A Technical and Economic Assessment of CO2 Capture Technology For IGCC

Download as pdf or txt
Download as pdf or txt
You are on page 1of 293

Carnegie Mellon University

A Technical and Economic Assessment of


CO2 Capture Technology for
IGCC Power Plants

A Dissertation
Submitted in Partial Fulfillment of the Requirements
for the Degree of

Doctor of Philosophy
in
Engineering and Public Policy

by

Chao Chen

Pittsburgh, Pennsylvania
December 2005
ABSTRACT

As an emerging technology for electric power generation, Integrated Gasification

Combined Cycle (IGCC) power plants are of increasing interest because of their potential

advantage for CO2 capture in addition to conventional pollution control. To further

explore this technology, this thesis develops a general modeling framework to provide

tools for assessing gasification-based energy conversion systems with various CO2

capture options on a systematic and consistent basis.

Many factors influence the performance and cost of an IGCC power plant.

Simulation studies of an oxygen-blown Texaco quench gasifier system with a water gas

shift (WGS) reactor and Selexol CO2 capture unit indicated that the CO2 avoidance cost

is lowest when the CO2 removal efficiency is in the range of 85%-90%. The overall cost

of IGCC systems with and without CO2 and storage varied significantly with coal quality

and plant size (among other factors). For low rank coals (sub-bituminous and lignite)

costs increased significantly relative to the nominal case with bituminous coal. It was also

found that larger IGCC plants have slightly higher thermal efficiency and lower capital

cost. Without incentive financing, however, an IGCC power plant without CO2 capture

was found to be less competitive (more costly) than PC and NGCC power plants in terms

of both the total capital requirement and cost of electricity production. However, IGCC

plants with CO2 capture were competitive with PC and NGCC capture plants without

incentive financing.

This thesis also provides an overview of available options and decisions factors for

using IGCC technology to repower aging PC power plants. Studies in this thesis show

-i-
that IGCC repowering is less capital intensive than greenfield plants, but the feasibility of

repowering is very site-specific. Under suitable conditions, IGCC repowering may be an

economically attractive option for existing PC plants.

This thesis also attempts to characterize key uncertainties affecting the performance

and cost of IGCC systems with CO2 capture through data mining and Monte Carlo

simulation. Most of the capital cost uncertainty in an IGCC capture plant comes from the

IGCC process, rather than the CO2 capture process. Considering the historical variability

of capacity factor and coal price for large U.S. coal plants, the COE of an IGCC capture

plant may be higher than the expected value based on typical deterministic assumptions.

This thesis also presents preliminary evaluations of IGCC systems using two

advanced technologies, the Ion Transport Membrane (ITM) system for oxygen

production and the GE H-class gas turbine system for power generation. Study results

show that these two technologies can significantly improve the competitiveness of IGCC

systems and will influence the application of IGCC technologies in the near future.

- ii -
ACKNOWLEDGEMENTS

This thesis was written with the generous contributions of time, advice, patient

guidance and support of many people.

First, I would like to express my gratitude to my thesis advisor, Prof. Edward S.

Rubin, for his unwavering support. He met with me for countless hours to lead me

carefully towards the creation of a final piece of work. His expertise, vast knowledge,

understanding, patience and kindness added considerably to my graduate experience, and

truly made a difference in my life. I doubt that I would ever be able to convey my

appreciation fully, but I owe him my eternal gratitude.

I would like to thank the members of my committee, Professors Jay Apt, Howard J.

Herzog, and Allen L. Robinson, for their constant encouragement and feedback at all

levels of this research project. Their inputs were very helpful in fulfilling the objectives

of this research.

I also want to acknowledge the extensive contributions of the entire IECM team.

My special thanks go to Mike Berkenpas for his never-ending assistance in computer

modeling, and technical writing, and to Connie Zaremsky for her tremendous input and

help in the manuscript editing during the stressful writing-up period. I would also like to

thank Anand Rao and Sean McCoy, two PhD students in our team, for our exchanges of

knowledge, skills, and venting of frustration during my graduate program, which

enriched my experience. I would like to thank the entire Department of Engineering and

Public Policy which provided a friendly and warm environment. I am especially thankful

- iii -
to Gloria Blake, Elizabeth Ganley and Victoria Finney for their help. Thank you all,

without you all, life would have been very difficult.

I would also like to thank my whole family for the support they provided me

through my entire life and in particular, I must acknowledge my wife, Li Li, without

whose love, encouragement and support, I would not have finished this thesis.

This research was supported by the Carnegie Mellon Electricity Industry Center

(CEIC) and the U.S. Department of Energy National Energy Technology Laboratory

(DOE/NETL).

- iv -
TABLE OF CONTENTS

ABSTRACT ............................................................................................................................................ I
ACKNOWLEDGEMENTS .......................................................................................................................III
TABLE OF CONTENTS .............................................................................................................................V
LIST OF FIGURES................................................................................................................................. VIII
LIST OF TABLES...................................................................................................................................... XI
NOMENCLATURE ................................................................................................................................ XIV
CHAPTER 1. INTRODUCTION ......................................................................................................... 22
1.1. CLIMATE CHANGE AND CO2 EMISSIONS ............................................................................ 22
1.2. IGCC—A PROMISING TECHNOLOGY FOR CO2 EMISSION CONTROL................................... 24
1.3. RESEARCH MOTIVATION AND OBJECTIVES ........................................................................ 25
REFERENCES (CHAPTER 1) ................................................................................................................. 27
CHAPTER 2. THE ROLE OF IGCC POWER PLANTS FOR ABATING CO2 EMISSIONS ...... 28
2.1. OVERVIEW OF IGCC SYSTEM ........................................................................................... 28
2.2. MAJOR COMPONENTS OF AN IGCC SYSTEM ...................................................................... 30
2.2.1. Coal handling equipment................................................................................................. 31
2.2.2. Gasification technology and gasifier ............................................................................... 31
2.2.3. Air Separation Unit (ASU)............................................................................................... 44
2.2.4. Syngas cooling ................................................................................................................. 46
2.2.5. Syngas clean-up ............................................................................................................... 47
2.2.6. Combined cycle power unit.............................................................................................. 49
2.3. LITERATURE REVIEW OF CO2 CAPTURE FROM IGCC SYSTEMS ......................................... 51
REFERENCES (CHAPTER 2) ................................................................................................................. 56
CHAPTER 3. PERFORMANCE AND ECONOMIC SIMULATION MODEL OF IGCC
SYSTEMS....................................................................................................................... 59
3.1. MODEL DESIGN BASIS ....................................................................................................... 59
3.1.1. Gasification technology selection .................................................................................... 61
3.1.2. Air separation unit ........................................................................................................... 61
3.1.3. Syngas clean up system.................................................................................................... 62
3.1.4. Gas turbine selection and steam cycle design.................................................................. 63
3.2. MAJOR PROCESS SECTIONS OF THE IGCC MODEL ............................................................. 64
3.2.1. Coal slurry preparation and gasification flowsheet ........................................................ 65
3.2.2. Low temperature gas cooling and clean up ..................................................................... 70
3.2.3. H2S capture and sulfur recovery section.......................................................................... 76
3.2.4. Clean syngas saturation, expend, and reheat section ...................................................... 81
3.2.5. Gas turbine section .......................................................................................................... 83
3.2.6. Steam cycle section .......................................................................................................... 88
3.2.7. Convergence sequence of the IGCC model...................................................................... 95
3.3. IGCC COST MODEL.......................................................................................................... 96
3.3.1. Oxidant Feed Section....................................................................................................... 97
3.3.2. Coal Handling Section and Slurry Preparation............................................................... 99
3.3.3. Gasification Section ....................................................................................................... 100
3.3.4. Low temperature gas cooling......................................................................................... 101
3.3.5. Selexol Section ............................................................................................................... 102
3.3.6. Claus sulfur recovery Section ........................................................................................ 103
3.3.7. Beavon-Stretford Tail Gas Removal Section.................................................................. 103
3.3.8. Boiler Feedwater System ............................................................................................... 104

-v-
3.3.9. Process Condensate Treatment...................................................................................... 105
3.3.10. Gas Turbine Section....................................................................................................... 105
3.3.11. Heat Recovery Steam Generator.................................................................................... 106
3.3.12. Steam Turbine ................................................................................................................ 107
3.3.13. General Facilities .......................................................................................................... 108
3.3.14. Total Capital Requirement of IGCC systems ................................................................. 108
REFERENCES (CHAPTER 3) ............................................................................................................... 113
CHAPTER 4. PERFORMANCE AND COST MODEL OF WATER GAS SHIFT REACTION
SYSTEM....................................................................................................................... 115
4.1. INTRODUCTION ............................................................................................................... 115
4.2. EFFECTS OF OPERATION TEMPERATURE AND TWO-STAGE SHIFT REACTION SYSTEM ....... 116
4.3. CLEAN SHIFT CATALYSTS ............................................................................................... 117
4.4. SULFUR TOLERANCE SHIFT CATALYSTS .......................................................................... 119
4.5. PERFORMANCE MODEL OF THE WATER-GAS SHIFT REACTION PROCESS ........................... 120
4.5.1. Input and output parameters of the WGS performance model....................................... 123
4.5.2. Performance model output............................................................................................. 123
4.6. COST MODEL OF WGS REACTION PROCESS ..................................................................... 129
4.6.1. Process facility cost ....................................................................................................... 129
4.6.2. Total capital requirement of WGS reaction system ....................................................... 133
REFERENCES (CHAPTER 4) ............................................................................................................... 134
CHAPTER 5. PERFORMANCE AND COST MODEL OF SELEXOL PROCESS FOR CO2
CAPTURE .................................................................................................................... 135
5.1. INTRODUCTION TO THE SELEXOL ABSORPTION PROCESS ................................................ 135
5.2. SELEXOL SOLVENT PROPERTY ........................................................................................ 137
5.3. TECHNICAL OVERVIEW SELEXOL PROCESS FOR ACID GAS REMOVAL ............................. 140
5.3.1. Selexol process for selective H2S removal ..................................................................... 141
5.3.2. Selexol process for H2S and CO2 removal ..................................................................... 142
5.3.3. An optimal design for Selexol process for sulfur and CO2 capture from IGCC systems 143
5.4. PERFORMANCE MODEL OF SELEXOL PROCESS ................................................................ 147
5.4.1. Performance model of Selexol process for CO2 capture................................................ 148
5.4.2. Power consumption model of Selexol process ............................................................... 157
5.5. COST MODEL OF THE SELEXOL PROCESS ......................................................................... 162
5.5.1. Process facility costs of the Selexol system for CO2 capture ......................................... 162
5.5.2. Total Capital Requirement of the Selexol process ......................................................... 169
REFERENCES (CHAPTER 5) ............................................................................................................... 171
CHAPTER 6. GREENFIELD IGCC POWER PLANT WITH AND WITHOUT CO2 CAPUTRE
....................................................................................................................................... 172
6.1. THE EFFECTS OF COAL TYPES ON IGCC PERFORMANCE .................................................. 173
6.2. EFFECTS OF CO2 CAPTURE EFFICIENCY ........................................................................... 181
6.3. EFFECTS OF PLANT SIZE .................................................................................................. 188
6.4. FINANCE ANALYSIS OF IGCC SYSTEMS .......................................................................... 190
REFERENCES (CHAPTER 6) ............................................................................................................... 199
CHAPTER 7. IGCC REPOWERING WITH CO2 CAPTURE ....................................................... 200
7.1. IGCC REPOWERING OPTIONS .......................................................................................... 201
7.1.1. Site Repowering ............................................................................................................. 201
7.1.2. Feedwater heating repowering ...................................................................................... 202
7.1.3. Boiler windbox repowering............................................................................................ 202
7.1.4. Heat recovery repowering ............................................................................................. 203
7.1.5. Evaluation of repowering options.................................................................................. 203
7.2. DECISION FACTORS FOR IGCC REPOWERING .................................................................. 204

- vi -
7.3. HEAT RECOVERY REPOWERING DESIGN .......................................................................... 206
7.4. IGCC REPOWERING ECONOMIC AND PERFORMANCE ANALYSIS ...................................... 211
REFERENCES (CHAPTER 7) ............................................................................................................... 216
CHAPTER 8. PERFORMANCE AND COST UNCERTAINTY ANALYSIS OF IGCC SYSTEMS
....................................................................................................................................... 217
8.1. METHODOLOGY FOR UNCERTAINTY ANALYSIS ............................................................... 218
8.2. PROBABILITY DISTRIBUTION ESTIMATION OF UNCERTAINTY PARAMETERS ..................... 219
8.2.1. Data visualization .......................................................................................................... 220
8.2.2. Probability distribution selection................................................................................... 220
8.2.3. Distribution functions of uncertain parameters ............................................................. 222
8.3. UNCERTAINTY ANALYSIS RESULTS ................................................................................. 226
REFERENCES (CHAPTER 8) ............................................................................................................... 231
CHAPTER 9. IGCC SYSTEMS WITH ADVANCED TECHNOLOGIES .................................... 233
9.1. ION TRANSPORTATION MEMBRANE (ITM)-BASED AIR SEPARATION UNIT .................... 234
9.2. GE H-CLASS TURBINES ................................................................................................... 237
9.3. IGCC SYSTEMS WITH ITM OXYGEN PRODUCTION .......................................................... 239
9.3.1. ITM performance model ................................................................................................ 239
9.3.2. IGCC designs with ITM air separation.......................................................................... 243
9.4. IGCC SYSTEMS USING GE H TURBINE ............................................................................ 248
9.5. IGCC SYSTEM WITH ITM AND H TURBINE ..................................................................... 250
REFERENCES (CHAPTER 9) ............................................................................................................... 253
CHAPTER 10. CONCLUSION ............................................................................................................ 254
10.1. MODEL DEVELOPMENT ................................................................................................... 254
10.2. MODEL APPLICATIONS .................................................................................................... 255
10.2.1. Greenfield IGCC plants ................................................................................................. 255
10.2.2. IGCC Repowering.......................................................................................................... 257
10.2.3. Uncertainty analysis of IGCC systems........................................................................... 258
10.2.4. IGCC with advanced technologies................................................................................. 258
10.3. SOME CONSIDERATIONS ABOUT FUTURE WORK .............................................................. 259
APPENDIX A. CO CONVERSION EFFICIENCY OF THE WGS REACTION ........................... 261
APPENDIX B. METHODOLOGY FOR CALCULATING THE CATALYST VOLUME OF THE
WGS REACTION........................................................................................................ 264
REFERENCES (APPENDIX B) ............................................................................................................. 269
APPENDIX C. CALCULATION PROCESS OF THE WGS REACTION SYSTEM .................... 270
APPENDIX D. CALCULATION PROCESS OF THE SELEXOL SYSTEM FOR CO2 CAPTURE
....................................................................................................................................... 276
APPENDIX E. PRELIMINARY DISTRIBUTIONS OF UNCERTAIN PARAMETERS.............. 284
REFERENCES (APPENDIX E) ............................................................................................................. 290

- vii -
LIST OF FIGURES

FIGURE 2 - 1 SIMPLIFIED PROCESS OF AN IGCC POWER PLANT [BROWN, 2003].................................... 30


FIGURE 2 - 2 SIMPLIFIED PROCESS OF THE LURGI DRY-ASH GASIFIER [BROWN, 2003] .......................... 34
FIGURE 2 - 3 SIMPLIFIED PROCESS OF THE KRW GASIFIER [BROWN, 2003] .......................................... 38
FIGURE 2 - 4 TEXACO GASIFIER WITH RADIANT SYNGAS COOLERS [BROWN, 2003] .............................. 41
FIGURE 3 - 1 AN IGCC SYSTEM WITHOUT CO2 CAPTURE ...................................................................... 60
FIGURE 3 - 2 AN IGCC SYSTEM WITH CO2 CAPTURE............................................................................. 60
FIGURE 3 - 3 SLURRY PREPARATION AND GASIFICATION FLOWSHEET ................................................... 66
FIGURE 3 - 4 SYNGAS COOLING SECTION FLOWSHEET OF THE REFERENCE PLANT ................................. 72
FIGURE 3 - 5 SYNGAS COOLING SECTION FLOWSHEET OF THE CAPTURE PLANT ..................................... 75
FIGURE 3 - 6 SULFUR REMOVAL AND RECOVERY SECTION FLOWSHEET ................................................. 80
FIGURE 3 - 7 FUEL SATURATION AND REHEAT SECTION FLOWSHEET OF THE REFERENCE PLANT ........... 82
FIGURE 3 - 8 CO2 CAPTURE, FUEL SATURATION, AND REHEAT SECTION FLOWSHEET OF THE CAPTURE
IGCC POWER PLANT ......................................................................................................... 83
FIGURE 3 - 9 GAS TURBINE SECTION FLOWSHEET .................................................................................. 86
FIGURE 3 - 10 GE 7FA GAS TURBINE AND STEAM CYCLE SECTION FLOWSHEET ...................................... 90
FIGURE 3 - 11 TYPICAL EXHAUST GAS TEMPERATURE PROFILE OF ONE PRESSURE SYSTEM ..................... 94
FIGURE 3 - 12 TYPICAL EXHAUST GAS/STEAM CYCLE TEMPERATURE PROFILE FOR THREE-PRESSURE
REHEAT HRSG SYSTEM .................................................................................................... 95
FIGURE 3 - 13 OXYGEN FLOW RATE VS. OXIDANT FEED SECTION COST ................................................... 98
FIGURE 3 - 14 COAL HANDLING SECTION COST VS. COAL FEED FLOW RATE........................................... 100
FIGURE 3 - 15 COAL FLOW RATE VS. GASIFIER COST ............................................................................. 101
FIGURE 3 - 16 LOW TEMPERATURE GAS COOLING SYSTEM COST VS. THE SYNGAS FLOW RATE .............. 102
FIGURE 3 - 17 GAS TURBINE COST VS. GAS TURBINE NET OUTPUT ......................................................... 106
FIGURE 3 - 18 STEAM TURBINE COST VS. STEAM TURBINE NET POWER OUTPUT .................................... 107
FIGURE 4 - 1 EFFECTS OF TEMPERATURE AND CO/STEAM ON THE CO CONVERSION OF THE WGS
REACTION (THIS FIGURE IS DERIVED BASED ON THAT THE ORIGINAL MOLAR
CONCENTRATION RATIOS OF CO TO H2O ARE 1.5, 2, 2.5, AND 3, AND THE ORIGINAL
CONCENTRATIONS OF CO2 AND H2 EQUAL ZERO) ........................................................... 115
FIGURE 4 - 2 TYPICAL CO VARIATION IN HIGH TEMPERATURE SHIFT AND LOW TEMPERATURE SHIFT
CATALYST BEDS [FRANK, 2003A] ................................................................................... 117
FIGURE 4 - 3 COAL GASIFICATION SYSTEM WITH A CLEAN WATER GAS SHIFT REACTION..................... 118
FIGURE 4 - 4 SCHEMATIC PROCESS OF A GASIFIER SYSTEM WITH A SOUR SHIFT................................... 120
FIGURE 4 - 5 MASS AND ENERGY FLOW OF THE WATER GAS SHIFT REACTION SYSTEM ........................ 122
FIGURE 5 - 1 CHARACTERISTICS FOR CHEMICAL AND PHYSICAL SOLVENTS [SCIAMANNA, 1988] ...... 138
FIGURE 5 - 2 SELEXOL FLOW DIAGRAM FOR SELECTIVE H2S REMOVAL [KUBEK, 2000] .................... 141
FIGURE 5 - 3 SELEXOL PROCESS FOR SULFUR AND CO2 REMOVAL [KOHL, 1985] .............................. 142
FIGURE 5 - 4 OPTIMIZED SELEXOL ABSORPTION PROCESS FOR H2S REMOVAL .................................... 144
FIGURE 5 - 5 OPTIMIZED H2S SOLVENT REGENERATION ..................................................................... 145
FIGURE 5 - 6 OPTIMIZED SELEXOL PROCESS FOR CO2 ABSORPTION .................................................... 146
FIGURE 5 - 7 OPTIMIZED SELEXOL REGENERATION THROUGH CO2 FLASH .......................................... 147
FIGURE 5 - 8 SIMPLIFIED SELEXOL PROCESS ....................................................................................... 150
FIGURE 5 - 9 CALCULATION PROCESS FOR THE FLOW RATE OF SELEXOL............................................. 155
FIGURE 5 - 10 CALCULATION PROCESS FOR THE OPERATING PRESSURE OF THE SUMP TANK ................. 157
FIGURE 6 - 1 EFFECT OF WATER PERCENTAGE IN SLURRY ON IGCC PERFORMANCE............................ 175
FIGURE 6 - 2 EFFECT OF WATER PERCENTAGE IN SLURRY ON TCR AND COE ..................................... 176
FIGURE 6 - 3 EFFECT OF COAL RANK ON THE EFFICIENCY AND HEAT RATE OF IGCC PLANTS .............. 178
FIGURE 6 - 4 THE EFFECT OF COAL RANK ON THE TCR AND COE OF IGCC PLANTS (FOR THE COE
CALCULATION, THE COAL PRICE RATIOS BASED ON THE ACTUAL MINE MONTH COAL PRICE
ARE: PITTSBURGH #8: ILLINOIS #6: PRB: ND LIGNITE=1:0.667:0.2:0.265) ................... 179
FIGURE 6 - 5 RELATIVE OXYGEN AND COAL MASS FLOW RATE PER MWH POWER GENERATION ......... 180
FIGURE 6 - 6 RELATIVE CO2 EMISSION FOR PER MWH POWER GENERATION ....................................... 180
FIGURE 6 - 7 POWER REQUIREMENT AND CAPITAL COST OF SELEXOL PROCESS FOR CO2 CAPTURE ..... 182
FIGURE 6 - 8 THERMAL EFFICIENCY OF IGCC POWER PLANTS WITH CO2 CAPTURE............................. 183

- viii -
FIGURE 6 - 9 ENERGY PENALTY FOR CO2 REMOVAL (THE THERMAL EFFICIENCY OF THE IGCC
REFERENCE PLANT WITHOUT IN THIS CASE IS 0.371)....................................................... 184
FIGURE 6 - 10 TOTAL CAPITAL COST OF AN IGCC POWER PLANT WITH CO2 CAPTURE .......................... 185
FIGURE 6 - 11TOTAL CAPITAL COST INCREASE PERCENTAGE OF IGCC POWER PLANTS WITH CO2 CAPTURE
(THE TOTAL CAPITAL REQUIREMENT OF THE REFERENCE PLANT IS 1547 $/KW IN THIS
STUDY) ........................................................................................................................... 185
FIGURE 6 - 12 COE INCREASE PERCENTAGE OF IGCC PLANTS WITH CO2 CAPTURE (IN THIS CASE, THE
COE OF THE REFERENCE PLANT IS 56 $/MWH) .............................................................. 186
FIGURE 6 - 13 CO2 AVOIDANCE COST OF IGCC PLANTS ........................................................................ 187
FIGURE 6 - 14 CO2 EMISSION RATE OF THE CAPTURE IGCC PLANT ....................................................... 188
FIGURE 6 - 15 COST OF ELECTRICITY, THERMAL EFFICIENCY AND TOTAL CAPITAL REQUIREMENT OF
DIFFERENT SIZE IGCC PLANTS WITHOUT CO2 CAPTURE ................................................. 189
FIGURE 6 - 16 COST OF ELECTRICITY, THERMAL EFFICIENCY, AND TOTAL CAPITAL REQUIREMENT OF
DIFFERENT SIZE IGCC PLANTS WITH CO2 CAPTURE (THE COE OF THE CAPTURE PLANT
INCLUDES THE CO2 TRANSPORTATION AND STORAGE COST AT A VALUE OF 10 $/TONNE-
CO2) ............................................................................................................................... 190
FIGURE 6 - 17 EFFECT OF PLANT SIZE ON THE CO2 AVOIDANCE COST ................................................... 190
FIGURE 6 - 18 TOTAL CAPITAL REQUIREMENT OF THE IGCC AND PC PLANT BASED ON DIFFERENT
CAPITAL STRUCTURES ..................................................................................................... 195
FIGURE 6 - 19 COST OF ELECTRICITY OF IGCC PLANT WITH DIFFERENT CAPITAL STRUCTURES ............ 196
FIGURE 6 - 20 TOTAL CAPITAL REQUIREMENT OF IGCC AND PC CAPTURE PLANTS UNDER DIFFERENT
CAPITAL STRUCTURES ..................................................................................................... 196
FIGURE 6 - 21 COE OF IGCC, PC AND NGCC CAPTURE PLANTS WITH DIFFERENT CAPITAL STRUCTURES
....................................................................................................................................... 197
FIGURE 7 - 1 ONE-PRESSURE, NON-REHEAT STEAM CYCLE WITH STEAM EXTRACTION FOR FEEDWATER
HEATING ......................................................................................................................... 207
FIGURE 7 - 2 TWO-PRESSURE, NON-REHEAT STEAM CYCLE WITH STEAM EXTRACTION FOR FEEDWATER
HEATING ......................................................................................................................... 208
FIGURE 7 - 3 THREE-PRESSURE, REHEAT STEAM CYCLE WITH STEAM EXTRACTION FOR FEEDWATER
HEATING ......................................................................................................................... 208
FIGURE 7 - 4 IGCC REPOWERING WITH ALL FEEDWATER HEATERS (MINIMUM REPOWERING ) ............ 210
FIGURE 7 - 5 IGCC REPOWERING WITH REMOVING SOME FEEDWATER HEATERS (MEDIUM REPOWERING)
....................................................................................................................................... 211
FIGURE 7 - 6 IGCC REPOWERING WITHOUT FEEDWATER HEATERS (MAXIMUM REPOWERING CASE) ... 211
FIGURE 7 - 7 CO2 AVOIDANCE COST OF IGCC REPOWERING PLANTS (THE GREENFIELD IGCC PLANT
WITHOUT CO2 CAPTURE IS USED AS THE REFERENCE PLANT TO CALCULATE THE CO2
AVOIDANCE COST. FULL CAPTURE REFERS TO CO2 CAPTURE, COMPRESSION, TRANSPORT
AND STORAGE; W/O T&S REFERS TO CO2 CAPTURE AND COMPRESSION WITHOUT
TRANSPORT AND STORAGE; W/O COMP. REFERS TO CO2 CAPTURE WITHOUT TRANSPORT,
COMPRESSION AND STORAGE)......................................................................................... 214
FIGURE 8 - 1 EMPIRICAL CUMULATIVE DISTRIBUTION FUNCTIONS OF THE CAPACITY FACTOR DATA AND
THE DISTRIBUTION OF THE WEIBULL(8.5, 0.81) WITH TRUNC(0, 1)................................. 224
FIGURE 8 - 2 CENTRAL APPALACHIAN COAL PRICE IN THE NEW YORK MERCANTILE EXCHANGE (THE
ORIGINAL COAL PRICES WERE GIVEN FOR JULY OF EACH YEAR; THE PRICES SHOWN HERE
WERE INFLATION ADJUSTED TO THE DOLLAR VALUE IN 2000) ........................................ 225
FIGURE 8 - 3 COMPARISON OF EMPIRICAL CUMULATIVE DISTRIBUTION FUNCTION OF CENTRAL
APPALACHIAN COAL PRICE DATA WITH THE DISTRIBUTION OF LOGNORMAL(1.169, 0.273)
....................................................................................................................................... 226
FIGURE 8 - 4 CUMULATIVE DISTRIBUTIONS OF THE TOTAL CAPITAL REQUIREMENT OF THE IGCC PLANT
(UNC. OF CAP. PROCESS IS GIVEN BY TABLE E-2; UNC. OF IGCC IS GIVEN BY TABLE E-1 IN
APPENDIX E; ALL FACTORS TAKE INTO ACCOUNT THE UNCERTAINTIES FROM TABLE E-1
AND E-2)......................................................................................................................... 227
FIGURE 8 - 5 CUMULATIVE DISTRIBUTION OF THE COST OF ELECTRICITY OF THE IGCC PLANT ........... 228
FIGURE 8 - 6 CUMULATIVE DISTRIBUTION OF THE CO2 AVOIDANCE COST ........................................... 230
FIGURE 9 - 1 SEPARATION MECHANISM OF MEMBRANE-BASED OXYGEN PRODUCTION [MATHIEU, 2002]
....................................................................................................................................... 235

