BS 05385-3-2014
BS 05385-3-2014
BS 05385-3-2014
Publication history
First published November 1989
Second edition, August 2007
Third (present) edition, November 2014
Contents
Foreword iii
1 Scope 1
2 Normative references 1
3 Terms and definitions 3
4 Exchange of information and time schedule 4
5 Materials 6
6 Design 12
7 Application of tiles – methods and materials 34
8 Application of mosaics – methods and materials 45
9 Inspection 47
10 Protection 48
11 Cleaning and maintenance 48
Annexes
Annex A (normative) Tile fittings 52
Annex B (informative) Special conditions included in BS 5385-4 55
Annex C (normative) Tiling onto underfloor heated bases 56
Annex D (normative) Pumped calcium sulfate-based screeds 64
Annex E (normative) Cement and sand levelling screeds conforming to
BS 8204-1 68
Annex F (normative) Recommended method for the assessment of levels and
surface regularity of levelling screeds 79
Annex G (normative) Cement and sand bedding 79
Annex H (informative) Guidance on the reduction of slip hazard 84
Bibliography 87
List of figures
Figure 1 – Illustration of selected definitions 4
Figure 2 – Typical edge protection and transition profiles 24
Figure 3 – Typical stair nosing profiles 25
Figure 4 – Some typical movement joints 29
Figure 4 – Some typical movement joints 30
Figure 4 – Some typical movement joints 31
Figure 4 – Some typical movement joints 32
Figure 4 – Some typical movement joints 33
Figure 5 – Light alloy frame with vacuum pads 44
Figure A.1 – Sit-on cove systems – dry pressed tiles 52
Figure A.2 – Flushfit cove systems – dry pressed tiles 52
Figure A.3 – Flushfit cove systems – dry pressed tiles 53
Figure A.4 – Typical floor channels – extruded tiles 53
Figure A.5 – Typical floor channels – dry pressed tiles 53
Figure A.6 – Typical step treads – dry pressed tiles 54
Figure A.7 – Typical step tread – dry pressed tiles [large format] 54
Figure C.1 – Type A heating system 56
Figure C.2 – Type B heating system 57
Figure C.3 – Type C heating system 58
Figure C.4 – Type D heating system 59
Figure C.5 – Type E heating system 60
Figure F.1 – Slip gauges for checking surface regularity 79
List of tables
Table 1 – Suitability of tile beds for different bases 17
Summary of pages
This document comprises a front cover, an inside front cover, pages i to iv,
pages 1 to 88, an inside back cover and a back cover.
Foreword
Publishing information
This part of BS 5385 is published by BSI Standards Limited, under licence from
The British Standards Institution, and came into effect on 30 November 2014. It
was prepared by Technical Committee B/539, Ceramic tiles and other rigid tiling.
A list of organizations represented on this committee can be obtained on
request to its secretary.
Supersession
This part of BS 5385 supersedes BS 5385-3:2007, which is withdrawn.
Presentational conventions
The provisions in this standard are presented in roman (i.e. upright) type. Its
recommendations are expressed in sentences in which the principal auxiliary
verb is “should”.
1 Scope
This part of BS 5385 gives recommendations for the design, installation and
maintenance of floor tiling using ceramic tiles and mosaics bedded on concrete,
cement and sand and calcium sulfate-based screeds, timber, flooring grade
asphalt and existing hard floor finishes in normal conditions. For special
conditions see BS 5385-4.
Tile fittings for use as skirting, step treads and channels are given in Annex A.
NOTE Where the floor tiling installation needs to meet specific functional or
environmental requirements, or to assist in counteracting potentially detrimental
effects on the installation and/or the structure, see BS 5385-4.
The special conditions described in BS 5385-4, for example, swimming pools,
shower areas, etc., are given in Annex B.
Annex C gives recommendations for tiling onto underfloor heated bases and
Annex D contains information on pumped calcium sulfate-based screeds.
Recommendations for the design and laying of levelling screeds are given in
Annex E. Reference is made to tiles bedded directly to a concrete base, but for
the design and construction of concrete bases see BS 8204-1.
Annex F contains a recommended method for assessing levels and surface
regularity and Annex G has guidance on cement and sand bedding. Annex H is
an informative annex providing guidance on the reduction of slip hazards.
The following flooring materials are not covered in this British Standard: natural
stone (granite, slate, marble, etc.) tiles and slabs of terrazzo, and composition
blocks (see BS 5385-5).
2 Normative references
The following referenced documents are indispensable for the application of
this document. For dated references, only the edition cited applies. For undated
references, the latest edition of the referenced document (including any
amendments) applies.
BS 4551, Mortar – Methods of test for mortar – Chemical analysis and physical
testing
BS 5385-4, Wall and floor tiling – Part 4: Design and installation of ceramic and
mosaic tiling in special conditions – Code of practice
BS 5385-5, Wall and floor tiling – Part 5: Design and installation of terrazzo,
natural stone and agglomerated stone tiles and slabs – Code of practice
BS 6213, Selection of construction sealants – Guide
BS 6925:1988, Specification for mastic asphalt for building and civil engineering
(limestone aggregate)
BS 8000-11:2011, Workmanship on building sites – Part 11: Internal and external
wall and floor tiling – Ceramic and agglomerated stone tiles, natural stone and
terrazzo tiles and slabs, and mosaics – Code of practice
BS 8203:2001+A1:2009, Code of practice for installation of resilient floor
coverings
BS 8204-1:2003+A1:2009, Screeds, bases and in situ floorings – Part 1: Concrete
bases and cement sand levelling screeds to receive floorings – Code of practice
BS 8204-5, Screeds, bases and in situ floorings – Part 5: Mastic asphalt underlays
and wearing surfaces – Code of practice
3.1 base/sub-floor
supporting structure beneath the tiles
Key
1 Grout 6 Reinforcement (optional)
2 Joint 7 Cement: sand screeded base
3 Tile or tesserae 8 Separating layer or optional damp-proof
membrane
4 Adhesive bed 9 Structural concrete base
5 Uncopline membrane 10 Damp-proof membrane
(optional)
At least six weeks should be allowed under good drying conditions for the
concrete structural floor to undergo initial drying shrinkage. If a levelling screed
is subsequently to be applied, the levelling screed should be left for at least a
further three weeks. These drying times should be considerably extended under
slow drying conditions, and depending upon the mass of the construction.
NOTE Where tiling is on a separating layer directly over the structural floor, the
period of six weeks is not critical.
The schedule should also allow time for the cutting of holes and chases and/or
other work involving the use of percussion tools in or on the floor that is to
receive the tile bed.
The schedule should provide for the completion of all necessary subsidiary work
including the commissioning of underfloor heating systems before the fixing of
tiles or mosaics begins. The schedule should include times for commencement
and completion of tiling or mosaic work to the different parts of the
construction, allowing sufficient time intervals between the operation of the
bedding, grouting and final cleaning down.
Provision should be made for adjustment to the time schedule to allow for
suspension of operations due to unfavourable weather or other conditions that
jeopardize the success of the installation. Alternatively, consideration should be
given to the possibility of providing a protective enclosure, e.g. cocooning, to
enable work to continue during unfavourable conditions.
