SPM Unit 2

The document discusses different software project life cycle models including waterfall, spiral, prototyping, incremental and RAD models. It describes the phases and advantages/disadvantages of each model. The waterfall model involves sequential phases from requirements to maintenance while incremental model involves interleaved activities with feedback. Spiral model emphasizes risk analysis through iterations. Prototyping is used to validate requirements or check design feasibility.

Uploaded by

shubhshubham616
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views22 pages

SPM Unit 2

The document discusses different software project life cycle models including waterfall, spiral, prototyping, incremental and RAD models. It describes the phases and advantages/disadvantages of each model. The waterfall model involves sequential phases from requirements to maintenance while incremental model involves interleaved activities with feedback. Spiral model emphasizes risk analysis through iterations. Prototyping is used to validate requirements or check design feasibility.

Uploaded by

shubhshubham616
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22

UNIT-II

Software Project Management (KCA-013)


PROJECT LIFE CYCLE AND EFFORT ESTIMATION
2.1 Software Process and Process Models

A Software product development process usually starts when a request for the
product isreceived from the customer.
 Starting from the inception stage:
o A product undergoes a series of transformations through a few identifiable
stages
o Until it is fully developed and released to the customer.
 After release:
o the product is used by the customer and during this time the product
needs to bemaintained for fixing bugs and enhancing functionalities.
This stage is called Maintenance stage.
 This set of identifiable stages through which a product transits from
inception toretirement form the life cycle of the product.
 Life cycle model (also called a process model) is a graphical or textual
representationof its life cycle.

2.2 Choice of Process Models

The no. of inter related activities to create a final product can be organized in
different ways and we can call these Process Models.
A software process model is a simplified representation of a software
process. Each model represents a process from a specific perspective. These generic
models are abstractions of the process that can be used to explain different
approaches to the software development.
Any software process must include the following four activities:
1. Software specification (or requirements engineering): Define the main
functionalities of thesoftware and the constrains around them.
2. Software design and implementation: The software is to be designed and
programmed.
3. Software verification and validation: The software must conforms to it’s
specification andmeets the customer needs.
4. Software evolution (software maintenance): The software is being modified
to meetcustomer and market requirements changes.
The various Process Models
areWater Fall Model
Spiral Model
Prototype Model
Incremental
Delivery

2.2.1Water fall model


The waterfall model is a sequential approach, where each fundamental activity of a
processrepresented as a separate phase, arranged in linear order.
In the waterfall model, you must plan and schedule all of the activities before starting
working onthem (plan-driven process).

Plan-driven process is a process where all the activities are planned first, and the
progress is measured against the plan. While the agile process, planning is incremental
and it’s easier to changethe process to reflect requirement changes.

The phases of the waterfall model are:

 Requirements

 Design

 Implementation

 Testing

 Maintenance
In principle, the result of each phase is one or more documents that should be approved
and the next phase shouldn’t be started until the previous phase has completely been
finished.
In practice, however, these phases overlap and feed information to each other. For
example, duringdesign, problems with requirements can be identified, and during coding,
some of the design problems can be found, etc.
The software process therefore is not a simple linear but involves feedback from one
phase to another. So, documents produced in each phase may then have to be modified
to reflect the changesmade.

