Final Report 2
Final Report 2
INTRODUCTION
Internal Amenities:
2000 sq.ft gym and meditation area
Earthquake resistant structure
Fire Fighting System
CCTV surveillance
1
Fig 1.2 Terrace Amenities Fig 1.3 Building Elevation
2
2. LAYOUT OF THE PROJECT
A wing –
B wing –
Flat no. 1 – 1 BHK (474 sq.ft)
Flat no. 2 – 2 BHK (763 sq.ft)
Flat no. 3 – 3 BHK (1195 sq.ft)
Flat no. 4 – 3 BHK (969 sq.ft)
There are numerous organizations involved in the development of the project. The
following organizations involved are:
There are many other agencies involved such as internal plaster (gypsum),
waterproofing, plumbing, false celling, excavation, electrical, window fixing, railing
fixing, door fixing.
3
Fig 2.1 A- wing Layout
4
Fig 2.2 B - wing Layout
3. SITE LAYOUT
4. SLAB CYCLE
Slab cycle is the process of casting of slab at each level in the construction
site.
First the column projections are made on site with the help of line dori made
with the help of center line drawing.
Then the starter shuttering is done. Height of each starter is 200mm.
Column mivan shuttering is done above starter of height 200mm.
6
After the casting of columns and lift wall, beam bottoms are placed at a level
of 2200mm from slab.
Beam steel is placed at the beam bottom and after that the slab steel
placement starts.
Spacers are place in slab & beam steel and ply shuttering.
After the checking by contractors & engineer from developer & consultant
engineer the casting is done.
The slab cycle is repeated accordingly.
5.
Fig 4.1 IN
ENTERING STAGE R.C.C Schedule
THE PROJECT
The project started in March 2022 and the work upto the 11 th slab for the residential
tower and the 4th slab for the car parking tower had been completed till June 2023.
I started the internship in June 2023 from where the work for the casting of the 12 th
slab was going on and the internal blockwork had been completed till the 5 th floor
7
and other work such as internal plaster, tile work, plumbing, electrical fittings, false
ceiling, Granite fixing, waterproofing etc work was being done at the same time.
The project was given on a labor contract for the RCC structure to United One and
the material is provided by the builder. Every Monday there is a weekly meeting held
with all the contractors to resolve the issues and tasks to be completed in the
following week. The meeting is held in the presence of the builders site engineers
and supervisors along with the main contractor’s engineers and supervisors with the
other agency contractors.
After the material is ordered, when they arrive in a few days time (depending on the
material). When they arrive they are checked by the supervisor and tests are
performed on them by the engineer and are accepted or rejected accordingly. All the
challans are collected by the supervisor and the entries in the register are made by the
site engineers to keep a record of the materials on the site.
Steel
Cement 53 OPC and PPC (JK Lakshmi and India cement)
AAC blocks of 3,4 and 6 inches (Godrej)
Aggregates 10 and 20 mm
Crush, River Sand and Plaster sand
Tile, Marble, and Granite
Plumbing
Door Fittings
Almost all agencies have their supervisors to monitor their work so that they can
finish their work in their respective time so that the slab cycle does not extend.
The foremen from different agencies are:
8
Carpenter
Fitter (steel management)
Labour
Gypsum
External Plaster
Electrical
Plumbing
Tile
False Ceiling
Fire Fighting
6.
Starters are of 100 and 200 mm and they are casted to check if the shuttering Is
proper and in line so that when the column is casted it doesn’t bulge. They are casted
with the help of ply wood.
They are checked in three steps:
9
The horizontal and vertical length is measured.
With the help of plum bob check if the shuttering is in line.
And with the help of line dori the right angle is to be checked.
When all the three points are checked and if they are correct then the columns
are to be casted.
A column is casted on a starter with the help of mivan shuttering. Mivan shuttering is
faster and a very accurate material for shuttering is reduces the average time of slab
cycle.
They are checked in the following way:
For Steel checking the number of bars are to be checked along with the
diameter of the bars by referring to the Schedule of columns drawings.
Plum bob are released from the top of the column face vertically and any 3
points are measured using measuring tape. If the measurements are same,
then they pass the check.
Columns are also checked for position by measuring from other columns.
Beams and slab are very important to be checked thoroughly because they are the
ones to start the load distribution process.
They are checked in the following way:
The length, width and the depth of the beam are checked thoroughly.
The beams number of bars are counted and are cross checked in the schedule.
There shouldn’t be any
gap in the beam (Gabdi)
The slab is checked by
counting the number of
bars in the short and long
span.
The indication of the
level of the slab is marked
with the help of line dori
and steel bars.
Before every casting the R.C.C
consultant sends their engineer to
check all the above-mentioned
points.
10
Fig 6.1.1 Beam Checking
11
Type of footing used in the society is Isolated & combined footing. A total of 4200
mm deep excavation was done.
Grade of concrete used in the foundation casting is M-40.
300 mm soling was done & 230 mm P.C.C was done at the base.