5 Materials
5.1 Transport and storage
The delivery of materials should be arranged to minimize handling. Adequate
precautions should be taken to guard against the possibility of damage.
Materials should be stored in clean, dry, frost-free (if necessary) lockable storage
to avoid excessive handling, theft and damage.
5.3 Mosaics
Ceramic tesserae should conform to the relevant physical properties (as given in
BS EN 14411) for their class according to water absorption and shaping, as
indicated in BS EN 14411:2012, Table 1.
For a mosaic that has been assembled with a backing material, the following
should be ensured.
a) The backing material and its adhesive should not occupy more than 25% of
the area of each tesserae (the critical factor is the spread of the adhesive
over the backs of the tesserae).
b) The backing material and its adhesive should not deteriorate in service and
should be compatible with the mortar or adhesive bed in accordance with
the manufacturers’ instructions.
c) For wet and external areas the backing material and the mesh glue should
be water-resistant and the mesh glue should show no loss of adhesion with
prolonged immersion.
Cement of all types should be used with care, because of the possible risk of
adverse skin effects. Suppliers’ material safety data sheets obtained at the
exchange of information stage described in 4.1g) should be used as a basis for
assessing and managing the risk associated with its use in a particular
application.
Cement should be stored under dry conditions and used in order of delivery and
within expiry date. Cement that contains air set lumps should not be used.
5.4.2 Aggregates
5.4.2.1 General
Aggregates should not contain any deleterious material in sufficient quantity to
adversely affect the surface of a cementitious levelling screed.
NOTE For example, lignite, coal and iron pyrites in the aggregate can cause “pop
outs”.
Some aggregates exhibit higher than average drying shrinkage and should not
be used, as they can give rise to a greater risk of cracking (see BRE
Digest 357 [4] and BS EN 1367-4).
5.4.3 Water
Water should be clean and free of materials deleterious to levelling screeds and
mortar beds in their fresh and hardened states (see BS EN 1008); drinking water
is suitable. Containers for storing or carrying water should be clean.
5.4.4 Reinforcement
Where light reinforcement is required in a levelling screed of the type described
in Annex E, a welded steel fabric of 2.5 mm diameter wire spaced at
approximately 50 mm × 50 mm centres should be used.
NOTE Heavier reinforcement conforming to BS 4483 might be necessary for use in
levelling screeds constructed for structural purposes.
5.4.6 Adhesives
5.4.6.1 Cement-based adhesives [cementitious
adhesives/hydraulically-hardening mortars]
Cementitious and dispersion/cement adhesives (Type C) should conform to
BS EN 12004.
WARNING: These products contain resins and hardeners that can cause skin
irritation and contact dermatitis. Follow the manufacturer’s instructions so
that, where appropriate, the necessary personal protective equipment is used
during mixing and application.
5.7.2 Sealants
Joint sealants should be selected and applied in accordance with the guidance
given in BS 6213. Sealant manufacturers’ advice should be taken into account as
the properties of individual sealants might vary. Generally, a sealant should be
capable of accommodating the anticipated amount of movement without loss of
adhesion to the sides of the joints and be able to withstand the normal service
conditions affecting the installation, e.g. resistant to water, ultraviolet light.
Sealants with a movement accommodation factor (MAF) (see BS 6213) of at
least 15% should be used over structural movement joints.
NOTE 1 Guidance on joint design is given in BS 6093 and guidance on the selection
of sealants in BS 6213.
NOTE 2 For further information on the installation of sealants see 6.8.2.
5.8 Chemical-resistance
Most chemically-resistant materials are proprietary and should be stored and
used in accordance with the manufacturer’s instructions.
5.9.4 Waxes
NOTE Unglazed ceramic floor tiles with a high water absorption, e.g. terracotta,
might need specialist treatment with a wax-based product. Such products reduce the
porosity of the surface and in most cases change the surface appearance and colour
of the tile surface.
6 Design
6.1 General
The relative importance of the following factors should be assessed at the
design stage so that due allowance is made for their possible effect on the
finished floor (solid and suspended floor floorings):
a) the load it has to support;
b) the type of tile used;
c) the resistance it provides to the passage of liquid water or water vapour
either from below or from above (see 6.5.2 and 6.5.3);
d) size changes produced by variations in moisture content and temperature
within the floor and the attack of various corrosive agents, e.g. in chemical
plant and industrial premises.
When possible, selection of the tiles or mosaics and bedding method should be
made at the structural design stage so that the appropriate depth can be
allowed between the base and the finished floor surface.
6.3 Bases
6.3.1 General
Concrete (see 6.3.2) and cement and sand levelling screeds are the most
common bases over which ceramic floor tiles and mosaics are laid but other
bases might be encountered, namely, calcium sulfate-based screeds
(see Annex D), timber (see 6.3.4), asphalt (see 6.3.5) and metal.
NOTE 1 In refurbishing work, it might sometimes be necessary to apply new
finishes over old floors such as ceramic tiles, terrazzo, wearing screeds, stone, etc.
Before the tile bed is applied:
a) the correct falls should have been incorporated in the base, where required;
b) the base should be free from contamination, loose areas of weak or friable
material and cracks liable to subsequent movement;
c) the base should be true to the specified plane (see also 7.1.2).
NOTE 2 Bases suitable to receive floor tiling in each case are summarized in Table 1.
In new work, the plane of the base in relation to that of the finished floor
surface should be specified; usually this is possible only if the floor tiles are
selected at the design stage. The level of the base in relation to the finished
floor surface should be such that the bed can be of the recommended thickness
uniformly throughout the installation.
In refurbishing work, as the new floor surface might be higher than the original,
any effect on existing features such as channels, outlets, skirtings, doorways, etc.
should be determined.
Where a separating layer is to be interposed between the base and the base
should be accurately formed and should have a true and smooth surface to
enable the tile bed to slide freely over the base in the event of differential
movement.
NOTE 3 For details on separating layers and uncoupling membranes see 5.5.
NOTE 4 Ceramic tiling is rarely adhered to a concrete base without a levelling
screed since it is not normally possible to achieve the required surface regularoty
(see Annex E).
6.3.2 Concrete
When tiling is bedded directly to a concrete base without a levelling screed, the
finish of concrete should be struck-off level with a straightedge and the surface
texture closed. When a bonded bed is required, laitance should be removed by
the use of appropriate mechanized surface preparation equipment.
6.3.4.1 General
Timber sub-floors are not the ideal bases for floor tiling, especially where heavy
static/dynamic loading is likely in service. If a timber sub-floor has to be used as
a base for floor tiling, it should be rigid and stable with respect to humidity and
moisture changes.
NOTE 1 Timber is not a suitable base for floor tiling in wet, frequently damp, or
high humidity areas, unless appropriate precautions are taken (see BS 5385-4).
When it is necessary to install wood based sheets and boards such as plywood,
the moisture content of the wood based sheets and boards should be close to
the equilibrium moisture content that prevails under the service conditions. In
heated domestic buildings, where the temperature is above 21 °C, to be in
equilibrium the moisture content of any wood based fabricated underlay
plywood should be between 6% and 10%. For installations in conservatories, on
heated timber sub-floors and areas with higher temperatures or lower humidity
levels the equilibrium moisture content might need to be at the lower moisture
content value, or even lower, since the average temperatures is higher than
those normally experienced in rooms in domestic buildings.