2.2.2Spiral Model

The spiral model is similar to the incremental model, with more emphasis placed
on risk analysis. The spiral model has four phases: Planning, Risk Analysis, Engineering
and Evaluation. A software project repeatedly passes through these phases in iterations
(called Spirals in this model). The baseline spiral, starting in the planning phase,
requirements is gathered and risk is assessed. Each subsequent spiral builds on the
baseline spiral. It is one of the software development models like Waterfall, Agile, V-
Model.
Planning Phase: Requirements are gathered during the planning phase. Requirements
like ‘BRS’ that is ‘Bussiness Requirement Specifications’ and ‘SRS’ that is ‘System
Requirement specifications’.
Risk Analysis: In the risk analysis phase, a process is undertaken to identify risk and
alternate solutions. A prototype is produced at the end of the risk analysis phase. If any
risk is found during the risk analysis then alternate solutions are suggested and
implemented.
Engineering Phase: In this phase software is developed, along with testing at the end of
the phase. Hence in this phase the development and testing is done.
Evaluation phase: This phase allows the customer to evaluate the output of the project
to date before the project continues to the next spiral.
Advantages of Spiral model:
 High amount of risk analysis hence, avoidance of Risk is enhanced.
 Good for large and mission-critical projects.
 Strong approval and documentation control.
 Additional Functionality can be added at a later date.
 Software is produced early in the software life cycle.
Disadvantages of Spiral model:
 Can be a costly model to use.
 Risk analysis requires highly specific expertise.
 Project’s success is highly dependent on the risk analysis phase.
 Doesn’t work well for smaller projects.
2.2.3Software Prototyping
A prototype is a version of a system or part of the system that’s developed quickly
to check the customer’s requirements or feasibility of some design decisions.So, a
prototype is useful when a customer or developer is not sure of the requirements, or of
algorithms, efficiency, business rules,response time, etc.
In prototyping, the client is involved throughout the development process, which
increases the likelihood of client acceptance of the final implementation.While some
prototypes are developed with the expectation that they will be discarded, it is possible
in some cases to evolve from prototype to working system.
A software prototype can be used:
[1] In the requirements engineering, a prototype can help with the elicitation and
validation of system requirements.It allows the users to experiment with the system,
and so, refine the requirements. They may get new ideas for requirements, and find
areas of strength and weakness in the software.Furthermore, as the prototype is
developed, it may reveal errors and in the requirements. The specification maybe then
modified to reflect the changes.
[2] In the system design, a prototype can help to carry out deign experiments to check the
feasibilityof a proposed design.For example, a database design may be prototype-d and
tested to check it supports efficient data access for the most common user queries.
The phases of a prototype are:
1. Establish objectives: The objectives of the prototype should be made explicit from
the start of the process. Is it to validate system requirements, or demonstrate
feasibility, etc.
2. Define prototype functionality: Decide what are the inputs and the expected output
from a prototype. To reduce the prototyping costs and accelerate the delivery
schedule, you may ignore some functionality, such as response time and memory
utilization unless they are relevant to the objective of the prototype.
3. Develop the prototype: The initial prototype is developed that includes only user
interfaces.
4. Evaluate the prototype: Once the users are trained to use the prototype, they then
discover requirements errors. Using the feedback both the specifications and the
prototype can be improved. If changes are introduced, then a repeat of steps 3 and 4
may be needed.
Prototyping is not a standalone, complete development methodology, but rather an
approach to be used in the context of a full methodology (such as incremental, spiral,
etc).

2.3 Incremental Delivery


Incremental development is based on the idea of developing an initial
implementation, exposing this to user feedback, and evolving it through several versions
until an acceptable system has been developed.The activities of a process are not
separated but interleaved with feedback involved across those activities.
Each system increment reflects a piece of the functionality that is needed by the
customer. Generally, the early increments of the system should include the most
important or most urgentlyrequired functionality.
This means that the customer can evaluate the system at early stage in the
development tosee if it delivers what’s required. If not, then only the current increment
has to be changed and, possibly, new functionality defined for later increments.

Incremental Vs Waterfall Model

Incremental software development is better than a waterfall approach for most


business, e-commerce, and personal systems.

By developing the software incrementally, it is cheaper and easier to make changes in the
softwareas it is being developed.

Compared to the waterfall model, incremental development has three important benefits:
1. The cost of accommodating changing customer requirements is reduced. The
amount of analysis and documentation that has to be redone is much less than
that’s required with waterfall model.
2. It’s easier to get customer feedback on the work done during development than
when the system is fully developed, tested, and delivered.
3. More rapid delivery of useful software is possible even if all the functionality hasn’t
been included. Customers are able to use and gain value from the software earlier
than it’s possiblewith the waterfall model.

2.4 Rapid Application Development

RAD model is Rapid Application Development model. It is a type of incremental


model. In RAD model the components or functions are developed in parallel as if they
were mini projects. The developments are time boxed, delivered and then assembled
into a working prototype. This can quickly give the customer something to see and use
and to provide feedback regarding the delivery and their requirements.
The phases in the rapid application development (RAD) model are:
Business modeling: The information flow is identified between various business
functions. Data modeling: Information gathered from business modeling is used to
define data objects thatare needed for the business.
Process modeling: Data objects defined in data modeling are converted to achieve the
businessinformation flow to achieve some specific business objective. Description are
identified and created for CRUD of data objects.
Application generation: Automated tools are used to convert process models into
code and theactual system.
Testing and turnover: Test new components and all the interfaces.
Advantages of the RAD model:
 Reduced development time.
 Increases reusability of components
 Quick initial reviews occur
 Encourages customer feedback
 Integration from very beginning solves a lot of integration issues.
Disadvantages of RAD model:
 Depends on strong team and individual performances for identifying business
requirements.
 Only system that can be modularized can be built using RAD
 Requires highly skilled developers/designers.
 High dependency on modeling skills
 Inapplicable to cheaper projects as cost of modeling and automated code
generation is veryhigh.
2.5 Agile Methods
The Agile methodology derives from a namesake manifesto, which advanced ideas
that were developed to counter the more convoluted methods that pervaded the
software development worlddespite being notoriously inefficient and counterproductive.
Promoting similar methods to Lean, the key principles of Agile are as follows:

