TPWS, 2019, Optimal Dynamic Line Rating Forecasts Selection Based
TPWS, 2019, Optimal Dynamic Line Rating Forecasts Selection Based
net/publication/330246445
CITATIONS READS
39 143
3 authors, including:
Georges N. Kariniotakis
MINES ParisTech
278 PUBLICATIONS 8,528 CITATIONS
SEE PROFILE
All content following this page was uploaded by Georges N. Kariniotakis on 20 October 2022.
Part of this work was carried out thanks to an exchange mobility grant energy systems, CS 10207, 1 rue Claude Daunesse 06904 SophiaAntipolis
awarded to the first author from the project ELECTRA IRP (Grant No 609687), Cedex, France.
funded in part by the European Commission under the 7th Framework (e-mails: romain.dupin, andrea.michiorri, georges.kariniotakis each with
Programme. @mines-paristech.fr).
R. Dupin, A. Michiorri and G. Kariniotakis are with MINES ParisTech, PSL
Research University, PERSEE - Centre for processes, renewable energies and
2
A state of the art of real applications of this kind in Europe case study used for the model evaluation. In section IV the main
is described in [10]. In [11] and [12], where the experiences of results are presented, and finally section V presents the
the NETFLEX project are described, probability τ is set as conclusions and perspective of this work.
equal to 2%. In [13], probability τ fixed levels of 1%, 5%, 10%
and 20% are tested. In [14], a probability τ of 1% is considered. II. MODELLING APPROACH
Other studies could also be quoted, such as [15] and [16], where The problem to be solved is the optimal operation of a grid on
τ probabilities of 10% and 2.5% are respectively considered. which some lines are equipped with DLR. It is similar to that
Recently, it has been proposed in the literature to no longer formulated in [18] and [22], which assess the DLR value in grid
set the value of DLR forecasts with a fixed level of frequency, management. Since several uncertainties are involved, a
but to use stochastic optimization instead. In [17] and [18], this stochastic optimisation approach is applied. Below, several
is done with two-stage stochastic optimization, which aims at problem formulations are proposed for setting the DLR
minimizing the sum of the generation costs, reserve allocation forecasts, according to different objectives set by the TSO.
and potential reserve activation due to DLR forecast errors. A A. Risk Neutral Strategy – Vertically Integrated Monopoly
similar approach is also proposed in [19], where instead of
We first consider that the electricity producers and electric
reserve activation, it is considered that the retroactions are system operators are the same actor. The problem addressed
achieved through voluntary and involuntary load reduction. here is described in [18] and can be modelled as a two-stage
References [20] and [21] both propose considering that the stochastic optimization problem.
constraint associated with the line ampacity could be replaced For a stochastic optimization problem taking into account
with a cost in the objective function in case of non-respect of DLR forecasts, different terms could be considered in the
the constraint. objective function. One important question concerns the
The above two approaches are radically different. The one introduction and use of penalties regarding situations in which
with the fixed quantiles favours a conservative approach the current is slightly higher than the thermal limits of the lines,
independent from opportunities to improve social welfare, as in [20], [21], [23]. Such cost definitions require knowledge
while ensuring a low risk level. On the contrary, with the second of potential incidents on the grid, their associated probability,
approach based on stochastic optimization, the authors consider and recourse actions when these costs are too high. In this
a risk-neutral approach and aim at maximizing the social paper, we consider a preventive approach regarding N-1
welfare. In this context, the term “social welfare” refers to the incidents, and penalties requiring a corrective approach are not
sum of the consumer and producer surpluses. If the load is introduced. It should be stressed that the simplifications
considered as inelastic towards prices, maximizing the social allowed with this preventive approach permits the use of lookup
welfare is equivalent to minimizing the operation costs. tables which are necessary to provide computations for a high
In this paper, we propose to evaluate the benefits of DLR number of observations in a reasonable time.
