ASSIGNMENT
ASSIGNMENT
INTERNATIONAL UNIVERSITY
INDUSTRIAL ENGINEERING AND MANAGEMENT
ASSIGNMENTS
MEMBER:
LAYOUT EXERCISE
50
70
70 70
A B C
40
40
40 100 80
60
F E D
130
`
13: 125
14: 100
23: 45 125 240
24: 105 1 3 6
34: 30 100 235
35: 235 30 160
36: 240
45: 85 45 80
46: 80 2 4 5
105 85
56: 160
13: 80
15: 25
23: 30 80 40
24: 100 1 3 4
35: 75
43: 40 75 100
52: 60 30
25
5 2
60
`
(1) (2)
E A C E A C
F B D F B D
`
a.
Minimun number of workstations required = 30/10 = 3 workstations
Actual workstations are 4, number of required volunteers are 4
Actual cycle time = max (9,7,9,5) = 9 mins
Number of package can be assembled in 4-hour period = 4 hours*60 mins/ 10 mins = 24
Efficiency = 30/(4*10) = 0.75 = 75%
b.
Efficiency if volunteers are plentify = 30/(4*9) = 0.83 = 83%
Number of package can be assembled in 4-hour period = 4 hours*60 mins/ 9 mins =26.6
`
Q = 120 units
Cycle time = 40 hour *60 min /120 unit = 20 min
The number of line = 62 min / 20 min = 3.1 ~ 4 workstation
One worker is assigned to each workstation, so require 4 workers
Efficiency = 62 min / (4ws*20min) = 0.775 = 77.5%
Q = 100 units
Cycle time = 40 hour *60 min /100 unit = 24 min
The number of line = 62 min / 24 min = 3 ws
One worker is assigned to each workstation, so require 3 workers
Efficiency = 62 min / (3ws*24min) = 0.861 = 86.1%
`
A B C E F
SCHEDULING EXERCISE
Patient A - Nurse 1
Patient B - Nurse 2
Patient C - Nurse 4
Patient D - Nurse 3
b. Total combined time taken by nurses = 9 hours. However since all nurses will be working in
parallel, all would be free from their tasks at the end of 3 hours (both Nurse 1 and Nurse 3 will take 3
hrs each).
`
SPT
Due
Task Processing Time(In days) Flow Time Lateness
Date
D 3 20 3 0
H 3 50 6 0
A 5 10 11 1
C 6 15 17 2
G 7 45 24 0
B 8 15 32 17
E 10 25 42 17
H 3 50 45 0
Total 180 37
Due Date
A 5 10 5 0
B 8 15 13 0
C 6 15 19 4
D 3 20 22 2
E 10 25 32 7
F 14 40 46 6
G 7 45 53 8
H 3 50 56 6
Tota
246 33
l
Slack = Time remaining before due date - remaining processing time => Due Date - Today's date -
Processing time
Ex: For activity A, Slack = 10-4-5 = 1 Likewise, Slack for other activities are calculated and Shortest
Slack time remaining activity will be scheduled first
A 5 10 1 5 0
B 8 15 3 13 0
C 6 15 5 19 4
`
E 10 25 11 29 4
D 3 20 13 32 12
F 14 40 22 46 6
G 7 45 34 53 8
H 3 50 43 56 6
Total 253 40
I will recommend SPT as it has lowest Flow time and lowest number of tardy jobs which means
maximum number of jobs can be done on-time also Mean tardiness is almost equal to the lowest
mean tardiness
a) According to the SPT rule the job with the shortest processing time is scheduled first in the
sequence and the job with the longest processing time is scheduled last in the sequence.
Flow time is calculated as the cumulative sum of the processing time .So according to the SPT
sequence the flow time is calculated below:
Mean flow time = Sum of the flow times of each jobs / Number of jobs
= (10+25+45+75) / 4
= 155 / 4
= 38.75
Tardiness is calculated as Flow time - Due date (When the value is negative it is taken as 0)
= (0+0+25+25) / 4
= 50/4
= 12.5
b) Sequencing by SLACK
According to the Slack rule the job with the shortest slack time remaining goes first and the job with
longest slack time reamaining goes last.
According to the above formula the slack time remaining for each job is calculated below
Flow time is calculated as the cumulative sum of the processing time of the jobs according to the
Mean flow time = Sum of the flow times of each job / Number of jobs
= (20+30+45+75) / 4
= 170 / 4
= 42.5
Tardiness is calculated as Flow time - Due date (When the value is negative it is taken as 0)
So using the above formula the tardiness for each job is calculated below
`
= (0+15+15+25) / 4
= 55 / 4
= 13.75
I would reccomend the shortest processing time(SPT) sequencing rule as it has the lower mean
tardiness among the two rules
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Milling A B C D E
Grinding A B C D E
Turning A B C E
b.
A B C D E
Milling 5 2 3 1 4
Grinding 1 2 2 3 1
Turning 4 5 1 0 2
Total 10 9 6 4 7
1 2 3 4 5 6 7 8 9 1 11 12 1 14 1 16 17 1 19 2 21
0 3 5 8 0
Milling D C E E A
Grinding D C E B A
Turning C E B A
Sequence of jobs is C D B A E
Activity A B C D E
Cutting 4 6 1 2 3
Sewing 2 3 3 4 1
Schedule as per Johnson Rule
Job C D B A E
Machine 1
Start 0 1 3 9 13
End 1 3 9 13 16
Machine 2
Start 1 4 9 14 16
End 4 8 12 15 17
Idle Time 1 0 1 1 1
`
MRP EXERCISE
Gross Requirent 20 40 30 10 45
Projected available 5 0 0 0 0
Net Requirement 35 30 10 45
Reorder quantity 76
Gross Requirent 20 40 30 10 45
Projected available 5 41 11 1 32
Net Requirement 35 44
Reorder Period 3
Gross Requirent 20 40 30 10 45
Projected available 5 40 10 0 0
Net Requirement 35 30 10 45
(i) L4L
(ii) EOQ
(iii) POQ
`
a. The table is final assembly of the top (purchased), Base (assembly), and Drawer (purchased). Thus
lead time for table is 2 days. Lead time for top and Drawer is 1 day, whereas, for base takes 2 days to
assemble. The base assembly is made from two side assemblies and one back panel (purchased). The
lead time of side assembly and back panel are 2 days and 1 day respectively. The side assembly is
made from two legs (purchased), two Side panel (purchased), and two drawer guides (purchased).
`
Product (1)
d. According to Part a – chart, the lead time for the base assembly is 5 days. If the base assemblies are
in inventory, the assembly for the base assembly is not required. The Lead time for Top and Drawer is
1 day and it requires 2 days to assemble the table, thus the total lead time reduces to 3 days.
Thus, for 3 days lead time the base assembly should be kept in inventory.