks (shearing strength 80 tf/m2). Based on
the stability analysis for CM class rock strength, requirement of dam basement length was
calculated as more than 234m and downstream slope of dam was set to as 1:2.3. It is wasteful for
adopting this dam shape; artificial concrete plug method was adopted. From the economical
point of view for the decreasing of dam concrete volume, the height of 35m above riverbed
basement with showing narrow width, artificial concrete plug method was adopted.
▼ EL.471.0m
▽ EL.366.0m
N.W.L
Downstream
1:2.3
Height H= 101.0
96.0 m
▼ EL.270.0m
L= x m
▼ EL.471.0m
▽ EL.366.0m
N.W.L
Downstream
1:0.8
HeightH= 101.0
66.0 m
Plug
35 m
▼ EL.270.0m
L= 234 m
Figure-III-3.10 Comparison with Dam Shape Without Plug and With Plug
As the result of above calculation, basic dimension of diversion tunnel is as shown in Figure-III-3.11.
3.50
3.50
7.00
(8) Drawings
Specifications for dam and resourvoir of Ayung Dam is shown in Table-III-3.11.
3. Spillway
1)Type Toe guide wall type with no gates
2)Design Discharge 1,270 m3/s (1/1,000)
3)Depth 3.0 m
4)Width 113 m(Net width)
Elevation
366 m
Elevation
366 m
EXISTING ROAD
EXISTING ROAD
BUANGGA
MELINGGIH
DAM AXIS
APPROACH ROAD
APPROACH ROAD
DAM
Axis of Dam
DIVERTION SECTION
B-B SECTION
Diversion of River
B Scale 1:200
A
Up Stream Coffrerdam
STANDARD SECTION OF STILLING WORK
Spillway Basin
Spillway
Electric Power Plan
A
Conduit
A-A SECTION
Scale 1:1000
Roadway of Dam
UPSTREAM
DOWNSTREAM
SCALE 1:1500
(2) Waterway
Based on the probable discharge analysis, design discharge for waterway with return period of 25
years was calculated as 570 m3/s for check dam in Ayung River and 240 m3/s for check dam in Siap
River. Depth of overflowing is calculated by formula as shown in below:
Q=(0.71h3+1.77B1)h3 3/2 (3.2)
Where, Q :Discharege(m3/sec) C:Coefficient (0.60~0.66) C=0.6
g :Gravity (9.8m/sec2) B1:Base width (m)
B2:Water width (m) m2:Slope Gradient (m2=0.5)
B2
h'
m m H0
h3
1 .0
1 .0
B
Figure-III-3.16 Calculation of Overflow Depth for Waterway
Specifications of waterways are summarized as shown in Table-III-3.13.
Table-III-3.13 Specifications of Waterways
Dam Design Discharge Base Width Overflow Depth
Ayung River 570 m3/s 20 m 6.0 m
Siap River 240 m3/s 10 m 5.2 m
(4) Drawings
Drawings of check dam are summarized as shown in Figure-III-3.18 - Figure-III-3.19.
AYUNG MAIN
Plan
A1=120.60m2 A1+A2=214.08m
A2=93.48m2
AYUNG BRANCH
Plan
A1=80.30m 2 A1+A2=164.82m 2
A2=84.52m 2
According to development plant as shown in Table-III-3.16, image landscape design with atmosphere
of Bali is shown in Figure-III-3.20.