based on an intermediate strategy, which aims at improving The objective function is risk neutral, the objective being to
social welfare while ensuring low levels of risk, required for minimize production costs of generators in the system plus the
application on the field. The key contributions can be costs of reserve allocation and potential activation (2):
summarized as follows:
∑ (πfuelg . Pg + Ig . πfixg ) +
1) Several alternative strategies for integrating DLR into g=1..Ng
planning operations are proposed. They aim at improving the up
∑ (πhupg . Hg + πhdog . Hgdo ) +
economic benefits, (referred to here also as the “social min (2)
g=1..Ng
welfare”) for a case where electricity consumption is inelastic up
towards price, while maintaining low values for several ∑ ∑ ρs ∙ (πrupg . R g,s + πrdog . Rdo
g,s )
{s∈Ns g=1..Ng }
parameters to which the Transmission System Operator (TSO)
is averse. The evaluation of these strategies allows us to where Ng is a set of conventional generators; Ig is a binary
understand the significant benefits of using risk-averse variable with value 1 describing a committed generator, and 0
strategies for DLR probabilistic forecasts, compared to if not; πfuelg is the fuel cost for generator g (€/MWh); πfixg is
traditional approaches that use fixed quantiles or risk-neutral
the commitment price for a conventional generator g (€/h); Pg
strategies.
2) We propose a test case and a methodology to evaluate the is the scheduled output of generator g (MW); πhupg and πhdog
economic value of both DLR forecast models and proposed are the costs for maintaining up and down reserve for a
up
strategies for using DLR forecasts. This is based on the use of generator g (€/MWh); Hg and Hgdo are the up and down reserve
lookup table and allow considering grid characteristics. service holding amounts for generator g (MW); Ns is the set of
3) The proposed study takes into account a high number of potential future realizations of DLR and other stochastic
realistic DLR probabilistic forecasts, generated with weather variable observations, with each scenario having a probability
station observations and machine learning methods. This is a ρs of occurrence set with probabilistic forecasts; πrupg and
more complete approach than similar ones proposed in the up
literature, which generally consider only a single virtual DLR πrdog are the reserve activation costs (€/MWh); and R g,s and
probabilistic forecast. Rdo
g,s are the activated reserves from a generator g at scenario s
(MW).
The paper is structured as follows: first, in section II, the The constraints are those of a DC power flow, and are
proposed methodology is presented. Section III presents the described in [18] and [22]. Here, N-1 constraints are added to
3
account for the risks of line failure, as proposed in [24], which It should be stressed that the risk aversion towards risk
investigates DLR use for transfer capacity setting. activation costs defined here is a trade-off solution: risk
aversion towards other parameters, such as load shedding,
B. Risk-Neutral Strategy – Separate Grid Operators and would be more representative of TSOs’ behaviour. However, it
Electricity Producers would make the problem more complex, and impossible to
In the previous strategy, the generation planning is affected compute for a very high number of scenarios and forecasts, as
by the potential recourse actions set by the TSO. It is however it is the case here. By considering these reserve costs as similar
unlikely that electricity producers would modify their day- to risk indices, it is thus possible to evaluate first different risk
ahead decisions according to the risks and potential costs of aversion functions, and also determine the economic value of
DLR forecast errors, which are assumed by the TSO. DLR forecast models in a latter approach.
In order to decouple the decision of the generator-planned The shape of the function vβ is arbitrarily set by the TSO,
production levels from the decision of the DLR forecast value, depending on its objectives. Here, three functions are proposed
a bilevel stochastic optimization problem is used here, with a inspired from [20], [21], where virtual costs associated with line
leader problem (3)-(4) and a follower problem (5): ampacity violations by currents are defined:
minx∈X,y∈Y F(x, y) • A linear function:
(3)
vβ (x) = (1 + β) ∙ x β≥0 (8)
s. t.
Gi (x, y) ≤ 0 for i ∈ {1,2, … , I} (4)
• A quadratic function:
y ∈ arg minz∈Y {f(x, z): g j (x, z) ≤ 0, j ∈ {1,2, … , J}} vβ (x) = x + β ∙ x² β≥0 (9)
(5)
For a test case such as the one described in [18], the property 4) For a scenario s associated with a DLR realization Δl,s , if
of reversibility could be considered regarding the states of Δl,s is lower than inferior to the DLR forecasted value Δl
generator production towards DLR values, where all selected by the TSO, the activated reserves are found by
conventional generators participate in recourse actions, and the computing the differences in the outputs of the different
reserve activation costs are proportional to the day-ahead generators associated with the solutions of the SCOPFs
prices. With the properties described above, the problem can be made with the line ratings equal to Δl,s and Δl .