After the casting of plinth beam, the total duration of slab cycle was 18-20 days. Slab
to slab height is 2900mm typical followed for every slab. Columns casting are done
by Mivan shuttering. Beams & Slab decking is done by wooden shuttering which
uses Avron plywood.
Sub-structure concreting, 1 & 2nd slab was casted by Ready mix concrete & 3rd slab
onwards on-site mix was done.
Diameter of steel used in column & beams are 12, 16, 20, 25 & 32mm.
Diameter of steel used in slab are 8, 10 & 12mm.
Diameter of steel used in stirrups are 8,10 and 12mm.
12
Fig 6.2.3 Slab Casting
A.A.C is a foam concrete material that is up to three times more lightweight than
regular bricks, and hence, is easy to handle and use too.
There are three types of blocks used at Himalaya site.
75 x 200 x 600 mm
100 x 200 x 600 mm
150 x 200 x 600 mm
External walls & partition walls of each flat are made by 150 mm A.A.C blocks &
internal walls like washroom and bedroom partition walls are made by 100 mm AAC
blocks.
First 200mm DPC is casted along the wall line.
Blocks are placed on DPC & is aligned with the help of plum bob.
Tuff fix chemical is applied between the joints.
13
The electrical system in a building is a crucial component that provides power for
various devices and systems. It consists of several key elements designed to ensure
the safe and efficient distribution of electricity throughout the building.
The electrical pipes are distributed in the specific way in which they are
put on the steel, so they get concealed while the concrete is casted. They
are also concealed in the columns of the structure.
After the pipes are distributed, they connect the lobby, the building and are
connected from the houses.
After all the pipes are connected according to the plan they are checked by
the engineer and the wires are put in them, which will be connected to a
power source and then it will get functional.
14
Fig 6.4.3 Electrical layout
15
6.5 WATERPROOFING
The waterproofing for the washrooms in this project is done in the following way -
The washroom is filled with water for 2 days to check for any leakage.
Once this is done, the plumbing agency installs the required pipes.
The voids in the piping area are filled with sand and then Brick Bat Coba is
done by placing red bricks and filling gaps with cement mortar.
After the Brick Bat Coba process, a waterproofing chemical is applied again,
and water is kept in the washroom for 2 days.
Finally, IPS (Interior Plaster Solution) is done, which is the final coat of
waterproofing.
The whole process of waterproofing is performed in 7-8 days for each washroom.
The process of the waterproofing in the Kitchen is done in a similar way as it is done
for the washrooms.
16
Fig 6.5.1 Base Coat work
17
Fig 6.5.2 Brick Bat Coba Fig 6.5.3 Final Coat Done
6.6. PLUMBING
In the past, a 6 mm layer of cement sand mortar was applied to the wall, followed by
a coating of Plaster of Paris. However, this method is now being replaced by a more
modern approach where a single coat of gypsum plaster is directly applied to the
surface.
Gypsum board false ceilings are made from gypsum plasterboards, which are
screwed to a metal frame that is attached to the soffit.
Distance between gypsum board and R.C.C slab is approximately 100mm.
19
Fig 6.7.1 Gypsum Sheet
Kitchen platform is constructed with the help of both Marble Patti and Granite Patti .
For making the kitchen platform the following procedure is followed :
Jhari work is done in the wall where the main platform and service platform
is going to placed which is about one and a half inches.
Sand is applied on the Indian Marble as it is a very smooth surface and needs
to be rough for better bonding.
Two Indian marbles are joined and used for the vertical support of the granite
platform. Araldite is the adhesive used to join the two Indian marbles.
After the vertical supports are created, Araldite is applied on the top of it to
place the Indian marble again as the support for the top platform.
After the Indian marble is place on top. Materials such as black sand and
cement mortar is applied on the top surface and then the granite is placed.
20
Fig 6.8.1 Marble Cutting Fig 6.8.2 Granite Cutting
Plaster serves as a thin layer of mortar that is applied to the surface of masonry work.
Its primary purpose is to act as a damp-proof coating over the brickwork.
Additionally, plastering provides a smooth and firm finish, enhancing the overall
appearance of the building.
To begin, we start by applying a layer of cement and sand mortar onto the
R.C.C surface to create a rough texture.
Once the mortar has fully dried, we proceed to water the surface for a period
of 2-3 days to ensure its hardness.
Following that, we apply a first coat of plastering measuring approximately
12mm in thickness. This coat is then allowed to dry completely.
Continuing the process, we water the surface for the next 4-5 days.
We then proceed to apply a final coat of plastering, measuring around 5-6mm
in thickness, and utilize an aluminum patti to achieve a smooth finish.
Lastly, we use a plum bob and a tile to ensure that a 90-degree angle is
achieved during the inspection phase.
1. Cement
2. Sand
3. Water
4. Admixtures
5. Glass Fiber
21
Recron 3S- 1 bag
Fig 6.9.1
6.10 Levelling the final Coat
TILING Fig 6.9.2 Final coat work
The most important part in the process of tiling work is marking off the level
throughout the house with help level pipe.
A Piece of tile also known as DHADA is placed at entrance of the house and each
rooms, kitchens so that a level can be marked thought the house. Here at site the
level is marked at 600mm level so the procedure of tile work can be done easily.