Plywood of an appropriate quality should be used and it should be correctly
stored and, if required, conditioned to the appropriate moisture content before
installation.
Glue bond class 3 exterior, in accordance with BS EN 314, should be used
NOTE 2 CE2+ marking does not necessarily designate adequate quality.
NOTE 3 Noggings might be required between joists in order to achieve the
required rigidity. The limit of deflection normally permitted for domestic timber
floors (see BS 5268-2) might be too great to avoid damage to tiling systems.
It should also be established that ventilation is adequate and that effective
damp-proof courses are correctly located.
The design should take into account the initial drying shrinkage of the timber
and subsequent movement due to seasonal moisture changes, bearing in mind
the type of heating.
NOTE 4 Failure to observe this can lead to subsequent warping and distortion of
the boards with consequential cracking and delamination of the tiling.
Where the rigidity is satisfactory but the moisture stability of the floor cannot
be assured, consideration should be given to the use of an appropriate
intermediate water resistant substrate system designed for use with tiling on
timber floors.
Screw fixings should be of adequate strength. The length of screw fixings should
be at least 2.5 times the thickness of the plywood material (for example, use a
minimum 45 mm length screw for 18 mm plywood) to ensure adequate
penetration into the timber sub-floor or joist/strut supports, bearing in mind
that there might be underfloor services that could be damaged by oversized
screws.
6.3.4.5 Adhesives
Proprietary deformable tile adhesives and grouts and water resistant membrane
systems specially formulated for fixing tiles onto timber bases (installed as
described in this clause) have been used successfully and these products should
be used strictly in accordance with the manufacturer’s instructions.
6.3.5 Asphalt
Flooring grade asphalt should be laid on a rigid base, e.g. concrete or levelling
screed, in accordance with BS 8204-5 for internal floors and in accordance with
BS 8218 for external locations. Before tile fixing commences the asphalt
sub-floor should be carefully examined to ensure that it is in a suitable condition
to receive ceramic tiles.
In internal locations the grades of asphalt used should be Type F 1076
conforming to BS 6925:1988 and should be suitable for the anticipated loads
and conditions.
NOTE 1 The ceramic floor tiles can be solidly bedded in cementitious adhesives, in
accordance with 7.2.1, such that the bed thickness does not exceed 6 mm.
In dry locations if the surface of the asphalt has a natural float finish the surface
should be clean and primed in accordance with the adhesive manufacturer’s
recommendations.
NOTE 2 It might not be necessary to prime the clean asphalt surface if the asphalt
surface has a sand-rubbed finish.
NOTE 3 In internal locations the ceramic tiles can also be bedded in a cement and
sand semi-dry mortar bed over a separating layer if appropriate for the type of tile
being fixed and the required floor finish levels.
In external locations the asphalt should be laid to falls in accordance with
BS 8218 as either a paving or roofing grade. The falls should not be less
than 1 in 80, but where rapid or effective drainage of water is essential the falls
should not be less than 1 in 60 nor greater than 1 in 35. The ceramic floor tiles
should be frost resistant (see 5.2) and suitable for bedding in a cement and sand
semi-dry mortar bed over a separating layer in accordance with G.8.
Sheets of the separating layer material should be overlapped and brought up
vertically at the perimeter of the semi-dry bed where it abuts upstands and
walls.
NOTE 4 In most cases a movement joint is required at the perimeter. This can be
formed with a compressible back up filler inserted between the upstands and mortar
bed, with the movement joint between the perimeter tiles and upstands being
finished with a suitable sealant (see 5.7 and 6.8).
The asphalt and the semi-dry mortar bed at the lower end of the fall should be
free draining into a suitable gully or drainage outlet.
NOTE 1 The tile bed chosen also depends on the traffic conditions (see 6.4.2).
NOTE 2 See Table G.1 for bed thicknesses (Annex G).
A)
See 6.3.6.
6.4.5 Slipperiness
NOTE 1 A tiled ceramic floor is not slippery when clean and dry. The slip resistance
of a floor in service is dependent upon the nature of its surface. It is important to
recognize that this can change over time and often merely during the process of
installation and finishing. Floor surface contaminantion (such as water, oil, dust) is
often the cause of slip accidents.
NOTE 2 Measurement of slip resistance values in the wet, by means of the
pendulum test method given in BS 7976, provides useful information for assessing
the likely slip resistance of flooring materials in water wet conditions in service,
though results are more difficult to interpret for barefoot applications and for
heavily textured surfaces.
When it is known that slippery conditions might arise in service and present a
significant hazard, tiles with slip resistant finishes suitable for the conditions and
location should be used.
Special attention should be paid to correct cleaning procedures as described
in 11.5, both to remove contamination and to ensure that cleaning agents that
could otherwise attack the surface are rinsed away.
NOTE 3 Further advice on the reduction of slip hazards is given in Annex G.
Table 2 Grouts and joint materials: resistance to intermittent contact with various liquids and
characteristics
NOTE 1 The base flange of profiles require appertures of adequate size to allow the
tile adhesive to support the tile edge through the profile.
NOTE 2 Further information is given in TTA document Technical Guidance Note 10 on
Tile Trim Profiles [7].
NOTE 1 The base flange of profiles require appertures of adequate size to allow the tile adhesive to support
the tile edge through the profile.
NOTE 2 Further information is given in TTA document Technical Guidance Note 10 on Tile Trim Profiles [7].
(b) Prefabricated joint with reinforced edges and capping over structural movement joint
Key
1 Flexible insert 6 Screed
2 Metal profile 7 Cement and sand mortar bed
3 Grout 8 Levelling bed
4 Tile 9 Mechanical fixing as necessary
5 Adhesive bed 10 Concrete base
11 Structural movement joint
NOTE 1 All drawings in Figure 4 illustrate principles only.
NOTE 2 Semi-dry mix beds have movement joints similar to those shown for levelling screeds.
NOTE 3 The base flange of profiles require appertures of adequate size to allow the tile adhesive to support
the tile edge through the profile.
Key
1 Sealant 8 Screed
2 Bond breaker tape 9 Concrete base
3 Metal angle 10 Levelling bed
4 Grout 11 Mechanical fixing as necessary
5 Tile 12 Back-up material
6 Adhesive bed 13 Structural movement joint
7 Cement and sand mortar bed
NOTE 1 All drawings in Figure 4 illustrate principles only.
NOTE 2 Semi-dry mix beds have movement joints similar to those shown for levelling screeds.
NOTE 3 The base flange of profiles require appertures of adequate size to allow the tile adhesive to support
the tile edge through the profile.
1) Sit-in 2) Sit-on
(e) Alternative perimeter joints (with skirtings)
Key
1 Sealant (optional) 3 Tile
2 Sealant 4 Back-up material
NOTE 1 All drawings in Figure 4 illustrate principles only.
NOTE 2 Semi-dry mix beds have movement joints similar to those shown for levelling screeds.
The desirable minimum joint widths are stated in 7.1.5 and, if the widths are
appreciably greater, the suitability of the joints should be considered in relation
to the expected traffic conditions.