- ix -
FIGURE 9 - 2 PROCESS TEMPERATURE AND OXYGEN PURITY OF DIFFERENT AIR SEPARATION
TECHNOLOGIES [PRASAS, 2002] ..................................................................................... 236
FIGURE 9 - 3 SIMPLIFIED SCHEMATIC PROCESS OF AN ITM UNIT ......................................................... 240
FIGURE 9 - 4 OVERVIEW OF AN IGCC SYSTEM FULLY INTEGRATING WITH THE ITM OXYGEN
PRODUCTION ................................................................................................................... 245
FIGURE 9 - 5 OVERVIEW OF AN IGCC SYSTEM WITH STANDALONE ITM OXYGEN PRODUCTION ......... 246
FIGURE 9 - 6 COMBINED POWER BLOCK CYCLE WITH GE H TURBINE [MATTA, 2000]......................... 249

-x-
LIST OF TABLES

TABLE 2 - 1 MAJOR MILESTONES OF THE HISTORY OF IGCC DEVELOPMENT (SOURCE: GE WEBPAGE) 29


TABLE 2 - 2 IMPORTANT CHARACTERISTICS OF THREE TYPES OF GASIFIERS [BROWN, 2003] ............... 42
TABLE 2 - 3 COMPARISON OF PARAMETERS OF GASIFICATION TECHNOLOGIES [U.K. DEPARTMENT OF
TRADE AND INDUSTRY, 1998] .......................................................................................... 43
TABLE 2 - 4 CLASSIFICATION OF FUEL GASES [FOSTER, 2003] ............................................................. 50
TABLE 3 - 1 STEAM AND GAS PRODUCT LINE STEAM TURBINE THROTTLE AND ADMISSION STEAM
CONDITIONS ...................................................................................................................... 64
TABLE 3 - 2 COAL COMPOSITION AND ITS CORRESPONDING INPUT IN ASPEN PLUS .............................. 66
TABLE 3 - 3 COAL SLURRY PREPARATION AND GASIFICATION PROCESS UNIT DESCRIPTION. ................ 69
TABLE 3 - 4 SYNGAS COOLING PROCESS UNIT DESCRIPTION OF THE REFERENCE PLANT ....................... 71
TABLE 3 - 5 SYNGAS COOLING PROCESS UNIT DESCRIPTION OF THE CAPTURE PLANT........................... 74
TABLE 3 - 6 SULFUR REMOVAL AND RECOVERY UNIT DESCRIPTION ..................................................... 79
TABLE 3 - 7 SULFUR REMOVAL AND RECOVERY UNIT DESCRIPTION ..................................................... 82
TABLE 3 - 8 GAS TURBINE UNIT DESCRIPTION ...................................................................................... 87
TABLE 3 - 9 STAG PRODUCT LINE STEAM TURBINE THROTTLE AND ADMISSION STEAM CONDITIONS .. 88
TABLE 3 - 10 STEAM CYCLE SECTION UNIT DESCRIPTION ....................................................................... 91
TABLE 3 - 11 REFERENCES USED FOR UPDATING THE IGCC COST MODEL ............................................. 96
TABLE 3 - 12 IGCC SYSTEM PROCESS AREAS ......................................................................................... 97
TABLE 3 - 13 PROCESS CONTINGENCY OF COST SECTIONS.................................................................... 110
TABLE 3 - 14 CAPITAL COST ELEMENTS OF AN IGCC POWER PLANT.................................................... 111
TABLE 3 - 15 UNIT COSTS OF CONSUMABLES (SOURCE: IECM MANUAL) ............................................ 112
TABLE 4 - 1 RANGE OF MODEL PARAMETER VALUES FOR THE WGS REACTION SYSTEM .................... 123
TABLE 4 - 2 INPUT AND OUTPUT PARAMETERS OF THE WGS REACTION SYSTEM ............................... 123
TABLE 4 - 3 WATER GAS SHIFT REACTOR COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000
[DOCTOR, 1996] ............................................................................................................. 130
TABLE 4 - 4 GAS-LIQUID HEAT EXCHANGER COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000
[DOCTOR, 1996] ............................................................................................................. 131
TABLE 4 - 5 GAS-GAS HEAT EXCHANGER COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000
[DOCTOR, 1996] ............................................................................................................. 132
TABLE 4 - 6 COST PARAMETERS OF WATER GAS SHIFT PROCESS......................................................... 133
TABLE 5 - 1 PROPERTY OF GLYCOL SOLVENT ..................................................................................... 137
TABLE 5 - 2 RELATIVE SOLUBILITY OF GASES IN SELEXOL SOLVENT [DOCTOR, 1994] ...................... 139
TABLE 5 - 3 SOLUBILITY OF GASES IN THE SELEXOL SOLVENT [KORENS, 2002] ............................... 139
TABLE 5 - 4 INPUT AND OUTPUT PARAMETERS OF SELEXOL MODEL................................................... 149
TABLE 5 - 5 SPECIFIC HEAT OF GASES IN THE SYNGAS ........................................................................ 151
TABLE 5 - 6 SOLUTION HEAT (BTU/LB-SOLUTE) OF GASES IN THE SELEXOL....................................... 152
TABLE 5 - 7 ABSORBER COST DATA ADJUSTED TO THE DOLLAR VALUES IN 2000 [DOCTOR, 1996].... 163
TABLE 5 - 8 POWER RECOVERY TURBINE COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000
[DOCTOR, 1996] ............................................................................................................. 164
TABLE 5 - 9 SUMP TANK COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR, 1996] .... 165
TABLE 5 - 10 RECYCLE COMPRESSOR COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR,
1996] .............................................................................................................................. 165
TABLE 5 - 11 SELEXOL PUMP COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR, 1996] 166
TABLE 5 - 12 CO2 COMPRESSOR COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR, 1996]
....................................................................................................................................... 166
TABLE 5 - 13 CO2 FINAL COMPRESSOR COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR,
1996] .............................................................................................................................. 167
TABLE 5 - 14 REFRIGERATION UNIT COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR,
1996] .............................................................................................................................. 168
TABLE 5 - 15 FLASH TANK COST DATA ADJUSTED TO THE DOLLAR VALUE IN 2000 [DOCTOR, 1996]... 169
TABLE 5 - 16 PARAMETERS FOR TCR OF SELEXOL PROCESS................................................................ 170
TABLE 6 - 1 TECHNICAL DESIGN ASSUMPTION OF THE IGCC POWER PLANT ...................................... 172
TABLE 6 - 2 ECONOMIC AND FINANCIAL ASSUMPTION OF THE IGCC POWER PLANT .......................... 172

- xi -
TABLE 6 - 3 COMPOSITIONS OF THE FOUR COALS AND THEIR WATER PERCENTAGE IN SLURRY .......... 177
TABLE 6 - 4 CAPITAL STRUCTURE OF A TYPICAL POWER PLANT PROJECT (SOURCE: IECM MANUAL) 191
TABLE 6 - 5 CAPITAL STRUCTURES AND COST OF CAPITAL FOR IGCC FINANCING ............................. 193
TABLE 7 - 1 ECONOMIC AND FINANCIAL ASSUMPTION FOR REPOWERING STUDIES ............................. 212
TABLE 7 - 2 STUDY RESULTS OF IGCC REPOWERING WITH AND WITHOUT CO2 CAPTURE .................. 213
TABLE 8 - 1 STATISTICAL DESCRIPTION OF POWER PLANT CAPACITY FACTOR DATA AND THE FITTED
WEIBULL DISTRIBUTION ................................................................................................. 223
TABLE 8 - 2 STATISTIC DESCRIPTION OF COAL PRICE DATA AND THE FITTED LOGNORMAL DISTRIBUTION
....................................................................................................................................... 225
TABLE 9 - 1 PERFORMANCE CHARACTERISTICS OF H-CLASS AND F-CLASS TURBINES [MATTA, 2000]239
TABLE 9 - 2 RECOMMENDED OPERATING PARAMETERS FOR ITM OXYGEN PROCESS DESIGN [AIR
PRODUCT, 2002]............................................................................................................. 242
TABLE 9 - 3 DESIGN PARAMETERS OF ITM UNITS IN THE ASPEN SIMULATION MODELS ..................... 244
TABLE 9 - 4 PERFORMANCE AND COST COMPARISON OF IGCC REFERENCE PLANTS WITH ITM ......... 247
TABLE 9 - 5 PERFORMANCE AND COST COMPARISON OF IGCC CAPTURE PLANT WITH ITM............... 248
TABLE 9 - 6 STEAM CYCLE PARAMETERS OF THE IGCC USING GE H TURBINE .................................. 249
TABLE 9 - 7 PERFORMANCE AND COST COMPARISON OF IGCC REFERENCE PLANTS USING DIFFERENT
GAS TURBINES................................................................................................................. 250
TABLE 9 - 8 PERFORMANCE AND COST COMPARISON OF IGCC CAPTURE PLANTS USING DIFFERENT GAS
TURBINES ........................................................................................................................ 250
TABLE 9 - 9 PERFORMANCE AND COST IMPROVEMENT OF THE IGCC REFERENCE PLANT USING ITM
AND GE 7H TURBINE ...................................................................................................... 251
TABLE 9 - 10 PERFORMANCE AND COST IMPROVEMENT OF THE IGCC CAPTURE PLANT USING ITM AND
GE 7H TURBINE .............................................................................................................. 252
TABLE C - 1 INPUT PARAMETERS OF THE WGS MODEL ...................................................................... 270
TABLE C - 2 CALCULATION OF THE CO CONVERSION EFFICIENCY IN THE HIGH TEMPERATURE REACTOR
....................................................................................................................................... 271
TABLE C - 3 CALCULATION OF THE CO CONVERSION EFFICIENCY IN THE LOW TEMPERATURE REACTOR
....................................................................................................................................... 271
TABLE C - 4 SYNGAS COMPOSITIONS FROM THE HIGH TEMPERATURE REACTOR ................................. 272
TABLE C - 5 SYNGAS COMPOSITIONS FROM THE LOW TEMPERATURE REACTOR.................................. 273
TABLE C - 6 CALCULATION OF CATALYST VOLUME AND PFC OF THE HIGH TEMPERATURE REACTOR 274
TABLE C - 7 CALCULATION OF CATALYST VOLUME AND PFC OF THE LOW TEMPERATURE REACTOR . 274
TABLE C - 8 PROCESS FACILITY COSTS OF THE HEAT EXCHANGERS .................................................... 275
TABLE D - 1 SELEXOL PROPERTIES FOR CALCULATION ....................................................................... 276
TABLE D - 2 PROPERTIES OF GASES IN SYNGAS ................................................................................... 276
TABLE D - 3 COMPOSITION OF SYNGAS BEFORE CO2 CAPTURE ........................................................... 277
TABLE D - 4 ASSUMPTION FOR POWER CONSUMPTION CALCULATION ................................................ 277
TABLE D - 5 CO2 CAPTURE EFFICIENCY AND FLASHING TANK PRESSURES .......................................... 277
TABLE D - 6 CO2 CAPTURE AMOUNT REQUIRED BY CAPTURE EFFICIENCY .......................................... 278
TABLE D - 7 CALCULATING THE FLOW RATE OF SELEXOL SOLVENT ................................................... 278
TABLE D - 8 CALCULATION OF THE OPERATING PRESSURE OF SUMP TANK ......................................... 279
TABLE D - 9 CALCULATION THE TEMPERATURE CHANGE OF SELEXOL DUE TO CO2 RELEASE FROM
FLASH TANK.................................................................................................................... 279
TABLE D - 10 GASES RETAINED IN THE SOLVENT AT THE FLASH TANK 1 .............................................. 280
TABLE D - 11 GASES RELEASED FROM THE SOLVENT AT THE FLASH TANK 1 ........................................ 280
TABLE D - 12 GASES RETAINED IN THE SOLVENT AT THE FLASH TANK 2 .............................................. 280
TABLE D - 13 GASES RELEASED IN THE SOLVENT AT THE FLASH TANK 2 .............................................. 281
TABLE D - 14 GASES RETAINED IN THE SOLVENT AT THE FLASH TANK 3 .............................................. 281
TABLE D - 15 GASES RELEASED IN THE SOLVENT AT THE FLASH TANK 3 .............................................. 281
TABLE D - 16 FINAL PRODUCT OF CO2 FROM SELEXOL ........................................................................ 281
TABLE D - 17 POWER CONSUMPTION CALCULATION ............................................................................. 282
TABLE D - 18 PROCESS FACILITY COST OF SELEXOL PROCESS .............................................................. 283
TABLE E - 1 DISTRIBUTION FUNCTIONS ASSIGNED TO THE PARAMETERS OF THE IGCC PROCESS (THE
DISTRIBUTION FUNCTIONS IN THIS TABLE, EXCEPT THE DISTRIBUTION OF THE FIXED

- xii -
CHARGE FACTOR, MAINLY COME FROM REFERENCE [1] AND WERE UPDATED WITH DATA
FROM REFERENCE [2] AND [3]) ....................................................................................... 284
TABLE E - 2 DISTRIBUTION FUNCTIONS ASSIGNED TO SELEXOL-BASED CO2 CAPTURE PROCESS ........ 286
TABLE E - 3 DISTRIBUTION FUNCTIONS ASSIGNED TO THE FUEL COST AND CAPACITY ....................... 286

- xiii -
NOMENCLATURE

α CO2 removed from the syngas (percent)

ω Selexol flow rate (lb-mole/hr)

ψ CO 2
Solution heat of CO2 in selexol (Btu/lb solute)

η Percentage of the theoretical recovery

η HS H2S removal efficiency (%)

η tur Power recovery turbine efficiency (%)

η comp Compressor efficiency (%)

η pump Pump efficiency (%)

γ Ratio of actual to required flow rate of selexol (fraction)

χi Solubility of gas component i in selexol (SCF/gallon-psia)

∆T Temperature increase of solvent in the absorber (F)

∆T1 Selexol temperature change due to heat transfer from syngas (F)

∆T2 Selexol temperature change due to solution heat (F)

∆TSel Selexol temperature difference between the inlet and outlet of the refrigeration
unit (C )

ξ CO conversion

ξh CO conversion in the high temperature shift reactor

ξl CO conversion in the low temperature shift reactor

ξ tot Total CO conversion in the shift reactors

B The amount of debt

C cat . Capital cost of catalysts (k$ in 2000)

C p,S Specific heat (constant pressure) of selexol (Btu/lb-F)

- xiv -
C p ,i Specific heat (constant pressure) of gas component i (Btu/lb-F)

C v ,i Specific heat (constant volume) of gas component i (Btu/lb-F)

dPpump Pressure increase in the pump (psia)

dPtur Decreased pressure of Selexol in the power recovery turbine (F)

dTHE Log mean temperature difference in the heat exchanger (C)

dTtur Decreased temperature of Selexol in the power recovery turbine (F)

dT pump Increased temperature of CO2 lean Selexol due to pumping (F)

dTh Approach temperature in the high temperature reactor (F)

dTl Approach temperature in the low temperature reactor (F)

(dT ) HE1 Log temperature difference in heat exchanger 1 (F)

(dT ) HE 2 Log temperature difference in heat exchanger 2 (F)

(dT) HE 3 Log temperature difference in heat exchanger 3 (F)

F Molar flow rate of air fed into the ITM unit (mole/hr)

F perm Molar flow rate of permeated oxygen (mole/hr)

f0 Total molar flow rate of syngas at the inlet of high temperature reactor (lb-
mole/hr)

f fuel Total molar flow rate of syngas (fuel) from Selexol process (lb-mole/hr)

f gas Flow rate of gas captured in Selexol (lb-mole/hr)

f Sel Flow rate of Selexol (gal/min or lb-mole/hr)

f SG ,i Total flow rate of syngas entering the absorber (lb-mole/hr)

f SG ,HE 2,o Total molar flow rate of syngas from the exit of heat exchanger 2 (lb-mole/hr)

f water Water molar flow rate entering heat exchanger 1 (lb-mole/hr)

- xv -
Hs Total dynamic pressure head of a turbine or pump (psia)

hp comp Power consumption of compressor (hp)

hp pump Power consumption of pump (hp)

hptur Power recovered through the power turbine (hp)

hp RC Power consumption of the recycle compressor (hp)

hp SP Power consumption of the Selexol pump (hp)

hTsatt .
Enthalpy of water at the saturation temperature (Btu/lb-mole)

h T0 Enthalpy of water at the inlet of heat exchanger 1 (Btu/lb-mole)

K Reaction equilibrium constant

k gas Specific heat capacity ratio of gas ( C p / C v )

Kh Shift reaction equilibrium constant in the high temperature reactor with taking
accounting of the approach temperature

K k ,real Shift reaction equilibrium constant in the high temperature reactor without
taking accounting of the approach temperature

Kl Shift reaction equilibrium constant in the low temperature reactor with taking
accounting of the approach temperature

K l,real Shift reaction equilibrium constant in the low temperature reactor without
taking of the approach temperature

k Reaction rate constant

M syn, S ,i Total molar flow rate of syngas through the sulfur removal system (lb-
moles/hr)

MWS Selexol molecular weight (lb/lb-mole)

N O , slump Operating train number of the sump tanks

N O ,reft Operating train number of the refrigeration unit

- xvi -
N O , tan k Operating train number of flash tank

N O , HE Operating train number of the heat exchanger

N O,S Number of operating sulfur removal absorber vessels

N O ,R Operating train number of reactor

N O,HE1 Operating train number of heat exchanger 1

N O ,HE 2 Operating train number of heat exchanger 2

N O ,HE 3 Operating train number of heat exchanger 3

N T ,reft Total train number of the refrigeration unit

N T ,tan k Total train number of flash tank

N T ,sump Total train number of sump tanks

N T , HE Total train number of the heat exchanger

N T ,S Total number of sulfur removal absorber vessels (operating plus spares)

N T ,abso Train number of absorbers

N T ,R Total train number of reactor

N T ,HE1 Total train number of heat exchanger 1

N T ,HE 2 Total train number of heat exchanger 2

N T ,HE 3 Total train number of heat exchanger 3

P0 Syngas pressure at the inlet of high temperature reactor (psia)

Pabso.,i Inlet pressure of absorber (atm)

Pperm Pressure of permeated oxygen (psia)

Po ,1 Total pressure at the outlet of recovery turbine #1 (psia)

- xvii -
Po , 2 Total pressure at the outlet of recovery turbine #2 (psia)

Pcomp ,i Inlet pressure of compressor (psia)

Pcomp ,o Outlet pressure of compressor (psia)

Pi Partial pressure of gas component i (psia)

Ptur ,o Outlet pressure of the turbines (atm)

PHE Pressure of syngas entering the heat exchanger (atm)

PHE 2 Pressure at heat exchanger 2 (atm)

PR Pressure in the shift reactor (atm)

Psc Steam cycle pressure (psia)

PFC avso Process facility cost of the absorber (US k$ in 2000)

PFCtur Process facility cost of power recovery turbine (US k$ in 2000)

PFC sump Process facility cost of sump tank (US k$ in 2000)

PFC RC Process facility cost of the recycle compressor (US k$ in 2000)

PFC SP Process facility cost of the Selexol pump (US k$ in 2000)

PFC comp1 Process facility cost of the CO2 compressor (US k$ in 2000)

PFC comp 2 Process facility cost of the compressor (US k$ in 2000)

PFC refr Process facility cost of the refrigeration unit (US k$ in 2000)

PFC tan k Process facility cost of flash tanks (US k$ in 2000)

PFC HE Process facility cost of the heat exchanger (US k$ in 2000)

PFC R Process facility cost of shift reactor (k$ in 2000)

PFC HE1 Process facility cost of heat exchanger 1

- xviii -
PFC HE 2 Process facility cost of heat exchanger 2

PFC HE 3 Process facility cost of heat exchanger 3

Q1 Heat released from the syngas to the solvent (Btu/hr)

QHE Heat load of the exchangers (kW), 1200~96000 /train

Q HE1 Heat exchanged in heat exchanger 1 (Btu/hr or kW)

Q HE 2 Heat exchanged in heat exchanger 2 (Btu/hr or kW)

Q HE 3 Heat exchanged in heat exchanger 3 (Btu/hr or kW)

q HE1 Heat released in heat exchanger 1 by per lb-mole syngas (Btu/lb-mole)

q HE 2 Heat released in heat exchanger 2 by per lb-mole syngas (Btu/lb-mole)

q HE 3 Heat absorbed in heat exchanger 3 by per lb-mole feed water (Btu/lb-mole)

R Overall recovery of the ITM unit

RT Theoretical overall recovery of the ITM unit

rB Cost of debt (borrowing rate)

rS Cost of equity

rWACC Average cost of capital after tax for the project

S Amount of equity

SV Space velocity in a reactor (1/hr)

T0 Temperature of syngas at the inlet of high temperature reactor (F)

TC Tax rate

Tevap Evaporation temperature of refrigerant (F)

TSG ,i Syngas temperature at the inlet of the absorber (F)

TSG ,o Syngas temperature at the outlet of the absorber (F)

- xix -
THE 2,o Temperature of syngas exiting the heat exchanger 2 (F)

Th Equilibrium temperature in the high temperature reactor (F)

Tl Equilibrium temperature in the low temperature reactor (F)

T sat. Temperature of saturation water (F)

TSG , HE 3,i Temperature of syngas at the inlet of heat exchanger 3 (F)

Twat.,HE 3,o Temperature of water at the exit of heat exchanger 3 (F)

Vcat. Catalyst volume (ft3)

Vcat.,h High temperature catalyst volume (ft3)

Vcat.,l Low temperature catalyst volume (ft3)

VCO2 ,res Volume flow rate of residual CO2 in the lean solvent (lb-mole/hr)

VCO2 ,abs Volume flow rate of CO2 captured in the absorber (lb-mole/hr)

Vi Volume flow rate of gas component i captured by Selexol (SCF/hr)

vi Specific volume of CO2 (SCF/lb-mole)

VF Volumetric flow rate of syngas (ft3/hr)

VFgas Volume flow rate of gas (ft3/min)

We, S Sulfur removal equipment power consumption (kW)

Wref . Power consumption of solvent refrigeration process (kW)

x feed Molar concentration of oxygen in the air

[ y] Molar concentration of species y in syngas

[ y]0 Molar concentration of species y in syngas entering the high temperature


reactor

- xx -
[ y] h ,o Molar concentration of species y in syngas exiting the high temperature
reactor

[ y]l ,o Molar concentration of species y in syngas exiting the low temperature


reactor

- xxi -
Chapter 1. INTRODUCTION

1.1. Climate change and CO2 emissions

Global climate change, a widely discussed topic in environmental studies,

represents a potentially serious threat to natural ecosystems, and to the quality of human

life on earth. Studies predict that the adverse consequences of climate change induced by

human activities will include some of the following in the future [World Energy

Assessment, 1999]:

• The average temperature of the global surface air will increase by 1.0~3.5°C

during this century.

