PRINCE2 Foundation - Sample Paper 2 - Digital
Sample
Paper 2
Question Booklet | Multiple Choice
Examination | 1 Hour
2) Which document is used to identify interested parties that need to be informed of project
closure?
D. Project brief
Any change to the products agreed at the start of a stage is monitored as part of the [ ? ]
A. directing a project
B. controlling a stage
D. closing a project
4) Which two statements about the 'continued business justification' principle are CORRECT?
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
6) When is it confirmed whether a project's objectives have been achieved? 10) Which two statements are CORRECT about the minimum requirements for applying the
B. During the final end stage assessment 1. Identified issues must be assessed for their impact on the business justification for the
project.
C. During the 'controlling a stage' process
2. Project issues must be captured, examined and managed throughout the project lifecycle.
D. During the 'managing product delivery' process 3. The actual status of products must be verified to ensure that this matches the authorized
state.
4. A budget must be established to pay for requests for change and their analysis.
7) Which statement correctly describes project assurance and quality assurance?
A. Project assurance provides assurance to the project's stakeholders whereas quality A. 1 and 2
organization C. 3 and 4
B. They are both the responsibility of the project board, but project assurance may be D. 1 and 4
delegated
C. They are both independent of the project management team 11) Which is a purpose of the 'controlling a stage' process?
D. Project assurance and quality assurance are both the responsibility of corporate,
programme management or the customer A. To agree, perform and deliver project work
8) Identify the missing words in the following sentence. C. To agree tolerances for the stage
If a baselined product requires modification, the recommended [ ? ] procedure, or equivalent D. To take action so that the stage remains within tolerance
12) What is likely to be avoided by applying the 'tailor to suit the project' principle?
4 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 5
13) Which is a responsibility of the team manager role? 18) What makes a project a PRINCE2 project?
A. To accept authorized work packages from the project manager A. It has project processes that satisfy the objectives of PRINCE2 processes
B. To review the highlight report for the previous reporting period B. It has a permanent project organization to deliver a long-term result
C. To review the tailoring approach and its implications for project controls C. It has established technology to improve business as usual
D. To examine and escalate issues, taking necessary corrective actions D. It applies some of the PRINCE2 principles
14) In which situation might the 'controlling a stage' process be used? 19) What is risk probability?
A. To manage a long initiation stage of a complex project A. The scale of the risk should it occur
B. To manage the activities of a complex programme B. The probable effect on the project being able to deliver its objectives
C. To organize support activities following the handover of products to operations C. A probable timeframe within which the risk may occur
D. To create an exception plan to replace the current stage plan D. A measure of the likelihood of the risk occurring
15) Which is a step in PRINCE2's recommended approach to planning? 20) Which describes the 'implement' step within the recommended risk management procedure?
A. Project support allocates the risk budget to fund the selected risk responses
A. Identify activities and dependencies B. The risk owner decides the best response to control the risk
B. Describe the means of communication for the project C. The risk owner and the risk actionee carry out activities to control and deal with the risk
C. Implement responses for opportunities D. The project manager formulates the risk management approach
16) What is an advantage of applying the 'learn from experience' principle? A. To ensure that there is authority to initiate the project
A. It allows the project board to delegate cost tolerances to the project manager C. To summarize how the organization's project management method will be tailored for
B. It allows the project team to fully understand their roles and responsibilities the project
C. It allows the project manager to delegate time tolerances to the team managers D. To request authority from programme, corporate management or the customer to
D. It allows the project team to identify improvements to be made during the project deliver the project
17) Which is a responsibility of the business representative on the project board? 22) Which is a minimum requirement for applying the risk theme?
A. To set tolerance levels for the project A. To assign risk actionees to undertake planned risk responses
B. To ensure the project represents value for money B. To escalate identified threats to the project board
C. To confirm the project delivers the required functionality C. To record identified threats in a risk register
D. To check the required quality levels are achieved by the project's products D. To establish a risk budget to fund responses to risks
6 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 7
23) If a work package is forecast to exceed its tolerances, how should a team manager inform the 28) Which process provides the project board with the information it requires in order to commit
24) Who is responsible for documenting any tailoring of work packages? 29) Which two statements describe a highlight report?
B. Project manager 2. It is used by the project board to monitor the progress of the stage and project.
C. Team manager 3. It is produced by the project manager when a new risk is identified.
25) Which is a minimum requirement for applying the quality theme? A. 1 and 2
30) Which product provides the version number of all products in a particular stage?
A. To establish the mechanisms to judge whether a project is desirable and achievable A. Issue register
B. To look for ways to improve the effectiveness of the management of the project B. Product status account
C. To control uncertainty to improve the ability of the project to succeed C. Product description
A. To establish mechanisms for managing issues that may impact the baseline
D. To describe how products will be delivered that are fit for purpose
8 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 9
31) Which two statements about the risk theme are CORRECT? 35) Which is a responsibility of the change authority?