6.10 Skirtings
NOTE 1 Skirtings (Figure 4e) can be employed for aesthetic reasons, for protecting
the base of wall surfaces, for ease of cleaning or to assist in forming a liquid-tight
system at the junction of floors and walls. The most common types of tile fittings
used for skirtings are given in Annex A.
Where it is important that the installation is resistant to the passage of water or
other liquid, and especially where “tanking” is necessary (see 6.5 and D.2), a
flushfit coved base skirting should be used. This allows a perimeter joint to be
positioned between the foot of the coved base and the adjacent floor tile to
accommodate movement and which, when filled with an impervious sealant,
contributes to a smooth uninterrupted resistant surface from horizontal to
vertical.
NOTE 2 In other circumstances, a coved base skirting known as a “sit-on” cove or,
alternatively, a tile with a square or rounded top edge, can be adapted. These
skirtings are fixed to the wall. Movement is accommodated by compressible back-up
material between the wall and the adjacent floor tiles. The joint between skirting
and floor tiles is filled with a sealant.
NOTE 2 Where tiles are bedded in cement and sand mortar beds a greater
variation in the surface regularity can be accommodated (see BS 8000-11:2011, 3.5.3).
If the surface regularity of the sub-floor is inadequate it should be corrected
before the tiling trade commences work on site, e.g. by the use of a smoothing
compound.
7.1.2.2 Preparation
Where a bonded tile bed is specified, the sub-floor should be correctly prepared
and the recommended bonding treatment carried out to ensure good adhesion
of the tile bed. Concrete surfaces should be suitably prepared to ensure that
adhesion is not impaired by any surface contamination. In most cases, the
concrete surface has laitance and lime bloom present that can be removed by
light mechanical means.
NOTE If the concrete has been treated with a curing agent, or has had a film of
laitance and fines worked up to its surface during finishing, the preparation to
remove these barriers to adhesion by equipment such as contained shot blasting is
usually necessary.
Where cement-based or reactive resin adhesives are used to bed the floor tiles
the sub-floor should be inspected prior to tiling to ensure that it is free of any
contamination, loosely adhered materials and other surface defects.
Where a bonded cement and sand bedding system is used the sub-floor should
be roughened using appropriate mechanized equipment designed specifically
for this purpose and a suitable bonding treatment used. If the concrete
sub-floor is of suspended construction, e.g. a precast concrete plank, care should
be taken to ensure that any roughening by mechanized equipment, e.g. by
scabbling, does not cause damage to the concrete. In such cases contained shot
blasting with coarse shot should be considered.
Where there is a risk of subsequent contamination, the surface preparation
should be delayed until shortly before the tile bed is laid.
7.1.2.3 Bonding
Before the cement and sand mortar bed is laid the concrete base should be
dampened down and excess water brushed off before the application of a
bonding grout or slurry is applied to the concrete. The bonding grout or slurry
should consist of cement mixed with an aqueous synthetic polymer dispersion,
so that a creamy consistency is obtained that can be brushed out or trowelled as
a thin coat on the prepared concrete sub-floor or a 1:1 cement:screed sand
aggregate (mixed by weight). The cement and sand bedding mortar should be
placed on the bonding grout or slurry whilst the slurry is still wet and workable.
The aqueous synthetic polymer dispersions and other proprietary bonding
agents should be fit for use in bonding cement and sand mortar beds to
concrete and applied in accordance with the manufacturer’s instructions but
roughening of the concrete sub-floor should still be carried out.
NOTE 1 Proprietary bonding agents may be used mixed with cement to form a
bonding slurry or applied direct to the base as an alternative to cement slurry.
NOTE 2 See BS 8204{1:2003+A1:2009, 6.4.2 for more information.
NOTE 3 There are permissible manufacturing tolerances for ceramic tiles as defined
in BS EN 14411.
Certain types of tiles, e.g. extruded or large format, might have permissible
surface flatness irregularities that cannot be satisfactorily accommodated within
the surface flatness tolerance permitted to the tile installer and this should be
taken into account when evaluating the achievable flatness of a floor tiling
installation.
Where tiles are bedded in adhesives, the sub-floor should conform to SR1
(see Annex E).
7.1.5 Joints
As a general rule, the width of joints in ceramic tiling should not exceed the tile
thickness. The width should not be less than 3 mm. Wider joints, for
example 10 mm wide, might be required to accommodate dimensional
irregularities in the tiles, to maintain modular discipline or to provide a
decorative effect.
Wherever practicable, the depth of the joints should be at least 6 mm.
Recommendations for joint filling materials and procedures are given in 7.3.
NOTE 2 Any voids under the tiles are vulnerable to damage under loads and
impacts, whilst in exterior situations, water can accumulate in voids so that damage
can occur on freezing.
Joints between tiles should be not less than 3 mm wide (see also 7.1.5).
The sub-floor should be clean, dry, of adequate strength and prepared to suit
the adhesive being used. The surface being adhered to should not be dampened
before applying the adhesive.
The precise recommendations of the adhesive manufacturer should be followed
concerning the mixing procedure, the method of use, the maximum thickness of
bed, the working time before and after spreading and the suitability of the
base. Cementitious adhesives should be mixed with clean water, carefully
following any specific instructions, to obtain the required consistency, usually a
fairly thick creamy slump-free mix. Cementitious adhesives should never be
mixed with more water or admixture than the maximum amount that is
recommended by the adhesive manufacturer otherwise the performance of the
adhesive will be impaired. Cementitious adhesives are also available that can be
mixed to a pourable consistency to facilitate the solid bedding of large format
floor tiles and such adhesives should be mixed and applied strictly in accordance
with the adhesive manufacturer’s instructions.
7.3 Grouting
7.3.1 General
Some bedding methods require that grout is applied during, or within a
prescribed interval after, the tile-laying operation (see 7.2.1.4 and 7.3.3). With
these exceptions, grouting should be carried out not sooner than 12 h nor later
than 48 h after the completion of the laying of the tiles. Sufficient time should
be allowed to elapse to ensure adequate setting of the bed to preclude
disturbance of the tiles during the grouting operation. On non-absorbent
backgrounds, it might be necessary to wait up to three days before the tile
adhesive is firm enough to permit grouting. When fixing tiles in adhesive, e.g.
rapid setting products, these timings might not be accurate and the adhesive
manufacturer’s instructions should be followed. The grouting should not be
unduly delayed as open joints can collect general building dust and debris.
In most tiling situations a cement and sand mortar or a proprietary
cement-based grout should be used.
Key
1 Thin ceramic panel
8.2 Workmanship
NOTE The application of mosaics requires efficient supervision and the employment
of skilled operatives working safely and using protective clothing and equipment
where appropriate. Many of the requirements for basic workmanship for floor tiling
also apply to laying mosaics.
In the finished work the outlines of the sheets of mosaic should not be
apparent, the joints between them being the same as those between the
tesserae. Joints within the mosaic sheets are formed during assembly and are
usually less than 3 mm wide.
Joint widths between tesserae, established when the mosaics were assembled,
should be maintained between sheets, otherwise the outline of the sheets is
defined and the overall effect of consistency of spacing of the tesserae is
marred.