 Satisfying customers is of foremost importance


 Develop projects with inspired contributors
 Interactions are best when done in person
 Software that works is a measure of progress
 Reflect and adapt on an ongoing basis
Additionally, the four core values of Agile are as
follows:
 Individuals and interactions over processes and tools
 Working software over comprehensive documentation
 Customer collaboration over contract negotiation
 Responding to change over following a plan
Regardless of which Agile methodology a team adopts, the benefits cannot be fully
realizedwithout the commitment of everyone involved.
2.5.1 Extreme Programming
One of the foremost Agile methodologies is called Extreme Programming (XP),
whichinvolves a high degree of participation between two parties in the software
exchange: customers
and developers. The former inspires further development by emphasizing the most useful
featuresof a given software product through testimonials. The developers, in turn, base
each successive setof software upgrades on this feedback while continuing to test new
innovations every few weeks.
XP has its share of pros and cons. On the upside, this Agile methodology
involves a high level of collaboration and a minimum of up-front documentation. It’s an
efficient and persistent delivery model. However, the methodology also requires a great
level of discipline, as well as plenty of involvement from people beyond the world of
information technology. Furthermore, in order for the best results, advanced XP
proficiency is vital on the part of every team member.
Extreme programming (XP) is a software development methodology which is intended
to improve software quality and responsiveness to changing customer requirements.
As a type of agile software development, it advocates frequent "releases" in short
development cycles, which is intended to improve productivity and introduce
checkpoints at which new customer requirements can be adopted.
Other elements of extreme programming include: programming in pairs or doing
extensive code review, unit testing of all code, avoiding programming of features until
they are actually needed, a flat management structure, code simplicity and clarity,
expecting changes in the customer's requirements as time passes and the problem is
better understood, and frequent communication with the customer and among
programmers. The methodology takes its name from the idea that the beneficial
elements of traditional software engineering practices are taken to "extreme" levels.As
an example, code reviews are considered a beneficial practice; taken to the extreme,
code can be reviewed continuously, i.e. the practice of pair programming.
Activities
XP describes four basic activities that are performed within the software development
process:coding, testing, listening, and designing. Each of those activities is described
below.
Coding
The advocates of XP argue that the only truly important product of the system
development process is code – software instructions that a computer can interpret.
Without code, there is no working product.
Coding can also be used to figure out the most suitable solution. Coding can also help
to communicate thoughts about programming problems. A programmer dealing with a
complex programming problem, or finding it hard to explain the solution to fellow
programmers, might
code it in a simplified manner and use the code to demonstrate what he or she means.
Code, say the proponents of this position, is always clear and concise and cannot be
interpreted in more thanone way. Other programmers can give feedback on this code by
also coding their thoughts.
Testing
Extreme programming's approach is that if a little testing can eliminate a few flaws, a lot
of testingcan eliminate many more flaws.
 Unit tests determine whether a given feature works as intended. Programmers write
as many automated tests as they can think of that might "break" the code; if all tests
run successfully, then the coding is complete. Every piece of code that is written is
tested before moving on to the next feature.
 Acceptance tests verify that the requirements as understood by the programmers
satisfy the customer's actual requirements.
System-wide integration testing was encouraged, initially, as a daily end-of-day activity,
for earlydetection of incompatible interfaces, to reconnect before the separate sections
diverged widely from coherent functionality. However, system-wide integration testing
has been reduced, to weekly, or less often, depending on the stability of the overall
interfaces in the system.
Listening
Programmers must listen to what the customers need the system to do, what "business
logic" is needed. They must understand these needs well enough to give the customer
feedback about the technical aspects of how the problem might be solved, or cannot be
solved. Communication between the customer and programmer is further addressed in
the planning game.
Designing
From the point of view of simplicity, of course one could say that system development
doesn't need more than coding, testing and listening. If those activities are performed
well, the result should always be a system that works. In practice, this will not work. One
can come a long way without designing but at a given time one will get stuck. The
system becomes too complex and thedependencies within the system cease to be clear.
One can avoid this by creating a design structurethat organizes the logic in the system.
Good design will avoid lots of dependencies within a system; this means that changing
one part of the system will not affect other parts of the system.
Advantages
Robustness
Resilience
Cost
savings
Lesser
risks

