TRFR FAT Test Program 20240229
TRFR FAT Test Program 20240229
TRFR FAT Test Program 20240229
REVISIONS
LiangShaoHua APPROVED BY APPROVED BY LiangShaoHua DATE:24.2.28
This test procedure covers shop inspection and tests for following equipment.
Equipment
ONAN/ONAF 35MVA/50MVA
YNd1
Oil immersed transformer
Rating (specification)
Rated capacity :50MVA/50MVA
Rated frequency:50Hz
Phase:3
Rated voltage: HV(Y):132kV(﹢4-12)×1.25%
LV(△):22kV
Rated current on principal tap: HV:218.7A
LV:1312 A
Visual Inspection check of construction and external appearance of the transformer will be made according to the
1 Visual inspection outline drawing and contract specifications. Manufacturer standard
a) Maker: The test results provided by CT manufacturer shall be included in the final factory files.
Check of the ratio
and polarity of b) Before assembly: Following test or inspection items will be done. Consistent with the nameplate
2 built-in current 1. Polarity check
transformers 2. Measurement of current ratio
The voltage ratio will be measured with the RATIO TESTER. And this test will be made at all tap positions.
The check of phase displacement will be made with the RATIO TESTER at the rated tap position .
IEC 60076-1(2011)
Criteria:
Measurement of
Error of voltage ratio
voltage ratio and
3 Should be within ±0.5%;
check of phase
displacement
Voltage relations(YNd1)
The winding resistance will be measured with a resistance measuring test set on all windings at all tap positions.
Test Circuit:
Ex). Measurement of HV winding between H1-H0
Measurement of
IEC 60076-1(2011)
4 winding resistance
Reference data
Insulation resistance between core and clamp will be measured with 2500V Megger for 1min. Manufacturer Standard
Criteria:
Check of core and (1) Core ~ clamp, earth The insulation resistance should
5
frame insulation exceed 500MΩ at 20℃.
(2) Clamp ~ core ,earth
(manufacturer standard)
(3) Core ~ clamp
Dielectric dissipation factor and capacitance measurement will be made at 50Hz-10kV with AI6000-A as follows.
(1) HV winding~LV winding·Ground
(2) LV winding~ HV winding·Ground
(3) HV winding· LV winding~Ground
(4) HV winding~LV winding
Measurement of
dissipation factor IEC 60076-1 (2011)
7
and capacitance Reference data
Following test will be carried for bushings after the transformer is installed IEC 60076-1 (2011)
8 Test of Bushing Dielectric dissipation factor should
- Measurement of dissipation factor and capacitance not exceed 0.5 % at 20℃.
(Manufacturer standard)
No-load loss and excitation current will be measured at the rated frequency at 90%,100%,110% of the rated voltage
at the rated tap position
The specified voltage will be supplied on LV line terminals and HV line terminals will be left open-circuited.
3-phase excitation current with low voltage will be measured at the same time.
Test circuit:
IEC 60076-1(2011)
Technical Spec.
Criteria:
The measured values should satisfy
Measurement of the following
9 no-load loss and guaranteed values
excitation current No-load loss
At 100% rated voltage
P0≤31kW
I0≤0.3%
Criteria:
The measured values should
satisfy the following
Measurement of guaranteed values
short-circuit
11 impedance and
load loss Pk75℃ ≤186kW
ek75℃:10%±7.5%
Zero-sequence impedance measurement will be made with suitable low voltage at rated tap position as follows.
Testcircuit:
IEC 60076-1(2011)
Measurement of
Technical Spec.
12 zero-sequence
impedance
Reference data
Wave shape
Standard impulse voltage wave shape:
T1 (wave front time):1.2μs±30%, IEC 60076-3(2018)
T2 (wave tail time) :50μs±20%
Note:
Wider tolerance may be accepted, if the capacitance of the winding to earth is very high and / or the inductance is Criteria:
very low, and if the standard wave shape cannot be achieved by installation of additional resistors ( Max. 500Ω ) in The absence of significant
the non-tested windings. differences between voltage
Test tap position and current transients
Lightning impulse a). phase H1 …….maximum tap recorded at reduced voltage
13
test b). phase H2………… .rated tap and those recorded at full
c). phase H3……… minimum tap test voltage, or between voltage and
current transients recorded at the
Test sequence same voltage constitutes
evidence that the insulation
has withstood the test.