1. It identifies how to manage risks at the corporate programme management or customer B. To prepare a team plan and agree it with the project manager
2. It aims to support better decision-making through a good understanding of threats and D. To approve or reject requests for change within the delegated limits
opportunities.
3. It explains the risk management activities to use to improve the chances of a project 36) What does applying the 'manage by stages' principle ensure?
delivering its objectives. A. That the customer's quality expectations and acceptance criteria are captured and agreed
4. It identifies, assesses and controls approved changes to the baseline. B. That the project is properly initiated before work begins on delivery of the project's
outputs
A. 1 and 2 C. That the project management team understands what they are accountable for
B. 2 and 3 D. That the project is only started and continued if it is desirable, viable and achievable
C. 3 and 4
A management stage can be longer when risk is [ ? ], typically in the middle of projects.
32) What must be recorded in the project initiation documentation to meet the minimum
33) Which theme establishes mechanisms to monitor and compare actual achievements against A. The post-project benefits reviews are performed
B. Change
D. Quality A. To understand the resources and costs to deliver the project's products
34) Which role is responsible for the management of a risk assigned to it? C. To do the minimum to decide whether it is worthwhile initiating the project
A. Project support D. To create the management product required to control the project
B. Risk owner
C. Risk actionee
D. Project assurance
10 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 11
40) In a customer/supplier context, which is a responsibility of a supplier? 45) Which is a purpose of a quality management approach?
A. To deliver the benefits of the project A. To define the customer's quality expectations for the project
B. To provide the project mandate B. To define the quality standards to be applied to a project
C. To deliver the outputs of the project C. To identify the level of quality required for each of the project's products
D. To provide the requirements for the products D. To summarize the planned quality management activities
41) Which is a minimum requirement for applying the organization theme? 46) How does defining a product's quality requirements support the 'focus on products'
B. To ensure that the change authority is delegated A. By providing the project's tolerances so that authority can be delegated
C. To ensure that all the responsibilities of the project board are fulfilled B. By providing the responsibilities for the project management team
D. To ensure that the supplier resources are available C. By providing the justification for the project to be initiated
B. At the frequency agreed in the work package A. It is a method specifically designed for technical projects
C. On completion of the quality-checking activities for each product B. It promotes continual learning in organizations
A. It enables the project board to assure that there is continued business justification 48) Which roles should NOT be combined?
B. It covers the day-to-day activities of the project manager A. Project board and change authority
C. It ensures there are regular progress meetings B. Project manager and team manager
D. It begins on completion of the 'initiating a project' process C. Executive and project manager
A. To identify, assess and control uncertainty within the project 49) Which is a characteristic of a project?
B. To establish a coding system for all components of the project's products A. It is considered low risk
C. To define the means of delivering the products B. It avoids stresses and strains between organizations
12 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 13
50) Which is an objective of the 'managing a stage boundary' process? 55) When should the 'managing a stage boundary' process be undertaken?
A. To request authorization to start the next stage A. Close to the end of each management stage
B. To ensure that all threats and opportunities for the current stage have been closed B. Close to the start of each management stage
C. To ensure that work on products allocated to the team for the next stage is authorized C. At the end of the final stage
D. To implement actions to resolve tolerance deviations from the stage plan D. At the end of the 'starting up a project' process
51) In which process is authorization given to deliver the project's products? 56) What is a project outcome?
D. Directing a project C. The result of the change derived from using the project's outputs
52) Which is a minimum requirement for applying the business case theme?
A. To document the responsibility for defining the standards for the business case 57) Identify the missing words in the following sentence.
B. To appoint a senior user from an area of the business impacted by the project The six aspects of project performance to be managed are [ ? ], costs, timescales and scope.
D. To delegate the development of the business justification to the project manager B. benefits, quality, risk
53) How is the project initiation documentation used during the 'closing a project' process? D. benefits, change, quality
A. It is used as the basis for comparing the original aim of the project against what was
actually achieved 58) Which management stages must a PRINCE2 project consist of, as a minimum?
B. It provides the controls for the final stage of the project A. Starting up, initiation, and at least one other stage for the rest of the project
C. It is updated to include relevant lessons from previous projects B. At least one stage for developing products, and a closing stage
D. It provides the project product description for approval by the project board C. Initiation, and at least one other stage for the rest of the project
D. Initiation, at least one stage for developing products, and a closing stage
54) Which process aims to ensure that during the project all parties understand the project
A. Starting up a project A. All stakeholders must be identified at the start of the project
D. Managing product delivery D. All three principle categories of stakeholder have their interests represented by the
project board
14 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 15
60) What should be provided by a project mandate?
16 PRINCE2® Foundation | Copyright© PeopleCert International Ltd. PRINCE2® Foundation | Copyright© PeopleCert International Ltd. 17