Setting out might have to be related to the siting of movement joints.
Movement joints should be detailed on working drawings but it is sometimes
necessary for the exact positioning of non-structural movement joints (6.8.1.3) to
be determined during the mosaic installation.
Surplus adhesive remaining on the face of the mosaics or in the joints should be
removed before it sets. Grouting should be carried out in accordance with 8.9.
8.8.3 Inspection
The completed tiling should be inspected after completion in accordance with
BS 8000-11:2011, 4.9.1.10 and with Clause 9 of this British Standard.
8.9 Grouting
NOTE Recommendations on grouting are given in 7.3.
Paper-faced mosaics should be grouted using material similar in type and colour
to that used for any pre-grouting.
The grout should be rubbed over the surface to fill the joints, either as the work
proceeds or when it is sufficiently firm, and given a preliminary cleaning.
After the grout has hardened sufficiently, the surface of the work should be
washed over with water and left clean.
When a proprietary grouting material is used, the manufacturer’s instructions
for cleaning off should be followed.
9 Inspection
The floor tiling should be inspected on completion as follows:
a) the finished tile surface should meet the requirements given in 7.1.4;
b) the straightness of the joints between the tiles should be checked in
accordance with 7.1.3.2.
NOTE See BS 8000-11:2011, 4.9.1.10.
10 Protection
Finished and partly finished flooring should be protected from damage or
contamination from following trades.
During the laying operation, the areas should be accessible to no-one but the
tiling operatives. Completed floor tiling should not be subject to traffic until the
bed has hardened and sufficient bond has developed between the bed and tiles.
Light pedestrian traffic should be allowed on floors bedded in non-rapid-setting
adhesive and in cement and sand mortars four days after completion of laying
and grouting, but heavier traffic should not be permitted to use the floor
for 14 days after completion.
Where tiles are laid in a rapid-setting adhesive the floor can take traffic earlier
than four days after completion. However, unless a rapid hardening grout is
used the four-day period should not be reduced. The precise times at which a
floor can safely put into service vary for different rapid-setting products, and the
manufacturer’s recommendations should be followed.
At all times the floor tiling should be kept clean and free from cement and
plaster droppings, and all materials likely to cause stains. The flooring should be
covered during work carried out on or over the floor involving substances that
could cause permanent staining, e.g. oils, grease, paint. Appropriate types of
sheets or boards should be laid loosely over the finished floor to protect it.
Sawdust should not be used for this purpose any earlier than three days after
grouting is completed.
If plant likely to cause damage has to be used, any parts in contact with the
floor surface should be padded; sliding of plant over the surface should not be
allowed. When heavy equipment has to be moved over the floor surface, special
precautions should be taken, probably involving the use of timber planking, to
ensure that the equipment, moving tackle and the protection itself are not
allowed to damage the tiled surface by abrasion.
Stair finishings, especially nosings, are vulnerable to damage from following
trades and should be protected by temporary casings.
The recommended drying times of all in situ floor bases are the minimum
required under optimum conditions and these drying times should be
considerably extended under adverse drying conditions on site, e.g. low
temperatures and/or wet conditions.
For external applications, work should also be protected both during and after
completion from frost or other unfavourable weather conditions.
Matt unglazed finishes are not damaged by the occasional use of scouring
powder, or household cleaners to remove particularly stubborn blemishes.
However, it should be noted that cleaning machines with abrasive pads, or the
use of coarse cleaning agents can damage the surfaces of polished unglazed and
shiny glazed tiles.
Care should be taken to ensure that cleaning agents are not allowed to come
into contact with adjacent fixtures and wall surfaces.
NOTE 3 Apart from normal usage or obvious misuse, surface contamination can
arise from:
a) residual cement film (see 11.2);
b) efflorescence (see 11.3);
c) surface sealing materials (see 11.4);
d) the reaction of cleaning agents with hard water (see 11.6);
e) unsuitable cleaning agents;
f) frequent use of unsuitable cleaning agents, including highly alkaline detergents
and chemicals (see 11.6).
11.3 Efflorescence
NOTE Efflorescence is aggravated by excessively damp conditions following
installation or prolonged delay in drying out and can be persistent if it is due to
rising moisture where damp resisting construction (see 6.5.2) is inadequate. The
deposit is very likely to disappear with washing but can reappear after drying; it is
very likely to diminish with progressive washing and the most effective treatment is
to increase the frequency of washing until the deposit ceases.
Persistent deposits can be treated with appropriate proprietary cleaners, but in
such cases the floor should be wetted and the free water removed before the
application of the cleaning agent. This treatment should be immediately
followed by thorough rinsing with clean water and drying.
Key
1 External angles 2 Mitre cut for internal angles
Key
1 External angles 2 Internal angle
Key
1 External angles 2 Internal angle
Key
1 Stepnosing tile (2402) 3 Mitre cut for internal angle
2 Stepnosing external angle file
(2402X)
NOTE For further information, see Approved Document M – Access to and use of
buildings [10].
Figure A.7 Typical step tread – dry pressed tiles [large format]
NOTE For further information, see Approved Document M – Access to and use of
buildings [10].
Key
1 Tile 6 Suitable loadbearing insulation
2 Adhesive 7 Structural base
3 Levelling screed 8 Perimeter movement joint
4 Steel mesh 9 Perimeter movement joint
5 Heating pipes
C.1.2 Type B
Fully floating floor screed (see BS EN 1264) should be at least 35 mm calcium
sulfate or modified cement, consisting of proprietary systems where pipes or
cables are recessed into grooves within the insulation layer and should be
installed strictly in accordance with the system manufacturer’s recommendations.
NOTE Figure C.2 shows a Type B heating system.
Key
1 Tile 6 Heating pipes
2 Adhesive 7 Suitable loadbearing insulation
3 Levelling screed 8 Structural base
4 Steel mesh reinforcement 9 Perimeter movement joint
5 Slip membrane 10 Perimeter movement joint
C.1.3 Type C
Fully floating floor screeds (see BS EN1264) should be to a specified average
thickness, laid level or laid to falls, with metal wire mesh reinforcement (a
welded steel fabric of 2.5 mm diameter wire spaced at approximately 50 mm
× 50 mm centres) laid upon a slip membrane, over a sub-screed, not less
than 45 mm thick, containing heating pipes or cables, all of which rest upon or
set into recessed grooves within a suitable thermal insulation layer in accordance
with the relevant Building Regulations by typically 90 mm to 100 mm thick,
supported by the structural slab.
NOTE Figure C.3 shows a Type C heating system.
Key
1 Tile 7 Heating pipes
2 Adhesive 8 Suitable loadbearing insulation
3 Levelling screed 9 Structural base
4 Steel mesh reinforcement 10 Perimeter movement joint
5 Slip membrane 11 Perimeter movement joint
6 Levelling screed
Key
1 Tile 6 Adhesive
2 Adhesive 7 Structural base (SRI)
3 Levelling screed (encapsulating layer) 8 Perimeter movement joint
4 Cable mat 9 Perimeter movement joint
5 Suitable loadbearing insulation or
backerboard
Key
1 Tile 6 Adhesive
2 Adhesive 7 Structural base (SRI)
3 Levelling screed (encapsulating layer) 8 Perimeter movement joint
4 Loose cables 9 Perimeter movement joint
5 Suitable loadbearing insulation or
backerboard
NOTE 2 Higher temperatures reduce the open time of the adhesive and might
induce higher contraction stresses on cooling.