• The global mean sea level is likely to rise by about 6cm per decade during this

century, mainly due to the thermal expansion of the ocean and the melting of

some land ice.

• Even though food production may increase in some areas, the high likelihood of

its decrease in other areas, especially in the tropics and subtropics, will bring

hardship to large segments of population.

• Fast climatic changes may result in the instability of ecosystems, causing natural

disasters such as floods and droughts.

• Some diseases currently contained within certain areas may spread further to

threaten new populations.

To minimize the impacts of climate change, it is important to pinpoint and eliminate

factors responsible for this phenomenon. It is well-known that a number of gases, such as

22
carbon dioxide, ozone, methane, nitrous oxide and CFCs in the atmosphere, induce the

greenhouse effect that drives global climate change. The contribution of carbon dioxide

is, however, dominant because of two reasons. First, the concentration of this gas is

already higher than other greenhouse gases in the atmosphere, and, second, human

activity on earth today is adding carbon dioxide to the atmosphere at historically

unprecedented rates.

The recent increase in the atmospheric concentration of carbon dioxide has resulted

from the large scale utilization of fossil fuels in modern times. Since the onset of the

industrial revolution, for instance, 296 gigatonnes of carbon from fossil fuels have been

released to the atmosphere, raising carbon dioxide concentration from 280ppm to

360ppm [World Energy Assessment, 1999].

At present, fossil fuels fulfill about 84.8% of the world’s primary energy

consumption needs [International Energy Annual 1999], and in the foreseeable future,

fossil fuels will still be the major energy source. Estimates indicate that the world’s fossil

fuel reserves contain approximately 6600 gigatonnes of carbon, with 5200 gigatonnes of

carbon in coal alone. In the absence of adequate measures to control the emissions of

carbon dioxide from these sources, the atmospheric concentration of carbon dioxide

could more than double by the end of this century [World Energy Assessment, 1999].

Concerns about the greenhouse effect call for new strategies regarding the use of coal to

reduce the emission of carbon dioxide into the atmosphere. The task of reducing carbon

dioxide emissions without abruptly cutting off the utilization of fossil fuels, however,

presents a serious challenge. The following section discusses some methods for facing

this challenge.

23
1.2. IGCC—a promising technology for CO2 emission control

As the most carbon-intensive and most abundant fossil fuel, coal is traditionally

utilized through combustion. Coal combustion plants produce flue gas streams consisting

mostly of nitrogen (from combustion air), with diluted concentrations of CO2.

Technologies have been developed to capture CO2 with low partial pressure from flue gas

stream, but the energy and economic performance of coal combustion power plants

would be degraded substantially. Post-combustion CO2 capture from coal combustion

plants would nearly double the cost of electricity (COE), and reduce their net output by

about 25-30% [Parson, 1998; Doctor, 1994; McCarthy, 1985]. Although oxyfuel can

make CO2 capture from coal combustion power plant much cheaper, the expensive

oxygen production required adds significantly to the overall plant cost. For these reasons,

there is growing interest in Integrated Gasification Combustion Cycle (IGCC) systems as

an alternative.

Gasification offers a way of converting coal to a gaseous state where it can be

cleaned and burnt in a gas turbine. CO2 emissions can be prevented in a gasification

power plant by transferring almost all carbon compounds to CO2 through the water gas

shift reaction, and then removing the CO2 before it is diluted in the combustion stage.

Hence, CO2 removal from IGCC requires considerably smaller and simpler process

equipment than the post-combustion CO2 removal [Herzog, 1999; Herzog, 1997].

Therefore, compared to coal combustion plants, IGCC power plants provide an option for

CO2 capture with relatively low cost and small energy losses.

In addition, IGCC systems are of interests to governments and utility companies in

many countries for other reasons. For example, the United Stated government may be

24
interested in developing reliable and cost effective IGCC systems for generating power

using its abundant coal reserves in order to reduce US dependence on foreign energy

sources.

1.3. Research motivation and objectives

As a new emerging coal-based technology, IGCC systems are becoming an

increasingly attractive option to limit CO2 emissions and other pollutants relative to

conventional coal power plants.

A number of previous studies have reported cost and performance results for IGCC

systems with CO2 capture [Michael, 1997; OLeefe, 2000; Doctor, 1997]. However, there

are no generally available process models that can be used or modified for studying

options of CO2 removal from IGCC systems in detail. Currently reported cost data also

are relatively limited and often incomplete, and uncertainties are seldom considered.

This research, therefore, is motivated by a desire to have a better understanding of

the technological options for CO2 capture from IGCC systems and their effects on the

performance and cost of IGCC systems. Some key research questions which need to be

addressed include: What kind of technologies may be used for CO2 capture? What are the

key parameters that affect the performance and the cost of IGCC systems with and

without CO2 capture? What are the uncertainties associated with IGCC system? How will

CO2 capture influence the future development and application of IGCC systems? How

will IGCC systems and CO2 capture benefit from developing technologies?

With these objectives in mind, this thesis develops a general framework to assess

the range of options for CO2 capture from IGCC power systems. In this general

25
framework, energy and economic models are developed to simulate the performance and

costs of IGCC systems with and without CO2 capture under different scenarios. Both new

and retrofit (repowering) applications of IGCC systems with and without CO2 capture are

studied. The thesis also characterizes key uncertainties affecting performance and costs.

It also assesses process design improvements and technology development trends that

offer the potential to reduce the cost of IGCC power generation with CO2 capture.

Through evaluating and comparing various IGCC power plant configurations in terms of

the cost, performance, and uncertainty, this thesis provides a method for systemic

comparison of IGCC options with and without CO2 capture.

26
REFERENCES (CHAPTER 1)

1. Doctor R.D., Molburg J.C., Thimmapuram P.R., 1997: Oxygen-Blown Gasification


Combined Cycle: Carbon Dioxide Recovery, Transport, and Disposal. Energy
Convers. Mgmt. Vol. 38, Suppl.

2. Doctor R.D., etc., 1994: Gasification combined cycle: carbon dioxide recovery,
transport, and disposal, ANL/ESD-24

3. Herzog H, 1999: An Introduction to CO2 Separation and Capture Technologies.


Cambridge, U.S.A: MIT Energy Laboratory Working Paper; 1999

4. Herzog H and Drake E., 1997: CO2 capture, reuse, and storage technology for
mitigating global climate change: A White Paper. DOE order #DE-AF22-96PC01257,
1997

5. International Energy Annual 1999, Energy information Administration, U.S.

6. Keith DW and Morgan MG, 2000: Industrial carbon management: a review of the
technology and its implications for climate policy, Elements of Change 2000, Aspen
Global Change Institute

7. McCarthy, C.B., and Clark W.N., 1985: Integrated gasification/combined cycle


(IGCC) electric power production-A rapidly emerging energy alternative. Presented at
symposium on coal gasification and synthetic fuels for power generation, San
Francisco, CA

8. OLeefe. L.F., Griffiths J., 2000: A single IGCC design for variable CO2 capture, 2000
Gasification technologies conference, San Francisco, California, Oct. 2000

9. Parson EA, Keith DW, 1998: Climate change - Fossil fuels without CO2 emissions,
SCIENCE, 282 (5391) NOV 6, 1998

10. World Energy Assessment, 1999: Energy and the challenge of sustainability,
http://www.undp.org/seed/eap/activities/wea/drafts-header.html

27
Chapter 2. THE ROLE OF IGCC POWER PLANTS FOR ABATING CO2
EMISSIONS

This section discusses the potential role of IGCC power plants for abating CO2

emissions. As the first step, it presents a brief introduction to gasification and IGCC

technology, starting with a generalized overview of IGCC systems. This is followed with

detailed descriptions of major IGCC components, including the air separation unit, coal

preparation facility, gasifier, syngas cooling unit, basic syngas cleanup options, and

combined cycle power block. Then the expected advantages of IGCC for abating CO2

emissions are discussed, along with technologies that can be incorporated into IGCC

systems for CO2 capture, and the process designs for IGCC systems with CO2 capture.

2.1. Overview of IGCC system

IGCC is an innovative electric power generation system that combines modern coal

gasification technologies with both gas turbine (Brayton cycle) and steam turbine

(Rankine cycle) technologies, and offers an exceptionally clean, flexible and cost-

efficient way to generate electricity. The gasification system converts coal or other solid

or liquid feed stocks such as petroleum coke or heavy oils into a gaseous syngas, which is

mainly composed of hydrogen (H2) and carbon monoxide (CO). The combustible syngas

is used to fuel a combined cycle generation power block to produce electricity.

The first commercial IGCC plants were put into service in 1980 in the U.S. through

DOE’s cooperative Clean Coal Technology (CCT) program. Through the rapid

development in recent 20 years, IGCC is now considered as a mature technology and a

viable coal power plant option. So far, four IGCC power plants have been commercially

running, and other IGCC projects are being planned. All these IGCC projects have

28
achieved, or are expected to achieve the lowest levels of criteria pollutant air emissions

(NOx, SOx, CO, PM10) among any coal-fueled power plants in the world [Brown, 2003].

Table 2-1 represents the major milestones during the course of IGCC development

history.

Table 2 - 1 Major milestones of the history of IGCC development (source: GE


webpage)

Time Events
1887 The first patent for a gasifier was granted to Lurgi GmbH in Germany.
1940 Commercial coal gasification to provide cities with gas for streetlights and domestic
consumption became common in Europe and the United States.
1950 The chemical industry began using gasification to make chemicals such as ammonia
and fertilizers. However, the feedstock was mostly crude oils rather than coal.
1970 The U.S. Department of Energy funded various studies to evaluate the feasibility of
gasifying coal and using syngas as a gas turbine fuel. These studies showed good
economics.
1980 Coolwater was commissioned in 1984, which demonstrated the feasibility of IGCC.
1996 Polk Tampa Electric plant was built, which successfully used nitrogen injection for
NOx control and demonstrated the commercial feasibility of IGCC technology,
Wabash River IGCC repowering plant began operation.
2000 Exxon Singapore plant was built, which employs the widest variety of gas turbine
fuels and operability range.
Present IGCC is now considered a mature technology and a viable coal power plant option.

A general figure of the major processes of an IGCC power plant is given by Figure

2-1. The first part of the IGCC process involves the chemical conversion of coal into

syngas, a mixture of mostly hydrogen and carbon monoxide. This conversion is carried

out in a gasifier, using very high temperature and only a limited amount of oxygen. When

the syngas leaves the gasifier, it must be cleaned of any particulates and other

contaminants such as sulfur, so that it can be used as a fuel for gas turbines for power

generation. After the syngas is cleaned, it is fed into a gas turbine, which turns an electric

generator to produce electric power. In addition, the hot exhaust gas from the gas turbine

29
flows into a heat recovery steam generator (HRSG) for steam production, which turns a

steam turbine that drives another electric generator to generate power.

Figure 2 - 1 Simplified process of an IGCC power plant [Brown, 2003]

2.2. Major components of an IGCC system

The major components of IGCC power plants, as shown in Figure 2-1, include the

coal handling facility, gasifier, air separation unit, syngas cooling process, syngas clean-

up processes, and combined cycle power block. Most of the components of IGCC power

plants are associated with processes that have been already widely used in the power,

petroleum refining, and chemicals industries. The following sections describe each of

these components.

30
2.2.1. Coal handling equipment

The coal handling facility is employed to unload, convey, prepare, store and feed

coal delivered to an IGCC power plant. Generally, the coal handling facility used for an

IGCC plant can be divided into five sections: unloading unit, feeding unit, crushing and

screening unit, stacking and reclaiming unit, and bunker [Joshi, 2000], which is largely

the same as that used at PC power plants.

2.2.2. Gasification technology and gasifier

The gasification process is the heart of an IGCC plant. The process is a partial

oxidation process which converts many carbon-based fuels, including most grades of

coal, into a synthesis gas (syngas). The fuel is fed into a pressurized vessel, which

contains controlled and limited amounts of oxygen or air and steam or water. The

chemistry of coal gasification reactions is quite complex. The basic conversion

procedures are as in the following. Rising temperature in the gasifier initiates

devolatilization and breaking of weaker chemical bonds to yield tars, oils, phenols and

hydrocarbon gases. The fixed carbon that remains after devolatilization is gasified

through reactions with O2, steam, CO2, and H2. The heat produced by the partial

oxidation provides most of the energy required to break chemical bonds in the feedstock,

and increases the products to the reaction temperature, and drives endothermic

gasification reactions [Rubin, 1989]. These reactions further produce the final syngas.

Syngas is a mixture of mainly hydrogen and carbon monoxide, with a small fraction of

CO2. A small amount of methane may also be present. Methane formation is a highly

exothermic reaction and does not consume oxygen and, therefore methane amount is

relatively higher in lower-temperature systems, and methane formation increases the

31
efficiency of gasification and the final heating value of the syngas [O’Brien, 2004].

Overall, about 70% of the feed fuel’s heating value is associated with the CO and H2

components of the gas [O’Brien, 2004], but this value can be higher or lower depending

upon the gasifier type and feed stock quality. Most gasification processes being

demonstrated use oxygen, instead of air, as the oxidant.

Coal gasification technology has been developed for over one hundred years and by

now more than one hundred processes of gasification have been developed [O’Brien,

2004]. According to the coal movement and coal/gas contact pattern in the gasifier,

gasification technologies can be classified into three types as the moving bed, fluidized

bed and entrained flow bed. Different types of gasifiers have advantages and

disadvantages of their own, and IGCC systems can incorporate any one of a number of

gasifier designs, but all are based on one of these three types [O’Brien, 2004, Rubin,

1989, Brown, 2003, Cargill, 2001]. The next section will briefly discuss these three types

of gasifiers.

Moving-bed gasifier

In moving-bed gasifiers, gas and solid contact in the pattern of counter flow, where

large particles of coal move slowly down through the gasifier and react with gases

moving up through it. Several different reaction zones are formulated that implement the

gasification process. In the drying zone at the top of the gasifier, the entering coal is

heated and dried, and the product gas is cooled before it leaves the reactor. The coal is

further heated and devolatized by higher temperature gas as it descends through the

carbonization zone. In the next zone, the gasification zone, the devolatized coal gasifies

by reaction with steam and carbon dioxide. Near the bottom of the gasifier is the

32
combustion zone, which operates at the highest temperature, where oxygen reacts with

the remaining char. For the moving bed gasifiers, the discharge gas temperature is

principally controlled by the feed coal moisture content. High-moisture lignite coal

produces a raw gas temperature of about 600 °F, and low-moisture bituminous coal

produces a raw gas temperature of over 1000 °F [Brown, 2003].

The cold gas efficiency (chemical energy in cold gas/chemical energy in fuel) of

moving bed gasifiers is higher than that of fluidized bed and entrained flow gasifiers, and

the oxidant requirement for moving bed gasifiers is also relatively lower. Because the

moving-bed gasifier has higher cold gas efficiency, a larger portion of the original

heating value of the coal turns into the chemical energy in the gas, instead of the thermal

energy in the gas. Hence, the moving bed gasifier typically does not require the high

temperature heat exchangers that are required by entrained-flow and fluidized-bed

systems. Thus, more of the total output is generated by the gas turbine and less by the

steam turbine in an IGCC system using a moving-bed gasifier. Because of lower gas

temperature, the volatile material in coal is difficult to decompose, and there is greater

concentration of methane and tar in gas.

The Lurgi dry-ash gasifier, shown in Figure 2-2, is a pressurized, dry ash, moving-

bed gasifier. It uses steam and O2 as the oxidants. It uses lump coal rather than pulverized

coal and, it produces tars. For the Lurgi gasifier, lump coal enters the top of the gasifier

through a lock hopper and moves down through the bed. A rotating coal distributor

ensures even distribution of coal around the reactor. Steam and oxygen enter at the

bottom and react with the coal as the gases move up the bed. Ash is removed at the

bottom of the gasifier by a rotating grate and lock hopper. The coal moves slowly down

33
the gasifier, and it is warmed by the syngas flowing upwards through the bed; thus the

coal is sequentially dried and devolatilized, then gasified. The countercurrent operation

results in a temperature drop in the reactor. Gas temperatures in the drying and

devolatization zone near the top are approximately 260 to 538 °C. The very bottom of the

bed is the hottest part of the gasifier (~1000 °C), where almost any remaining coal is

oxidized. The CO2 produced at the bottom reacts with carbon higher in the bed to form

CO [DOT, 1998].

Figure 2 - 2 Simplified process of the Lurgi dry-ash gasifier [Brown, 2003]

The Lurgi dry-ash gasifier uses about a 4-5:1 ratio of steam to O2 as oxidant. The

result of this is that the temperature in the dry-ash system is kept sufficiently low at all

34
points. Thus, the ash does not melt, and can be removed as a dry ash. The low

temperature of the dry-ash system means that it is suited more to reactive coals, such as

lignite, than to bituminous coals [DOT, 1998].

Fluidized-Bed gasifier

For a fluidized-bed gasifier, coal is typically supplied through one side of the

reactor, and oxidant and steam are supplied near the bottom. Fluidized-bed reactors can

efficiently mix coal particles in the reactor vessel. Thus, a constant temperature is

sustained that is below the ash fusion temperature, which avoids clinker formation and

possible de-fluidization of the bed. This means that fluidized bed gasifiers are best suited

to relatively reactive fuels, such as biomass. Some char particles are entrained in the raw

gas as it leaves the top of the gasifier, but are recovered and recycled back to the reactor

via a cyclone. Ash particles which are removed below the bed give up heat to the

incoming steam and recycle gas. Fluidized bed gasifiers may differ in ash conditions and

in design configurations for improving char use [Worldbank, 2000].

The fluidized bed gasifier has the advantages of simpler reactor structure, uniform

and moderate operating temperature, easy operating, accepting a wide range of solid

feedstock, free of tar and phenol, and moderate oxygen and steam requirements. In

conventional fluidized bed coal gasifiers, like the Winkler gasifier, absence of selected

ash discharge design results in low temperature operation and higher carbon content in

bottom ash, which causes low carbon conversion, limited coal feedstock resources and

relatively small gasification capacity [Worldbank, 2000].

35
There are relatively few large fluidized bed gasifiers in operation. Commercial

versions of this type of gasifier include the high temperature Winkler (HTW) and KRW

designs. The latter gasifier was incorporated into the Piñon Pine Coal Gasification Plant

[Cargill, 2001].

The KRW gasification process, originally developed by M.W. Kellogg Company, is

a pressurized, dry feed, fluidized bed slagging process. The gasifier design is shown in

Figure 2-3. The KRW technology is capable of gasifying all types of coals, including

high sulfur, high-ash, low rank, and high-swelling coals, and it is also capable of

gasifying bio-derived and refuse-derived waste. The only solid waste from the plant is a

mixture of ash and calcium sulfate, which is identified as a non-hazardous waste [NETL,

2000]. Coal and limestone, crushed to below 1/4", are transferred from feed storage to the

KRW fluidized-bed gasifier via a lock hopper system. Gasification takes place by mixing

steam and air (or oxygen) with the coal at a high temperature. The fuel and oxidant enter

the bottom of the gasifier through concentric high velocity jets, which assure complete

mixing of the fuel with oxidant and char and limestone that collects in the gasifier. Upon

entering the gasifier, the coal immediately releases its volatile matters, which are

oxidized rapidly to supply the endothermic heat of reaction for gasification. The oxidized

volatiles form a series of large bubbles that rise up in the center of the gasifier, which

cause the char and sorbent in the bed to move down the sides of the reactor and back into

the central jet. The recycling of solids cools the jet and efficiently transfers heat to the

bed material. Steam, which enters with the oxidant and through a multiplicity of jets in

the conical section of the reactor, reacts with the char in the bed, converting it to syngas.

36
At the same time, the limestone sorbent, which has been calcined to CaO, reacts with H2S

released from the coal during gasification to from CaS [NETL, 2000].

As the char reacts, the particles become enriched in ash. Repeated recycling of the

ash-rich particles through the hot gas of the jet melts the low-melting components of the

ash, which causes the ash particles to stick together. These particles are cool when they

return to the bed, and this agglomeration permits the efficient conversion of even small

particles of coal in the feed. The velocity of gases in the reactor is selected to maintain

most of the particles within the bed. The smaller particles that are carried out of the

gasifier are recaptured in a high efficiency cyclone and returned to the conical section of

the gasifier. Eventually, most of the smaller particles agglomerate when they become

richer in ash and gravitate to the bottom of the gasifier. Since the ash and spent sorbent

particles are substantially denser than the coal feed, they settle to the bottom of the

gasifier, where they are cooled by a counter-current stream of recycled gas [Cargill,

2001].

The char, ash, and spent sorbent from the bottom of the gasifier flow to the fluid-

bed sulfator, where both char and calcium sulfide are oxidized. The CaS forms CaSO4,

which is chemically inert and can be disposed of in a landfill. Sulfur released from

burning residual char in the sulfator is also converted to CaSO4 [Cargill, 2001].

37
Figure 2 - 3 Simplified process of the KRW gasifier [Brown, 2003]

Entrained-flow gasifier

In an entrained-flow gasifier, fine coal particles react with steam and oxygen at high

temperatures. Entrained-flow gasifiers have the ability to gasify all coals regardless of

rank. Depending on designs, entrained-flow systems may use different coal feed systems

(dry or water slurry) and heat recovery systems.

In an entrained flow bed, the contact time of gas and solid is very short, which is

only about several seconds, but the reaction rate and gasification capacity is greater

because of higher gasification temperature (1200-1500 °C) and smaller diameter of

38
pulverized coal (<100um). On the other hand, because of higher operating temperature,

part of the coal energy is converted to heat and its cold gasification efficiency is lower.

High gas temperature also makes gas cleaning and waste heat recovery system more

expensive [Worldbank, 2000]. Entrained-flow gasifiers have the following

characteristics:

• Ability to gasify all coals regardless of coal rank, caking characteristics, or

amount of coal fines (although feed stocks with lower ash content are favored)

• Uniform temperatures

• Very short fuel residence time in gasifier

• Solid fuel must be very finely divided and homogeneous

• Relatively large oxidant requirements

• Large amount of sensible heat in the raw gas

• High-temperature slagging operation

• Entrainment of some molten slag in the raw gas.

Nearly all commercial IGCC systems in operation or under construction are based

on entrained-flow gasifiers. Commercial entrained-flow gasifier systems are available

from GE Energy Gasification Technology (formerly ChevronTexaco), ConocoPhillips,

Shell, Prenflo, and Noell [Rosenberg, 2004]. The commercial gasification processes

believed most suited for near-term IGCC applications using coal or petroleum coke feed

39
stocks are the GE Energy, ConocoPhillips, and Shell entrained-flow gasifiers [SFA

Pacific, 2003].

ChevronTexaco gasification technology uses a single-stage, downward-feed,

entrained-flow gasifier, shown as Figure 2-4. Fuel/water slurry (e.g., 60-70% coal) and

95% pure oxygen (from an air separation unit) are fed to at the top of a hot, pressurized

gasifier. The fuel and oxygen react exothermally to produce raw fuel gas and molten ash

at a temperature ranging from 2200 to 2700 °F, and a pressure greater than 20

atmospheres. Operation at the elevated temperatures eliminates the production of

hydrocarbon gases and liquids in the syngas. In the syngas cooler design-type, the hot gas

flows downward into a radiant syngas cooler where high-pressure steam is produced. The

syngas cooler is specifically designed to meet the conditions of high thermal gradients

and the ability to handle soot. The syngas passes over the surface of a pool of water at the

bottom of the radiant syngas cooler and exits the vessel. The slag drops into the water

pool and is fed from the radiant syngas cooler sump to a lock hopper. The black water

flowing out with the slag is separated and recycled after processing in a dewatering

system. The slag is eventually removed through a lock hopper. This design configuration

maximizes heat recovery for steam production, as well as CO production, which is

appropriate for an IGCC application. After exiting the gasifier, the syngas is further

cooled and cleaned by a water scrubber, and the fine particulate matter and char may be

recycled to the gasifier. The cooled, water-scrubbed syngas consists mainly of hydrogen

and carbon monoxide, and contains no hydrocarbons heavier than methane. Metals and

other ash constituents become part of the glassy slag [Cargill, 2001].

40
Figure 2 - 4 Texaco gasifier with radiant syngas coolers [Brown, 2003]

An alternate design to the use of a radiant syngas cooler is the use of an exit gas

quench. In this design mode, hot gas exiting the reaction chamber is cooled by direct

contact with water, and then enters a scrubber for particulate and soot removal. This

design provides an effective mechanism to add water to the syngas to promote the water-

gas shift reaction and maximize hydrogen production. The quench design mode is often

used to accommodate heavy hydrocarbon feedstock [Brown, 2003].

