0% found this document useful (0 votes)
426 views3 pages

23) Tooling Management Procedure

Uploaded by

Sagar Daund
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
426 views3 pages

23) Tooling Management Procedure

Uploaded by

Sagar Daund
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Quality Assurance Procedure Doc No - REPL/QAP/TM/01

Origin Date – 01.04.2018


Tool Management Rev. No. / Date – 01/27.01.2024

1. PURPOSE
The purpose of this document is to establish and implement a system for tooling
management, including the identification, storage, retrieval and disposal of tooling’s.

2. SCOPE OF APPLICATION
This procedure applies to all tooling maintained by REPL.

3. RESPONSIBILITY
ME Manager – Tooling related activity including new tool purchase & order, approval of
new tool, tooling maintenance, disposal of NC tool.
Production In-charge – Overall responsibility for tooling’s storage and maintenance
activities.
4. DEFINITIONS AND ACRONYMS
a. Tool management - A tools management system provides a complete solution for
equipment life cycle management from procurement to usage, tools maintenance.
5. PROCEDURE
a. Tooling Manufacturing Feasibility Consideration
 During Quality Planning the quality characteristics, which have to be
controlled during production are identified.
 All tooling equipment are designed on the basis customer drawing & type of
machine. Tool development team is responsible for Tool drawing approval.
 Tools are manufactured from outsourced supplier.
 After receiving tool from supplier, tools are verified according to tool
specification as per inspection report - REPL/MD/TIR/R0
 After confirming, tools are issued to production department.

b. New Tooling Purchase


Existing tool purchase followed in below cases-

 After getting requirements from production department


 If tool life is over 80%
 If tool break
 If changes done in tooling / process
Requirements are sent to existing supplier with same design. There are one
spare tool are kept in stock.

Prepared By :- Checked By :- Approved By :-


Quality Assurance Procedure Doc No - REPL/QAP/TM/01

Origin Date – 01.04.2018


Tool Management Rev. No. / Date – 01/27.01.2024

c. Tool Identification & Storage


 Tool description as per part name & no. given in drawing.
 All Tools are stored in vertical Tool storage rack.
 There are many trays available in rack. All trays are identified with numbers.
 Tool list are displayed on each Rack.
 Whenever required particular Tool, enter the tray no according to the list.

d. Tooling Maintenance
 For the tools (Hob, Shaper, shaver, broach), tool re-sharpening frequency
decided in tool history card & Work Instruction -
REPL/MD/WI/SCTRC/R1
 Tool re-sharpening details noted in tool history card -
REPL/MD/F/FLPI/R1
 Some tools (Inserts) are replaced as per decided frequency –
REPL/MD/SOP/SOFT TURNING/R0 &
REPL/MD/SOP/HARD TURNING/R1
 Breakage tools Analysis as per work instruction - REPL/MD/WI/BT/R0

e. Non-conforming Tools
 If it is confirmed that the tool specification are outside of required accuracy,
rework of Tool at supplier scope.
 Life end tools scrap as per work instruction - REPL/MD/WI/ST/R1

f. Customer Tools management


 If Tools received from customers preserve the same Tool and follow the
Sequence – c. to e.

g. Not in use tool


 If Tools are not in use then follow WI as per REPL/WI/NIUT/01

Prepared By :- Checked By :- Approved By :-


Quality Assurance Procedure Doc No - REPL/QAP/TM/01

Origin Date – 01.04.2018


Tool Management Rev. No. / Date – 01/27.01.2024

5. REFERENCES
IATF16949:2016; Clause – 8.5.1.6

6. RECORDS
Sr. No. Description Retention Period Custodian

1 Tool inspection report REPL/MD/TIR/R0 Tooling

2 Tool history card REPL/MD/F/HLHC/R1 Tooling

7. REVISION HISTORY
REVISION HISTORY
Rev Description of Change Section Effective Date

R00 Initial release 01.04.2018

01 Rework scope of NC Tools defined as NC 5. e 27.01.2024


raised in IQA Jan. 2024

Prepared By :- Checked By :- Approved By :-