Once the floor tiling is installed, the heating system should not be run for at
least ten days in order to allow the tile bedding to cure/dry thoroughly.
Usually in normal environments, the temperature of the tiling layer and its
background (internal tiling) might not vary from each other to such extremes, but
where tiles and panels, particularly dark coloured ones are installed externally or in
areas subject to intense direct sunlight (e.g. sun rooms, conservatories, atria, etc.),
the tiling layer can heat up and cool very quickly whilst the background might not.
Conversely, any significant drying shrinkage of the background which continues after
tiles or panels have been installed directly onto it might result in the build{up of
lateral stresses within the tiling system.
Thermal expansion/contraction should be considered when using very large
ceramic tiles and panels, especially those with a coefficient of linear thermal
expansion that differs greatly from that of the heated sub-floor.
When the value for the coefficient of thermal expansion of any hard flooring
material is required this information should always be obtained from the
technical data provided by the manufacturer or supplier.
C.4.3 Insulation
The insulation selected for use with the heating system should have a
compressive strength compatible with the floor loadings.
NOTE Typically, for commercial applications the insulation will require a minimum
compressive strength of 350 MPa.
Any deviations in the levels and surface regularity of the base slab should be
taken into consideration when determining the thickness of the pumpable
self-smoothing screed to be laid, so as to ensure the minimum/maximum
thickness can be achieved.
Pump applied calcium sulfate-based screeds can be installed as a base for
ceramic floor tiling and mosaics however the designer should appreciate that
such screeds should only be used in locations where the applied screed is neither
exposed to moisture, nor subsequently become wet. The same restraints that
apply to wall tiling on gypsum (calcium sulfate) plaster should be observed in
this respect.
Where the ceramic floor tiling is likely to be exposed to intermittent wetting,
the surface of the calcium sulfate-based screed should be protected by the
application of an appropriate waterproof coating or tanking system prior to the
installation of the floor tiling to prevent ingress of moisture into the calcium
sulfate-based screed beneath the floor tiling. The design should also ensure that
lateral ingress of moisture from adjacent screeds, walls and other abutting
structures, as well as through any joints in the floor tiling, is prevented
(see 6.5 for additional guidance on this point).
The applied calcium sulfate-based screed should be dry before the floor tiling is
installed. If testing for dryness is required before the installation of ceramic floor
tiling, this should be in accordance with the calcium sulfate screed
manufacturer’s recommendations.
NOTE 1 Further information on the drying of calcium sulfate-based screeds is given
in the document Tiling to Calcium Sulfate Based Screeds prepared by The Tile
Association [13].
Movement joints should be installed in the floor tiling and where necessary in
the calcium sulfate-based screed as recommended in 6.8.
The surface of the pump applied calcium sulfate-based screed should be checked
and prepared so that any cohesively weak, friable and dusty surface residues are
removed by the use of appropriate surface preparation techniques.
D.4 Drying
Screed drying time is approximately 1 mm per day up to 40 mm thickness in
adequate temperatures and drying conditions. Sample drying times are given in
Table D.2. This period should be increased for screeds thicker than 40 mm and in
poor drying conditions.
Good drying conditions should be provided as soon as the screed is laid. The
screed should be protected from very rapid drying or draughts on the first day,
but thereafter atmospheric humidity should be low, i.e. not greater than 65 °RH,
and the air temperature should be adequate (e.g. 20 °C) so that moisture can
evaporate.
NOTE Good ventilation or the use of dehumidifiers can assist in reducing the
atmospheric humidity.
50 60
60 80
E.1.2.1 Bonding
The adequacy of the bond of the levelling screed to the base should be
considered in relation to the floor tiling to be applied and its subsequent use.
Where maximum bond between the levelling screed and the base is required,
the method for preparation of the base given in E.2.2.2 should be followed. A
base with only a tamped surface is unsuitable and a levelling screed laid over
such a base should be considered as unbonded.
Levelling screeds should be considered as unbonded where the base:
a) has been contaminated, e.g. with oil;
b) contains admixtures to reduce permeability;
c) has a damp-proof membrane between it and the levelling screed.
Where an insulating quilt is between the levelling screed and the base the
levelling screed should be considered as floating.
E.1.2.2 Thickness
The thickness of the levelling screeds should be as follows.
a) Bonded levelling screed: when laid on and bonded to a set and hardened
base prepared as in E.2.2.2, the minimum thickness of the levelling screed at
any isolated point should be 25 mm. The design thickness should be 40 mm.
In some circumstances, the thickness of the levelling screed might have to
be increased above 40 mm, but it should be noted that above this thickness
there is an increasing risk of loss of adhesion with the base. If the degree of
preparation described in E.2.2.2 cannot be achieved then the levelling
screed should be considered as unbonded.
b) Unbonded levelling screed: when laid on a damp-proof membrane, a
separating layer or a base that incorporates an admixture that reduces
permeability or has been contaminated, e.g. with oil, or a base that for any
E.1.4 Joints
Formed daywork joints between strips of levelling screeds should be vertical butt
joints.
NOTE 1 Acceptance limits for the various categories of in situ crushing resistance
are given in Table E.2.
In making the selection the designer should take into account the thickness of
the tile and the method of laying.
NOTE 2 For any traffic conditions, tiles laid with thin-bed adhesives tend to require
a higher in situ crushing resistance category than those laid by other methods.
Whilst bearing in mind the possible extra cost of a higher category screed, the
designer should, at the same time, not lose sight of the consequences of a
failure of the floor due to the breakdown of a lower category screed.
Table E.1 Choice of in situ crushing resistance category for levelling screeds
Thinner Heavier A
B
C
Thicker Lighter D
Category D should be selected only where an unbonded tile bed is to be used.
Table E.3 Classification of surface regularity [SR] of direct finished base slab or levelling
screed
E.1.10 Admixtures
The following admixtures should be used.
a) Air entraining: air entraining admixtures should conform to BS EN 934-2.
NOTE 1 Admixtures which entrain a small amount of fine air bubbles might
help to reduce “bleeding” of free water and improve the finished surface of the
concrete. An excessive amount of entrained air can reduce the strength and
abrasion resistance of the concrete to unacceptable levels.
b) Water reducing: water reducing admixtures should conform to BS EN 934-2.
NOTE 2 These admixtures can be used to improve workability and reduce the
water content otherwise required in the mix. They can also entrain a small
quantity of air.
c) Superplasticizing: superplasticizing admixtures should conform to
BS EN 934-2.
NOTE 3 These admixtures greatly increase workability at normal water
contents for a short period to produce “flowing concrete” which needs little or
no compaction. Alternatively, they can be used as water reducing admixtures.
To ensure satisfactory adhesion, the surface of the compacted lower layer should
be lightly roughened, e.g. by raking, before adding the second layer. The upper
layer should be placed and compacted immediately after compaction of the
lower layer.
Where a levelling screed is laid on a compressible insulation layer, extra
attention should be given to ensure adequate compaction, e.g. by the use of a
slightly wetter mix.