Disadvantages
It assumes constant involvement of customers
Centered approach rather than design-centered
approachLack of proper documentation

2.6 Managing Interactive Processes

Booch suggests that there are two levels of development:


 The macro process
 The micro process
Macro process
 Establish core requirements (conceptualization).
 Develop a model of the desired behavior (analysis).
 Create an architecture (design).
 Evolve the implementation (evolution).
 Manage post delivery evolution (maintenance).
Micro process
 Identify the classes and objects at a given level of abstraction.
 Identify the semantics of these classes and objects.
 Identify the relationships among these classes and objects.
 Specify the interface and then the implementation of these classes and objects
In principle, the micro process represents the daily activity of the individual
developer, orof a small team of developers.
The macro process serves as the controlling framework of the micro process. It
representsthe activities of the entire development team on the scale of weeks to
months at a time.The basic philosophy of the macro process is that of incremental
development: the system as a
whole is built up step by step, each successive version consisting of the previous ones
plus a number of new functions.

2.7 Basics of Software estimation


Estimation techniques are of utmost importance in software development life
cycle, where the time required to complete a particular task is estimated before a
project begins. Estimation is the process of finding an estimate, or approximation,
which is a value that can be used for some purpose even if input data may be
incomplete, uncertain, or unstable.

The four basic steps in software project estimation are:


1) Estimate the size of the development product. This generally ends up in either
Lines of Code (LOC) or Function Points (FP), but there are other possible units of
measure. A discussion of the pros & cons of each is discussed in some of the
material referenced at theend of this report.
2) Estimate the effort in person-months or person-hours.
3) Estimate the schedule in calendar months.
4) Estimate the project cost in dollars (or local currency)

The major shortcomings of SLOC measure:

 No precise definition
 Difficult to estimate at start of a project
 Only a code measure
 Programmer-dependent
 Does not consider code complexity

2.8 Effort and Cost estimation techniques

The Effort and Cost estimation techniques are


o Algorithmic models, which use effort drivers representing
characteristics of thetarget system and the implementation
environment to predict effort.

o Expert judgment, based on the advice of knowledgeable staff.

o Analogy, where a similar, completed project is identified and its actual


effort isused as the basis of the estimate.

o Parkinson, where the staff effort available to do a project becomes the


estimate.

o Price to win, where the estimate is a figure that seems sufficiently low
to win acontract.

o Top-down, where an overall estimate for the whole project is broken


down intothe effort required for component tasks.

o Bottom-up, where component tasks are identified and sized and these
individualestimates are aggregated.

2.9 COSMIC full function points

 COSMIC FFP – Common Software Measurement International


Consortium FullFunction Point.
 COSMIC deals with decomposing the system architecture into a
hierarchy ofsoftware layers.
 Unit is Cfsu(COSMIC functional size units).
A Data Movement moves one Data Group. A Data Group is a unique cohesive set of
data (attributes) specifying an ‘object of interest’ (i.e. something that is ‘of interest’
tothe user). EachData Movement is counted as one CFP (COSMIC function point).

COSMIC recognizes 4 (types of) Data Movements:


Entry moves data from outside into the process
Exit moves data from the process to the outside
world Read moves data from persistent storage to
the process Write moves data from the process to
persistent storage.
Function Points
Function points were defined in 1979 in Measuring Application Development
Productivity by Allan Albrecht at IBM. The functional user requirements of the software
are identified and each one is categorized into one of five types: outputs, inquiries,
inputs, internal files, and external interfaces. Once the function is identified and
categorized into a type, it is then assessed for complexity and assigned a number of
function points. Each of these functional user requirements maps to an end-user
business function, such as a data entry for an Input or a user query for an Inquiry. This
distinction is important because it tends to make the functions measured in function
points map easily into user-oriented requirements, but it also tends to hide internal
functions (e.g. algorithms), which also require resources to implement.
There is currently no ISO recognized FSM Method that includes algorithmic complexity
in the sizing result. Recently there have been different approaches proposed to deal
with this perceived weakness, implemented in several commercial software products.
The variations of the Albrecht-based IFPUG method designed to make up for this (and
other weaknesses) include:
 Early and easy function points – Adjusts for problem and data complexity with two
questions that yield a somewhat subjective complexity measurement; simplifies
measurement by eliminating the need to count data elements.
 Engineering function points – Elements (variable names) and operators (e.g.,
arithmetic, equality/inequality, Boolean) are counted. This variation highlights
computational function. The intent is similar to that of the operator/operand-based
Halstead complexity measures.
 Bang measure – Defines a function metric based on twelve primitive (simple) counts
that affector show Bang, defined as "the measure of true function to be delivered as
perceived by the user." Bang measure may be helpful in evaluating a software unit's
value in terms of how muchuseful function it provides, although there is little evidence
in the literature of such application.
The use of Bang measure could apply when re-engineering (either complete or
piecewise) is being considered, as discussed in Maintenance of Operational
Systems—An Overview.
 Feature points – Adds changes to improve applicability to systems with significant
internal processing (e.g., operating systems, communications systems). This allows
accounting for functions not readily perceivable by the user, but essential for proper
operation.
 Weighted Micro Function Points – One of the newer models (2009) which adjusts
function points using weights derived from program flow complexity, operand and
operator vocabulary,object usage, and algorithm.
Benefits
The use of function points in favor of lines of code seek to address several additional
issues:
 The risk of "inflation" of the created lines of code, and thus reducing the value of the
measurement system, if developers are incentivized to be more productive. FP
advocates refer to this as measuring the size of the solution instead of the size of
the problem.
 Lines of Code (LOC) measures reward low level languages because more lines of
code are needed to deliver a similar amount of functionality to a higher level
language. C. Jones offersa method of correcting this in his work.
 LOC measures are not useful during early project phases where estimating the
number of lines of code that will be delivered is challenging. However, Function
Points can be derived from requirements and therefore are useful in methods such
as estimation by proxy.

