S-Loto Written Procedures
S-Loto Written Procedures
S-Loto Written Procedures
(Revised 6/18)
Introduction
During normal operation, guards must be in place to protect employees from
contacting moving or dangerous parts of machines or equipment that could lead
to entanglement, amputation/laceration, and pinching, pinning, crushing, or other
injury. However, it may be necessary to remove or inactivate guards during
maintenance and repair operations. In these situations, a lockout/tagout (LO/TO)
program must be observed, which typically includes development and
implementation of written equipment and task-specific LO/TO procedures, as well
as other program requirements. See EHS SOP, Lockout/Tagout for Machines
& Equipment: Program Overview.
Regulatory Basis
The content of this SOP and UNL’s LO/TO program is based on the
Occupational Safety and Health Administration (OSHA) general industry
standard, 29 CFR 1910.147, The Control of Hazardous Energy.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
While written procedures are not required if ALL of the above conditions are met,
all mandatory LO/TO steps must be completed in the prescribed order.
Hazard Identification
The first step in LO/TO involves identifying all forms of potentially hazardous
energy associated with the specific machinery/equipment and task at hand.
This involves evaluating and understanding all potentially hazardous energy
sources (remember, there may be more than one), including: potential magnitude
of damage and injuries that each energy source could cause, if uncontrolled; and
isolation point(s) for each type of hazardous energy. Types of energy to consider
include electrical, hydraulic, pneumatic, thermal, chemical, mechanical, gravity,
and radiation energy.
Communicate
All affected employees who work on or near machinery/equipment that is the
subject of a LO/TO procedure must be informed of the intent to apply LO/TO.
They must be advised to refrain from attempts to restart the equipment/machine
or other action that may adversely affect safety during the duration of the LO/TO.
They must be informed of the person who is responsible for the LO/TO and the
method that will be used to notify them when the LO/TO is complete.
Shut-down
Shut down must be conducted using the standard procedures established for the
machine or equipment (not emergency procedures or other shortened/simplified
method).
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
Isolate
After shutdown of the machinery/equipment, the next step is to physically locate
and operate all energy isolation devices. An energy isolation device is “a
mechanical device that, when utilized or activated, physically prevents the
transmission or release of energy, including but not limited to the following:
• A manually-operated electrical circuit breaker;
• A disconnect switch;
• A manually-operated switch by which the conductors of a circuit can be
disconnected from all ungrounded supply conductors, and, in addition, no
pole can be operated independently;
• A line valve, bolted blank flange, and bolted slip blinds;
• A block (e.g., a safety block); or
• Any similar device used to block or isolate energy.
Push-buttons, selector switches, safety interlocks and other control circuit type
devices are NOT energy isolation devices. Programmable logic controllers
(PLCs) are used in many machine applications. These circuit control devices are
NOT considered energy-isolating devices for purposes of the LO/TO standard.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
Verify
The last step to take before actually conducting the repair/service work is to
verify that the LO/TO procedures and devices have effectively isolated and de-
energized all energy sources associated with the machinery/equipment.
Verification must consider both primary and stored-energy sources. If there is
potential for build-up of energy during the service/maintenance/repair, the
verification must be on-going throughout the entire service/maintenance/repair
period.
Usually, verification must include both visual inspection and physical testing.
Visual inspection involves confirmation that switches, valves, breakers, etc. have
been properly moved to and secured in the “off” or “safe” position. Visual
inspection also verifies that LO/TO and other protective devices have been
applied to the control points in a manner that prevents unsafe movement of the
switches or valves. Additionally, a visual inspection is used to verify that isolation
has taken place by determining that all motion has stopped and all coasting parts
such as flywheels, grinding wheels, saw blades, etc. have come to rest.
Service
All service/maintenance should be conducted only by qualified individuals who
are knowledgeable of the machinery/equipment and in accordance with
manufacturer’s specifications and/or industry standards, as applicable.
Inspect
After the service/repair work is complete, and before LO/TO devices are removed
and energy is restored to machinery/equipment, the work area must be inspected
to ensure that:
• Non-essential items have been removed from the machine and operating
area;
• Machinery/equipment components are operationally intact; and
• Employees are safely positioned.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
Remove LO/TO
Once it has been determined through the inspection process that a safe condition
exists and guards have been replaced or properly re-positioned, LO/TO devices
may be removed by the authorized employee who placed them.