2 Diversion Works(L=340m)
2.1 Diversion Length m 340.0
(Figure:7.5m×7.5m Semi-Horse Shaped Tunnel)
2.2 Open Inlet・Outlet site 2.0
2.3 Coffer Dam site 2.0
3 Permanent Works(Concrete Gravity Dam)
3.1 Excavation m3 514,000.0
3.2 Artificial Plug m3 50,000.0
3.3 Concrete Works m3 240,000.0
3.4 Artificial Concrete Abutment m3 750.0
3.5 Grout Works
1) Consolidation Grout m 2,600.0
2) Curtain Grout m 29,500.0
3) Rim Grout m 500.0
3.6 Crown Road of Dam site 10.0
4 Temporary Equipment
1) Concrete Plant t 750.0
2) Tower Crane (13.5t×75m) set 1.0
3) Feed Plant t/hr 150.0
5 Power Station
Excavation m3 14,000.0
Concrete Structure m3 3,000.0
Power Station(7900kwv) set 1.0
6 Sabo Dam
Excavation m3 1,000.0
Concrete Works m3 12,000.0
7 Road Works
1) Earth Works & Pavement m2 18,550.0
2) Excavation(Rock) m3 5,000.0
3) Surface Course(Concrete:25cm) m2 18,550.0
5) Beacon・Signal etc m 1,667.0
6) Steel bridge t 390.0
8 Disporsal Area
Left bank m3 1,250,000.0
Right bnak m3 250,000.0
Embankment (Backfulling) m3 1,495,000.0
9 Outlet&Electric Power Gate
1) Intake Gate t 540.0
2) Conduit Pressure Pipe t 110.0
The outline of construction method and work item based on the construction quantity is shown in
Table-III-3.23.
Table-III-3.23 Work Item of Construction Plan, Method and Quantity
No. Work Item Content and Construction Method Construction Quantity
Temporary road and
1 Construction of Temporary road L=2,630m, B=7~8m
Improvement Work.
Diversion tunnel shall be constructed on the left
bank side to do excavation of the river bed. It
L=340m
2 Diversion Work shall be set up cofferdam at mouth and outflow of
(Half-horse-shoe :7.5m×7.5m)
diversion tunnel and a river bed shall be made dry
work.
Before the diversion of river, it shall be made to
finish excavation beyond the crown of dam. After
the diversion of river, it shall be made to finish Excavation Quantity
3 Dam Excavation
excavation under the crown of dam . Excavation = 520,000 m3
shall be begun from the top, and onboard work and
conveyance work shall be done on the river bed.
Gravity Dam Gravity Dam shall be constructed with ELCM
4 Concrete Works = 291,000 m3
(Concrete Works) (Extended Layer construction method)
Consolidation Grouting
Drilling and Consolidation grouting, curtain grouting and rim
5 = 2,600m
Grouting Works grouting shall be carried out.
Curtain Grouting = 29,500m
Protection work shall be done for cut slope of the
Slope Protection
6 temporary road, cut slope of dam excavation and
Works
temporary cut slope of other excavation.
It shall be thrown away in the place beyond EL370,
Disposal Area and soil shall be done. Disposal area shall be set up Capacity of Disposal Area
7
Works in the dam right bank upper reaches part, and it = 1,450,000m3
shall be placed beyond EL370.
Excavation Work and Concrete Work for Main Dam are as shown in followins:
<Rightt Site>
<Left Site>
Bulldozer(32t)、Crawler(150kg)、Breaker of
l i
Bulldozer(8t)
Backhoe Loader(1.2m3)
<River Bed>
Dam concrete works are consists of main dam work(EL.305m upper), artificial concrete
plug(EL.275m~305m) and artificial concrete abutment work (around dam crown). Concrete volumes
are estimated as about 291,000m3. Outline of concrete works are shown in the Table-III-3.24.
Table-III-3.24 Outline of Concrete Work (for Main Dam).
Monthly
Total months of Mean monthly
Concrete Placement Construction
Item Construction placement Remark
Lift Schedule acceptable
Work quantity
day
Dam body concrete River bed 2
1.5m 312 day 16 day 21.5 month 11,500 m3
months
Artificial concrete
ditto 108 ditto 7.0 7,150
plug
Abutment on either Placement is
bank 2.5 80 25 3.2 125 quantity
/one-time
Construction Schedule
Concrete Work is calculated as 312 days in total. As for items, placements days of concrete are
222days, suspensions by the structure thing execution inside dam are 60 days and placements of
concrete form are 30 days.
If acceptable days for placement of concrete are made 16 days. Total months of construction works are
21. 5 months and the amount of average placement for a month becomes 11,500 m3. Specifications of
Production equipment, the amount of bone material stock and a conveyance equipment are shown as
the following Table-III-3.25.