resolved by solving different Security Constrained Optimal 5) Then, considering the levels of probability ρs of a DLR
Power Flows (SCOPF) according to the following steps: observation Δl,s , it is possible to select an optimal value for
1) A first SCOPF is resolved to initialize the problem, where the DLR forecast Δl .
the line ratings are set at the value that corresponds to the By considering a limited set of possible states of load L1 and
SLR, to define the list of the activated generators Ig . L2 (in this work, 20 for each load area, going from 0% of the
2) After setting Ig , a SCOPF is computed for each possible nominal load to 100%), DLR planned forecasts (100, going
value of line rating Δl . from 100% of the SLR to 200%) and DLR potential
3) For each forecast Δl , the values of allocated reserves observations (100, going from 100% of the SLR to 200%), it is
up
Hg /Hgdo are set by: a) running a SCOPF with a line rating possible to compute the different SCOPFs for each state in
set as Δl , b) calculating the difference between generator which DLR improvements bring benefits. Thus, lookup tables
outputs in this situation and generator outputs after the can be built (Fig. 1), each value of the table being associated to
SCOPF in step 1. This method implies that the problem a tuple of scenario, and the use of this tool allows reducing
associated with the SCOPF is strictly convex, which may considerably the computation time for a period associated to a
not be the case with a linear approach. In the study proposed high number of observations (Fig. 2).
here, a negligible quadratic component is added to the
generator cost function, in order to ensure strict convexity.
Fig. 1. For a load scenario (L1, L2), a DLR forecast Δl and a DLR observation Δl,s , computation process for setting the associated value in the lookup table.
Fig. 2. Flowchart associated to the computations made with the lookup tables.
5
set as equal to 5. In most of the studies associated with DLR for the up-reserve activation.
forecasts, the forecasts are used with fixed quantiles varying The computations of DC optimal power flows are carried out
from 1% to 10%, which thus requires using the forecast model using PyPower [32], and the security constraints are added by
to provide percentile forecasts. However, here, these forecasts generating constraints obtained with Benders cuts. It is
are used as inputs of risk-averse strategies, which aim at considered that no line failures could occur on line 8-7, this part
providing results that are similar to 1%-quantile DLR forecasts of the grid being operated in a radial configuration.
in terms of risks. For this reason, the model provides a set of Lines 8-9 and 8-10 are considered to be equipped with DLR
999 quantile forecasts, for quantiles ranging from 0.1% to functionality, and to have exactly the same DLR value at each
99.9% in 0.1% steps. An example of such forecasts is shown time. These two lines are indeed connected from bus 8 to buses
in Fig. 4. 9 and 10, the latter two being at the same position. The reason
The Mean Absolute Percentage Error (MAPE) and reliability for choosing these two lines is the fact that they appear to be
criteria are considered here to evaluate the performance of the congested when computing the Total Transfer Capacity from
forecast models with regard to state-of-the-art models. First, area 1 to area 2.
regarding the MAPE, a comparison can be made with the
persistence model, i.e. a model where a forecast is set as equal
to the observations made at the moment of the forecast.
For this case, the MAPE for the QRF and the persistence
model are equal to 11.1% and 16.1% respectively. The relative
difference of 31% is in line with the results found in [15].
In terms of reliability, the frequency of overestimation for
quantiles 0.1%, 1% and 2% is equal to 0.8%, 1.8% and 2.7%
respectively. With binomial laws, considering perfectly reliable
forecasts and the number of considered forecasts, it is easy to
find that such frequencies should respectively be inferior to
0.14%, 1.11% and 2.16% with a level of probability of 99%.
The proposed forecast model is then not reliable, even if the last
two frequencies are in line with the results found in [14] and
[30].
Despite this weakness, this model is considered as
acceptable. The first reason is based on recent research made on
DLR forecasts, which indicate that the performances of the
model are close to the models currently used by the TSOs.
