ARC503 House construction project

ID Task WBS Task Name Duration Start Finish Predecessors 2014


Mode Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov
1 1 Housing Association Project START 505 days Mon 02/12/13Fri 06/11/15 1 505 day
2 1.1 Inception 20 days Mon 02/12/13Fri 27/12/13 1.1 20 days
3 1.1.1 Client's objectives 10 days Mon 02/12/13 Fri 13/12/13
4 1.1.2 PM Appointment and commissionin10 days Mon 16/12/13 Fri 27/12/13 3
5 1.2 Feasibility 35 days Mon 16/12/13Fri 31/01/14 1.2 35 days
6 1.2.1 Project Brief 5 days Mon 16/12/13 Fri 20/12/13 3
7 1.2.2 Site investigation and studies 30 days Mon 23/12/13 Fri 31/01/14 6
8 1.3 Strategy 20 days Mon 03/02/14Fri 28/02/14 1.3 20 days
9 1.3.1 Appointment of project team 15 days Mon 03/02/14 Fri 21/02/14 7
10 1.3.2 Procurement route established 5 days Mon 24/02/14 Fri 28/02/14 9
11 1.4 Pre‐construction 105 days Mon 03/03/14Fri 25/07/14 1.4 105 days
12 1.4.1 Planning Approval 90 days Mon 03/03/14 Fri 04/07/14 10
13 1.4.2 Tender Action 15 days Mon 07/07/14 Fri 25/07/14 12
14 1.5 Construction 235 days Mon 28/07/14Fri 19/06/15 1.5 235 days
15 1.5.1 Preparation 50 days Mon 28/07/14Fri 03/10/14 1.5.1 50 days
16 1.5.1.1 Site excavation 25 days Mon 28/07/14 Fri 29/08/14 13
17 1.5.1.2 Pile foundations 25 days Mon 01/09/14 Fri 03/10/14 16
18 1.5.1.3 Car parking Space 15 days Mon 01/09/14 Fri 19/09/14 16
19 1.5.2 Walls 20 days Mon 10/11/14Fri 05/12/14 1.5.2 20 days
20 1.5.2.1 Brick/Block loadbearing walls 20 days Mon 10/11/14 Fri 05/12/14 22
21 1.5.3 Floors 85 days Mon 06/10/14Fri 30/01/15 1.5.3 85 days
22 1.5.3.1 Ground floor concrete slab 25 days Mon 06/10/14 Fri 07/11/14 17
23 1.5.3.2 Precast concrete upper floors 40 days Mon 08/12/14 Fri 30/01/15 20
24 1.5.4 Roof Construction 80 days Mon 08/12/14Fri 27/03/15 1.5.4 80 days
25 1.5.4.1 Main Construction 50 days Mon 08/12/14 Fri 13/02/15 20
26 1.5.4.2 Waterprooing 30 days Mon 16/02/15 Fri 27/03/15 25
27 1.5.5 Installations 60 days Mon 30/03/15Fri 19/06/15 1.5.5 60 days
28 1.5.5.1 Renewable Technology 30 days Mon 30/03/15 Fri 08/05/15 26
29 1.5.5.2 Windows and Doors 15 days Mon 30/03/15 Fri 17/04/15 26
30 1.5.5.3 Services 30 days Mon 11/05/15 Fri 19/06/15 28
31 1.6 Commissioning 25 days Mon 22/06/15 Fri 24/07/15 30
32 1.7 Completion/Handover 65 days Mon 27/07/15Fri 23/10/15 1.7 65 days
33 1.7.1 Final inspection 30 days Mon 27/07/15 Fri 04/09/15 31
34 1.7.2 Practical Completion 5 days Mon 07/09/15 Fri 11/09/15 33
35 1.7.3 Client training 25 days Mon 14/09/15 Fri 16/10/15 34
36 1.7.4 Occupation 5 days Mon 19/10/15 Fri 23/10/15 35
37 1.8 Post completion review 10 days Mon 26/10/15Fri 06/11/15 1.8 10 days
38 1.8.1 Project Report 10 days Mon 26/10/15 Fri 06/11/15 36
39 2 Housing Association Project FINISH 0 days Fri 06/11/15 Fri 06/11/15 38 2 06/11

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: Procurement and Project Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 25/03/15
Milestone External Milestone Manual Task Start‐only Critical Split
Summary Inactive Task Duration‐only Finish‐only Progress