2.10COCOMO II: A Parametric Productivity Model


Constructive COst Model II (COCOMO II) is a model that allows one to estimate the cost,
effort, and schedule when planning a new software development activity. COCOMO II is
the latest major extension to the original COCOMO (COCOMO 81) model published in
1981. It consists of three sub models, each one offering increased fidelity the further
along one is in the project planning and design process. Listed in increasing fidelity,
these sub models are called the
Applications
Composition, Early
Design, and
Post-architecture models.

COCOMO II can be used for the following major decision situations


 Making investment or other financial decisions involving a software development
effort
 Setting project budgets and schedules as a basis for planning and control
 Deciding on or negotiating tradeoffs among software cost, schedule,
functionality,performance or quality factors
 Making software cost and schedule risk management decisions
 Deciding which parts of a software system to develop, reuse, lease, or purchase
 Making legacy software inventory decisions: what parts to modify, phase out,
outsource,etc
 Setting mixed investment strategies to improve organization's software
capability, viareuse, tools, process maturity, outsourcing, etc
 Deciding how to implement a process improvement strategy, such as that
provided in theSEI CMM
The original COCOMO model was first published by Dr. Barry Boehm in 1981, and
reflected thesoftware development practices of the day. In the ensuing decade and a half,
software developmenttechniques changed dramatically. These changes included a move
away from mainframe overnightbatch processing to desktop-based real-time turnaround;
a greatly increased emphasis on reusing existing software and building new systems
using off-the-shelf software components; and spending as much effort to design and
manage the software development process as was once spent creating the software
product.
These changes and others began to make applying the original COCOMO model
problematic. Thesolution to the problem was to reinvent the model for the 1990s. After
several years and the combined efforts of USC-CSSE, ISR at UC Irvine, and the COCOMO
II Project Affiliate Organizations, the result is COCOMO II, a revised cost estimation
model reflecting the changes in professional software development practice that have
come about since the 1970s. This new, improved COCOMO is now ready to assist
professional software cost estimators for many years to come.

2.11Staffing Pattern

Putnam was the first to study the problem of what should be a proper staffing
pattern forsoftware projects. He extended the classical work of Norden who had
earlier investigated the
Staffing pattern of general research and development type of projects. In order to
appreciate the staffing pattern desirable for software projects, we must understand
both Norden’s and Putnam’s results.

Norden’s Work
 Nordern studied the staffing patterns of several R&D projects.
 He found the staffing patterns of R&D projects to be very different from the
manufacturingor sales type of work.
 Staffing pattern of R&D types of projects changes dynamically over time for
efficient manpower utilization.
 He concluded that staffing pattern for any R&D project can be approximated
by theRayleigh distribution curve.

Putnam’s Work

 Putnam studied the problem of staffing of software projects.


 He found that staffing pattern for software development projects has
characteristics verysimilar to R&D projects
 He adapted the Rayleigh-Norden curve to relate the no of delivered lines of
code to theeffort and the time required to develop the product.
 Initially less no of developers are needed.
 As the project progresses and more detailed work is performed, the number of
developersincreases and reaches a peak during product delivery
 After delivery, the no. of project staff falls consistently during product maintenance.