3-k CHECK DAMS


Alternative Name: Grade Control BMP DESIGN APPROACH
Pollutant Source
DESCRIPTION Control
Check dams are barriers placed across swales, ditches, and other constructed Hydrologic Source
drainages to reduce channel slope and flow length. Check dams slow runoff Control
velocity and promote infiltration, thereby reducing channel erosion and serving as Stormwater Treatment
coarse sediment traps above each check dam.
SCALE OF APPLICATION
APPLICABILITY All SFR and MFR < 1
acre
 Constructed drainages on steeper slopes where runoff velocities exceed 5 feet
per second. MFR 1-5 Acre and
CICU < 5 acres
 May be placed below spillways to reduce water velocity and erosion. MFR and CICU > 5
acres and all WQIPs
 Helps establish grass linings and other vegetation in swales or drainage ditches
where erosion is a concern. TYPE OF APPLICATION
 Not applicable in natural streams except as part of an approved restoration plan. Temporary
Permanent
Advantages
 Captures the incidental discharge of sediment.
 Reduces channel down-cutting by slowing flow velocities within channels.
 Promotes runoff infiltration and sediment deposition at each check dam.
 Reduces peak stormwater runoff.

Disadvantages
 Sediment trapped behind each check dam can be re-suspended by
subsequent runoff, if not cleaned out regularly and after large storms.
 May be breached during large storms, releasing trapped sediment.
 Will reduce conveyance capacity in channel, leading to a higher probability
for flow to overtop BMP structures/facilities.
 Check dams may smother vegetation through excessive sedimentation or
long periods of submergence.

TRPA BMP Handbook Chapter 4: BMP Toolkit


May 2014 4.3-k Check Dams
Page 51
Check dams installed in water spreading area (top) and vegetated swale (bottom).

DESIGN CONSIDERATIONS
 Check dams may be installed as a temporary best management practice for
project construction or as a permanent component of a stormwater
management strategy. Porous check dams may be temporary or permanent
installations, while non-porous check dams are permanent.

Chapter 4: BMP Toolkit TRPA BMP Handbook


4.3-k Check Dams May 2014
Page 52
 Porous check dams: Low piled or stacked linear structures made of rock,
gravel, sand bags, fiber rolls, logs, pine needles, and other materials that allow
some water flow, limiting water pressure against the dam. Native rock or
wood materials found on-site may be used, if appropriate, to reduce cost.
Materials should not have the potential to be a pollutant source (e.g. low
quality sand bags, railroad ties, or other wood treated with creosote). Porous
check dams release part of the flow through the structure, reducing head of
flow over the dam and the forces against the side of the dam. Porous check
dams integrate well with vegetation in stream restoration projects.
 Solid check dams: Low grade control structures made of a non-porous
material such as concrete, metal, or masonry. These structures require design
by a licensed professional civil engineer and are more expensive to construct
than porous check dams.

 Check dams are typically installed in a series within constructed drainages for
increased effectiveness. Distance between check dams is based on channel
slope; general guidelines are as follows. Note that spacing closer than 20 feet is
not recommended to facilitate cleaning and maintenance.

Channel Slope Check Dam Spacing


1% 200 feet
2% 100 feet
4% 50 feet
6% 33 feet
8% 25 feet
10 % 20 feet

 Use check dams with caution on slopes greater than 6 percent; consider erosion
potential of bank and channel bed materials.
 The height of check dams is typically no more than 2 to 3 feet, from the toe to
the center of the check dam. The center of the check dam should be 6 inches
lower than the sides.
 Check dams should be anchored or keyed-in to the bottom and sides of the
channel with a trench and filter fabric to prevent undermining. Materials should
be extended beyond channel bank, typically one-third the width of the channel,
to prevent cutting around the dam.
 Using many small check dams within a channel is preferable to having fewer but
larger check dams; larger structures have an increased likelihood of failure with
resulting channel erosion.
INSTALLATION CONSIDERATIONS
 Locate check dams in straight reaches of channels. Washout or bank failure is
more likely if they are installed in channel bends.
 Design check dams perpendicular to the channel with a centered spillway to
ensure spilling flow is directed to the center of the channel, away from the
downstream banks. A weep hole may be added to each permanent check dam

TRPA BMP Handbook Chapter 4: BMP Toolkit


May 2014 4.3-k Check Dams
Page 53
near the bottom of the downstream face to allow the retained volume of water
to slowly drain out.
 Set the toe of the upstream dam at the same elevation as the top of the
downstream dam.
 Protect the channel downstream of each dam with a rock apron and/or filter
fabric to prevent headcutting of the channel and undercutting of the dam.
 For temporary rock check dams, use 8 to 12 inch diameter rocks. Place the rock
mechanically or by hand and avoid dumping the rock directly into the channel.
Place geotextile fabric under the rock to reestablish the natural channel bottom
when the check dam is removed.
 Construct gravel or other bagged check dams by stacking bags tightly across the
channel.
 Entrench/key-in fiber rolls into the banks and channel bottom and firmly stake
them in place (Refer to Section 4.5-q, Fiber Roll).
 Remove temporary check dams and accumulated sediment when the channel is
no longer needed.
INSPECTION AND MAINTENANCE
 Inspect temporary check dams on a regular basis (i.e. weekly) and before, during,
and after storms. Remove accumulated sediment behind each check dam when
the sediment reaches one-half the height of the dam.
 For permanent check dams, create an operation and maintenance plan that
includes regular inspections of structural integrity and removal of accumulated
sediment.
 Consider seasonal impacts. For instance, check dams will require closer scrutiny
during spring snowmelt and rain-on-snow events, or may require more frequent
cleaning in the fall from leaves and pine needles.
 Replace any missing or damaged rock, gravel bags, fiber rolls, etc., to maintain
maximum effectiveness.
EFFECTIVENESS CONSIDERATIONS
Check dams are relatively simple structures that are effective at reducing gradient,
slowing water flow, and reducing erosion and sediment transport. They must be
properly installed and regularly maintained for functionality; failed check dams are
common and may be significant sediment sources if breached.

Chapter 4: BMP Toolkit TRPA BMP Handbook


4.3-k Check Dams May 2014
Page 54
Check Dam Figure

THE TAHOE REGIONAL PLANNING AGENCY (TRPA) SHALL NOT BE RESPONSIBLE FOR THE ACCURACY OR COMPLETENESS OF ELECTRONIC COPIES OF THIS DETAIL.

TRPA BMP Handbook Chapter 4: BMP Toolkit


May 2014 4.3-k Check Dams