41
Table 2 - 2 Important characteristics of three types of gasifiers [Brown, 2003]

Gasifier type Moving bed Fluidized bed Entrained


flow
Commercial Lurgi KRW Texaco,
Manufacturer Shell
Ash conditions Dry ash slagging Dry ash Agglomerating Slagging
Fuel size limits 6-50 mm 6-50 mm <6 mm < 6 mm <0.1 mm
Acceptability Yes Yes Possibly No, non-caking Yes
of caking coal
Preferred Lignite, Bituminous, Lignite, Lignite, Lignite,
feedstock reactive anthracite, reactive bituminous, reactive
bituminous, pet coke, bituminous, anthracite, bituminous,
anthracite waste anthracite, cokes, anthracite,
wastes waste biomass, pet cokes
wastes
Ash content No < 25% No No limitations <25%
limits limitation preferred limitation preferred
Preferred ash >2200 <2370 >2000 >2000 <2372
melting
temperature, F
Exit gas Low (800- Low (800- Moderate Moderate High
temperature, °F 1200) 1200) (1700- (1700-1900) (>2300)
1900)
Gasification 435+ 435+ 15 15-435 <725
pressure, psia
Oxidant Low Low Moderate Moderate High
requirement
Steam High Low Moderate Moderate Low
requirement
Unit capacity, 10-350 10-350 100-700 20-150 Up to 700
MWh
Key Hydrocarbon liquids in raw Large char recycle Large
distinguishing gas amount of
characteristics sensible of
heat energy
in the hot
raw gas
Key technical Utilization of fines & Carbon conversion Raw gas
issue hydrocarbon liquids cooling

42
Table 2 - 3 Comparison of parameters of gasification technologies [U.K.
Department of Trade and Industry, 1998]

Type of Ash Fixed bed Fluidized Entrained flow bed


gasifier agglomerating bed
fluidized bed
Gasification Oxygen blow Lurgi HTW K-T Texaco
technology (atmosphere) pressurized

Coal feeder Dry, crushed Lump Lump Dry, Pulverized Slurry


tyep crushed coal
Gasification ~1080 C 800~1000 C 800~1000 800~1000 ~1800 C ~1400 C
temperature C C
Gasification ~30 kPa ~20 kPa 2.24 MPa 1.0~2.5 34~48 kPa 3.4 MPa
pressure MPa
Ash agglomerating solid solid solid slag slag
removed
Gasification 92% 95.2% O2+steam O2+steam O2+steam O2+steam
medium O2+steam O2+steam
Oxygen/coal 0.454 0.64 0.41 0.37 0.7 1.17
Nm3/kg
Steam/coal 0.94 1.37 1.65 0.37 0.27 0.92
kg/kg
Carbon ~90 >95 >95 ~95 99 >95
conversion
%
Cold gas ~73 ~85 ~85 76 76 ~76
efficiency %
Carbon 7.7 11 9
content in
ash %

A general comparison of these three types of gasifiers, and a specific comparison of

some commercial gasifiers are given in Table 2-2 and Table 2-3, respectively.

43
2.2.3. Air Separation Unit (ASU)

This section discusses the function of the air separation units (ASU) in IGCC power

plants, followed by descriptions of current commercial technology and developing

technology for oxygen production.

Is ASU necessary for IGCC systems?

All coal gasification processes require an oxidant for the gasification reactions. Air,

oxygen, or oxygen-enriched air can be used as oxidant for gasification processes. The

choice of oxidant affects the amount of nitrogen the gasification system has to handle,

and depends on the application, types of gasifiers, and the degree of the system

integration. Air-blown gasification eliminates the need for the ASU. Oxygen-blown

IGCC systems, however, have several advantages over air-blown IGCC systems.

Syngas from an oxygen-blown gasifier has a heating value ranging from 250 to 400

Btu/scf, compared to an air-blown gasifier with 90 to 170 Btu/scf fuel gas and high

nitrogen content [Rubin, 1989]. Syngas with a medium heating value can potentially be

used as a replacement for natural gas as gas turbine fuel. In addition, the moderate

heating value of the gas helps minimize the size of the gasifier and auxiliary systems. The

cold-gas efficiency is 7-10 percentage points higher for oxygen-blown gasification than

air-blown gasification due to the avoidance of nitrogen dilution. Gasifier operability and

carbon conversion also improves with the use of oxygen [Rubin, 1989]. Comparing to

oxygen-blown gasification, air-blown gasification creates additional technical challenges

for the gas clean up and combustion turbine operation. Air-blown gasification also is less

suited for cost effective separation and capture of CO2 due to the diluted CO2 by nitrogen.

For these reasons, the next generation of IGCC facilities are expected to be based on

44
entrained-flow, oxygen-blown gasification technologies [Rosenberg, 2004]. To date, all

of the gasification processes demonstrated for commercial IGCC plants is oxygen-blown

systems.

Cryogenic oxygen production and novel air separation methods

Currently, air separation in large scale is achieved by using a cryogenic process in

which air is cooled to a liquid state and then subjected to distillation. The basic elements

of an air separation are [Air Products, 2004].

• Filtering and compressing air

• Removing contaminants, including water vapor and carbon dioxide (which would

freeze in the process)

• Cooling the air to very low temperature through heat exchange and refrigeration

processes

• Distilling the partially-condensed air (at about -300˚F / -185˚C) to produce

oxygen.

• Warming oxygen and waste streams by heat exchange with incoming air

Cryogenic oxygen production, commercialized early in the 20th century, is an

established process that is used extensively worldwide. Currently cryogenic processes

remain the most economically efficient separation method of making high purity oxygen

for high production rate plants. However, an ASU based on the cryogenic process

requires a large amount of power and accounts for the largest parasitic load on an

45
oxygen-blown IGCC plants. In addition, cryogenic processes in general have large capital

cost, due mostly to the cost of compressors, turbines, and numerous heat exchangers for

high pressure requirements and the recovery of refrigeration energy [Holt, 2001].

For these reasons, lowering the cost of air separation will significantly improve the

economics and efficiency of IGCC power plants and lower their capital costs. The

Department of Energy is sponsoring a research project to develop a novel air separation

technology--the Ion Transport Membrane Oxygen (ITM). ITM is based on ceramic

membranes that selectively transport oxygen ions when operated at high temperature. A

commercial-scale ITM oxygen module with a capacity of producing 0.5 ton/day oxygen

has been run by Air Products. It is predicted that ITM oxygen module capable of

producing 1000 ton/day oxygen will be available in 2010. According to Air Products, this

technology has the potential to lower the cost of producing oxygen by more than 30%

[Air Products, 2004]. Hence, it is expected that the upgrade in air separation technology

will significantly improve the economics of IGCC systems [O’Brien, 2004].

2.2.4. Syngas cooling

Coal gasification systems operate at high temperatures and produce raw, hot syngas

at temperatures from 800 to 1800 °C. The syngas from the gasifier has to be cooled

down for cleanup. Heat recovery is typically utilized to cool down the syngas and

increase overall system efficiency. Heat recovered can represent about 15% of the energy

in the feed fuel, but this varies with the gasification technology employed (5% for

moving bed to 25% for entrained flow processes) [Bruijn, 2003]. Depending on the

design of a gasifier, the raw syngas leaving the gasification reactor can be cooled by

radiant and/or convective heat exchange and/or by a direct quench system, which injects

46
either water or cool recycle gas into the hot raw syngas. In most IGCC plant design

configurations, saturated steam raised from cooling the raw gasifier syngas is sent to the

heat recovery steam generator (HRSG) for superheat and reheat. The steam and water

systems are integrated between the gasification island and the power conversion block,

but the superheated steam is generally better generated in the HRSG than in the raw

syngas coolers [Bruijn, 2003].

2.2.5. Syngas clean-up

The raw syngas produced by the gasification contains various impurities. However,

the concentrations of these various components depend on the feedstock composition and

the specific gasification process employed. The primary feedstock impurities of concern

are the sulfur and ash constituents. In gasification, the sulfur is converted mainly to H2S

and COS, a portion of the ash and unburned carbon is entrained as particulates. Small

amounts of HCN and NH3, and traces of metal carbonyl compounds, are also produced

[McCarthy, 1985].

Particulate materials have to be removed from raw syngas before it can be used as a

fuel of gas turbine to avoid damaging the turbine. This is generally accomplished by

cooling the syngas to much lower temperatures, and then using conventional cleaning

methods including cyclones or water scrubbers. The particulate material, including char

and fly ash, is then typically recycled back to the gasifier [Bruijn, 2003]. Another option

to water scrubbing for particulate removal is the use of ceramic candle filters or sintered

metal filters [Korens, 2002].

47
Next the syngas is treated in “cold-gas” clean up processes, also known as the Acid

Gas Recovery (AGR) process, to remove most of the H2S, carbonyl sulfide (COS) and

nitrogen compounds. The primary processes are chemical solvent-based processes or

physical solvent-based processes. Sulfur recovery processes recover sulfur either as

sulfuric acid or as elemental sulfur. The most common removal system for sulfur

recovery is the Claus process, which produces elemental sulfur from the H2S in the

syngas [O’Brien, 2004].

Carbonyl sulfide (COS), which is usually present at a several hundred ppmv level in

syngas from coal and petroleum residues, is difficult to remove in AGR units. Therefore,

further sulfur removal may be accomplished by the addition of a COS hydrolysis unit

(before the AGR), which catalytically converts COS to H2S. For high sulfur coal, IGCC

plants that use COS hydrolysis, together with conventional AGR and sulfur recovery

units, have been able to achieve nearly 99% sulfur recovery [Wabash Energy Ltd, 2000].

DOE is currently working on new syngas cleanup systems in which the syngas will

need to be cooled only moderately [Simbeck, 2002]. Such a system would have higher

process efficiency achievable without syngas cooling and removal of water from the

syngas. Potential capital and operating cost savings of these new processes are related to

their reduced complexity compared to current cold gas cleanup processes. Hence, once

these technologies are commercialized, the economics and environmental friendliness of

IGCC power plants is expected to improve.

The focus of most new syngas cleanup programs is the removal of the sulfur,

chloride, alkali, and particulates from syngas at temperatures close to the highest inlet

48
temperature at which gas turbine fuel control and delivery systems could be designed.

This level was set at about 1,000 ºF by the requirement for very low alkali (potassium and

sodium) content of the fuel gas to prevent alkali corrosion of hot gas turbine components

and the desire to avoid expensive materials and unreliable refractory-lined piping [Todd,

1994; Holt, 2001]. However, both industry interest and government interest in such

processes have declined for several reasons [Stiegel, 2001], including the technical

challenge of the process and equipment development, the trend toward more stringent air

emissions and the success of the demonstration and commercial O2-blown gasification

projects.

2.2.6. Combined cycle power unit

The clean syngas is sent to the combined cycle power unit. In a combined cycle

system, the first generation cycle involves the combustion of syngas in a combustion

turbine. The gas turbine powers an electric generator, and the hot exhaust gases from the

gas turbine is directed to a heat recovery steam generator to produce steam for a steam

turbine to complete the combined power cycle.

For any gas turbine manufacturer, the fuels that will be used will have a profound

effect upon both the machine design and the materials of construction. It is most

meaningful from the standpoint of turbine application to classify gaseous fuels by their

calorific values, which cover a very wide range: from a low of about 100 Btu/ft3 to a high

of 5,000 Btu/ft3. Table 2-4 shows such a classification of gaseous fuels.

49
Table 2 - 4 Classification of fuel gases [Foster, 2003]

Classification by Calorific value Primary gas


Typical specific fuels
calorific value kcal/nm3 (Btu/scf) components
10700-44500 Liquefied Petroleum Propane
Very high
(1200-5000) Natural gas liquids Butane
Natural gas
7100-10700
High Synthetic natural gas Methane
(800-1200)
Sour gas
Coal gas
Hydrogen
2700-7100 (O2 blown syngas)
Medium Carbon monoxide
(300-800) Coke oven gas
Methane
Refinery gas
Carbon Monoxide
900-2700 Coal gas (air blown
Low Hydrogen
(100-300) syngas)
Nitrogen
Under 900 Carbon Monoxide
Very low Blast furnace gas
(under 100) Nitrogen

Historically, natural gas has been the primary fuel for gas turbines. According to

Table 2-4, comparing to natural gas, the volumetric heating value of cleaned syngas is

about 40-50 percent that of natural gas, so a much larger volume of fuel is required with

syngas firing to provide the necessary energy input to the gas turbine. Hence, when

syngas is used as fuel for modern combustion turbines, there are some process

differences. Recently GE initiated a program of extensive analysis to investigate the

combustion characteristics of a number of lower-heating-value fuels. Based upon the

results of this study, full scale single-burner and sector tests were conducted to confirm

expected performance of their MS5000 and LM2500 engine. In general, the only change

required to the standard combustion system is modification of the gas fuel nozzle to

handle the increased volume of fuel. A variation in heating value of more than 20 percent

could be tolerated while still maintaining adequate combustor performance. Many

improvements that have maintained flexibility for lower grade fuels have been made in

50
the modern, higher temperature machines such as the MS6001, MS7001, and MS9001

units [Foster, 2003].

The exhaust temperature from the combustion turbine is generally about 1100°F,

which can make additional power through a steam cycle. A HRSG can produce steam by

cooling the combustion turbine flue gas. This steam is supplied to a steam turbine to

generate additional electric power. In addition, the HRSG is always used to superheat the

high-pressure steam generated in the syngas cooler since satisfactory superheater

materials have not been demonstrated in the reducing atmosphere of a syngas cooler

[Rubin, 1989].

2.3. Literature Review of CO2 capture from IGCC systems

As one of the most promising technologies for CO2 capture from coal-fueled power

plants, IGCC power plants with CO2 capture have been studied in some previous studies

over the past 15 years [Holt 2003]. These studies covered conceptual technology

descriptions, flowsheet modeling and simulation. This section provides a review of the

literatures associated with CO2 capture from IGCC power plants.

Doctor et al. [Doctor 1994, 1996] developed engineering evaluations of CO2

capture technologies combined with IGCC power plants. The base case for this study was

a 458 MW IGCC system that used an air-blown KRW agglomerating fluidized-bed

gasifier, Illinois No.6 bituminous coal feed, and in-bed sulfur removal. This study

investigated several commercial available chemical and physical solvents for CO2 capture

from IGCC plants, which included amine, glycol , chilled methanol and hot potassium

carbonate, and two emerging technologies for CO2 capture were also considered, which

51
were high-temperature CO2 separation with calcium-based sorbents and ambient

temperature facilitated transport polymer membranes for acid gas removal. The CO2

capture efficiency was set to be 90%. From the IGCC plant, a 500-km pipeline took the

CO2 to geologic sequestering. This group also did case studies of Shell gasifier-based

multi-product system with CO2 capture. Life Cycle Analysis (LCA) was adopted in their

studies. For these cases, the net electric power production was reduced by 73.6~185.1

MW, with a CO2 release rate of 0.29~0.53 kg/kWh. The life cycle CO2 sequestering costs

ranged from $113 to $201/ton of CO2.

Chiesa et al. [Chiesa, 1999] evaluated the energy balances, performance and cost of

electricity for two IGCC plants based on oxygen-blown, Texaco gasifiers and large,

heavy-duty gas turbines. In one plant, the raw syngas exiting the gasifier was cooled in a

high-temperature, radiation cooler; in the other it is quenched by the injection of liquid

water. Selexol systems were employed to recovery 90% CO2 in the syngas after shift

reaction. Comparing to the reference plants, the thermal efficiencies of the capture plants

were reduced by 5 to 7 percentage points and the cost of electricity were increased by

about 40 percent.

Haslbeck et al. [Haslbeck, 2002] investigated CO2 capture from oxygen-blown,

Destec- and Shell-based IGCC power plants. The reference plants fed with Illinois #6

coal, using W501G gas turbine and, three pressure level sub-critical reheat steam cycle,

had a net output of 400 MW. Selexol process was used for CO2 capture with an overall

capture efficiency of 87%, and the CO2 final product was compressed to 2100 psia. For

the Destec case with CO2 capture, the net output was reduced by 42 MW, and the thermal

efficiency was decreased by 6.6 percentage points. The COE also showed a

52
corresponding increase to 54.5 from 40.9 $/MWh. For the Shell case with CO2 capture,

the net output was reduced by 61 MW, and the thermal efficiency was decreased by 7.3

percentage points. The COE showed a corresponding increase to 62.9 from 40.6 $/MWh.

The study from the report of Parsons [Parsons, 2002] investigated oxygen-blown E-

gas and GE 7H turbine based IGCC power plants with and without CO2 capture. For the

reference plant, particulate was removed by the hot side filter, MDEA for sulfur removal

were employed. For the capture plant, two-stage Selexol are used for H2S and then CO2

removal at capture efficiency of 90%, and then CO2 is compressed to 2200 psig. The net

output of the reference plant was 424.5 MW, and the net output of capture plant was

reduced by 21 MW. Comparing with the capture plant, the thermal efficiency was

decreased by 6.1 percentage points. The COE also showed a corresponding increase to

65.7 from 52.4 $/MWh at a capacity factor of 65%.

O’Keefe et al. [O’Keefe, 2002] studied a 900 MW IGCC power plant configured to

remove 75% of the feed carbon as CO2. The authors’ aim was to present a concept using

currently available commercial technology to provide an IGCC plant with the option to

capture CO2. The plant used Texaco Quench gasifiers followed by a sour shift system, a

physical absorption acid gas removal, a sulfur recovery system, and a combined cycle

unit consisting of two GE 9FA gas turbines and a single steam turbine. The coal

feedstock was Pittsburgh 8. Selexol was used for acid gas removal. 75% of the carbon in

the coal was removed, but this could be higher. The capture of 75% of the carbon in the

coal results in a loss of efficiency of only two percentage points and a decrease in net

output of 3%, or 26MW.

53
A research group of the Foster Wheeler [Foster Wheeler, 2003] assessed the current

state of the art of coal-based 750 MWe nominal IGCC, with and without CO2 capture,

and the potential for improvements, between now and 2020. Two types of gasifier were

selected, one was the slurry feed gasifier, with product gas cooling by Water Quench

(Texaco quench gasifier); the other one was dry feed gasifier, with product gas cooling in

a waste heat recovery boiler (Shell gasifier). Several chemical solvents and physical

solvents for H2S removal and CO2 capture are investigated. An open-cut coal from

eastern Australia was used for these plants. All the IGCC plant configurations were based

on two 9FA frame gas turbines. The ASU based on the cryogenic process was integrated

with gas turbines. Nitrogen produced by the ASU and exceeding the process consumption

was injected into the gas turbine for NOX reduction and power augmentation.

Sensitivities to a variety of potentially significant parameters, such as gasification

pressure, separate removal of CO2 and H2S vs. production of a combined CO2/H2S

stream, are assessed to help to determine the way forward for IGCC with CO2 capture.

For each alternative plant configuration, overall performances and investment cost were

estimated and used to evaluate the electric power production cost. For some alternatives

specific optimization studies had been made in order to select the most convenient acid

gas removal process and the best arrangement of the shift reactors. This study showed

that dry feed gasifier-based IGCC displayed a higher thermal efficiency, however slurry

feed gasifier-based IGCC required a lower investment, and in term of cost of electricity

and cost of CO2 recovery, slurry feed gasifier based IGCC was marginally better than the

dry feed gasifier based IGCC. The authors also pointed out that the pressure at which

gasification was operated was an important design parameter for IGCC optimization.

54
Increasing the gasifier operating pressure, the heat recovery on the syngas stream was

enhanced, the driving force for physical solvent scrubbing of CO2 was increased and the

equipment size was reduced.

According to the above review, the costs of CO2 capture and sequestration from

new IGCC plants added 25-50% to the COE and reduced the thermal efficiency by 10-

20% percent. Most studies concluded that the costs of pre-combustion CO2 capture from

syngas in an IGCC plant was much lower than the post combustion removal from

Pulverized Coal (PC) or Natural Gas Combined Cycle (NGCC) plants. Most studies

focused on the use of bituminous coals. In addition, for bituminous coals the costs of CO2

removal vary significantly between the various coal gasification technologies and, the

advantage in capture costs over PC plants heavily depends on the gasification technology

selected.

The IGCC studies surveyed in this section covered the main gasification

technologies offered by ChevronTexaco, Shell and ConocoPhillips (E Gas). Among these

studies, Texaco quench gasifier was likely to provide the lowest cost option, and the

Selexol process was usually used for CO2 capture from IGCC systems.

55
REFERENCES (CHAPTER 2)

1. Air products, 2004: ITM Oxygen for Gasification, presented at Gasification


Technologies Conference, Washington, D.C.

2. Brown J.R., Manfredo L., Hoffmann J., and Ramezan M., 2002: Major
Environmental Aspects of Gasification-based Power Generation Technologies,
Final Report, Project Prepared for and Supported by: Gasification Technologies
Program, National Energy Technology Laboratory, DOE

3. Bruijn et al, 2003: Treating Options for Syngas, presented at the Gasification
Technologies Conference, San Francisco

4. Buchanan T.,DeLallo M., Schoff R., and White J., 2002, Evaluation of Innovative
Fossil Fuel Power Plants with CO2 Removal, Technical report prepared for EPRI,
Palo Alto, CA

5. Cargill P., 2001: Pinon Pine IGCC Project - Final Technical Report to the
Department of Energy, Sierra Pacific Resources, Reporting Period August 1, 1992
to January 1, 2001

6. Chiesa P. and Consonni S., 1999: Shift Reactors and Physical Absorption for
Low-CO2 Emission IGCCs, Journal of Engineering for Gas Turbines and Power,
Vol. 121

7. Clayton S.J., Stiegal G.J., Wiemer J.G., 2002: Gasification Markets and
Technologies – Present and Future: An Industry Perspective, National Energy
Technology Laboratory (NETL) U.S. Department of Energy (Report No.
DOE/FE-0447)

8. Doctor R.D., etc., 1994: Gasification combined cycle: carbon dioxide recovery,
transport, and disposal, Report prepared by ANL/ESD

9. Doctor R.D., etc., 1996: KRW oxygen-blown gasification combined cycle carbon
dioxide recovery, transport, and disposal, Report prepared by ANL/ESD

10. Edward L. P., Shelton W.W., and Lyons J.L., 2002: Advanced Fossil Power
Systems Comparison Study, Final report prepared for National Energy
Technology Laboratory

11. Foster, A.D., Doering H.E., and Hilt M.B., 2003, Fuels Flexibility in Heavy Duty
Gas Turbines, GE Company Schenectady, New York

12. Foster Wheel, 2003: Potential for improvement in gasification combined cycle
power generation with CO2 capture. Report # PH4/19, May 2003

56
13. O’Keefe L.F., Griffiths J., Weissman R.C., De Puy R.A., and Wainwright J.M.,
2002: A Single IGCC Design for Variable CO2 Capture, Fifth European
Gasification Conference

14. Haslbeck J.L., 2002, Evaluation of Fossil Power Plants with CO2 Recovery,
Parsons Infrastructure & Technology Group Inc., February 2002

15. Holt N., Booras G., and Todd D., 2003: A Summary of Recent IGCC Studies of
CO2 Capture for Sequestration By Presented at The Gasification Technologies
Conference San Francisco, CA

16. Holt N., 2001: Coal Gasification Research, Development and Demonstration –
Needs and Opportunities, 2001 Gasification Technologies Conference, sponsored
by the gasification Technologies Council and EPRI, San Francisco, CA

17. Korens N., Simbeck D.R., Wilhelm D.J., 2002: Process Screening Analysis of
Alternative Gas Treating and Sulfur Removal for Gasification, Revised Final
Report prepared for National Energy Technology Laboratory, U.S. Department of
Energy

18. Joshi M.M., 2000, Quality Assured maintenance Management For Coal Handling
Plant. http://www.plant-
maintenance.com/articles/Maintenance_Management_QA.pdf

19. McCarthy, C.B., and Clark W.N., 1985: Integrated gasification/combined cycle
(IGCC) electric power production- A rapidly emerging energy alternative.
Presented at symposium on coal gasification and synthetic fuels for power
generation, EPRI, Palo alto, CA

20. O’Brien J.N., Blau J., Rose M., 2004: An Analysis of the Institutional Challenges
to Commercialization and Deployment and Deployment of IGCC Technology in
the U.S. Electricity Industry: Recommended Policy, Regulatory, Executive and
Legislative Initiatives, Final Report, Project Prepared for and Supported by: DOE,
NETL, Gasification Technologies Program and National Association of
Regulatory Utility Commissioners

21. Parsons E., NETL, “Advanced fossil power systems comparisons study”, NETL
report, 2002

22. Rosenberg W.G., Alpern D.C., Walker M.R., 2004: Deploying IGCC in This
Decade With 3 Party Covenant Financing, Volume I

23. Rubin, E., 1989: Implications of Future Environmental Regulation of Coal-Based


Electric Power, Annual Rev. Energy, 14:19-45

24. SFA Pacific, Inc., 2003: Evaluation of IGCC to Supplement BACT Analysis of
Planned Prairie State Generating Station

57
25. Simbeck D.R., 2002: Industrial Perspective on Hot Gas Cleanup, Presentation at
the 5th International Symposium on Gas Cleaning at High Temperatures, U. S.
DOE National Energy Technology Laboratory

26. Stiegel G.J., Clayton S.J., and Wimer J.G., 2001: DOE’s Gasification Industry
Interviews: Survey of Market Trends, Issues and R&D Needs, 2001 Gasification
Technologies Conference, sponsored by the Gasification Technologies Council
and EPRI, San Francisco, CA

27. Todd D.M., 1994: Clean Coal and Heavy Oil Technologies for Gas Turbines,
Paper No. GER-3650D, 38th GE Turbine State-of-the-Art Technology Seminar,
GEZ-7970, General Electric Company, Schenectady, NY

28. U.K. Department of Trade and Industry, 1998: Gasification of Solid And Liquid
Fuels For Power Generation - Status Report,
http://www.dti.gov.uk/cct/pub/tsr008.pdf

29. Wabash Energy Ltd, 2000: The Wabash River Coal Gasification Repowering
Project, U.S. Department of Energy Topical Report Number 20, prepared for
National Energy Technology Laboratory, U.S. Department of Energy

30. World Bank, 2000:


http://www.worldbank.org/html/fpd/em/power/EA/mitigatn/igccsubs.stm#igcctec
h

31. NETL, 2000:


http://www.netl.doe.gov/coalpower/gasification/description/gasifiers.html#Lurgi

58
Chapter 3. PERFORMANCE AND ECONOMIC SIMULATION MODEL OF
IGCC SYSTEMS

The purpose of this chapter is to summarize the information of IGCC modeling

process. Plants with and without CO2 capture are modeled with Aspen Plus. The details

include the design basis, the mass and energy balances of major units of the IGCC

systems, design specifics which is required by commercial available technologies, and

the convergence sequence, which specifics the calculation sequence of the simulation

model.