Communicate
Affected employees should then be notified that LO/TO devices have been
removed. This communication must occur before the equipment/machine is
restarted and only after inspection confirms a safe condition.
Restart
The machinery/equipment should be restarted using the appropriate start-up
sequence and procedures.
Written Procedures
Appendix A to this SOP contains an adaptation of OSHA’s typical, minimal
lockout procedure (29 CFR 1910.147, Appendix A), which supervisors can use
as a guide in developing written procedures.
Periodic Review
Supervisors must periodically (at least annually) review written procedures &
observe employees performing tasks to verify continued efficacy and employee
adherence to LO/TO procedures. The OSHA standard requires documentation
of such review to include:
• Date of review;
• Name of the person conducting the review;
• Identification of the machinery/equipment/procedure that was reviewed;
• Name(s) of employee(s) involved in the review (generally the name(s) of
the employee(s) who were actually implementing the procedure).
• Description of any deficiencies in the procedure or implementation of the
procedure and corrective actions taken.
The review must include discussion with “Authorized” and “Affected Employees”
to reinforce each employee’s responsibilities relative to the procedure.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
Appendix B: OSHA Typical, Minimal LO/TO Procedures
Applicability
Department
Equipment/Machine
(Name/make/model or description
(attach photo if desired, as well as
diagrams of controls, hazardous points-
of-operation, etc.).
Equipment Location
Author of this Procedure
Date of this Procedure
Purpose
This procedure establishes the minimum requirements for the lockout of energy isolating
devices whenever maintenance or servicing is done on the specified
machine/equipment. It shall be used to ensure that the machine or equipment is
stopped, isolated from all potentially hazardous energy sources, and locked out before
employees perform any servicing or maintenance where the unexpected energization or
start-up of the machine or equipment or release of stored energy could cause injury.
Sequence of Lockout
(1) Notify all affected employees (as listed below) that servicing or maintenance is
required on the machine or equipment and that the machine or equipment must be shut
down and locked out to perform the servicing or maintenance.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
(2) Identification of Hazardous Energy: Hazardous energy associated with this
machine or equipment is described below and must be known by the authorized
employee. The authorized employee must be informed of the type and magnitude of the
energy that the machine or equipment utilizes, the hazards of the energy, and the
methods to control the energy. Consider all forms of potentially hazardous energy
associated with the machine or equipment, such as: electrical, hydraulic, pneumatic,
thermal, chemical, mechanical, gravity, and radiation energy.
Hazards of the
Type of Energy
energy considering Danger Zone(s)
(e.g., chemical,
Magnitude type and magnitude and Isolation
thermal,
(e.g., electrocution, Point(s)
mechanical, etc.)
amputation, etc.)
(3) Shut-down: If the machine or equipment is operating, shut it down by the normal
stopping procedure. Types and locations of machine/equipment operating controls are
summarized below. Recommendation: Attach copy of schematic showing location of
operating controls.
(4) Isolate: De-activate the energy isolating device(s) so that the machine/equipment is
isolated from the energy source(s). Recommendation: Attach copy of schematic
showing location of energy isolating devices.
(5) Apply LO/TO. Lock out the energy isolating device(s) with assigned individual
lock(s).
(6) Relieve Stored Energy: Stored or residual energy (such as that in capacitors,
springs, elevated machine members, rotating flywheels, hydraulic systems, and air, gas,
steam, or water pressure, etc.) must be dissipated or restrained by methods such as
grounding, repositioning, blocking, bleeding down, etc.
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu
Type of Stored Energy Method to Dissipate or Restrain
(7) Verify: Ensure that the equipment is disconnected from the energy source(s) by first
checking that no personnel are exposed, then verify the isolation of the equipment as
described below (include make/model or description of test equipment). If operating
controls are activated, return them to the neutral or "off" position after verifying the
isolation of the equipment. Use visual and physical verification methods.
(9) Inspect: Check the machine or equipment and the immediate area around the
machine to ensure that nonessential items have been removed and that the machine or
equipment components are operationally intact. Check the work area to ensure that all
employees have been safely positioned or removed from the area. Verify that the
controls are in neutral and guards/interlocks/safety devices have been repositioned.
Change Summary:
Date Summary of Changes
(Created 5/11)
UNL Environmental Health and Safety · (402) 472-4925 · http://ehs.unl.edu