Secondly, the reliability criterion is here used to evaluate the
model, but there is no evidence in the literature that this Fig. 5. IEEE 24-bus reliability test system. The lines equipped with DLR are
parameter is the most important one regarding DLR forecasts, marked in red.
and other criteria as the sharpness might be more important. As
an example, with the traditional use of a fixed quantile, it might Lines 8-9 and 8-10 are considered to be equipped with DLR
be considered that a TSO might prefer to use 1% quantile functionality, and to have exactly the same DLR value at each
forecasts from a non-reliable but sharp forecast model than 2% time. These two lines are indeed connected from bus 8 to buses
quantile forecasts from another model, more reliable but less 9 and 10, the latter two being at the same position. The reason
sharp. Such questions are still not answered, and they are to be for choosing these two lines is the fact that they appear to be
addressed by using simultaneously DLR forecasts with congested when computing the Total Transfer Capacity from
different statistical properties and economic models providing area 1 to area 2.
an evaluation of the value of the forecasts. In future work, the The line dynamic ampacity is set as equal to its initial value
development of the tool presented in this paper based on the use provided in the grid data, multiplied by the DLR divided by the
of lookup tables aims at realizing such a research of the required SLR value. For this study, it cannot be below its nominal value.
properties of DLR forecast models. Three SLR values are used, one for each season, and are set
such as to below the observed DLR for 99% of the time for the
III. CASE STUDY year 2009. The seasons are defined as winter (December to
February), spring/autumn (March to May and September to
A. Network Description November) and summer (June to August). Different values of
The IEEE 24-bus grid is considered here (Fig. 5), with the SLR are defined for each weather station.
same characteristics as the ones in [31]. It is split into two areas,
B. Load Series
each of which is considered with different load values.
The reserve allocation and activation costs are set similarly In most studies involving grid simulations using DLR
to [18]: the costs for up and down reserve allocation, πhupg and forecasts, only a given configuration of the grid is used.
πhdog , are set as equal to 6 €/MWh for every generator g; the However, the grid configuration has a significant impact on the
DLR impact and the selection of the optimal forecast.
reserve activation costs are set as equal to the fuel price for the
We therefore propose generating load time series with a
down-reserve activation, and as equal to 150% of the fuel price
bootstrap process, considering only congestion situations, and
7
taking the frequencies of the different situations from a study of other congestions have appeared. These other congestions
historical time series. ENTSO-E data for the year 2010 are could be new congestions on other lines or changes in
exploited for this goal. Historical data from France (area 1) and congestion natures from thermal limitations to stability or
Germany (area 2) are used, since these data feature a high voltage drop limitations [34].
variety of congestion issues for the bootstrap process.
IV. RESULTS
In order to evaluate the value of the different strategies, the
cost reductions from the initial total system costs, LSLR (€), to
the final total system costs obtained when DLR forecasts are
used, LDLR (€), are considered as benefits. They are normalized
by dividing them by the total LSLR costs associated with the
situations where SLR is used:
LSLR− LDLR
Benefits = 100% ∙ (11)
LSLR
Fig. 6. Evolution of the benefits as a function of the values of the selected fixed
In addition to the benefits, financial losses and risks are also quantiles. The two yellow circles are associated to the use of fixed quantiles
evaluated, using three indices: equal to 1% and 20%.
1) The frequency of events requiring reserve activations due
The observed benefits are computed for the studied period
to overestimations of DLR forecasts (%).
and shown on Table I, with the associated risk and loss indices
2) The total cost of reserve activation Cres act (€) for the
associated being also shown.
studied period. As with the benefits, this cost is normalized
The expected benefits, which are equal to the average of the
using the total costs of the system when the SLR is used:
Cres act expected benefits for the whole set of resolved optimization
Cres act,n = 100% ∙ (12) problems, were also computed, and for every situation
LSLR considered in this paper, we found that the relative difference
between the expected and observed benefits was less than 2%.