3.1. Model design basis

Figure 3-1 provides a simplified overview of the reference plant configuration,

which does not incorporate CO2 recovery. This layout is a typical oxygen-blown IGCC

with cold-gas cleanup in which H2S is captured by an acid gas removal system. The

cleaned gas is then saturated and reheated before it is fed into gas turbine combustion

chamber. The hot exhaust from gas turbine is used to generate steam for a steam cycle

through the HRSG. Oxygen is supplied by an air separation unit.

Figure 3-2 is an overview of the capture plant configuration. Comparing to the

reference plant, a water gas shift reactor is added to increase CO2 partial pressure through

converting CO into CO2. CO2 is captured in a Selexol process, a commercial glycol-

based process for acid gas removal.

59
Figure 3 - 1 An IGCC system without CO2 capture

Figure 3 - 2 An IGCC system with CO2 capture

The objective of this modeling study is to assess coal-based IGCC plants with and

without CO2 capture based on current commercial available technology, hence equipment

60
selection and system design of this IGCC system focuses on mature technologies and

methodologies

3.1.1. Gasification technology selection

Currently, many different types of gasifier are commercially available, such as

Texaco, Shell, E-gas. This study is based on the oxygen-blown, slurry feed Texaco

quench gasifier with product gas cooling by water quench, which is the most widely used

gasifier type in IGCC plants. In addition, the Texaco quench gasifier is known for its

low-capital cost requirement.

Currently available Texaco gasifiers can be operated in a wide pressure range, from

15 bar to 70 bar. For a given capacity an increase of the gasification pressure will reduce

the size of the equipment but increase the operating costs. In this study, a medium

pressure (42 bar) gasifier is adopted. Considering that the final destination of the syngas

in an IGCC is the combustion chamber of the gas turbine, which available today with a

rang of 20~30 bar, a gas expander is installed between the gasification and the gas

turbine, which can offset the extra operation cost due to the high gasification pressure.

3.1.2. Air separation unit

The state-of-the-art air separation plants are based on cryogenic mechanism.

Various ASU configurations can be used in IGCC systems, ranging from complete

integration, in which all of the air for the ASU is provided by the gas turbine compressor,

to zero integration in which the ASU is a completely stand-alone unit providing only

oxygen to gasifiers. Considering operation stability and flexibility, the “stand alone”

option is employed.

61
For the “stand alone” option, low pressure air separation plant is chosen, with its

own air compressors delivering air to the cryogenic process at the minimum pressure

requirement to meet the energy demand of the process. In this case, syngas

humidification is generally preferred to nitrogen addition for NOx control to avoid the

large nitrogen compression energy consumption.

3.1.3. Syngas clean up system

Raw syngas from gasification unit is hot, humid and contaminated with H2S, and

COS. Before used as gas turbine fuel, this raw syngas has to be cleaned by removing all

the contaminants and prepared at the proper conditions of temperature, pressure and

water content to meet the requirement of the gas turbine combustion under conditions of

desired environmental performance and operation stability.

The key factor in achieving the environmental performance of IGCC systems is

sulfur removal from the syngas. Sulfur is contained in two types of acid gases, H2S and

COS. The first step in the sour gases removal process is to remove the carbonyl sulfide

(COS) from the gas stream. For an IGCC system without CO2 capture, the conventional

method is to pass the syngas through a fixed bed, catalytic hydrolysis reactor, which will

hydrolyze the COS to CO2, H2S and CO. Hence for the plant without CO2 capture, a

particle scrubber is employed to remove solids entrained in the syngas, then COS

hydrolysis reactors are used to converted COS into H2S. The Selexol/Claus/SCOT

process is used for sulfur removal and recovery.

For the capture plant, after particle removal, the water gas shift reactor is used to

convert CO into CO2. The CO shift catalyst also hydrolyses COS to H2S. Hence there is

62
no need of a separate COS hydrolysis system. Two types of catalyst are usually used for

the water gas shift reaction [IEA, 2003]:

• Sour shift catalysts based on Co-Mo, which operate at medium/high temperature

and requiring a steam/dry gas volume ratio in the range of 1.1-1.6. This type of

catalysts can withstand high concentration of sulfur in syngas.

• Clean shift catalysts based on Fe-Cr or Cu, which operate at high temperature or

low temperature and require a steam/dry gas volume ratio equal to 1. For this type

of catalyst, the total sulfur content of syngas should be less than 10 ppm.

For IGCC systems with Texaco quench design, preliminary thermodynamic

analysis shows that sour shift dominates the clean shift option because syngas at particle

scrubber outlet has all the characteristics required by the sour shift reaction (temperature

and steam to carbon ratio). In the capture plant, the acid gases, H2S and CO2, are

removed through two Selexol processes, separately.

3.1.4. Gas turbine selection and steam cycle design

Syngas produced by gasification process is a type of Low Calorific Value (LCV)

fuel. GE gas turbines applied to LCV applications have accumulated rich experience and

hold a leading position in this field. In this study, GE 7FA is selected, which has been

designed to operate at base load conditions on syngas at Tampa Electric [Brdar, 2003].

Selection of a single- or multiple-pressure steam cycle for a specific application is

determined by economic evaluation, which considers the plant-installed cost, fuel cost

and quality, plant-duty cycle, and operating and maintenance cost. According to the

63
recommendation of GE, single- and multiple-pressure non-reheat steam cycles are

applied to systems equipped with GE gas turbines that have rating point exhaust gas

temperatures of approximately 1000°F / 538°C or less. Multiple-pressure reheat steam

cycles are applied to systems with GE gas turbines that have rating point exhaust gas

temperatures of approximately 1100°F / 593°C or greater [Chase, 2003]. Table 3-1 gives

such recommendations in detail. Since the exhaust gas temperature of GE 7FA is

approximately 1104 °F/596 °C, a three-pressure reheat steam cycle is employed in this

study.

Table 3 - 1 Steam and gas product line steam turbine throttle and admission steam
conditions

Heat Recovery Steam Cycle Non-Reheat Three-Pressure Reheat Three-Pressure


Steam Turbine Size (MW) ≤ 40 > 40 <60 ≥ 60 > 60
Throttle Pressure (psig) 820 960 1200 1400-1800
Throttle Temperature (°F) 40 approach to Gas Turbine 1000-1050
Exhaust Gas Temperature
Reheat Pressure (psig) 300-400
Reheat Temperature (°F) 1000-1050
IP Admission Pressure (psig) 100 120 155 300-400

IP Admission Temperature (°F) 20 Approach to Exhaust Gas Temperature upstream of


Superheater
LP Admission Pressure (psig) 25 25 25 40

LP Admission Temperature (°F) 20 Approach to Exhaust Gas Temperature upstream of


superheater

3.2. Major process sections of the IGCC model

The present model consists of slurry preparation units, gasification units with

quench, particle removal, low temperature gas cooling and clean up units, fuel expender,

fuel gas saturator and reheater, by product sulfur production, gas turbine system, steam

64
cycle system, and heat integration among different units. In addition to these units and

heat integration, the model also incorporates auxiliary power consumption for ASU and

summary files of the whole IGCC system.

Each major process section mentioned above is referred to as a flowsheet section in

Aspen models. Within each flowsheet, unit operation models represent specific

components of that process. There are user-specified inputs regarding key design

assumptions for each unit model. The numerical values of these design assumptions are

shown in this report. However, users can change these values to simulate their specific

design alternatives. The major flowsheet sections in the IGCC system are presented as in

the following.

3.2.1. Coal slurry preparation and gasification flowsheet

Coal from the coal grinding system is continuously fed to the grinding mill. Grey

water from waste water treatment facility is used for slurrying the coal feed. The coal

slurry with a desired slurry concentration is pumped into the gasifier. In this section, the

methodology used to model coal preparation is presented.

Coal is a type of non-conventional solid, and its composition has to be input by the

user in forms which Aspen accepts. In Aspen, the component attributes of coal are

specified in three forms: PROXANAL for proximate analysis, ULTANAL for ultimate

analysis, and SULFANAL for sulfur analysis. Table 3-2, as an example, gives the typical

compositions of Pittsburgh #8 coal and its input values for Aspen model. Aspen Plus

estimates the heat of coal combustion based on its PROXANAL, ULTANAL, and

SULFANAL. Users can also enter the heat of combustion directly.

65
Table 3 - 2 Coal composition and its corresponding input in Aspen Plus

Coal composition
(wet basis) PROXANAL ULTANAL SULFANAL
Element Value Element Value Element Value Element Value
ASH 7.24 MOISTURE 5.05 ASH 7.63 PYRITIC 1.23
CARBON 73.81 FC 49.855 CARBON 77.74 SULFATE 0
HYDROGEN 4.88 VM 42.515 HYDROGEN 5.14 ORGANIC 1
NITROGEN 1.42 ASH 7.63 NITROGEN 1.5
CHLORINE 0.06 CHLORINE 0.06
SULFUR 2.13 SULFUR 2.23
OXYGEN 5.41 OXYGEN 5.7

Figure 3 - 3 Slurry preparation and gasification flowsheet

Figure 3-3 illustrates the mass and heat flows in the coal slurry preparation process

and gasification units, and Table 3-3 shows the corresponding unit operations that are

simulated in Aspen Plus. The coal slurry is compressed up to 710 psia through a slurry

pump, which is simulated by a unit named as “SlurryPump”. Gasification simulation

calculates the Gibbs free energy of the coal. However, the Gibbs free energy of coal

cannot be calculated because it is a non-conventional component. Hence, a RYield unit,

which simulate a reactor with a known yield, and does not require reaction stoichiometry

66
and kinetics, named as “DeCoal” is used to decompose the coal into its constituent

elements based on the ultimate composition analysis of coal.

The gasification unit converts coal slurry into syngas. The coal slurry and oxygen

from the air separation unit react in the gasifier at high temperature (approximately 2450

°F), high pressure (approximately 620 psia in this study) and under the condition of

insufficient oxygen to produce syngas. Syngas consists primarily of hydrogen and carbon

monoxide with lesser amounts of water vapor, carbon dioxide, hydrogen sulfide,

methane, and nitrogen. Traces of carbonyl sulfide and ammonia are also formed. Ash

presenting in the coal melts into slag. Hot syngas and molten slag from the gasifier flow

downward into a quench chamber, which is filled with water, and is cooled into medium

temperature (approximately 450 °F). The slag solidifies and flows to the bottom of the

quench chamber.

In addition to CO, H2 and CO2, small amounts of CH4, HCl, COS and NH3 are also

formed. Various amounts of H2S depending on the sulfur content of the feed coal.

The Texaco process uses an entrained flow gasifier. Slagging is an important

problem with this type of gasifier. The slagging formation is modeled as follows.

In this study the gasification process is modeled on the fixed carbon conversion

model [Altafini, 2003; Zaimal, 2002], and simulated in three steps. At first, slag

formation is simulated in the Slag block based on the following stoichiometric reaction.

The stoichiometric coefficients of carbon and ash are determined by the ash percentage in

the coal and carbon loss in the gasification process.

67
mC+nAshÆSlag

Second, coal slurry from the Slag block mixed with oxygen from the ASU unit

enter the gasifier reactor, reactions occur in the reactor is simulated in GasifRx unit,

which is based on RGibbs model. RGibbs models chemical equilibrium by minimizing

Gibbs free energy. Chemical reactions and their approach temperatures1 modeled in this

equilibrium gasifier reactor are as follows [Altafini, 2003; Zaimal, 2002, Zhu, 2003]:

C+2H2ÆCH4 (approach temperature: -300°F)

C+H2OÆCO+H2

C+O2ÆCO

2CO+O2Æ2CO2 (approach temperature: -550°F)

CH4+2O2ÆCO2+2H2O (approach temperature: -500°F)

S+H2ÆH2S (approach temperature: -500°F)

N2+3H2Æ2NH3 (approach temperature: -500°F)

CO+H2SÆCOS+H2 (approach temperature: -500°F)

1
The approach temperature is a pseudo-temperature used in Aspen to adjust

calculated equilibrium concentrations to actual (observed) values under non-equilibrium

conditions.

68
Cl2+H2Æ2HCl (approach temperature: -300°F)

The reaction temperature and heat loss, which is assumed to be 1% of the total low

heating value of the inlet coal flow, in the gasification reactor is maintained by adjusting

the inlet flow rate of oxygen.

Third, raw syngas and molten slag discharge from the reactor into the quench

chamber, which is simulated by the Quench unit. The Quench unit performs rigorous

vapor-liquid equilibrium calculations to determine the thermal and phase conditions of

syngas saturation process. In this quench unit, molten slag is cooled down and separated

from the syngas.

Table 3 - 3 Coal slurry preparation and gasification process unit description.

No Aspen unit ID Unit parameters Unit function


1 CoalMult (Mult) Multiplication factor: Manipulate slurry flow rates through
0.5~5 Design Spefic
2 SlurryPMP Discharge P=710 psi This unit simulate coal slurry pump
(Pump)
Efficiency=Default
3 DeCoal(RStoic) Pressure=620 psi This block decomposes coal into its
elements using the Calcularor
Temperature=59 F
4 MkSlag (RStoic) Pressure=620 psi Simulate the stoichiometric reaction
which produces slag based on the
Temperature=59 F
coal’s ultimate analysis and carbon
loss percentage in gasification
process
5 GasifRX (RGibbs) Pressure=620 psi Simulate the stoichiometric reactions
occurring in the gasifier. Heating loss
Temperature=2450 F
in the gasifier is maintained as 1% of
Products: O2, N2, H2, CO, the total LHV of coal through Design
CO2, H2O, CH4, H2S, NH3, Specific
COS, HCL
6 Quench (Flash 2) Pressure drop=15 psi Simulate the quench process of
syngas, slag cooling and separation
Heat duty=0 But/hr

69
3.2.2. Low temperature gas cooling and clean up

Raw syngas from the quench chamber enters the scrubber to remove solid particles.

Figure 3-4 illustrates the mass flows in the syngas cooling process, and Table 3-4 shows

the corresponding unit operations that are simulated in Aspen Plus. The scrubber is

simulated by the block PartRemv, which separates solids from the syngas. As the first

step of sour gases removal, the syngas passes through a fixed bed, catalytic hydrolysis

reactor, which hydrolyzes the COS to CO2 and H2S, and the HCN to NH3 and CO.

Activated alumina type catalysts are generally employed for this application, and COS

concentrations approaching equilibrium levels can be achieved. This reactor is modeled

by a block named COSHydro, which is a rigorous equilibrium reactor based on

stoichiometric approach for the following hydrolysis reaction:

COS+H2OÆH2S+CO2

Syngas after COS hydrolysis is at a temperature of approximately 460 °F, which

has to be cooled down to approximately 100 °F for H2S removal. Blocks named as

SgasCol1~5 simulate this cooling process. Condensate water from this cooling process is

collected for the syngas quench and scrubber processes. Heat released from syngas

cooling is recovered to produce low pressure steam (390°F/48 psia) for steam cycle, and

intermediate pressure hot water (408°F/325 psia) for syngas saturation and reheating. The

flow rate of feed water for the low pressure steam and intermediate pressure hot water is

manipulated by the Design Specification SGTEMP, which adjusts the feed water flow

rate to satisfy the syngas temperature at the exit of the last syngas cooler is 100°F. The

flow rate ratio of the low pressure steam to the intermediate pressure hot water is

70
controlled by another Design Specification SGIPFLOW, which adjusts the flow rate of

the intermediate pressure hot water to meet the need of syngas saturating and reheating.

Table 3 - 4 Syngas cooling process unit description of the reference plant

No Aspen unit ID Unit parameters Unit function


1 Scrubber Pressure drop=10 psia Simulate the scrubber process of
(Flash 2) Heat duty=0 But/hr particle removal from raw syngas
2 COSHydro Pressure drop=5 psia Simulate the COS hydrolysis process
(REquil) Heat duty=0 But/hr converting COS into H2S
3 SgasCol1 Pressure drop=3 psia Simulate syngas cooler
(Heater)
4 SgasCol2 Pressure drop=3 psia Simulate syngas cooler
(Heater)
5 SgasCol3 Pressure drop=5 psia Simulate syngas cooler
(Heater)
6 SgasCol4 Pressure drop=3 psia Simulate syngas cooler
(Heater)
7 SgasCol5 Pressure drop=5 psia Simulate syngas cooler
(Heater)
8 FWPMP2 Discharge pressure=18 psia Simulate feed water pump
(Pump) Efficiency=default value
9 FWPMP3 Discharge pressure=18 psia Simulate feed water pump
(Pump) Efficiency=default value
10 FWSPLIT Indicate that feed water is divided into
(SPLIT) two streams, the flow rate to the LP
steam evaporator is manipulated by the
Design Specification SGIPFLOW

71
Figure 3 - 4 Syngas cooling section flowsheet of the reference plant

Figure 3-5 illustrates the mass flows in the syngas cooling process of the capture

plant, and Table 3-5 shows the corresponding unit operations that are simulated in Aspen

Plus. For the capture plant, syngas from the scrubber is at a temperature of approximately

420 °F. The water gas shift reaction occurs at two rectors, the high temperature reactor

and the low temperature reactor, which are simulated by block HTShift and LTShift. In

the shift reactors, the following reactions occur in the presence of catalysts:

72
CO+H2OÆCO2+H2

COS+H2OÆH2S+CO2

Because the shift reaction is exothermic, there is high quality energy available for

generating high pressure and intermediate pressure steam during the syngas cooling

process. Blocks named as HTCol1~4 and LTCOl1~5 simulate this cooling process. The

condensate water from this cooling process is collected for syngas quench and scrubber

processes. The high pressure steam is sent to the high pressure steam turbine. Part of the

intermediate pressure is used for syngas reheating, and the rest is sent to the steam cycle.

The flow rate of the feed water for the high pressure steam and the intermediate pressure

steam is manipulated by the Design Specification SGTEMP, which adjusts the feed water

flow rate to maintain the design syngas temperature at the exit of last syngas cooler. The

flow rate ratio of intermediate pressure steam to the high pressure steam is controlled by

another Design Specification SGSHIFT, which adjusts the flow rate of the high pressure

feed water to meet the temperature requirement for the low temperature shift reaction.

73
Table 3 - 5 Syngas cooling process unit description of the capture plant

No Aspen unit ID Unit parameters Unit function


1 Scrubber Pressure drop=10 psia Simulate the scrubber process of
(Flash 2) Heat duty=0 But/hr particle removal from raw syngas
2 SgasHet (Heater) Pressure drop=4 psia Simulate the syngas heater
Temperature=469.4 F
3 HTShift (Requil) Pressure drop=4 psia Simulate the high temperature shift
Heat duty=0 Btu/hr reactor
4 HTCol1 (Heater) Pressure drop=4 psia Simulate syngas cooler
5 HTCol2 (Heater) Pressure drop=3 psia Simulate syngas cooler
6 HTCol3 (Heater) Pressure drop=4 psia Simulate syngas cooler
7 HTCol4 (Heater) Pressure drop=5 psia Simulate syngas cooler
8 LTShift (Requil) Pressure drop=5 psia Simulate the low temperature shift
Heat duty=0 Btu/hr reactor
9 LTCol1 (Heater) Pressure drop=4 psia Simulate syngas cooler
10 LTCol2 (Heater) Pressure drop=4 psia Simulate syngas cooler
11 LTCol3 (Heater) Pressure drop=4 psia Simulate syngas cooler
12 LTCol4 (Heater) Pressure drop=4 psia Simulate syngas cooler
13 LTCol5 (Heater) Pressure drop=5 psia Simulate syngas cooler
14 FWPMP1 (Pump) Discharge pressure=365 Simulate feed water pump
psia
Efficiency=default value
15 FWPMP3 (Pump) Discharge Simulate feed water pump
pressure=1734 psia
Efficiency=default value
16 FWSPLIT (SPLIT) This unit is used to indicate that feed
water is divided into two streams, the
flow rate to the intermediate pressure
steam evaporator is manipulated by
the Design Specification SGSHIFT

74
Figure 3 - 5 Syngas cooling section flowsheet of the capture plant

75
3.2.3. H2S capture and sulfur recovery section

After COS hydrolysis, almost all of the sulfur in the gasifier feedstock is converted

into H2S. Figure 3-6 illustrates the mass and energy flows in the sulfur removal and

recovery section, and Table 3-6 shows the corresponding unit operations that are

simulated in Aspen Plus. In this modeling study, Selexol process, a physical solvent

system, is employed to capture H2S. A block, named as SulfSep, is used to simulate this

Selexol process. In this block, approximately 99% of H2S is removed from the syngas.

The H2S rich gas and the flash gas from the Selexol process are sent to the Claus/Scot

unit for sulfur recovery.

The Claus process has been the sulfur recovery workhorse for applications with

large amounts of sulfur. The Clause process is carried out in two stages. In the first stage,

about one third of the gases from the Selexol unit, which exits at about 120 °F, are burned

in the first furnace. This first furnace is simulated by the block named Furnace. In this

block, the following reaction is modeled based on stoichiometric mechanism which is

close to the real situation in the reactor. Low pressure air from an air compressor is used

as the oxidant of Claus reaction.

H2S+O2ÆSO2+H2O with 33% of H2S converted

The remaining acid gases enter the second stage furnace, where the H2S and SO2

react in the presence of a catalyst to form elemental sulfur:

2H2S+SO2Æ3S+2H2O

76
The gas is cooled in a waste heat boiler and then sent through a series of reactors

where more sulfur is formed. The sulfur is condensed and removed between each reactor.

An Aspen block, ClausRxr, is used to simulate the reactors, where 98% of H2S is

recovered because the Claus process is limited by chemical equilibrium to removal

efficiencies of approximately 98% if three catalytic reactor stages are employed. To

achieve higher removal efficiencies, a tail gas treating unit is required.

SCOT process is a conventional tail gas treating process. In the process, the tail gas

from the Claus unit and the flash gas from the Selexol unit are heated to approximately

570 °F in an in-line burner, which serves the dual purpose of heating the gas stream and

producing a reducing gas, which is needed in the downstream reactor. The effluent from

the burner is then passed over a cobalt-molybdenum catalyst. In the reactor, all of the SO2

and CS2 are converted to H2S by a combination of hydrogenation and hydrolysis

reactions. This process is modeled by the block named BsComb. In this block, the

following combustion and hydrogenation reactions occur:

CO+0.5ÆCO2

CH4+2O2ÆCO2+2H2O

SO2+3H2ÆH2S+2H2O

COS+H2OÆH2S+CO2

The reactor effluent gas is then cooled and processed through a Stretford unit,

where H2S is converted to elemental sulfur, and remaining gases exhaust to the

77
atmosphere. The block named StretFrd is used to model this process, where the following

reactions occur:

2H2S+O2Æ2S+2H2O

2H2+O2Æ2H2O

The block QMix, which simulates the heat recovery process of the waste heat

boiler, collects heat from the above reactors to preheat the feed water from the steam

cycle.

78
Table 3 - 6 Sulfur removal and recovery unit description

No Aspen unit ID Unit parameters Unit function


1 SulfSep (Sep) Flue gas: T=85 F, P=32 atm This unit simulates the Selexol
Acid gas: T=120 F, P=22 psia process for H2S removal.
Flash gas: T=58 F, P=115 psia
2 CAirComp Type: Isentropic Model the air compressor for
(Compr) Discharge pressure=23 psia Claus process
Isentropic efficiency=0.9
3 CAirMix1 Simulate the mixer of air and acid
(Mixer) gas from Selexol unit
4 Furnace (RStoic) Pressure drop=0 psia Simulate the first stage of Clause
Temperature=589 F process, where about one third of
acid gas from Selexol process is
burned.
5 ClausRxR Pressure drop=0 psia Simulate the second stage of
(RStoic) Temperature=589 F Clause process, where the H2S
and SO2 react in the presence of a
catalyst to form elemental sulfur.
6 ClausSep (Sep) Simulate the sulfur removal
process between each reactor,
water condensate, and tail gas
separation.
7 BsComp1 Type: Isentropic Model the air compressor for Scot
(Compr) Discharge pressure=30 psia process
Isentropic efficiency=0.9
8 BsComp2 Type: Isentropic Model the tail gas compressor for
(Compr) Discharge pressure=30 psia Scot process
Isentropic efficiency=0.9
9 BsMix (Mixer) Simulate the mixer of tail gas and
air
10 BsComb (RStoic) Pressure drop=0 psia Simulate the tail gas treatment
Temperature=400 F process, which converts SO2 into
H2S with the aid of a cobalt-
molybdate catalyst
11 Stretfrd (RStoic) Pressure drop=0 psia Simulate sulfur recovery process,
Temperature=100 F where H2S reacts with O2 to
generate Sulfur
12 QMix (Mixer) Simulate the waste heat boilers
which recover heat generated in
sulfur recovery process for feed
water heating in steam cycle

79
Figure 3 - 6 Sulfur removal and recovery section flowsheet

80
3.2.4. Clean syngas saturation, expend, and reheat section

Clean syngas from the Selexol unit for sulfur removal could be used as the fuel of

the gas turbine. In order to meet the emission and pressure requirements of the gas

turbine combustion, the fuel is saturated, expended, and preheated before entering the

combustion chamber. For the reference plant, fuel from the Selexol unit at a temperature

is heated up by the condensate water from the syngas cooling process in the heat, which

is simulated by the block FuelHet1. The heated fuel is expended in a turbine expender to

generate electricity, and its pressure is reduced to match the pressure at the gas turbine

combustor. Fuel from the expender enters the saturator to mix with the intermediate

pressure hot water produced in the syngas cooling process. Before entering the gas

turbine combustion chamber, the saturated fuel is preheated up to about 400 °F by the

intermediate pressure hot water from syngas cooling unit. Figure 3-7 illustrates the mass

and energy flows in the sulfur removal and recovery section, and Table 3-7 shows the

corresponding unit operations that are simulated in Aspen Plus.