HV and LV terminals
a. one 50% reduced full wave
b. one 100% full wave
c. one 50% reduced chop wave
d. two 100% chop wave
e. two 100% full wave
HVneutral terminals
a. one 50% reduced full wave
b. three 100% full wave
IEC 60076-3(2018)
Criteria:
The absence of significant
Lightning impulse differences between voltage
Test and current transients
13 ex. Test circuit of H0 terminal
- continued - recorded at reduced voltage
and those recorded at full
test voltage, or between voltage and
current transients recorded at the
same voltage constitutes
evidence that the insulation
has withstood the test.
IEC 60076-3(2018)
Criteria:
The test is successful if
(2) LV~HV·ground
no collapse of the test
Test voltage -----44kV (50Hz) Test duration ------ 1 min.
Applied voltage voltage and earth current
14 occurs.
test
Remark
TR: Testing transformer
VD: Voltage Divider
V: Voltmeter
A: Ampere meter
Line terminal AC
withstand voltage IEC60076-3(2018)
test The test is successful if
15 no collapse of the test
voltage and earth current
occurs.
Auxiliary X1 H1
transformer
X2
~
~ X3
~ H0
H3 H2 IEC 60076-3 (2018)
C Criteria:
3φ The continuous level of partial
Induced voltage 200Hz discharge at U2 does not exceed
PT
test with partial Gen. 250pC
V
16 discharge C1 C1
measurement C2 C2
Test voltage(Phase to phase)
Ur=132kV
U1=2×Ur =264kV C1
U2=1.58×Ur =208.56kV C2
U3=1.20×Ur= 158.4kV
U1
U2 A B C D E
U3 1min 5min 60min 1min
The measurement will be made for completely assembled transformer as following conditions.
1. To measure background noise
IEC 60076-10 2016
Determination of 2. Applying the no-load voltage of the rated frequency
18 Sound press level≤77 dB
sound levels 3. At 1m away from the principal radiating surface with forced (ONAN)
4. At 2m away from the principal radiating surface with forced(ONAF2)
1.Frequency ranges---20Hz~2MHz
2. Measuring conditions
(a). HV terminals (LV terminals open circuit)
①Source: H1, Receiving: H0 ②Source: H2, Receiving: H0
③Source: H3, Receiving: H0
IEC 60076-1(2011)
3. Test circuit (ex. Between H1 to H0) IEC 60076-18(2012)
Measurement of
19 frequency response
Criteria:
Reference data
Oil test for transformer oil sample will be madeas following items:
Technical Spec.
1. Water content test 2.Dielectric strength test 3.Dissipation factor test 4.Dissolved gas analysis
Manufacturer standard
Insulation Oil Test 2. Dissolved gas analysis will be performed 4 times as follows
20 Criteria:
• At the start of the test schedule ,before dielectric test C2H2 should not be detected.
•After dielectric test,before temperature rise test
•After temperature rise test
After the transformer completely assembled, oil leakage test willbe made as follows.
Test pressure --- 0.035MPa (When completely filled with oil), applied to the top of the conservator of the IEC 60076-1(2011)
transformer. Manufacturer standard
21
Oil leak age tes t Test duration --- 24 hours
The oil leakage will be checked by touching and visually. If there are any points of suspected oil leakage, these shall Criteria: No leakage
be checked with white or other approved indicator.
IEC 60076-1(2011)
After the tap-changer fully assembled on the transformer,the following tests will be carried out.
IEC 60214-1(2003)
a.When the transformer is non-energized, 8 operation cycles should be completed under 100% rated operation
On-load Manufacturer standard
Tap-changing voltage. Criteria:
22 b. When the transformer is non-energized, 1 operation cycle should be completed under 85% rated operation voltage.
Operation Test Each item should be no trouble.
c. The transformer is on the condition of non-energized. Tap changer should complete 1 operation cycle while
Each operation test should
no-load test.
be performed without
d. 10 times tap-changing should be completed in the range of rated tapping of plus and minus 2 while load test.
failure.
Measurement of
23 the power taken by Measurement of the power and current taken by the cooling fan motors IEC 60076-1(2011)
the fans will be made at the rated voltage and rated frequency. Reference data