3) The frequency of errors with a cost above a defined
This is not surprising, considering the high amount of
threshold f_reserve(threshold) (%). The idea behind this is
observations used and the fact that the stochastic part of the
to address the fact that TSOs may aim at maintaining the
benefits, which is the total costs of the activated reserves, is
DLR error magnitude below a certain threshold most of the
lower than 10% and 3% of the total benefit, respectively with
time. This is especially the case when the reserve may be
the use of risk-neutral optimization and a 1% quantile DLR
hard to call, which could be considered as when it is costly.
forecast. We can thus consider that the expected and observed
The threshold is arbitrarily defined equal as to €1500.
benefits are equal. This allows us to compare forecast models
Situations involving such events are qualified as incidents.
and DLR forecast setting strategies by setting the same levels
A. Traditional Strategies of observed benefits, which are considered as known because
A first study is made by considering traditional methods, i.e. equal to the expected benefits.
the use of fixed quantiles and risk-neutral strategies. Three
TABLE I
strategies are tested: STRATEGY COMPARISON: OBSERVED BENEFITS, FREQUENCY OF ERRORS AND
1) Low arbitrary quantile τ of 1% is selected. FREQUENCY OF INCIDENTS.
2) High arbitrary quantile τ of 20% is selected. Strategy Benefit Overestimation Reserve f_reserve(1500€)
3) The value of the DLR forecast is dynamically set to used (%) frequency (%) costs (%) (%)
minimize the expected operational costs, with a risk- SLR 0.00 0.00 0.000 0.00
neutral strategy.
τ = 1% 0.61 0.72 0.016 0.17
Regarding the choice of the quantile of 20%, it is to stress
that when the selected quantile becomes superior to 20%, the τ = 20% 0.97 4.17 0.105 1.30
benefits converge toward a value of 0.97%. This is shown on
Figure 3, where the evolution of the observed benefits with the Risk-neutral
1.01 3.62 0.085 1.10
strategy
value of a fixed selected quantile is represented.
The results shown on Figure 3 are to be compared to [33], Perfect
1.10 0.00 0.000 0.00
where a similar figure is provided. Contrary to the Figure 3, [33] forecast
shows that benefits do not converge but drop sharply when
quantiles reach values superior to 20%. This difference in Several results are noteworthy. We start by comparing the
behaviour between the results presented here and [33] is due to results with existing literature. Regarding levels of benefits, we
the fact that the grid characteristics are considered in our study, consider study [5], where DLR is considered for dispatching on
and that when DLR forecast values increase above a given an IEEE 30-bus grid and benefits of around 1% of the
threshold no further improvements are observed on the grid, operational costs are found. Here, as shown in Table I, we find
either because the congestions have been erased or because
8
ACKNOWLEDGEMENT
The European Centre for Medium-Range Weather Forecasts
(ECMWF) is acknowledged for the provision of the Numerical
Weather Predictions. The authors would like to thank Prof. M.
Matos of INESC TEC for our useful discussions.
REFERENCES
[1] W. CIGRE, 12, Thermal Behaviour of Overhead Conductors, Tech.
Brochure, 2002.
[2] “IEEE Standard for Calculating the Current-Temperature Relationship
of Bare Overhead Conductors,” IEEE Std 738-2012 Revis. IEEE Std
738-2006 - Inc. IEEE Std 738-2012 Cor 1-2013, pp. 1–72, Dec. 2013.
[3] T. O. Seppa, “Guide for selection of weather parameters for bare
overhead conductor ratings,” CIGRE WG B, vol. 2, 2006.
[4] M. W. Davis, “A new thermal rating approach: The real time thermal
rating system for strategic overhead conductor transmission lines – Part
I: General description and justification of the real time thermal rating
system,” IEEE Trans. Power Appar. Syst., vol. 96, no. 3, pp. 803–809,
May 1977.
[5] M. A. Bucher, M. Vrakopoulou, and G. Andersson, “Probabilistic N-1
security assessment incorporating dynamic line ratings,” in IEEE
Power Energy Society General Meeting, Vancouver, Canada, 2013.
[6] M. Khaki, P. Musilek, J. Heckenbergerova, and D. Koval, “Electric
power system cost/loss optimization using dynamic thermal rating and
linear programming,” in Electric Power and Energy Conference
Fig. 8. Frequency of incidents in function of economic benefits, depending on (EPEC), 2010 IEEE, Halifax, Canada, 2010.
the use of a fixed quantile (red) or a dynamic selection, set with linear penalties [7] C. J. Wallnerström, Y. Huang, and L. Söder, “Impact From Dynamic
(green), quadratic penalties (orange) and exponential penalties (blue). The Line Rating on Wind Power Integration,” IEEE Trans. Smart Grid, vol.
yellow circle is associated with the use of 1% DLR quantile forecasts. The 6, no. 1, pp. 343–350, Jan. 2015.
lower figure is a zoom of the upper one for the benefits in the area between [8] D. M. Greenwood and P. C. Taylor, “Investigating the Impact of Real-
0.3% and 0.8%. Time Thermal Ratings on Power Network Reliability,” IEEE Trans.