Now for the flooring tile work the following work procedure is followed :
The process begins with the placement of a small piece of tile used for
marking a level.
Next, the cleaning work (GHADAI) is carried out inside the apartment to
ensure a smooth and clean surface for the placement of materials required for
tiling.
A layer of sand, approximately 50-55mm in thickness, is spread throughout
the house in the areas where tiling will be done.
Cement is then mixed with water to create a slurry, which is applied over the
sand layer.
The placement of tiles starts from the corner of the room to ensure ease of
placement throughout the apartment.
Once the tiles are placed, grouting work is done to fill the gaps between the
tiles, often referred to as filling of SANDHA.
After completing all the necessary procedures, the placement of tiles is
checked for accuracy. Any remaining SANDHA is filled, and a final cleaning
is carried out.
22
Process for the tiling work on the walls of kitchen and washrooms is done in the
following way :
For the tilling walls only cement mortar is used.
Marking is done for the placement of tiles on the wall .
Cement Mortar is applied on the back surface of the tile, and it is placed on
the walls.
Grouting process is applied and all the sandhas are filled up.
Tiles that are installed correctly will be even with each other, with no gaps.
This ensures a level surface and a seamless look.
Sound test is done by knocking on tiles. There would be issue in the sound if
there any gap left behind the tiles.
Grout lines should be consistent and straight, with no gaps between the tiles.
There should be no excess grout on tile surfaces.
Tiles are firmly attached to the floor.
Tiles are not chipped or cracked.
23
Fig 6.10.4 Application of tiles
The doors that have been provided are fire-resistant doors that adhere to the
guidelines set by the Chief Fire Officer (CFO).
The door frames have dimensions of 45x900 mm and 45x2100 mm, while the doors
themselves have dimensions of 810x2000 mm. The process of installation:
The first layer of the door frame is securely fastened to the wall using anchor
fasteners.
The second layer of the frame is then affixed to the first layer using adhesive
and left to dry for a full day.
On the following day, the hinges are carefully drilled, and the door is attached
to the frame.
Lastly, the door is checked for alignment and functionality to ensure a
successful installation.
24
Aluminum window frames offer numerous benefits for buildings due to their
strength, lightweight nature, and resistance to rust. These frames are highly
favored for both residential and commercial settings as they provide
durability, aesthetic appeal, and are easy to maintain.
In the case of the four-track aluminum window used in Himalaya, three of the
tracks are designated for the windows, while the fourth track serves as a
mosquito net.
An overhead tank is crucial for consistent water supply by utilizing gravity, ensuring
reliable water pressure in buildings. It facilitates uninterrupted water access during
power outages and emergencies. Essential for residential, industrial, and agricultural
use, overhead tanks contribute to water efficiency and support daily activities.
The capacity of the overhead tank is:
WING-A WING-B
OHT Domestic 18000 Liters 17000 Liters
OHT Flushing 20000 Liters 20000 Liters
Fire Tank 15000 Liters 15000 Litres
26
Fig 6.13.1 Drawing of Overhead Tank
For the underground tank casting we had excavated soil of 580 brass which made the
construction of the UGT possible.
Underground tanks are vital for water storage, especially in areas with limited space
or aesthetic considerations. They provide discreet storage while preventing water
contamination and temperature fluctuations. Commonly used in urban settings, these
tanks enhance water conservation, ensuring a reliable and hidden solution for diverse
water storage needs.
WING-A WING-B
Underground Domestic 42000 Liters 42000 Liters
Underground Flushing 15000 Liters 15000 Liters
Fire Tank 75000 Liters 75000 Liters
27
Fig 6.14.1 PCC for Underground Tank
6.15 SOFTWARES
AutoCAD:
Autodesk AutoCAD is one of the Computer Aided Design software tools used for
Technical Drawing in the construction industry. It is mainly used by architect and
drafter to design blueprints, bridges, and roads. It helps us to find the length or size
of footing, column, retaining wall, beam, and slab. It also helps us to visualize and
understand how the building will look after completion of construction.
Microsoft Excel:
Microsoft excel is a helpful and powerful program for documentation and data
analysis. It’s a spread sheet program with number of column and rows. Onsite it
helps to maintain all the data of work completed on each day, material entry and
most importantly for preparing Bill of Quantity (BOQ) and Bar Bending Schedule
(BBS) and during calculations for ordering and cross checking all the materials.
28
6.16 CUBE TESTING
30
Fig 6.16.3 M-30 Cubes 28 Days Report
31
7. IN PLANT TRAINING OUTCOME
In addition to that, I had the privilege of being part of the sales team, where I learned
how to effectively present the site and showcase sample flats to potential clients.
One of the most valuable aspects of this internship was the opportunity to handle
real-world situations and find solutions. The presence of experienced individuals on
the site, including laborers, site engineers, supervisors, and foremen, greatly
contributed to my learning experience as they were always available to guide and
clarify any doubts I had.
Overall, this internship has provided me with practical knowledge and a deeper
understanding of the construction industry.
32
8. REFERENCES
33