2nd March - 24 - PMP Answer File - Daily Q&A
2nd March - 24 - PMP Answer File - Daily Q&A
2nd March - 24 - PMP Answer File - Daily Q&A
Question - 1
Q. You are observing a chart which has a line drawn between the X and Y axis. The X-axis shows the
time and Y-axis shows the data points. What kind of information can you find here?
(c) Variance
Answer: A.
A run chart is a line graph of data plotted over time. This chart helps you see the pattern in the
process. (Note: A run chart does not have control limits; therefore, it cannot tell you whether or not
the process is stable.).
Question - 2
Your project team is located in different locations. Your schedule is delayed and you’re facing many
issues. Which of the following is the best solution to this problem?
Answer: C.
When the team is located in different places and performance is poor, you can bring them together
to improve performance.
Question - 3
Q. You publish some informative notes on the company’s web portal and ask stakeholders to review
it. What kind of communication method is this?
(a) Pull
(b) Push
(c) Interactive
Answer: A.
In a pull communication method, you keep information somewhere and ask stakeholders to access
it.
Question - 4
Q. You have developed a risk response plan which says if the trigger occurs, the risk response owner
asks the risk action owner to implement the plan and update him with the result. What is the trigger
condition in risk management?
Answer: A.
Question - 5
Q. You are reviewing seller-prepared documents and quality audits are conducted during the seller’s
execution of the work with an objective to identify performance success and failure. What process is
this?
Answer: B.
You are doing procurement performance reviews, which is a tool and technique of the control
procurement process. Here, you review the seller's performance against the conditions laid down in
the contract.
Question - 6
Q. John is a stakeholder of your project and is known for creating problems. During the project
execution, you noticed that he started creating problems with your project and you are afraid that if
this issue is not solved, it will affect your project. So, to avoid this situation, which of the following
should you do?
Answer: C
If you see any problems with any of your team members, you should talk with them to find the
cause.
Question - 7
Q. Alice is a new team member in your project and she does not have much experience. As the
project is big and involves many governmental departments, you ask Alice to pay more attention to
some standards and regulations. Which of the following statements is true about the standards and
regulations?
Answer: D.
Regulations are always mandatory, you cannot escape them. On the other hand, standards are
guidelines to help you to accomplish tasks with tested and approved methods or procedures.
Question - 8
Q. Your project has successfully completed; the deliverable is handed over to the client, and you are
in the close phase or project process. Which of the following activities will you not perform in the
close phase or project process?
Answer: C.
During the close project or phase process, you update the lessons learned and release the resources.
Accepting deliverable is the output of the validate scope process.
Question - 9
Q. You are sitting in a group discussion with 13 stakeholders and collecting ideas. Now you are in the
final stage and are selecting the final idea. As there are many ideas, you decide to vote. After voting
you see that a particular idea receives 7 votes, so you go with that option. What kind of decision
making is this?
(a) Unanimity
(b) Majority
(c) Plurality
(d) Dictatorship
Answer: B
Question - 10
Q. You have been given a task to estimate a budget for your project. You are using a bottom up cost
estimation technique to calculate the cost of each activity. Management told you that the
management reserve will be 6% of the cost baseline. Which of the following represents the
budgeted cost of the project?
Answer: A.