Where reinforcement is used, it should be placed in about the middle third of
the thickness of the screed.
NOTE This can only be achieved if the thickness of the reinforcement is correctly
chosen in relation to the thickness of the creed so that the total thickness of the
steel fabric at the overlaps can fit into the middle third of the screed depth. This can
be achieved by laying the levelling screed to about half its thickness, compacting it,
lightly roughening the surface with a rake, laying the reinforcement on the
compacted layer and then immediately placing and compacting the upper layer.
Dimensions in millimetres
Key
1 Side elevation 2 Top plan
The traditional “beating-in” of tiles involves thoroughly tapping the tiles with a
flat faced wooden block which, dimensionally, is usually approximately 300 mm
× 100 mm × 50 mm. Alternatively, some floor tiling contractors use vibrating
machines for beating-in. During this operation the tile joints should be
regulated and an occasional check made to establish that full contact is being
achieved between tiles and the slurried bed by lifting a tile out at random; any
slurry or mortar disturbed should be made good before the tile is replaced.
There should be no delay between spreading the slurry on the semi-dry mix bed,
placing the tiles and tapping them in.
Where tiles have been bedded using a vibrating machine, grouting should be
completed within four hours. Where proprietary manufactured grouts are to be
used, the manufacturer’s instructions should be followed.
NOTE Some large format tiles might not be suitable for the semi-dry bedding
technique; being too large for beating in or to allow the bed to be compacted to
the same degree as with a smaller tile.
G.12 Admixtures
When admixtures are incorporated in cement and sand grout they should be
used in accordance with the admixture manufacturer’s instructions.
Only materials and admixtures approved by the manufacturer should be
incorporated in their proprietary grouting products.
H.1 General
NOTE The guidance below follows the various HSE documents [14], [15], [16], [17],
and [18] and applies to all types of impervious floor coverings.
Ceramic floor tiles are not slippery when clean and dry. The slip resistance of a
floor in service depends on the nature of its surface, and this can change over
the lifetime of the floor. Flooring surfaces in common use generally have
acceptable slip resistance provided they are clean, dry, free from oil, fat and
other slippery substances and have received thorough cleaning after installation,
and continue to receive appropriate maintenance in service. The likelihood of
slipping on a floor is increased by the presence of contamination; the most
common contaminant is water but others including oil, grease, soap, dust, lint
and sand are also possible. The likelihood of slipping also varies with the type of
footwear worn by pedestrians (see H.3).
Instruments that purport to measure slip resistance are actually measuring
coefficient of friction in standard test conditions, which might vary considerably
from those in service. For instance, it is important that tests in wet conditions
are used to assess slip resistance on a wet floor, and that the thickness of the
layer of water in the test is similar to that which is present under a sliding heel,
as is the case with the Pendulum test.
Surface roughness can provide useful complementary information. Monitoring
the change in the roughness (Rz) of a surface due to wear and other factors can
be helpful in gauging the likely change in slip resistance, although it is not a
substitute for proper measurement of slip resistance (see BS 1134). The required
surface roughness depends on the contaminant, for example, dirty water is likely
to require a higher surface roughness than clean water because the viscosity is
higher.
Slipping incidents can occur in which the person is able to recover their stance,
or if they fail, do not injure themselves to any great extent. Comprehensive
records of all slip incidents, including those which do not result in serious injury,
and thorough investigation to uncover the root causes of these events helps to
identify problem areas and allow action to be taken before a serious accident
does occur. Records also allow patterns to be identified, giving further clues to
the action required to reduce the hazard.
H.2 Design
The measures that can be taken by designers, in consultation with their clients,
to promote safe conditions in service include:
a) considering the likely contaminants that are likely to be present in service
and specifying the floor surface and measures required to maintain it in a
safe condition;
b) anticipating the cleaning and maintenance regime necessary and making
the necessary provisions for it;
c) providing adequate entrance flooring systems at foyers and entrances to
intercept water and dirt brought in by traffic. At entrances, if wet footprints
can be seen beyond the entrance matting, the entrance matting is
compromised and additional temporary matting is to be used. The entrance
matting surface is to:
1) remain effective;
2) extend to the entrance threshold;
3) not leave gaps (where supplementary mats are used);
4) not present a trip hazard;
d) the proper cleaning, maintenance and replacement where necessary of
entrance flooring systems, in order to maintain their effectiveness. Matting
can be securely fixed so that it does not present a tripping hazard;
e) the use of canopies over entrances;
f) positioning entrances to reduce the effects of prevailing weather;
g) the use of ventilation systems to help reduce the impact of wet weather
and/or cleaning;
h) people pulling or pushing loads generally require a surface with a higher
slip resistance to operate safely.
Poor lighting, inside or outside, can significantly increase the risk faced by
pedestrians. Limited lighting can also skew individuals’ perceptions or
expectations of the degree of slipperiness of a walking surface. Steps, stairs and
ramps present an increased risk and need to be clearly identified and well lit.
Accidents generally occur when unexpected changes in floor conditions are
encountered. It is often the difference between the dry and wet (contaminated)
coefficient of friction that is important. Specifiers need to remember this and
not simply choose a floor covering material with a high dry coefficient of
friction value. It is also good practice to avoid significantly different flooring
materials (in terms of their slip resistance) in adjacent areas.
If contamination is likely to be present, then flooring with enhanced slip
resistance can be used. The use of such floorings is particularly important on
slopes and in areas where tiling is laid to falls to drain water from foreseeably
wet areas (expert advice might be required).
H.3 Service
The measures that can be taken by the owner or occupier of the building to
promote safe conditions in service include identifying potentially wet areas and
using an appropriate surface there, establishing an effective
cleaning/maintenance procedure that uses appropriate cleaning materials,
confirming that these procedures are conducted at the appropriate frequency
and using normal measures of good housekeeping.
NOTE The Management of Health and Safety at Work Regulations 1999 [19]
require the employer to make an assessment of the risks of slipping caused by
conditions in his workplace and to take the necessary measures to minimize them.
Slip resistance can only be maintained by frequent effective cleaning with
appropriate detergent and cleaning tools. The flooring product manufacturer
might provide details of cleaning methods. When a wet cleaning process is used,
a thorough final rinse with fresh, clean water is particularly important. It is
particularly important to leave smooth floors dry after cleaning.
Areas of smooth floor coverings wet as a result of cleaning call for clear
identification and small areas of local contamination are to be cordoned off.
Freshly cleaned surfaces need to be completely dry before the floor is returned
to use.
Good housekeeping practices are the first defence against slip and fall accidents.
Good housekeeping is therefore a state to be maintained (rather than merely
achieved) by the following measures:
a) make sure that your cleaning method is effective for the type of floor you
have;
b) do not introduce more slip or trip risks while cleaning is being done;
c) leave smooth floors dry after cleaning or exclude pedestrians until the floor
is dry;
d) remove spillages promptly;
e) have effective arrangements for both routine cleaning and dealing with
spills;
f) use the appropriate detergent mixed at the correct concentration. If a
detergent is used, a rinse with fresh, clean water is especially important;
g) clean in sections, so there is a dry path through the area;
h) use warning signs: consider using cones carefully as they do not act as a
barrier and only warn of the hazard;
i) provide information on alternative routes.