81
Table 3 - 7 Sulfur removal and recovery unit description

No Aspen unit ID Unit parameters Unit function


0 CO2Sep (Sep) Simulate the CO2 capture process in a
Selexol unit for the capture plant
1 FuelHet1 Pressure drop=5 psia Simulate the fuel heater
(Heater) Temperature=290 F
2 FuelExpd Type: Isentropic Simulate the fuel expender which
(Compr) Discharge pressure=280 psia reduce the pressure of fuel to match
Isentropic efficiency=0.9 the requirement of gas turbine
combustor requirement
3 Satur Pressure drop=15 psi Simulate the fuel saturator, where
(Flash 2) Heat duty=0 But/hr water steam volume percentage in the
fuel is increased up to 16%
4 FuelHet2 Pressure drop=5 psia Simulate the fuel heater which heat
(Heater) Temperature=401 F the fuel to a temperature of 401 F

Figure 3 - 7 Fuel saturation and reheat section flowsheet of the reference plant

For the capture plant, fuel from the Selexol unit is sent to another Selexol unit for

CO2 capture, which is simulated by the block CO2Sep. The CO2 capture efficiency and

power consumption is calculated based CO2 capture model, which will be discussed later.

Fuel after CO2 capture is heated up by the hot water from syngas saturator. The fuel

heater is simulated by the block FuelHet1. The heated fuel is expended in a turbine

82
expender to generate electricity, and its pressure is reduced to match the pressure at the

gas turbine combustor. Fuel from the expender enters the saturator to mix the

intermediate pressure saturation water to added warm steam in the syngas. Before

entering the gas turbine combustion chamber, the saturated fuel is preheated by the

intermediate pressure steam from syngas cooling unit. Figure 3-8 illustrates the mass and

energy flows in the sulfur removal and recovery section, and Table 3-7 shows the

corresponding unit operations that are simulated in Aspen Plus.

Figure 3 - 8 CO2 capture, fuel saturation, and reheat section flowsheet of the
capture IGCC power plant

3.2.5. Gas turbine section

The gas turbine section design bases on the GE 7FA gas turbine system. Although

the original turbine design specifications are based on a natural gas rather than a coal

derived syngas, GE heavy-duty gas turbines have operated successfully burning alternate

gaseous fuels with heating values ranging from 11.2 to 116 MJ/m3 (300 to 3100 Btu/ft3

lower heating value) [Foster, 2003]. Figure 3-9 illustrates the mass and energy flows in

83
gas turbine section, and Table 3-8 shows the corresponding unit operations that are

simulated in Aspen Plus.

The pressure ratio of GE 7FA is 15.5, hence the air at the ambient conditions (59 F,

14.7 psia, and 60 percent relative humidity) is compressed up to 230 psia at a three-stage

compressor. The pressure ratio of each compression stage is one third of the total

pressure ratio. The compressor has several extraction points, from which some amount of

compressed air is removed and injected into the blades and vanes of the hottest turbine

stages for cooling. For GE 7FA gas turbine, approximately 11% of the total air flow rate

is used for gas turbine cooling.

The three-stage compressor is simulated by three units, GTComp1, GTComp2, and

GTComp3. The outlet pressures for these three stages are 37.82, 93.3 and 230 psia,

respectively. Three cooling air streams are moved at the outlet of each stage for turbine

cooling.

The saturated and reheated fuel and the air from the last stage of the compressor

enter the gas turbine combustion chamber, which is simulated by the block GTBurn. The

following chemical reactions are employed to simulate the combustion process:

2CO+O2Æ2CO2

2H2+O2Æ2H2O

CH4+1.5O2ÆCO+2H2O

2H2S+3O2Æ2H2O+2SO2

84
COS+1.5O2ÆCO2+SO2

2NH3+2.445O2Æ0.1N2+1.71NO+0.09NO2+3H2O

N2+1.05O2Æ1.9NO+0.1NO2

An amount of intermediate pressure steam from the steam cycle is used for the

combustion chamber cooling. The cooling process is simulated by the block GT_Qloss.

The heated steam comes back to the steam cycle. The firing temperature of GE 7FA gas

turbine is approximately 2350 °F, this temperature is maintained by a Design

Specification TIT, which manipulates the inlet temperature of the first stage gas turbine

by adjusting the flow rate of the coal slurry.

Hot combustion product gases enter the three-stage turbines at pressures of 228,

92.45, 37.29 psia, respectively. The outlet pressure of the last stage turbine is 15.2 psia.

The three turbines are modeled by three blocks, GTTurb1, GTTurb2, and GTTurb3. The

exhaust temperature of GE 7FA is 1106 °F, which is maintained through a Design

Specific TEXHAUST. The hot exhaust gases enter the HRSG to produce steam for the

steam cycle.

The overall mass flow rate in a gas turbine is typically limited by the turbine nozzle.

When the March number at the turbine nozzle is unity, the flow at the inlet of gas turbine

expender is choked. The choke flow rate calculation used in this model based on the

model developed by Frey [Frey, 2001]. The design specification TCHOKE sets the flow

rate of air at the compressor inlet to meet the choked flow condition.

85
Figure 3 - 9 Gas turbine section flowsheet

86
Table 3 - 8 Gas turbine unit description

No Aspen unit ID Unit parameters Unit function


1 GTMix1 Simulate the mixing of fuel and the
(mixer) compressed air for gas turbine
combustion
2 GTMix2 Simulate the mixing of cooling air
(mixer) and the combustion products
3 GTMix3 Simulate the mixing of cooling air
(mixer) and the combustion products
4 GTMix4 Simulate the mixing of cooling air
(mixer) and the combustion products
5 GTComp1 Discharge pressure=37.82 psia Simulate the fist stage of gas turbine
(Compr) Isentropic=0.918 compressor
6 GTComp2 Discharge pressure=93.3 psia Simulate the fist stage of gas turbine
(Compr) Isentropic=0.918 compressor
7 GTComp3 Discharge pressure=230 psia Simulate the fist stage of gas turbine
(Compr) Isentropic efficiency=0.918 compressor
8 GTBurn Pressure=228 psia Simulate the gas turbine combustor
(RStoic) Heat duty=0 Btu/hr
9 GT_Qloss Pressure drop=0 psia Simulate the heat loss in the
(Heater) Temperature change=16 F combustor during to cooling process
10 GTTurb1 Discharge pressure=92.45 psia Simulate the first stage of the gas
(Compr) Isentropic=0.919 turbine
11 GTTurb2 Discharge pressure=37.49 psia Simulate the second stage of the gas
(Compr) Isentropic=0.919 turbine
12 GTTurb1 Discharge pressure=15.2 psia Simulate the third stage of the gas
(Compr) Isentropic=0.919 turbine
13 GTSplit1 This block splits the compressed air
(Split) from the first stage of the gas turbine
compressor for gas turbine first stage
rotor cooling
14 GTSplit2 This block splits the compressed air
(Split) from the first stage of the gas turbine
compressor for gas turbine second
stage vane cooling
15 GTSplit1 This block splits the compressed air
(Split) from the first stage of the gas turbine
compressor for gas turbine first stage
vane cooling

87
3.2.6. Steam cycle section

The major components of the steam cycle section include the heat recovery steam

generator, the steam turbines (high, intermediate, and low pressure), condenser, the steam

bleed for gas turbine cooling, the recycle water pump and heater, and the deaerator. As

discussed above, a three-pressure reheat HRSG is adopted for this IGCC system. The

major parameters of this HRSG are given in Table 3-9.

Table 3 - 9 STAG product line steam turbine throttle and admission steam
conditions

Heat Recovery Steam Cycle Reheat Three-Pressure


Throttle Pressure (psig) 1400
Throttle Temperature (°F) 1000
Reheat Pressure (psig) 300
Reheat Temperature (°F) 1000
IP Admission Pressure (psig) 300
IP Admission Temperature (°F) 20 Approach to Exhaust Gas Temperature
upstream of Superheater
LP Admission Pressure (psig) 40
LP Admission Temperature (°F) 20 Approach to Exhaust Gas Temperature
upstream of superheater

Steam cycle process

The three-pressure reheat steam cycle is shown schematically in Figure 3-10, and

Table 3-10 gives the corresponding operation units in the Aspen Plus model. The

feedwater coming from the steam turbine condenser is preheated up to 221.9 °F in the

feed water preheater, which is simulated by the block FWHeat. The heat recovered from

the sulfur recovery process/and steam removed from the low pressure turbine is used to

preheat the feed water. The preheated feedwater enters the deaerator, which is simulated

88
by the block Dearer. After deaeration, the feed water is compressed up to 52 psia, and

enters the low pressure economizer, which is simulated by the block LPEc. In the low

pressure economizer, the feedwater is heated up to 253° F. Part of the low pressure feed

water is used to generate the superheated low pressure steam at 42 psia/500 °F through

the low pressure evaporator, which is modeled by the block LPEvap, and the low

pressure superheater, which is modeled by the block LPSupH. Another amount of the

feedwater is compressed up to 360.2 psig, and heated up to 408 °F in the intermediate

pressure economizer, which is simulated by the block IPEc2. Part of the intermediate

pressure feed water is used to generate the superheated intermediate pressure steam at

303 psia/581 °F through the intermediate pressure evaporator, which is modeled by the

block IPEvap, and the intermediate pressure superheater, which is modeled by the block

IPSupH. Another part of the intermediate feedwater is compressed to 1824.4 psia, and

heated up to 585 °F in the high pressure economizer, which is molded by the block

HPEc3. The high pressure hot water enters the high pressure evaporator, which is

modeled by the block HPEvap, to generate the high pressure saturation steam.

Before entering the high pressure turbine, the high pressure saturation steam is

heated up to 1000 °F in the high pressure superheater, which is simulated by the block

HPSupH. Steam from the high pressure turbine at 336 psia/606 °F mixes with the

intermediate pressure superheated steam, then is heated up to 1000 °F after flowing

through the reheater, which is modeled by the block ReHeat. The reheated steam flows

through the intermediate turbine, which is simulated by block IPTur1 and IPTur2. The

steam from the intermediate turbine at 40 psia/501.9 °F mixes with the steam from the

low pressure superheater, and then passes through the low pressure turbine, which is

89
simulated by block LPTur1, and LPTur2. The steam from the low pressure turbine at 0.67

psia/93.5 °F is condensed at the condenser, which is modeled by the block Cond.

Figure 3 - 10 GE 7FA gas turbine and steam cycle section flowsheet

90
Table 3 - 10 Steam cycle section unit description

No Aspen unit ID Unit parameters Unit function


Discharge pressure=20 psia
1 PmpMK (PUMP) Simulate the make up feed water pump
Efficiency=default value
Discharge pressure=17 psia
2 CndPmp1 (Pump) Simulate the condensate water pump
Efficiency=default value
Indicate the mixing of make up feed
3 FWMix (Mixer)
water and the condensate water
Pressure=17 psia Simulate the pre-heater of the feed
4 FWHeat (Heater)
Vapor fraction=0 water
Indicate the mixing of feed water and
5 DearMix (Mixer)
the low pressure hot water
Pressure=16.3 psia
6 Deaer (Flash 2) Simulate the deaerator
Vapor fraction=0.005
Indicate a amount of feed water is split
7 LPLoop (Fsplit)
to the low pressure economizer
Discharge pressure=52 psia Simulate the low pressure feed water
8 LPPump (Pump)
Efficiency=default value pump
Pressure drop=4 psia Simulate the low pressure economizer
9 LPEc (Heater)
Temperature=253 F for low pressure steam generation
Indicate a amount of low pressure feed
10 SP_LPEc (Fsplit)
water is split to the deaerator
Simulate the low pressure evaporator,
Pressure drop=4 psia
11 LPEvap (Flash 2) where the blow down is 1% of the inlet
Vapor fraction=0.99
water
Pressure drop=-2 psia Simulate the low pressure steam
12 LPSupH (Heater)
Temperature=500 F superheater
Indicate a amount of feed water is split
13 SP_Pmps (Fsplit)
to the intermediate pressure economizer
Discharge pressure=360.2 psia Simulate the intermediate pressure
14 IPPmp (Pump)
Efficiency= default value pump
Pressure=342.1 psia Simulate the first intermediate pressure
15 IPEc1 (Heater)
Temperature=253 F economizer
Pressure=325 psia Simulate the second intermediate
16 IPEc2 (Heater)
Temperature=408 F pressure economizer
Simulate the intermediate pressure
Pressure=308.8psia
17 IPEvap (Flash 2) evaporator, where the blow down is 1%
Vapor fraction=0.99
of the inlet water
Pressure=303psia Simulate the high pressure steam
18 IPSupH (Heater)
Temperature=581 F superheater

91
Table 3 – 10 continued
No Aspen unit ID Unit parameters Unit function
Discharge pressure=1824.4 psia
19 HPPmp (Pump) Simulate the high pressure pump
Efficiency= default value
Pressure=1733.2 psia Simulate the first high pressure
20 HPEc1 (Heater)
Temperature=253°F economizer
Pressure=1646.5 psia Simulate the second high pressure
21 HPEc2 (Heater)
Temperature=408°F economizer
Pressure=1564.2 psia Simulate the third high pressure
22 HPEc2 (Heater)
Temperature=585°F economizer
Simulate the high pressure evaporator,
Pressure=1486psia
23 HPEvap (Flash 2) where the blow down is 1% of the inlet
Vapor fraction=0.99
water
Pressure=1400 psia Simulate the high pressure steam
24 IPSupH (Heater)
Temperature=1000°F superheater
Discharge pressure=336 psia
25 HPTur (Compr) Simulate the high pressure turbine
Isentropic efficiency=0.92
Indicate the mixing of superheat
26 Re_Mix (Mixer) intermediate pressure steam and the
steam from high pressure turbine
Pressure=300 psia
27 ReHeat (heater) Simulate the steam reheater
Temperature=1000°F
Discharge pressure=60 psia Simulate the first stage of the
28 IPTur1 (Compr)
Isentropic efficiency=0.92 intermediate pressure turbine
Discharge pressure=40 psia Simulate the second stage of the
29 IPTur2 (Compr)
Isentropic efficiency=0.92 intermediate pressure turbine
Indicate the mixing of low pressure
30 LPMix (Mixer) superheat steam and the steam from the
intermediate turbine
Discharge pressure=24 psia Simulate the first stage of the low
31 LPTur1 (Compr)
Isentropic efficiency=0.89 pressure turbine
Indicate a amount of low pressure
32 BleedLP (Fsplit) steam is removed to the feed water pre-
heater
Discharge pressure=0.67 psia Simulate the second stage of the low
33 LPTur2 (Compr)
Isentropic efficiency=0.89 pressure turbine
Simulate the condenser, where the
Pressure=0.6252
34 Cond (Heater) steam from the last stage of the low
Vapor fraction=0
pressure turbine is condensed

92
Design specifications of the steam cycle

• Gas turbine exhaust stack temperature

In general, the HRSG stack temperature should be kept as low as possible to extract

as much gas turbine exhaust energy as possible to maximize cycle efficiency.

Occasionally, a concern with high sulfur gas turbine fuels is acid condensation on low

temperature heat transfer surfaces. In these cases, a low pressure turbine extraction may

be used to heat feedwater above the acid dew point prior to feedwater supply to the

HRSG economizer. In this study, the stack temperature of the gas turbine exhaust gases is

set to be 230 °F. This temperature is maintained by the design specification TSTACK,

which can adjust the feed water flow rate of the HRSG to meet the requirement of the

stack temperature.

• Pinch, sub-cool, and approach temperature

As shown in Figure 3-11, the pinch temperature is the temperature difference

between the gas turbine exhaust temperature and the temperature of saturation water at

the inlet of evaporator. The approach temperature is the temperature difference between

the main steam temperature and the GT exhaust temperature. The sub-cool temperature is

the temperature difference between the water temperature at the outlet of the economizer

and the temperature of the saturation water.

93
Figure 3 - 11 Typical exhaust gas temperature profile of one pressure system

If the pinch temperature and the approach temperature are too big, the gas turbine

exhaust energy will not be utilized efficiently. On the other hand, if they are too small,

heat transfer area will be very large, which will raise the capital cost. Generally, the pinch

temperature rage is from 8 to 20 °C, and the approach temperature range from 5 to 20 °C.

In order to avoid some of hot water in economizers evaporating, typically the sub-cool

temperature range is from 5 to 20 °C. The temperature profile of this three-pressure

reheat HRSG is shown by Figure 3-12.

The approach temperature and the sub-cool temperature can be satisfied by setting

the main steam temperature and the outlet temperature at the outlet of an economizer.

The pinch temperature is satisfied through a design specification TPINCH, which adjusts

the feedwater flow rates entering the high, intermediate, and low pressure economizers.

94
Figure 3 - 12 Typical exhaust gas/steam cycle temperature profile for three-
pressure reheat HRSG system

3.2.7. Convergence sequence of the IGCC model

Using the sequential-modular (SM) strategy, Aspen Plus performs flowsheet

calculations by executing each unit operation block in sequence, and using the calculated

output streams of each block as feed to the next block. When flowsheets with recycle

loops, design specifications, or optimization problems, it must be solved iteratively. In

this study, the convergence sequence is based on eleven design specifications and seven

calculators with FORTRAN blocks. Some of them are mentioned in earlier sections of

this report and the rest are elaborated upon in this section.

The water to coal ratio is varied by the FORTRAN block H2OCOAL in order to

meet the specified coal slurry composition. The elemental composition of coal

decomposition is calculated by the FORTRAN block DECOM based on the ultimate

composition analysis of the coal.

95
The FORTRAN block BSAIR maintains the air flow rate entering the combustion

reactor of the SCOT process based on the stoichiometric calculation. The FORTRAN

block CLAIR maintains the air flow rate entering the first reactor of the Claus process

based on the stoichiometric calculation. The flow rate of the make up feedwater for the

steam cycle is determined by the FORTRAN block STMAKUP, which takes into account

the blowdown in the IGCC system.

3.3. IGCC Cost Model

The cost models for oxygen-blown Texaco quench IGCC systems are developed

through updating a previous IGCC cost model developed by Frey [Frey, 1993]. The

references used for updating the cost model are given by the following table.

Table 3 - 11 References used for updating the IGCC cost model

Report No. Company Authors Year Sponsor Gasifier


1. Evaluation of Innovative Parsons W. Owens, 2000 DOE/EPRI E-gas
Fossil Fuel Power Plants
with CO2 Removal
2. Texaco Gasifier IGCC Base EG&G W. Shelton 2000 NETL Texaco
Cases J. Lyons
3. KRW Gasifier IGCC Base EG&G W. Shelton 2000 NETL KRW
Cases J. Lyons
4. Shell Gasifier IGCC Base EG&G W. Shelton 2000 NETL Shell
Cases J. Lyons
5. A single IGCC design for GE/Texac O’Keefe 2002 Texaco
variable CO2 capture o L.F.
Griffiths J.
6. Market-Based Advanced DOE 1999 DOE Destec
Coal Power Systems
7. Shift reactors and physical P. Chiesa 1999 Texaco
absorption for Low-CO2 S. Consonni
emission IGCCs

96
For the purpose of estimating the direct capital cost of the plant, the IGCC system is

divided into thirteen process areas as listed in the following table. The following section

gives the direct cost of each process area in a dollar value at 2000 year.

Table 3 - 12 IGCC system process areas

No. Cost section


1 Coal handling:
2 Oxidant feed
3 Gasification
4 LTGC
5 Selexol
6 Claus plant
7 Beavon-Stretford
8 Boiler feedwater treatment
9 Process condensate treatment
10 Gas turbine
11 HRSG
12 Steam turbine
13 General facilities

3.3.1. Oxidant Feed Section

This process section typically has an air compression system, an air separation unit,

and an oxygen compression system. The direct cost depends mostly on the oxygen feed

rate to the gasifier, as the size and cost of compressors and the air separation systems are

proportional to this flow rate. The direct cost model for the oxidant feed section is:

N T ,OF T a0.067 M O,G ,i 0.5618


DC OF = 196.2 ( ) (R2=0.86).....(3-1)
1 − η 0ox.073 N O,OF

97
N T ,OF , N O ,OF
where = the total trains of ASU and the total operating trains of ASU,

separately.

Ta ( 0 F ) = Ambient air temperature; 20 ≤ Ta ≤ 95; 0 F

M O ,G ,i (lbmole / hr ) = Gasifier oxygen inlet flow rate;

M O , G ,i
625 ≤ ≤ 17000 lbmole / hr
N O ,OF

η ox = oxygen purity; 0.95 ≤ η ox ≤ 0.98

This regression is based on the equation developed by Frey [Frey, 1993], and

revised using data from reports [3], [5-7]. Figure 3-13 gives the data points used for this

regression.

120000
Gasifier oxygen inlet flowrate (lb mole/hr)

100000

80000
Ref. 6
Ref. 7
60000
Ref. 3
40000 Ref. 5

20000

0
0 5000 10000 15000 20000
Oxidant feed section cost (k$ in 2000)

Figure 3 - 13 Oxygen flow rate vs. oxidant feed section cost

98
3.3.2. Coal Handling Section and Slurry Preparation

Coal handling involves unloading coal from a train, storing the coal, moving the

coal to the grinding mills, and feeding the gasifier with positive displacement pumps.

Slurry preparation trains consist of vibrating feeders, conveyors, belt scale, rod mills,

storage tanks, and positive displacement pumps to feed the gasifier. Coal feed rate to

gasifier on as-received basis is the most common and easily available independent

variable. The direct cost model for the coal handling is based on the overall flow to the

plant rather than on per train basis.

DC CH = 8.27M CF,G ,i (R2=0.8) (3-2)

where M CF,G ,i ( tons / day) : Gasifier as-received coal feed flow rate; 2,800~25,000

tons/day.

This regression is based on the equation developed by Frey [Frey, 1993], and

revised using data from reports [3-5], and [7]. Figure 3-14 gives the data points for coal

handling section cost analysis.

99
50000

Coal handling section cost (k$ in 2000)


45000
40000
35000
Ref. 7
30000
Ref. 3
25000
Ref. 4
20000
Ref. 5
15000
10000
5000
0
0 2000 4000 6000
Gasifier as-received coal feed flow rate
(ton/d)

Figure 3 - 14 Coal handling section cost vs. coal feed flow rate

3.3.3. Gasification Section

The Texaco quench gasification section of an IGCC plant contains gasifier, gas

scrubbing, gas cooling, slag handling, and ash handling sections. The direct capital cost

model is a function of the as-received coal flow rate.

DC G = 24770 N T ,G ln(M CG ,G ,i / N O,G ) − 167453 (3-3)

where N T ,G , N O ,G = the total trains of gasifier and the total operating trains of

gasifier, separately.

M CF,G ,i ( tons / day) = Gasifier as-received coal feed flow rate; 1,300~3,300

tons/day.

This regression is based on data from reports [1] and [3]. The data points are given

in Figure 3-15.

100
40000

Gasifier as-received coal flow rate (ton/d)


35000

30000

25000
Ref. 3
20000
Ref. 1
15000

10000

5000

0
0 1000 2000 3000 4000
Gasifier cost (k$ in 2000)

Figure 3 - 15 Coal flow rate vs. gasifier cost

3.3.4. Low temperature gas cooling

The low temperature gas cooling section consists primarily of a series of shell and

tube heat exchangers. The syngas mass flow is assumed to be the major determinant of

the process area capital cost as in the original cost model.

0.9
⎛ M syn ,LT ,i ⎞
DC LT = 0.0519 N T ,LT ⎜⎜ ⎟
⎟ (R2=0.92) (3-4)
⎝ N O,LT ⎠

where N T ,LT, N O,LT = the total trains and the total operating trains of low

temperature gas cooling, separately.

M syn ,LT,i (lb / hr ) = syngas inlet flow rate of low temperature gas cooling section,

⎛ M syn ,LT,i ⎞
650,000 ≤ ⎜⎜ ⎟ ≤ 1,300,000

⎝ N O ,LT ⎠

This regression is based on the data from reports [3-5]. The data points are shown in

Figure 3-16.

101
25000

Low temperature gas cooling section


20000

15000 Ref. 3
Ref. 4
10000 Ref. 5

5000

0
0 200000 400000 600000 800000 1000000 1200000 1400000
Syngas flow rate (lb/hr)

Figure 3 - 16 Low temperature gas cooling system cost vs. the syngas flow rate

3.3.5. Selexol Section

Hydrogen sulfide in the syngas is removed through counter-current contact with the

Selexol solvent. The cost of the Selexol section include the acid gas absorber, syngas

knock-out drum, syngas heat exchanger, flash drum, lean solvent cooler, regenerator air-

cooled overhead condenser, acid gas knock-out drum, regenerator reboiler, and pumps

and expanders associated with the Selexol process. The direct capital cost model for the

Selexol section is:

0.304 N T ,S M syn ,S,i 0.98


DC S = ( ) (R2=0.94) (3-5)
(1 − ηS ) 0.059 N O ,S

where N T ,S, N O,S = the total trains and the total operating trains of Selexol section

for H2S capture, separately.