Power Syst., vol. 29, no. 5, pp. 2460–2468, Sep. 2014.
[9] A. Michiorri et al., “Forecasting for dynamic line rating,” Renew.
V. CONCLUSIONS Sustain. Energy Rev., vol. 52, pp. 1713–1730, Dec. 2015.
[10] I. Albizu, E. Fernandez, A. J. Mazon, K. J. Sagastabeitia, M. T.
Recently, the use of two-stage stochastic optimization Bedialauneta, and J. G. Olazarri, “Overhead line rating forecasting for
problems for setting DLR forecasts has been investigated in the the integration of wind power in electricity markets,” in 2015
literature. However, most of these studies propose risk-neutral International Conference on Clean Electrical Power (ICCEP),
strategies, in which the DLR forecast setting only aims at Taormina, Italy, 2015, pp. 382–388.
[11] H.-M. Nguyen, J.-L. Lilien, and P. Schell, “Dynamic line rating and
optimizing social welfare, and the TSO’s risk aversion is not ampacity forecasting as the keys to optimise power line assets with the
considered. As a result of this last point, a TSO may still prefer integration of res. The European project Twenties Demonstration inside
to continue setting DLR forecasts using fixed quantiles, thus Central Western Europe,” presented at the CIRED, Stockholm,
disregarding the potential benefits of more developed Sweden, 2013, p. 0946.
[12] H.-M. Nguyen, J.-J. Lambin, F. Vassort, and J.-L. Lilien, “Operational
strategies. experience with Dynamic Line Rating forecast-based solutions to
In this paper, we have proposed new methods for setting increase usable network transfer capacity,” Proc. 45th Sess. Counc.
DLR using DLR probabilistic forecasts and the solving of a Large Electr. Syst. CIGRE, 2014.
bilevel stochastic optimization problem, taking into account a [13] H. E. Hoekstra, C. P. J. Jansen, J. Hagen, J. W. Van Schuylenburg, J. S.
P. Wisse, and W. J. Zitterrsteijn, “Weather forecasted thermal line
risk aversion function. The results are promising: while rating model for the Netherlands,” in CIGRE Session, Paris, France,
ensuring low costs for the TSO or a low frequency of incidents, 2012.
the benefits associated with DLR forecasts could be relatively [14] T. Ringelband, P. Schäfer, and A. Moser, “Probabilistic ampacity
improved to the order of 20%. forecasting for overhead lines using weather forecast ensembles.,”
Electr. Eng., vol. 95, no. 2, 2013.
This work opens up several research topics. First, the [15] J. L. Aznarte and N. Siebert, “Dynamic Line Rating Using Numerical
proposed methodology uses DLR quantile forecasts with Weather Predictions and Machine Learning: A Case Study,” IEEE
probability levels below 1%. Such DLR forecasts have not been Trans. Power Deliv., vol. 32, no. 1, pp. 335–343, Feb. 2017.
investigated in the literature to date, and the interest of such [16] “DLR Forecasting Presented at FERC - Nexans.” [Online]. Available:
http://www.nexans.us/eservice/US-en_US/navigatepub_0_-
forecasts is demonstrated here. Secondly, the methodology 32903/DLR_Forecasting_Presented_at_FERC.html. [Accessed: 08-
requires several forecasts of load and energy production, and a May-2018].
frame would need to be defined for such applications with other [17] M. A. Bucher and G. Andersson, “Robust Corrective Control Measures
stochastic features. Finally, we have shown that the choice of in Power Systems With Dynamic Line Rating,” IEEE Trans. Power
Syst., vol. 31, no. 3, pp. 2034–2043, May 2016.