In occupational settings it is often possible to select the footwear to be worn.
An informed choice of footwear might offer some protection against the
incidence of slipping accidents. Footwear needs to be properly cleaned and
maintained to remain effective. In situations where no control over footwear is
possible the condition of the floor is even more crucial in reducing the
likelihood of slipping accidents.
Bibliography
Standards publications
For dated references, only the edition cited applies. For undated references, the
latest edition of the referenced document (including any amendments) applies.
BS 1134, Assessment of surface texture – Guidance and general information
BS 4483, Steel fabric for the reinforcement of concrete – Specification
BS 5268-2, Structural use of timber – Part 2: Code of practice for permissible
stress design, materials and workmanship
BS 5606, Guide to accuracy in building
BS 6093, Design of joints and jointing in building construction – Guide
BS 6100-0, Building and civil engineering – Vocabulary – Introduction and index
BS 7976 (all parts), Pendulum testers
BS 8102, Code of practice for protection of structures against water from the
ground
BS 8204-3, Screeds, bases and in situ floorings – Part 2: Polymer modified
cementitious levelling screeds and wearing screeds – Code of practice
BS EN 1008, Mixing water for concrete – Specification for sampling, testing and
assessing the suitability of water, including water recovered from processes in
the concrete industry, as mixing water for concrete
BS EN 1367-4, Tests for thermal and weathering properties of aggregates –
Part 4: Determination of drying shrinkage
BS EN 1990:2002+A1:2005, Eurocode – Basis of Structural Design
BS EN 14188-1:2004, Joint fillers and sealants – Part 1: Specifications for hot
applied sealants
BS EN 14188-2:2004, Joint fillers and sealants – Part 2: Specifications for cold
applied sealants
BS EN 14188-3:2006, Joint fillers and sealants – Part 3: Specification for
preformed joint seals
BS EN ISO 11600:2003+A1:2011, Building construction – Jointing products –
Classification and requirements for sealants
BS ISO 13007-3, Ceramic tiles – Grouts and adhesives – Terms, definitions and
specifications for grouts
CP 102, Code of practice for protection of buildings against water from the
ground
Other publications
[1] GREAT BRITAIN. Building and Construction Regulations under the Factories
Act 1961. London: The Stationery Office.
[2] GREAT BRITAIN. Lifting Operations and Lifting Equipment Regulations
(LOLER) 1998. London: The Stationery Office.
[3] GREAT BRITAIN. Manual Handling Operations Regulations 1992. London:
The Stationery Office.
[4] GREAT BRITAIN. Building Research Establishment Digest 357. London: BRE.
[5] GREAT BRITAIN. Tiling to timber substrates and alternative products.
Staffordshire: The Tile Association.
[6] GREAT BRITAIN. Tiling to raised flooring systems. Staffordshire: The Tile
Association.
[7] GREAT BRITAIN. Technical Guidance Note 10 on Tile Trim Profiles.
Staffordshire: The Tile Association.
[8] GREAT BRITAIN. Disability Discrimination Act 2005. London: The Stationery
Office.
[9] GREAT BRITAIN. Equality Act 2010. London: The Stationery Office.
[10] GREAT BRITAIN. Approved Document M – Access to and use of buildings.
National Building Specification: London.
[11] GREAT BRITAIN. The Cleaning of Ceramic Tiles. Staffordshire: The Tile
Association.
[12] GREAT BRITAIN. Slip Resistance of Hard Floorings. Staffordshire: The Tile
Association.
[13] GREAT BRITAIN. Tiling to calcium sulfate based screeds. Staffordshire: The
Tile Association.
[14] GREAT BRITAIN. Preventing slips and trips at work, INDG225 (rev2). Sudbury:
HSE Books.
[15] GREAT BRITAIN. Stop slips in kitchens – Floor cleaning. Sudbury: HSE Books.
[16] GREAT BRITAIN. Slips and trips: The importance of floor cleaning – Slips and
Trips 2. Sudbury: HSE Books.
[17] GREAT BRITAIN. Assessing the slip resistance of flooring, GEIS2. Sudbury: HSE
Books.
[18] GREAT BRITAIN. Slips and trips – Hazard spotting checklist. Sudbury: HSE
Books.
[19] GREAT BRITAIN. The Management of Health and Safety at Work
Regulations 1999. London: The Stationery Office.
About us Revisions
We bring together business, industry, government, consumers, innovators Our British Standards and other publications are updated by amendment or revision.
and others to shape their combined experience and expertise into standards We continually improve the quality of our products and services to benefit your
-based solutions. business. If you find an inaccuracy or ambiguity within a British Standard or other
The knowledge embodied in our standards has been carefully assembled in BSI publication please inform the Knowledge Centre.
a dependable format and refined through our open consultation process.
Organizations of all sizes and across all sectors choose standards to help Copyright
them achieve their goals. All the data, software and documentation set out in all British Standards and
other BSI publications are the property of and copyrighted by BSI, or some person
Information on standards or entity that owns copyright in the information used (such as the international
We can provide you with the knowledge that your organization needs standardization bodies) and has formally licensed such information to BSI for
to succeed. Find out more about British Standards by visiting our website at commercial publication and use. Except as permitted under the Copyright, Designs
bsigroup.com/standards or contacting our Customer Services team or and Patents Act 1988 no extract may be reproduced, stored in a retrieval system
Knowledge Centre. or transmitted in any form or by any means – electronic, photocopying, recording
or otherwise – without prior written permission from BSI. Details and advice can
Buying standards be obtained from the Copyright & Licensing Department.
You can buy and download PDF versions of BSI publications, including British
and adopted European and international standards, through our website at Useful Contacts:
bsigroup.com/shop, where hard copies can also be purchased. Customer Services
If you need international and foreign standards from other Standards Development Tel: +44 845 086 9001
Organizations, hard copies can be ordered from our Customer Services team. Email (orders): [email protected]
Email (enquiries): [email protected]
Subscriptions
Subscriptions
Our range of subscription services are designed to make using standards
Tel: +44 845 086 9001
easier for you. For further information on our subscription products go to
Email: [email protected]
bsigroup.com/subscriptions.
With British Standards Online (BSOL) you’ll have instant access to over 55,000 Knowledge Centre
British and adopted European and international standards from your desktop. Tel: +44 20 8996 7004
It’s available 24/7 and is refreshed daily so you’ll always be up to date. Email: [email protected]
You can keep in touch with standards developments and receive substantial
Copyright & Licensing
discounts on the purchase price of standards, both in single copy and subscription
format, by becoming a BSI Subscribing Member. Tel: +44 20 8996 7070
Email: [email protected]
PLUS is an updating service exclusive to BSI Subscribing Members. You will
automatically receive the latest hard copy of your standards when they’re
revised or replaced.
To find out more about becoming a BSI Subscribing Member and the benefits
of membership, please visit bsigroup.com/shop.
With a Multi-User Network Licence (MUNL) you are able to host standards
publications on your intranet. Licences can cover as few or as many users as you
wish. With updates supplied as soon as they’re available, you can be sure your
documentation is current. For further information, email [email protected].