ηS (%) = the H2S capture efficiency of Selexol system, 83.5%~99.7%.

102
M syn ,S,i (lbmol / hr ) = syngas inlet flow rate of Selexol section. 2,000~67,300

lbmol/hr

This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

3.3.6. Claus sulfur recovery Section

The Claus plant contains a two-stage sulfur furnace, sulfur condensers, and

catalysts. It cost is estimated as a function of the element sulfur outlet flow rate of the

Claus unit.

M S, C , o
DC C = 6.96 N T ,C ( ) 0.668 (R2=0.97) (3-6)
N O ,C

where N T ,C , N O,C = the total trains and the total operating trains of Claus section

for sulfur capture, separately.

M S,C ,o (lb / hr ) = the element sulfur outlet flow rate of the Claus, 695~18,100.

This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

3.3.7. Beavon-Stretford Tail Gas Removal Section

The capital cost of a Beavon-Stretford unit is expected to vary with the volume flow

rate of the input gas stream and with the mass flow rate of the sulfur produced.

M S,BS,o
DC BS = 63.3 + 72.8N T ,BS ( ) 0.645 (R2=0.99) (3-7)
N O ,BS

103
where N T ,BS, N O ,BS = the total trains and the total operating trains of Beavon-

Stretford for sulfur capture, separately.

M S,BS,o (lb / hr ) = the element sulfur outlet flow rate of Beavon-Stretford, 75~1,200.

This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

3.3.8. Boiler Feedwater System

The boiler feedwater system consists of equipment for handling raw water and

polished water in the steam cycle, including a water mineralization unit for raw water, a

dimineralized water storage tank, a condensate surge tank for storage of both

dimineralized raw water and steam turbine condensate water, a condensate polishing unit,

and a blowdown flash drum. The cost model considers both raw water flow rate through

the demineralization unit and the polished water flow rate through the polishing unit. The

polished water includes steam turbine condensate and makeup water, and condensate

from the miscellaneous process users such as waste water treatment.

DC BFW = 0.16M 0rw.307 M 0pw.435 (R2=0.99) (3-8)

where M rw (lb/hr) = the flow rate of raw water, 24,000~614,000.

M pw (lb/hr) = the flow rate of polished water in the steam cycle,

234,000~3,880,000

This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

104
3.3.9. Process Condensate Treatment

The process condensate treatment area consists of strippers, air cooled heat

exchangers, and knock-out drums. It is expected that the process condensate treatment

direct cost will depend primarily on the scrubber blowdown flow rate.

M SBD 0.6
DC PC = 10670( ) (3-9)
300000

where M SBD (lb / hr ) = the blowdown flow rate.

This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

3.3.10. Gas Turbine Section

A number of design factors affect the cost of a gas turbine in an IGCC system. In

this study, the cost model for the gas turbine was developed for a GE Frame 7F gas

turbine.

DC GT = 168MWe (R2=0.92) (3-10)

where, MWe = the net output of GE7F gas turbine (MW).

This regression is based on the data from reports [3] and [7]. The data points used

for regression are given in Figure 3-17.

105
70000

60000
Gas turbine cost (k$ in 2000)
50000

40000 Ref. 7
30000 Ref 3

20000

10000

0
0 100 200 300 400 500
Gas turbine net output (MWe)

Figure 3 - 17 Gas turbine cost vs. gas turbine net output

3.3.11. Heat Recovery Steam Generator

The HRSG is a set of heat exchangers in which heat is removed from the gas

turbine exhaust gas to generate steam, including the superheater, reheater, high pressure

steam drum, high pressure evaporator, and the economizers. The direct cost of the HRSG

is a simple regression model based on the high pressure steam flow rate to the steam

turbine.

M hps ,HR ,o
DC LT = −5943 + 7.98 × 10 −3 N T ,HR Phps
1.526
, HR , 0 ( ) 0.242 (R2=0.96) (3-11)
N O,HR

where N T ,HR , N O ,HR = the total trains and the total operating trains of HRST,

separately.

Phps ,HR ,o (lb / hr ) = the high pressure steam mass flow rate of HRSG,

M hps ,HR ,o
66,000 ≤ ( ) ≤ 64,0000
N O ,HR

106
This regression is based on the equation developed by Frey [Frey, 1993], and

adjusted with the chemical engineering price index.

3.3.12. Steam Turbine

A typical steam turbine consists of the high-pressure, intermediate-pressure, and

low-pressure turbine stages, a generator, and an exhaust steam condenser. The cost model

is given by

DC GT = 0.145We (R2=0.92) (3-12)

where We = the net output of gas turbine (kW), 200,000~500,000

This regression is based on the data from reports [6-7], which are shown in Figure

3-18.

40000
Steam turbine cost (k$ in 2000)

30000

Ref. 7
20000
Ref. 6

10000

0
0.E+00 5.E+04 1.E+05 2.E+05 2.E+05 3.E+05 3.E+05 4.E+05
Steam turbine net output (kW)

Figure 3 - 18 Steam turbine cost vs. steam turbine net power output

107
3.3.13. General Facilities

The general facility section includes cooling water system, plant and instrument air,

potable and utility water, and electrical system. Most studies assume that the direct cost

of the general facilities is approximately 14%-17% of the direct costs of other sections. In

the present study the direct cost of the general facilities is assumed to be approximately

15% of the total direct cost of the above 12 sections. Based on the direct cost of each

section, the process facility cost of each section is estimated as 1.2 times of its direct cost

[Frey, 1993].

3.3.14. Total Capital Requirement of IGCC systems

The following cost and parameter estimation of IGCC systems follows the

principles given by the EPRI Technical Assessment Guide (1993), which is widely

considered the industry standard and has long been an authoritative source of cost and

performance information on advanced and conventional power generation, storage,

transmission and distribution.

The total process facilities cost (PFC) of the IGCC system is the summation of the

individual process facility costs. Based on the PFC, the engineering and home office

costs can be estimated. The engineering and home office costs include the costs

associated with: (1) engineering, design, and procurement labor; (2) office expenses; (3)

licensing costs for basic process engineering; (4) office burdens, benefits, and overhead

costs; (5) fees or profit to the architect/engineer. EPRI recommends that a value of 7 to

15 percent of the process facility cost as the engineering and home office cost.

Therefore, a value of 10 percent is used here as a default.

108
Project contingency costs reflect the expected increase in the capital cost estimate

that would result from a more detailed cost estimate for a specific site. Usually, project

contingency is assigned as a multiplier of the process facility cost. A typical value for the

project contingency for a preliminary level cost estimate, as defined by the EPRI

Technical Assessment Guide, is 20 percent.

Another major cost item is the process contingency. The process contingency is

used in deterministic cost estimates to quantify the expected increase in the capital cost of

an advanced technology due to uncertainty in performance and cost for the specific

design application. In the EPRI cost method, the process contingency is estimated based

on separate consideration of contingencies for each process section. The contingency is

expressed as a multiplier of the sum of the plant facility cost for each process area. The

process contingency decreases as the commercial experience with a process area

increases. For example, in a fully commercialized process that has been used in similar

applications, the process contingency may be zero. The ranges of process contingency

factors for IGCC systems are shown in Table 3-13.

109
Table 3 - 13 Process contingency of cost sections

Cost section Process contingency


Coal handling: 0.05
Oxidant feed 0.05
Gasification 0.15
LTGC 0
Selexol 0.1
Claus plant 0.05
Beavon-Stretford 0.1
Boiler feedwater treatment 0
Process condensate treatment 0.3
Gas turbine 0.125
HRSG 0.025
Steam turbine 0.025
General facilities 0.05

The total plant cost (TPC) is the sum of process facility cost, the engineering cost,

the process contingency, and the project contingency. An allowance for funds during

construction (AFDC) is calculated based on the TPC as a function of the amount of time

it would take to construct the plant. Methods for computing the AFDC are documented

elsewhere [EPRI, 1993] and are not repeated here. The total plant investment (TPI)

represents the sum of the total plant cost and the AFDC.

The final measure of the capital cost is the total capital requirement (TCR). The

TCR includes the total plant investment plus owner costs for royalties, startup costs, and

initial inventories of stock feed. Preproduction costs typically include one month of both

fixed and variable operating costs and two percent of total plant investment. Inventory

capital is estimated as 0.5 percent of total process capital excluding catalyst. The initial

catalyst cost requirement is estimated based on the unit price of the catalysts and their

110
volumes. The total capital cost and O&M cost calculation processes are given in Table 3-

14.

Table 3 - 14 Capital cost elements of an IGCC power plant

Capital cost elements Value


Total process facilities cost Sum of the PFC of each section
Engineering and home office 10% PFC
General facilities 15% PFC
Project contingency 20% PFC
Process contingency See Table
Total plant cost (TPC) = PFC+Engineering fee+General facilities+Project & Process
Allowance for funds during construction Calculated based on discount rate and
(AFDC) construction time
Royalty fees 0.5% PFC
Preproduction fees 1 moth fee of VOM&FOM
Inventory cost 0.5% TPC
Total capital requirement (TCR) = TPC+AFDC+Royalty fees+Preproduction fee+Inventroy
Fixed O&M cost (FOM)
Total maintenance cost 2% TPC
Maintenance cost allocated to labor 40% of total maintenance cost
Administration & support labor cost 30% of total labor cost
Operation labor $25/hour
Variable O&M cost (VOM)
Fuel cost Depends on coal type
Consumable See Table 3-15

111
The fixed operation and maintenance costs, including labor, administration and

support cost are estimated as a fraction of the total plant cost. The variable cost and

expenses associated with operating the plant include: the consumable and fuel cost. The

unit costs of consumable are given by Table 3-15.

Table 3 - 15 Unit costs of consumables (Source: IECM manual)

Material Unit cost Unit


Sulfuric acid 119.52 $/ton
NaOH 239.04 $/ton
Na2 HPO4 0.76 $/lb
Hydrazine 3.48 $/lb
Morpholine 1.41 $/lb
Lime 86.92 $/ton
Soda ash 173.85 $/ton
Corrosion Inh 2.06 $/lb
Surfactant 1.36 $/lb
Chlorine 271.64 $/ton
Biocide 3.91 $/lb
Selexol Solv. 1.96 $/lb
Claus catalyst 478.08 $/ton
B/S catalyst 184.71 $/ft^3
Fuel oil 45.64 $/bbl
Plant air ads. 3.04 $/lb
Water 0.79 $/Kgal

112
REFERENCES (CHAPTER 3)

1. IEA Greenhouse Gas R&D Program, 2003: Potential for improvement in gasification
combined cycle power generation with CO2 capture, IEA report, report number
PH4/19

2. Brdar R.D., Jones R.M., 2003: GE IGCC Technology and Experience with Advanced
Gas Turbines, GE Power Systems, GER-4207

3. Chase D.L., Kehoe P.T., 2003: GE Combined-Cycle Product Line and Performance,
GE Power Systems, GER-3574G

4. IEA, 2000: Modeling and simulation for coal gasification, IEA Coal Research 2000,
ISBN 92-9029-354-3

5. Foster A.D., Doering H.E., and Hilt M.B., 2003: Fuel flexibility in heavy-duty gas
turbines, GE Company, Schenectady, New York

6. IEA Greenhouse Gas R&D Program, 2003: Potential for improvement in gasification
combined cycle power generation with CO2 capture, IEA report, report number
PH4/19

7. Brdar R.D., Jones R.M., 2003: GE IGCC Technology and Experience with Advanced
Gas Turbines, GE Power Systems, GER-4207

8. Chase D.L., Kehoe P.T., 2003: GE Combined-Cycle Product Line and Performance,
GE Power Systems, GER-3574G

9. IEA, 2000: Modeling and simulation for coal gasification, IEA Coal Research 2000,
ISBN 92-9029-354-3

10. Foster A.D., Doering H.E., and Hilt M.B., 2003: Fuel flexibility in heavy-duty gas
turbines, GE Company, Schenectady, New York

11. Frey H. C., 2001: Probabilistic modeling and evaluation of the performance,
emissions, and cost of Texaco gasifier-based integrated gasification combined cycle
systems using ASPEN, Janu. 2001

12. Owens W., 2000: Evaluation of Innovative Fossil Fuel Power Plants with CO2
Removal, 2000

13. Shelton W., Lyons J., 2000: Texaco Gasifier IGCC Base Cases, PED-IGCC-98-001,
last revision June 2000

14. Shelton W., Lyons J., 2000: NETL, KRW Gasifier IGCC Base Cases, PED-IGCC-98-
005, last revision June 2000

113
15. Shelton W., Lyons J., 2000: Shell Gasifier IGCC Base Cases, PED-IGCC-98-005,
last revision June 2000

16. O’Keefe L.F. Griffiths J., 2002: A single IGCC design for variable CO2 capture, Fifth
European Gasification Conference, April, 2002

17. Office of Fossil Energy, U.S. Department of Energy, 1999: Market-based advanced
coal power systems, Final report, May 1999

18. Chiesa P., Consonni S., 1999: Shift reactors and physical absorption for Low-CO2
emission IGCCs, Journal of engineering for gas turbines and power, 121 (2): 295-305
APR 1999

19. Zhu, Yunhua, 2004: Evaluation of Gas Turbine and Gasifier-Based Power Generation
Systems, PhD Dissertation, North Carolina State University August 2004.

114
Chapter 4. PERFORMANCE AND COST MODEL OF WATER GAS SHIFT
REACTION SYSTEM

4.1. Introduction

The water-gas shift (WGS) reaction is an industrially important reaction, which is

also a key part of the CO2 capture system in an IGCC power plant, for it converts almost

all the CO in syngas into CO2 for CO2 capture before combustion. Without this

conversion via the water gas shift reaction, the pre-combustion CO2 capture from IGCC

would not be an attractive option due to the low CO2 partial pressure of CO2 in the raw

syngas. The reaction is given as follows [David, 1980].

CO + H20 ↔ CO2 + H2 (4-1)

1
CO conversion percentage

0.95
CO/H2O=1.5
0.9 CO/H2O=2
CO/H2O=2.5
0.85
CO/H2O=3
0.8

0.75
400 600 800 1000
Equilibrium temperature (F)

Figure 4 - 1 Effects of temperature and CO/steam on the CO conversion of the


WGS reaction (This figure is derived based on that the original molar
concentration ratios of CO to H2O are 1.5, 2, 2.5, and 3, and the
original concentrations of CO2 and H2 equal zero)

This reaction is exothermic. Figure 4-1 shows the effect of the reaction temperature

of the water gas shift reaction on the equilibrium conversion of CO. Equilibrium will

favor CO conversion to CO2 at low temperatures. The equilibrium will also favor CO

conversion at high steam-to-CO ratios. The steam-to-CO ratio is determined by the

115
chemical process. For IGCC systems with CO2 capture, the steam required is

supplemented by existing upstream steam or water quench addition.

4.2. Effects of operation temperature and two-stage shift reaction system

Practically, the water gas shift reaction occurs in an adiabatic system with the

presence of a catalyst accelerating the reaction rate. In an adiabatic system, the CO slip is

determined by the exit temperature of the shift reactors, because low temperatures result

in low equilibrium levels of CO. On the other hand, favorable kinetics occurs at higher

temperatures. Either high steam-to-gas ratio or low temperature can improve CO

conversion percentage, but it also requires higher capital and operation cost. Hence, there

is a tradeoff between CO conversion percentage and costs.

Conversion in a single reactor is equilibrium limited. As the reaction proceeds, the

rise in temperature due to the exothermal reaction eventually restricts further reaction.

This limitation can be overcome with a two stage water gas shift reaction--a high

temperature shift reactor followed by a low temperature shift reactor. An inter-bed

cooling process is employed between the two reactors to keep the reaction occurring at

low temperature in the second reactor. Attainment of low equilibrium CO slip from the

low temperature reactor is critical to the efficient and economic operation of plants. A

typical CO variation in a two stage shift reactors is shown in Figure 4-2.

116
Figure 4 - 2 Typical CO variation in high temperature shift and low temperature
shift catalyst beds [Frank, 2003a]

4.3. Clean shift catalysts

Gases used in water gas shift reactors often contain sulfur component, such as H2S

and COS. These sulfur components have a detrimental effect on the activation of some

shift catalysts, which will be poisoned and lose activation in the presence of sulfur

components. On the other hand, sulfur components are necessary to maintain the

activation of some other shift catalysts. For the former type of shift catalysts, sulfur

components must be removed from reaction gases before the water gas shift reaction.

Hence this type of catalysts is so-called “clean shift catalyst”. A schematic flowsheet of

coal gasification system with a clean water gas shift reaction is given in Figure 4-3. The

syngas from the gasifier is cooled down, and fed to the soot scrubber to remove the bulk

of the carbon. Then it is further cooled for sulfur removal. Before passing to the shift

reactors, steam is added to the syngas to meet requirements of steam-to-carbon ration.

The inlet temperature of the second stage of the shift reaction is controlled by the

feed/effluent heat exchanger.

117
Figure 4 - 3 Coal gasification system with a clean water gas shift reaction

As mentioned above, a low operating temperature will give the most favorable

thermodynamic equilibrium and hence the minimum slip of carbon monoxide. For a two-

stage shift reaction system, the ideal operation is the low temperature shift reactor with

the lowest possible inlet temperature. There are two boundaries which limit the operation

temperature of the low temperature shift reactor. One is the activity of the catalyst at

lower temperature; the other is the dew-point of the process gases because condensation

on shift catalyst will weaken the clean catalyst pellets at low temperatures [Frank, 2003].

It has been reported that a low pressure plant was able to operate the low

temperature shift reactor at an inlet temperature of only 340 °F, because of the low dew-

point of the process gas [Frank, 2003a]. The dew-point of the process gas increases with

the increase of pressure. Hence, for high pressure cases it is the dew point, not the

activity of the catalyst, is more likely to be an operating limitation. IGCC systems usually

operate at a pressure high enough to allow the low temperature shift reaction to be

operated close to the dew point of the process gas. A safety margin above the dew point

should be used to ensure complete evaporation of water droplets that may form in the

cooler. This is adopted as a design criterion for a water gas shift reaction in an IGCC

system with a clean shift reaction.

118
For a two-stage shift reaction with clean shift catalysts, the iron-based catalyst is the

common commercially available high temperature catalyst. The commonly used low

temperature clean shift catalysts are copper-based. Both high temperature and low

temperature catalysts require activation by in situ pre-reduction steps. Since both

catalysts burn up when exposed to air (pyrophoric), they must be sequestered during

system shutdown when only air flows through the system [Frank 2003a].

The lifetimes of Cu-based catalysts and Fe-based catalysts are determined by the

poison-absorbing capacity of the catalysts. These poisons are inevitably present in the

process gas, such as syngas from coal gasification, or introduced with steam. As

mentioned above, the key poison in syngas is sulfur. Hence a sulfur removal process is

required upstream of the water gas shift reaction.

4.4. Sulfur tolerance shift catalysts

The so-called sour shift catalysts are sulfur tolerant, and sulfur is required in the

feed gas to maintain the catalyst in the active sulphided state. This type of catalyst is

usually cobalt-based.

Figure 4-4 shows the schematic process of a gasifier system with a sour shift

reaction. The syngas from the gasifier is quenched, and then the saturated syngas is fed to

the soot scrubber, to remove the bulk of particles before passing to the sour shift reactors.

The inlet temperature of the second stage of the shift reaction is controlled by the cooling

process. After heat recovery, the cooled syngas from the second shift reactor is passed to

the sulfur removal system.

119
Figure 4 - 4 Schematic process of a gasifier system with a sour shift

The sour shift catalyst has demonstrated its high and low temperature performance,

ranging from 210°C to 480°C, and work properly up to a pressure as high as 1160 psia

[Frank, 2003b]. Because the catalyst is not impregnated with a water-soluble promoter it

can be operated closer to the dew point and will not lose activity when wetted

occasionally.

In a gasification plant, the average catalyst life in the first stage shift reactor was 2.5

years, and 5-8 years in the second reactor [Frank, 2003b]. The difference in catalyst life

in the two reactors is highly influenced by the gas quality. These data of catalysts’

lifetime are adopted for the estimation of the operation and maintenance cost of the water

gas shift reaction system.

4.5. Performance model of the water-gas shift reaction process

This section presents the performance model developed for the WGS reaction

process. This is a general performance model for a two-stage shift system with either

clean shift catalysts or sulfur tolerant shift catalysts. The purpose of the performance

model is to characterize the change in syngas composition and flow rate as a function of

inlet condition to the WGS reactor and key design parameters of the WGS system. The

performance model also characterizes the heat integration between the shift reaction

system and the steam cycle system.

120
A general water gas shift reaction process model is illustrated in Figure 4-5. The

black box in this figure includes a high temperature reactor, a low temperature reactor

and several heat exchangers for heat recovery. The performance of the shift reaction was

first modeled in the Aspen Plus. In this model, the syngas from a gasifier is mixed with

steam or quenched at a given temperature and pressure, and then fed into the high

temperature reactor. Most of the CO in the syngas is converted to CO2 in the high

temperature reactor at a fast reaction rate. Because the water gas shift reaction is

exothermic, the syngas from the high temperature reactor has to be cooled before being

fed into the low temperature reactor. Further CO conversion is achieved in the low

temperature reactor. The shifted syngas from the low temperature reactor is cooled down

again for subsequent CO2 capture in a Selexol process. Part of the heat from syngas

cooling is used to heat the fuel gas from Selexol process, and the other part of the heat is

integrated into the steam cycle.

In this model, the reactions in the two reactors are assumed to achieve equilibrium

states. On the other hand, the shift reaction in a real reactor only approaches an

equilibrium state. In order to compensate for the difference between the equilibrium state

assumption and the real state in a reactor, the approach temperature method is used to

adjust the model equilibrium temperatures. The difference between the model

temperature and the design reaction temperature is referred to as the approach

temperature. The approach temperature is determined through comparing model outputs

with practical data from shift reactors in the industry field. Thus, with the approach

temperature, the reactor model is assumed to reach an equilibrium state at a higher

121
temperature than the design temperature, which makes the CO conversion efficiency in

the model to match the realistic situation.

Figure 4 - 5 Mass and energy flow of the water gas shift reaction system

The Aspen model had been executed thousands of times with varying the inlet

temperature, pressure and syngas composition. The value ranges of these parameters are

given in Table 4-1 which covers the possible ranges of gasification operation. The inlet

temperature was varied in a step of 30 F, and the inlet pressure was varied by a step of

100 psia. At the same time, 50 different syngas compositions were used. A total of 9000

cases were run. Based on the Aspen simulation results, statistical regression methods

were then used to develop relationships between the inlet conditions and the final

products of the WGS reaction. Using these regression relationships, the entire water gas

shift reaction system can be treated as a “black box” when it is used in the IECM

framework.

122
Table 4 - 1 Range of model parameter values for the WGS reaction system

Parameter Inlet Inlet CO in H2 in CO2 in H2O in CH4 in


temperature pressure the the the the the
(F) (psia) syngas syngas syngas syngas syngas
(vol%) (vol%) (vol%) (vol%) (vol%)
Value 440-755 150-1500 20-60 15-55 5-30 5-30 0.5-20

4.5.1. Input and output parameters of the WGS performance model

The input and outlet parameters of this model include the temperature, pressure, and

flow rates of the inlet and the outlet syngas as shown in Table 4-2. The input parameters

are used to calculate reaction rates and the composition changes after the reaction.

Table 4 - 2 Input and output parameters of the WGS reaction system

Input parameter Output parameter


Syngas Temperature (F) Shifted Temperature (F)
from syngas
Pressure (psia) Pressure (psia)
gasifier
Flow rate (lb-mole/hr) Flow rate (lb-mol/hr)
Molar concentrations of Molar concentration
CO, CO2, H2O, H2, N2, CH4 CO, CO2, H2O, H2, N2, CH4
Steam/carbon molar ratio Reaction rate & Catalyst volume (ft3)
Feed Pressure (psia) HP & IP Temperature (F)
water steam
Temperature (F) Flow rate (lb-mol/hr)

4.5.2. Performance model output

This section discusses the performance outputs of this model. In this section, the

CO to CO2 conversion is defined and calculated using the chemical equilibrium constant.

The outlet temperatures and syngas composition of the two shift reactors are regressed

from Aspen model simulation results. The heat released from the syngas cooling is also

quantified for the energy balance calculation of the whole IGCC system. The detailed

calculation processes of CO conversion efficiency and catalyst volumes are given in

123
Appendix A and B. Appendix C shows the practical utilization of this model through a

case study.

Shifted syngas composition

The water gas shift reaction occurring in both the high and low temperature reactors

changes the concentration of syngas species and the temperature of the syngas. The CO

conversion efficiency ( ξ ) can be used to show how much CO is converted into CO2 in

one reactor or in two reactors.

CO flowrate in (lb ⋅ mol / hr ) − CO flowrate out (lb ⋅ mol / hr )


ξ= (4-2)
CO flowrate in (lb ⋅ mol / hr )

A numerical model is set up to calculate the CO conversion in a shift reactor for

given inlet parameters. The detailed calculation process is given in Appendix A.