Table-III-3.25 Outline of Construction for Dam Body Works(Concrete Work)
Equipment classification. Item
1) Production equipment ・16 hours( Day and night execution. )
・Maximum one-day quantity = 1,200m3(around EL.332.0 m)
・Maximum one-hour quantity=75 m 3/ hr
2) Stock and Supply of ・Daily Necessary Maximum Quantity.Coarse Aggregate =2.860m3/day、
Aggregate Fine Aggregate=360m3/day
・The bin which can keep capacity on 3 days of a maximum quantity is set up.
3) Conveying Equipment for ・Main placement and Conveying Equipment:Tower Crane
Dam body execution (13.5t×75m)1set.
・4.5m3 Vessel Dump
・9m3 Gland Hopper
・10tDamp Truck
The construction schedule of Ayung Dam Project is shown in the Table-III-3.26 from the above
examination.
2 Diversion Works
Excavation 340m
Concrete Lining 340m
Inlet/Outlet Structure 2site
Coffer Dams 2site
4 Temporary Facilities
Main Concrete Plant 2.25x2
Tower Crane Installation 13.5tx75m
Water Treatment Plant 150t/hr
5 Power Station
3
Excavation 6000m
Foundation Treatment Ls
Structural Concrete 3,000m3
Architectural $ Equipment Works 7900kw
6 Sabo Dams
Excavation 2site
Concrete 2site
7 Spoil Bank
Right site 1,250,000m3
Left site 250,000m3
Remark
Badung River originated in hillside with 150m in elevation runs north to south through the center of
Denpasar City on the way and flows into Benoa Straight. Area of basin is about 37.7 km2, length is
approximately 30km and rounded river gradient is about 1/500. There are houses and stores densely in
the some sections which show insufficient height of dikes or narrow width along the river. Badung
River is one of the typical urban rivers judging from the urbanization ratio of 55% in the river basin at
present. However, due to good location for business as well as residences, it is forecasted to reach about
80% of river basin in the future. Buagan Weir located in the downstream is the main river facility for
irrigation use as well as domestic use.
Mati River originated in hillside with 80m in elevation near Sempide runs north to south, joining to
Tebe River at downstream near Kuta, and flows into the Benoa Straight. Mati River is also one of
typical urban river with catchments area 38.4km2 , length 20km, and river gradient I=1/400. There are
no dikes or narrow channel from Ulun Tanjung Weir in downstream to Umadui Weir in upstream.
According to river improvement plan by Indonesian Government, the area which surrounded both Mati
River and its right tributary Lebakmudin River in the upstream of Umadui Weir shall be designed for
retarding basin for flood control.
Same as Badung River basin, the ratio of urbanization in river basin currently reaches to about 50% and
estimated as 80 % in the future, the need for more land development for housing is very strong due to
the good location, and in the future it will be 80% of river basin.
Many flooding have been repeating along the area in Badung River and Mati River since 1979 which
recrded. In March 4th,1984, Monang Manning, Suwung and Pamecutan area located in Mati River Basin
were inundated at the estimated area of 700 ha and depth of 0.3m for about two days. More than 200
houses and stores near Kumbasari market located along Badung River also damaged in January 8, 1980.
Lately, December 12, 2005, the section between Maruti Street located in upstream and Pulau Misol
Street located in downstream along Badung River hit and damaged by flood. (Refer to Figure-III-4.1)
To prevent these damages by flood, flood control plan shall be settled and river improvement such as
excavation of riverbed, revetment and normalization shall be designed during feasibility study.
<Bank Slope Failure near Upstream of JL. P. Misol (From Left Bank Side)>
For the flood control plan and river planning, referring to not only Indonesian standards and criteria but
also the Japanese standard for flood control plan and design, the following items were settled:
Based on the recommended minimum return period of Design Flood as shown in the Flood
Control Manual, return period of flood control plan for both Badung River and Mati River shall
be adopted for 25 years.
For the following items, Japanese Standard for River Planning and Design was adopted by
referring to Flood Control Manual of Indonesian government.
