Höegh Training Session 3, Rev1 - Plant Description

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

3.

Plant Description

TGE Marine Gas Engineering


2023 | Bonn, Germany
Plant Description

• LNG FUEL GAS SYSTEM - FUNCTION & PROCESS


• LOCATION OF FUEL GAS SYSTEM (FGS)
• TGE LIST & SYMBOLOGY OF P&ID’S FOR MAIN COMPONENTS
• MAJOR COMPONENTS; DESIGN CONSTRUCTION & FUNCTION
• SPECIAL EQUIPMENT RELATED TO FGS
• HP SYSTEM – SAFETY CONSIDERATIONS

2 | Plant Description | 2023


Plant Description

General PFD

• Fuel Gas Preparation Room


• Tank with TCS
• Bunker stations

• Engine room (Auxiliaries)

3 | Plant Description | 2023


Plant Description – Location of FG System

• LNG fuel gas tank is located on decks 1 to


3 (see number 1)

• Tank connection space (TCS) of the fuel gas


tank is located on deck 4 (see number 3)

• Bunker stations are located on deck 5 (see


number 2 & 4)

• Fuel gas preparation room (FGPR) is


located in deck 1 and 2 (see number 5)

4 | Plant Description | 2023


Plant Description – FG Tank

• LNG fuel gas tank with 2 x TCS

• Cylindrical length: abt. 32.9 m

• Diameter: 8m

• Width: 2 x 6.7 m

• 350 mm insulation

5 | Plant Description | 2023


Plant Description – Location of FG system in FGPR

FG preparation room

6 | Plant Description | 2023


Plant Description – TCS

TCS – Tank Connection Space

7 | Plant Description | 2023


Plant Description – TCS

TCS – Tank Connection Space SB

8 | Plant Description | 2023


Plant Description – Bunkering station

Bunkering Station

9 | Plant Description | 2023


Plant Description – Major Components

MAJOR COMPONENTS; DESIGN CONSTRUCTION & FUNCTION


• BOG compressor
• LP FG Pump
• HP FG Pump
• HP Gas Heater

10 | Plant Description | 2023


Plant Description – BOG compressor

11 | Plant Description | 2023


Plant Description – BOG compressor

Function:

BOG from tank will be


pressurized for LP consumers
and recondenser.

Flow: 400 -1050 kg/h


Speed by VFD: 370-735 rpm

12 | Plant Description | 2023


Plant Description – LP LNG Pump

LP LNG pump (Svanehoj) ready to ship

13 | Plant Description | 2023


Plant Description – HP FG Pump

HP Fuel Gas Pump

14 | Plant Description | 2023


Plant Description – HP Gas Heater

Function:
Heating of HP LNG from -150°C up to 45°C by
Water/Glycol (WG)

15 | Plant Description | 2023


Plant Description

SPECIAL EQUIPMENTS RELATED TO THIS FGS


- Recondenser
- HP Buffer Vessel
- Liquid separator

16 | Plant Description | 2023


Plant Description – Recondenser

System is based on TGE’s


proprietary control for HP-FGS

Added equipment: HP-BOG


condenser & Recondenser

Recondenser is standard
equipment for LNG import
terminals;
The actual design was
adapted to more dynamic
operation

17 | Plant Description | 2023


Plant Description - Recondenser

P8054
PCV

BOG A/E, Boiler


heater P8001
P8001
PIC
PCV

P8054
PIC
BOG Compressor
P8057 LP Buffer P6919
PIC Vessel PIC

LP fuel gas LP fuel gas


vaporizer heater
P8057
PCV
P6440
PCV

P6422
TDIC
HP fuel gas HP BOG HP fuel gas
P5503 P6423 pump Condenser heater
PIC TDIC
Main Engine
P6421
Fuel Gas Tank TDIC
Recondenser
Static Mixer
LP fuel
gas pump
F6412
FCV

18 | Plant description | 2023


Plant Description - Recondenser

19 | Plant Description | 2023


Plant Description - Recondenser

Recondenser is using some of the sub-cooling for BOG liquefaction; Unit control must ensure safe operation of HP
pump.

Minimum Suction Subcooling is depending on cold end design of HP pump


20 | Plant Description | 2023
Plant Description - Recondenser

Recondenser general aspects

• Recondenser is a slow reacting device (significant lag time)

• Recondenser works best in steady state operation (slow control loops)

• In HP-pump suction we must keep a safe margin to the bubble point of the HP-pump feed condition.

Recondenser dynamic aspects

• In the dynamic simulation load drops to approx. 60 % of peak load are observed frequently within several
seconds
• Recondenser control must ensure that no excess vapour is mixed to HP-feed during load drop

• Recycling of HP-feed after recondenser to tank is thermodynamic nonsense and will result in overall increased
BOR (boil off rate).

21 | Plant Description | 2023


Plant Description – HP buffer vessel

Function:

HP buffer vessel will


harmonize the pressure in
the HP discharge line to
the MEGI.

Volume: 200 ltr.


Weight: 1000 kg

22 | Plant Description | 2023


Plant Description – Liquid separator

Function:

HP flow will be separated in the


separator. Liquid phase back to
tank, vapour phase to LB FG
consumer or to tank.

23 | Plant Description | 2023


Plant Description – HP System safety measures

Safety measures for HP system:

• Welded connections or use


of RTJ flanges
• Flange guards
• Reduction of exposure by
automation and
access restrictions

24 | Plant Description | 2023