penalty function has an important impact on the final result. For [18] Y. Chen, F. Teng, R. Moreno, and G. Strbac, “Impact of dynamic line
the illustration of the potential benefits, evaluation indices and rating with forecast error on the scheduling of reserve service,” in
10
Power and Energy Society General Meeting (PESGM), Boston, USA, works at the MINES ParisTech PERSEE Centre as a senior scientist and head
2016. of the Renewable Energies and Smart Grids Group. He has authored more than
[19] K. Kopsidas, A. Kapetanaki, and V. Levi, “Optimal Demand Response 220 scientific publications in journals and conferences. He has been involved
Scheduling With Real-Time Thermal Ratings of Overhead Lines for as participant or coordinator in more than 40 R&D projects in the fields of
Improved Network Reliability,” IEEE Trans. Smart Grid, vol. 8, no. 6, renewable energies and distributed generation. Among them, he was the
pp. 2813–2825, 2017. coordinator of some major EU projects in the field of wind power forecasting
[20] B. Banerjee, D. Jayaweera, and S. M. Islam, “Alleviating post- such as Anemos, Anemos.plus and SafeWind projects. His scientific interests
contingency congestion risk of wind integrated systems with dynamic include among others timeseries forecasting, decision making under
line ratings,” in Power Engineering Conference (AUPEC), 2014 uncertainty, modeling, management and planning of power systems.
Australasian Universities, Perth, Australia, 2014.
[21] B. Banerjee, S. M. Islam, and D. Jayaweera, “Monte Carlo based
method for managing risk of scheduling decisions with dynamic line
ratings,” in Power & Energy Society General Meeting, Denver, USA,
2015.
[22] F. Teng, R. Dupin, A. Michiorri, G. Kariniotakis, Y. Chen, and G.
Strbac, “Understanding the Benefits of Dynamic Line Rating under
Multiple Sources of Uncertainty,” IEEE Trans. Power Syst., vol. 33, no.
3, pp. 3306–3314, 2018.
[23] B. Banerjee, D. Jayaweera, and S. M. Islam, “Optimal scheduling with
dynamic line ratings and intermittent wind power,” in PES General
Meeting| Conference & Exposition, 2014 IEEE, National Harbor, USA,
2014.
[24] M. Miura, T. Satoh, S. Iwamoto, and I. Kurihara, “Application of
dynamic rating to evaluation of ATC with thermal constraints
considering weather conditions,” in 2006 IEEE Power Engineering
Society General Meeting, Montreal, Canada, 2006.
[25] N. Meinshausen, “Quantile Regression Forests,” J. Mach. Learn. Res.,
vol. 7, no. Jun, pp. 983–999, 2006.
[26] Y. Zhang and J. Wang, “GEFCom2014 probabilistic solar power
forecasting based on k-nearest neighbor and kernel density estimator,”
in IEEE Power Energy Society General Meeting, Denver, USA, 2015.
[27] T. Chen and C. Guestrin, “Xgboost: A scalable tree boosting system,”
in Proceedings of the 22nd acm sigkdd international conference on
knowledge discovery and data mining, 2016, pp. 785–794.
[28] G. Ke et al., “Lightgbm: A highly efficient gradient boosting decision
tree,” in Advances in Neural Information Processing Systems, 2017, pp.
3146–3154.
[29] J. Snoek, H. Larochelle, and R. P. Adams, “Practical bayesian
optimization of machine learning algorithms,” in Advances in neural
information processing systems, 2012, pp. 2951–2959.
[30] X. Sun, P. B. Luh, K. W. Cheung, and W. Guan, “Probabilistic
forecasting of dynamic line rating for over-head transmission lines,” in
IEEE Power Energy Society General Meeting, Denver, USA, 2015.
[31] C. Grigg et al., “The IEEE Reliability Test System-1996. A report
prepared by the Reliability Test System Task Force of the Application
of Probability Methods Subcommittee,” IEEE Trans. Power Syst., vol.
14, no. 3, pp. 1010–1020, Aug. 1999.
[32] R. Lincoln, PyPower. 2017.
[33] R. Dupin, A. Michiorri, and G. Kariniotakis, “Dynamic line rating day-
ahead forecasts - cost benefit based selection of the optimal quantile,”
presented at the CIRED Workshop, Helsinki, Finland, 2016, pp. 122–
126.
[34] L. Dawson and A. Knight, “Applicability of Dynamic Thermal Line
Rating for Long Lines,” IEEE Trans. Power Deliv., vol. 33, no. 2, pp.
719–727, 2018.