1) Design Rainfall
2) Run-off Calculation Method
3) Design Flood
4) Flood Control Measures
5) Hydraulic Calculation
6) River Engineering
7) River Facilities and Bridges
Figure-III-4.2 Calculation Result for Current River Flow Capacity (Badung River)
2) Calculation method
Peak discharge flow calculated by Rational Formula is given as follows:
Qp=1/3.6・f・R・A (4.1)
where, Qp:Maximum Discharge (m3/sec),
f:Dimensionless Runoff Coefficient,
R: Average rainfall intensity within arrival time of flood(mm/hr)
A:Catchments Area (km2)
3) Runoff Coefficient
For flood plan, taking into account of land cover condition, land use and urbanization, runoff coefficient
for Badung River basin should be calculated by weighted average method corresponding with classified
coefficient of land use condition
a) Densely residential Area : 0.9
b) Residential Area : 0.9
c) Cropping field ,Waste land : 0.6
d) Paddy field : 0.8
e) Mountain area : 0.7
4) Arrival Time of Flood
Kraven’s Formula was used for calculation of arrival time of flood.
T=L/W (4.2)
I Less than 1/100 1/100~1/200 More than1/200
W 3.5m/s 3.0m/s 2.1m/s
5) Rainfall Intensity
Rainfall intensity was calculated by using daily rain fall intensity formula as shown in below,
rt =R24/24(24/T)2/3 (4.3)
where rt:Rainfall Intensity (mm/hr)
T:Arrival time of flood (hr),
R24:24 hours rainfall (= daily rainfall, m)
Note) Total catchments area of 37.7 km2 is based on the report “PERENCANAAN PENGELOLAAN SEDIME TUKAD
BADUNG DI KOTA DENPASAR, 2001”
7) Run-off Calculation
Conditions for Run-off Calculation
Return Period: As scale of return period 5, 10, 20, 25, 30, 50, 100 years are adopted for the
calculation.
Run-off Co-efficient: Two cases of co-efficient were set up for the runoff calculation; the one is for
current land use, another one is for future land use by taking into urbanization in Badung river basin. In
this calculation, percentage of 80% in river basin will be presumed to be developed.
Probable Daily Rainfal: 24 hours rainfall data for each return period are used.
Result of Run-off Calculation: Result of run-off calculation is shown in Figure-III-4.4.
TK.MEDIH TK.TAGTAG
From the Table-III-4.3, discharge with 25 years return period at river mouth is 233.9m3/sec on the basis
of current land use condition, and 239.4m3/sec with increasing 5.5m3/sec due to developing ratio with
80% of urbanization for watershed area.
As mentioned above, Badung River runs thorough the massed housing area as well as business area,
there are no space for the widening of river. Therefore, typical cross section with the riverbed
excavation and parapet wall should be adopted. Longitudinal profile should be designed to be steeper
slope due to riverbed excavation. Repair work for Buagan Weir mainly operating to irrigate paddy field
located in the downstream is also adopted based on the flow capacity calculation.
Land use regulations or flood control reservoir such as retarding basin are not to be planned on this river
improvement plan.
1) Section for River Improvement
Section for river improvement should be designated from just upstream of Buagan weir (Distance mark
No.88-50) to NO.194 distance mark near Maruti Street with about 5,700 m as shown in Figure-III-4.7
UBUNG
G A T O T S U B R O T O S T .
KAMPONG OF JAWA
JE M B . JL. M A R U T I
T
± B .1 9 4
E
B
DANGIN PURI
E
BALUN
R
IV
E
R
G U N U N G A
G U N G S T .
L = 5680 M
R IV
MO
NA
NG
NG
MA
JEMATANG
N IN
DU
G
BA
TE
UK
U
BERABAN
BATANYUH
UM
AR
DIPONO
T. S
T A R A K A N S T
KERDUNG WEIR
GORO ST.
PULA
INTAKE
U KA
WE ST
.
BUAGAN
WEIR
B U A G A N W E IR
± B . X IX
MOVING
WEIR
25
ELEVATION (M) 20
B. 192
B. 194
15
Current river bed
Design river bed I = 1/650
Design water level I = 1/650
Left bank
10
Right bank
B. XIX
Planed bank
5
0 1000 2000 3000 4000 5000 600
DISTANCE (M)
B .1 5 0
1 8 .5 -3 7 .0 m
0 .3 m
1 .0 m
3 .6 m
+ 1 5 .2 2 2 m
0 .0 -3 .0 m 1 1 .0 -3 2 .0 m 0 .0 -4 .0 m