Based on the definition of the CO conversion and stoichiometric factors of the

reaction, the CO concentration of syngas exiting the high temperature reactor is given by,

[CO] h ,o = [CO]0 ⋅ (1 − ξ h ) (4-3)

where [CO] h ,o = the molar concentration of CO in the syngas exiting the high

temperature reactor

[CO]0 = the molar concentration of CO in the syngas entering the high temperature

reactor

ξ h = the CO conversion in the high temperature reactor

124
Based on the shift reaction (Eq. 4-1) and the definition of CO conversion, the molar

concentrations of H2, CO2 and H2O after the high temperature reactor are given by,

[CO 2 ] h ,o = [CO 2 ]0 + [CO]0 ⋅ ξ h (4-4)

[H 2 ] h ,o = [H 2 ]0 + [CO]0 ⋅ ξ h (4-5)

[H 2 O] h ,o = [H 2 O]0 − [CO]0 ⋅ ξ h (4-6)

Using the CO conversions definition and Equation (4-3), the CO concentration of

shifted syngas after the low temperature reactor is to be given by,

[CO]l,o = [CO]0 ⋅ (1 − ξ tot ) (4-7)

where [CO]l,o = the molar concentration of CO in the syngas exiting the low

temperature reactor

ξ tot = the total CO conversion in the high and low temperature reactors

Then the concentrations of H2, CO2 and H2O after the low temperature reactor are

given by,

[H 2 ]l,o = [H 2 ]0 + [CO]0 ⋅ ξ tot (4-8)

[CO 2 ]l,o = [CO 2 ]0 + [CO]0 ⋅ ξ tot (4-9)

[H 2 O]l,o = [H 2 O]0 − [CO]0 ⋅ ξ tot (4-10)

125
Flow rate of high pressure saturation steam

In the following two sections, temperature changes and flow rates of water and

syngas are calculated, and then used for the following cost model.

Syngas from the high temperature reactor is cooled down to a temperature which is

determined by the dew point of syngas before it is fed into the low temperature reactor.

According to the heat integration design, heat from the exothermic reaction is recovered

to generate high pressure saturated steam for the steam cycle.

The temperature of the saturation steam is determined by the high pressure steam

cycle in the power block. Using the data from the ASME steam and water table (1967),

the temperature is given by the following regression equation:

T w ,sat (F) = 328.34 + 0.3565Psc − 0.0002Psc2 + 6 ⋅ 10 −8 Psc3 − 7 ⋅ 10 −12 Psc4

(R2=0.99) (4-11)

where Psc (psia) = the pressure of steam cycle, (300 ~ 3000 psia)

The heat released by the syngas after the high temperature reactor is determined by,

Q HE1 (Btu / hr ) = q HE1 ⋅ f SG ,0 (4-12)

where f SG ,0 = the total molar flow rate of syngas entering the high temperature

reactor (lb-mole/hr);

q HE1 = the heat released per lb-mole syngas after the high temperature reactor,

which is regressed and given by (Btu/lb-mole),

126
q HE 1 ( Btu / lbmol ) = P00.0360 T01.2874 [CO ]10.14347 [CO 2 ] 0−0.4734
0 .3150 0.0003 0 .0139
(R2=0.95) (4-13)
[H 2O] 0 [H ]
2 0 [N ]
2 0

where P0 = the pressure of syngas entering the high temperature reactor (psia)

T0 = the temperature of syngas entering the high temperature reactor (F)

[i ]0 =the molar concentration of species i entering the high temperature reactor

Based on the total heat available and the saturation temperature, the flow rate of the

saturation high pressure steam ( f HPS , lb-mole/hr) can be calculated by the following

equation,

QHE1
f HPS = (4-14)
(hTw , sat − hT0 )

where hTw , sat = the enthalpy of the steam at the saturated temperature (Btu/lb-mole)

hT0 = the enthalpy of high pressure feed water at the inlet temperature (Btu/lb-mole).

Flow rate and temperature of the intermediate pressure steam

The syngas from the low temperature reactor is cooled to 100 F for sulfur removal,

and the heat is recovered to generate the intermediate pressure steam. The total heat Qtot

(Btu/hr) released when the syngas from the low temperature reactor is cooled down to

100 °F is given by,

127
Q tot = f l,o (9.255⋅ Tl,o − 0.316⋅ Pl,o − 1386.1 ⋅ [CO]l,o − 297.779⋅ [CO2 ]l,o − 1485.34 ⋅ [H 2 ]l,o
+ 17595.87 ⋅ [H 2 O]l,o − 1439.29 ⋅ [N 2 ]l,o − 331.533⋅ [CH4 ]l,o )

(R2=0.95) (4-15)

where f l ,o = the molar flow rate of syngas exiting the low temperature reactor (lb-

mole/hr);

Tl ,o = the syngas temperature at the outlet of the second reactor

Pl ,o = the syngas pressure at the outlet of the second reactor

[i ]l ,o = the molar concentration of species i at the outlet of the second reactor

In order to meet the approach temperature requirement in the superheater, the final

temperature of the intermediate pressure steam ( THPS ) is set to be 10 F lower than the

outlet temperature of the syngas from the second shift reactor, and the feedwater

temperature is set to be 59 F. Hence the flow rate of the intermediate pressure steam

( f IPS , lb-mole/hr) is given by,

( f HPS + f IPS ) ⋅ (hIPsat − hFW ) + f IPS ⋅ (hIPS − hIPsat ) = Qtot (4-16)

where f HPS = the flow rate of the high pressure saturation steam (lb-mole/hr)

hIPsat = the enthalpy of the intermediate pressure saturation water at the inlet

temperature (Btu/lb-mole)

hFW = the enthalpy of the feedwater (Btu/lb-mole)

128
hIPS = the enthalpy of the final intermediate pressure steam (Btu/lb-mole)

4.6. Cost model of WGS reaction process

This section presents the economic model developed for the water gas shift reaction

process. The cost model is comprised of the capital cost model and the annual operating

and maintenance (O&M) cost model. The capital cost of the WGS reaction system

includes the following major process areas: the first stage shift reactor, the second shift

reactor and the cooling units. For each of these major areas, its process facilities cost

model is developed at first.

4.6.1. Process facility cost

The process facility cost of the reactor includes the reaction vessel, structural

supports, dampers and isolation valves, ductwork, instrumentation and control, and

installation costs. The reactor vessels are made of carbon steel. The process facility costs

of the shift reactors are estimated based on the reactor volumes, which is assumed to be

1.2 times the catalyst volume [Doctor, 1994]. The catalyst volume calculation process is

described in Appendix A.

Process facility cost of shift reactors

The process facility costs of the high and low temperature shift reactors are

regressed as a function of reactor volume and operation pressure using the data in Table

4-3.

1 .2V cat . 0.4883 2.028


PFC R = 0 .9927 ⋅ N T , R [17 .6487 ( ) PR ] (R2=0.9) (4-17)
N O ,R

129
where PFC R = the process facility cost of the reactor (US$ in 2000)

N T , R = the total number of the reactor trains

N O , R = the number of the reactor operating trains

Vcat . = the volume of catalyst (m3)

PR = the operation pressure of the reactor (atm)

Table 4 - 3 Water gas shift reactor cost data adjusted to the dollar value in 2000
[Doctor, 1996]

Cost ($ in 2000) Reactor volume(m3) Pressure(atm)


82864.8 22.6 31.1
38692.2 34 18.7

59189.0 9.684 31.0

21495.0 11.553 18.7

Process facility cost of heat exchangers

In this model, two types of heat exchangers are used, which are the gas-liquid type,

and the gas-gas type. Generally, the cost of a heat exchanger depends on its heat

exchange surface, which is determined by the heat load of the exchanger and the

temperature difference between the hot and cold flows. To allow for variations in these

parameters, the process facility cost of the gas-liquid type heat exchanger was regressed

using the data in Table 4-4,

QHE 0.6855
PFC HE1 = 1.0064 ⋅ N T , HE ⋅ [13.7528(dTHE ) −0.6714 ( ) ] (R2=0.91) (4-18)
N O , HE

130
where PFC HE1 = the process facility cost of the gas-liquid heat exchanger (US k$

in 2000)

N T , HE = the number of total train of the heat exchanger

N O , HE = the number of the operating train of the heat exchanger

Q HE = the heat load of the heat exchanger (kW)

dTHE = the log mean temperature difference (C)

Table 4 - 4 Gas-liquid heat exchanger cost data adjusted to the dollar value in 2000
[Doctor, 1996]

Log mean temperature


Cost (K$ in 000) Pressure (atm) difference (C ) Heat load (kW)
625.4 30.7 68.2 16421.6
615.0 30.7 90.8 21052.4
210.2 18.7 190.4 9298.0
168.2 19.4 148.6 5036.0
472.9 19.4 121.0 19534.9
315.3 19.4 13.7 1293.1
210.2 18.7 190.4 9298.0
99.8 19.4 153.5 2407.3
210.2 20.4 190.4 9298.0
634.6 68.1 52.0 12119.7
210.2 157.8 190.4 9298.0

Based on the data in Table 4-5, the process facility cost of the gas-gas type heat

exchanger is given by,

− 0.1143 Q HE 2 0.3881
PFC HE 2 = 0.9927 ⋅ N T , HE 2 [ 24.4281 ⋅ PHE
0.2804
2 (dTHE 2 ) ( ) ]
N O ,HE 2

131
(R2=0.94 (4-19)

where PFC HE 2 = process facility cost of gas-gas heat exchanger (US k$ in 2000)

N T , HE = the total train number of the heat exchanger

N O , HE = the operating train number of the heat exchanger

Q HE = the heat load of the heat exchanger (kW)

dTHE = the log mean temperature difference in the heat exchanger

Table 4 - 5 Gas-gas heat exchanger cost data adjusted to the dollar value in 2000
[Doctor, 1996]

Pressure Log mean


Cost (k$ in 2000) (atm) temperature (C ) Heat load (kW)
1757.3 30.7 98.0 17319.5
1757.3 30.7 90.7 16776.2
2205.4 19.4 10.0 42480.7
3131.2 30.7 318.4 100832.3
2606.0 31.6 340.4 95833.1
897.1 68.1 17.2 1223.6
2193.5 18.7 31.8 25641.0
1294.8 18.7 19.4 4034.0
644.3 20.4 69.1 2407.3
849.9 20.4 71.4 5036.0
692.1 20.4 57.5 2407.3
966.5 18.7 51.2 5036.0

132
4.6.2. Total capital requirement of WGS reaction system

The total process facilities cost of the water gas shift reaction system is the

summation of the individual process facility costs above plus the cost of initial catalyst

charge. This is added because it is also a large and integral part of the reaction system.

Following the EPRI Technical Assessment Guide (1993), the total capital requirement

and O&M cost of the WGS reaction system is given in the following table.

Table 4 - 6 Cost parameters of water gas shift process

Capital cost elements Value


Total process facilities cost Sum of the PFC of each equipment
Engineering and home office 10% PFC
General facilities 15% PFC
Project contingency 20% PFC
Process contingency 5% PFC
Total plant cost (TPC) = PFC+Engineering fee+General facilities+Project & Process
i
Allowance for funds during construction Calculated based on discount rate and
(AFDC) construction time
Royalty fees 0.5% PFC
Preproduction fees 1 month of VOM&FOM
Inventory cost 0.5% TPC
Total capital requirement (TCR) = TPC+AFDC+Royalty fees+Preproduction fee+Inventory cost
Fixed O&M cost (FOM)
Total maintenance cost 2% TPC
Maintenance cost allocated to labor 40% of total maintenance cost
Administration & support labor cost 30% of total labor cost
Operation labor 1 jobs/shift
Variable O&M cost (VOM)
High temperature catalyst $250/ft3, replaced every 2.5 years
Low temperature catalyst $250/ft3, replaced every 6 years

133
REFERENCES (CHAPTER 4)

1. Campbell J.S., 1970: Influences of catalyst formulation and poisoning on activity


and die-off of low temperature shift catalyst, Industrial & engineering chemistry
process design and development, 9(4): 588

2. Davis R.J., 2003: All That Glitters Is Not AuO, Science, Vol. 301, Issue 5635

3. Dmitrievich A., 2002: Hydrodynamics, mass and heat transfer in chemical


engineering. Taylor & Francis Press, New York

4. Doctor R.D., 1994: Gasification combined cycle: carbon dioxide recovery,


transport, and disposal, ANL/ESD-24, Argonne National Laboratory, Argonne, IL

5. Doctor R.D., 1996: KRW oxygen-blown gasification combined cycle carbon


dioxide recovery, transport, and disposal, ANL/ESD-34, Argonne National
Laboratory, Argonne, IL

6. Enick R.M. and Busfamante F., 2001: Very High-Temperature, High-Pressure


Homogenous Water Gas Shift Reaction Kinetics, 2001 AIChE Annual Meeting,
Reno

7. Frank P., 2003a: Low Temperature Shift Catalysts for Hydrogen Production,
Johnson Matthey Group

8. Frank P., 2003b: Sulfur Tolerant Shift Catalyst -Dealing with the Bottom of the
Barrel Problem, Johnson Matthey Group

9. Newsome D.S., Kellogg P., 1980: The Water-Gas Shift Reaction, CATAL. REV.-
SCI. ENG., 21(2)

10. Park J.N., Kim J.H., 2000: and Ho-In Lee, A Study on the Sulfur-Resistant
Catalysts for Water Gas Shift Reaction IV. Modification of CoMo/ g-Al2O3
Catalyst with K, Bull. Korean Chem. Soc. Vol. 21, No. 12

11. ASME steam table (saturation: pressure), http://www.e-


cats.com/databook/Page%2047.htm

12. Twigg M.V., 1989: Catalyst handbook, second edition, Wolfe publishing Ltd

134
Chapter 5. PERFORMANCE AND COST MODEL OF SELEXOL PROCESS
FOR CO2 CAPTURE

5.1. Introduction to the Selexol absorption process

The Selexol process uses a physical solvent to remove acid gas from the streams of

synthetic or natural gas. It is ideally suited for the selective removal of H2S and other

sulfur compounds, or for the bulk removal of CO2. The Selexol process also removes

COS, mercaptans, ammonia, HCN and metal carbonyls [Epps, 1994].

The Selexol process, patented by Allied Chemical Corp., has been used since the

late 1960s. The process was sold to Norton in 1982 and then bought by Union Carbide in

1990 [Epps, 1994]. The Dow Chemical Co. acquired gas processing expertise, including

the Selexol process, from Union Carbide in 2001. The process is offered for license by

several engineering companies—the most experienced of which with the process is

probably UOP [UOP, 2002].

The Selexol process has been used commercially for 30 years and has provided

reliable and stable operations. As of January 2000, over 55 Selexol units have been put

into commercial service [Kubek, 2000], which cover a wide variety of applications,

ranging from natural gas to synthetic gas. By now, Selexol process has been the dominant

acid-gas removal system in gasification project. Moreover, increasingly interests to

control CO2 emission in the world may lead to Selexol application widely, particularly for

coal gasification plants. Actually, the use of the Selexol solvent has a long history in

gasification process, and was chosen as the acid-gas removal technology for the

pioneering work in this area. Due to its outstanding record, the Selexol process continues

to be the preferred choice for acid-gas removal today, and has recently been selected for

135
several large projects around the world [Breckenridge, 2000]. Relevant experiences for

gasification are as follows [Kubek, 2000].

• About 50 Selexol units have been successfully commissioned for steam

reforming, partial oxidation, natural gas, and landfill gas. Of these, 10 have been

for heavy oil or coal gasifiers.

• The 100 MW Texaco/Cool Water (California) 1,000 t/d coal gasifier plant for

IGCC demonstration was operated continuously for about five years in the 1980s.

The Selexol unit performed extremely well. The process delivered H2S-enriched

acid gas to a Claus plant while removing 20 to 25% of the CO2 and treating a high

CO2/H2S ratio feed gas.

• The TVA/Muscle Shoals (Alabama) 200 t/d coal gasifier demonstration plant was

operated continuously for about five years in the early 1980s. It employed a

Texaco gasifier, a COS hydrolysis unit, and a Selexol unit to convert coal to clean

synthesis gas, and CO2 as an alternative feed to an existing ammonia-urea plant.

The COS hydrolysis and Selexol units were stable and had a high on-stream

factor. The Selexol unit delivered an H2S-enriched acid gas to elemental sulfur

production, a pure (< 1 vppm total sulfur) synthesis gas to NH3 synthesis, and

removed part of the CO2 to provide high-purity CO2 for urea production.

In this section, the technical background information of Selexol process is

reviewed. This information is used to provide a basis for the development of performance

models of Selexol systems for CO2 emission control of IGCC plants.

136
5.2. Selexol solvent property

The Selexol acid gas removal process is based on the mechanism of physical

absorption. The solvent used in the Selexol acid removal system is a mixture of dimethyl

ethers polyethylene glycol with the formulation of CH3(CH2CH20)nCH3, where n is

between 3 and 9 [Epps, 1994]. The general properties of the glycol solvent is given in

Table 5-1 [Sciamanna, 1988; Newman, 1985].

Table 5 - 1 Property of glycol solvent

Property Value
Viscosity @25C,cp 5.8
Specific gravity@25C,kg/m^3 1030
Mole weight 280
Vapor pressure @25C, mmHg 0.00073
Freezing point C -28
Maximum operating Temp., C 175
Specific heat@25C Btu/lb F 0.49

The performance of a physical solvent can be predicted by its solubility. The

solubility of an individual gas follows the Henry’s law—the solubility of a compound in

the solvent is directly proportional to its partial pressure in the gas phase. Hence, the

performance of the Selexol processes enhances with increasing the partial pressures of

sour gases. This is one of the major advantages of physical solvents, such as Selexol, over

chemical solvents, such as methyldiethanolamine (MDEA), for acid gases removal from

the high pressure syngas. As shown in Figure 5-1, compared to physical solvents,

chemical solvents, such as methyldiethanolamine (MDEA) and diethanolamine (DEA),

have higher absorption capacity at relatively low acid gas partial pressures. However,

their absorption capacities plateau at higher partial pressures. The solubility of an acid

137
gas in physical solvents increases linearly with its partial pressure. Therefore, chemical

solvent technologies are favorable at low acid gas partial pressures and physical solvents

are favored at high acid gas partial pressures. Furthermore, the physical absorption allows

for the solvent to be partially regenerated by pressure reduction, which reduces the

energy requirement compared to chemical solvents.

Figure 5 - 1 Characteristics for Chemical and Physical Solvents [Sciamanna, 1988]

Higher partial pressure leads to higher solubility in physical solvents of all

components of a gas stream, but the attractiveness of the Selexol system is that it has a

favorable solubility for the acid gases versus other light gases. Comparing with some acid

gases, H2 and CO have much lower solubility in the solvent. For instance, as shown in

Table 5-2, CO2 is 75 times more soluble than H2, and H2S is 670 times more soluble than

H2 in Selexol.

138
Table 5 - 2 Relative solubility of gases in Selexol solvent [Doctor, 1994]

Gas CO2 H2 CH4 CO H2S COS SO2 NH3 N2 H2O


Solubility 1 0.01 0.0667 0.028 8.93 2.33 93.3 4.87 0 733

Table 5-3 shows the actual solubility of various gases at 25°C in the Selexol solvent.

The solubility data in Table 5-3 are based on single component solubility. It would be

expected that these values should be approximately the same for non-polar components

even in acid gas loaded solvents [Korens, 2003].

Table 5 - 3 Solubility of Gases in the Selexol Solvent [Korens, 2002]

Gas CO2 H2 CH4 CO H2S COS HCN C6H6 CH3SH H2O


Solubility,
Ncm2/g.bar 3.1 0.03 0.2 0.08 21 7.0 6600 759 68 2200
@25°C

The solvent may be regenerated by releasing the absorbed sour gases. The

regeneration step for Selexol can be carried out by either thermally, or flashing, or

stripping gas. In addition to its solubility, the Selexol solvent has some other positive

advantages to gasification applications [Kubek, 2000].

• A very low vapor pressure that limits its losses to the treated gas

• Low viscosity to avoid large pressure drop

• High chemical and thermal stability (no reclaiming or purge) because the solvent

is true physical solvent and do not react chemically with the absorbed gases

[Shah, 1988]

• Nontoxic for environmental compatibility and worker safety

139
• Non-corrosive for mainly carbon steel construction: the Selexol process allows for

construction of mostly carbon steel due to its non-aqueous nature and inert

chemical characteristics

• Non-foaming for operational stability

• Compatibility with gasifier feed gas contaminants

• High solubility for HCN and NH3 allows removal without solvent degradation.

• High solubility for nickel and iron carbonyls allows for their removal from the

synthesis gas. This could be important to protect blades in downstream turbine

operation.

• Low heat requirements for regeneration because the solvent can be regenerated by

a simple pressure letdown

5.3. Technical Overview Selexol process for acid gas removal

This section presents a technical overview of Selexol absorption processes for sour

gases removal, with particular focus on the effects of the sour remove requirements on

the design of Selexol process.

Although a Selexol process can be configured in various ways, depending on the

requirements for the level of H2S/CO2 selectivity, the depth of sulfur removal, the need

for bulk CO2 removal, and whether the gas needs to be dehydrated, this process always

includes the following steps—sour gas absorption, solvent regeneration/sour gas

recovery, and solvent cooling and recycle. These general steps for the Selexol process for

acid gas removal are described by the following cases.

140
5.3.1. Selexol process for selective H2S removal

Figure 5 - 2 Selexol Flow Diagram for Selective H2S Removal [Kubek, 2000]

A typical Selexol flow diagram for selective H2S removal is shown in Figure 5-2.

The feed gas and the lean solvent counter currently contact at high pressure and lower

temperatures in an absorber, where desired levels of H2S, COS and CO2 are absorbed into

the solution. Regeneration of the acid gas rich solvent is fulfilled through a combination

of flashing and thermal regeneration. Acid gases absorbed in the solvent released first

from one or more flash tanks at reduced pressures, then from the stripper by thermal

regeneration with steam stripping at elevated temperatures and low pressure. A solvent

heat exchange is employed to cool down the solvent. The regenerator overhead vapors

(acid gas and steam) are routed to a condenser plus knockout drum, and the condensed

water is returned to the unit to maintain water balance. The high- pressure flash gas

vapors are compressed and returned to the absorber for greater H2 and CO recovery and

to provide H2S-enrichment of the acid gas for the Claus plant.

141
5.3.2. Selexol process for H2S and CO2 removal

Through taking advantage of the high H2S to CO2 selectivity of Selexol solvent,

Selexol solvent processes can also be configured to capture H2S and CO2 together with

high levels of CO2 recovery. This is usually accomplished by staging absorption for a

high level of H2S removal, followed by CO2 removal. Figure 5-3 shows a Selexol process

layout for synthesis gas treating where a high level of both sulfur and CO2 removal are

required. H2S is selectively removed in the first column by a lean solvent, and CO2 is

removed from the H2S-free gas in the second absorber. The second-stage solvent can be

regenerated with air or nitrogen if very deep CO2 removal is required.

Figure 5 - 3 Selexol Process for Sulfur and CO2 Removal [Kohl, 1985]

A COS hydrolysis unit may be required if a high level of H2S and COS removal is

required. At the Sarlux IGCC plant in Italy, which gasifies petroleum pitch, the Selexol

unit allows a COS hydrolysis step and gives an acid gas that is 50-80 vol.% H2S to the

Claus plant. This acid gas composition is the result of an H2S enrichment factor of about

142
2 to 3 through the Selexol unit. The H2S content of the purified gas from the Selexol

absorber at that plant is about 30 ppmv [Korens, 2002].

5.3.3. An optimal design for Selexol process for sulfur and CO2 capture
from IGCC systems

A variety of flow schemes of Selexol processes permits process optimization and

energy reduction. The following is a description of an optimal design of a Selexol process

which removal sulfur and CO2 from syngas from IGCC systems. This optimal design is

based on revising a Selexol process, originally designed by UOP, for H2S and CO2

removal from syngas for the production of ammonia (UOP, 2002).

The H2S Absorption flowsheet for the optimized configuration is shown in Figure

5-4. Syngas from the gas cooling section of the gasification process enters the H2S

absorber where it is contacted with CO2-saturated Selexol solvent from the CO2-removal

portion of the facility. The pre-saturated solvent from the CO2 removal area is chilled

with refrigeration before fed into the absorber, which can increase the CO2 and H2S

loading capacity of the solvent. The use of pre-loaded solvent prevents additional CO2

absorption in the H2S absorber, and it also minimizes the temperature rise across the

tower, which negatively affects the H2S solubility and the selectivity of the solvent. H2S

is removed from the syngas. The H2S absorber overhead stream is mixed with the entire

solvent stream from the CO2 absorber. Therefore, significantly bulk CO2 is removed in

this pre-contacting stage which reduces the loading in the CO2 Absorber. The rich solvent

from the H2S absorber is fed to the H2S solvent regeneration facility.

143
Figure 5 - 4 Optimized Selexol absorption process for H2S removal

Figure 5-5 presents a process flow diagram for the optimized H2S solvent

regeneration section. The rich solvent from the H2S absorber is pumped to high pressure

and heated in the lean / rich exchanger. The solvent then enters the H2S solvent

concentrator, which operates at a pressure higher than the H2S absorber, thus the recycle

gases can be recycled to the H2S absorber without compression. Due to the relative

difference in solubility in Selexol solvents, CO2 is removed from solution preferentially

over H2S, which results in an enriched H2S concentration in the solvent. The CO2

removed in the H2S solvent concentrator is the majority of the recycle gases back to the

H2S absorber. The enriched solvent from the H2S solvent concentrator is flashed down to

lower pressure. The flash gas again contains a higher proportion of CO2 than H2S. This

stream is also recycled back to the H2S absorber. This recycle stream is relatively small

because much of the CO2 was removed at high pressure. The solvent from the flash drum

enters the Selexol stripper for regeneration.

144
Figure 5 - 5 Optimized H2S Solvent Regeneration

The optimized CO2 absorption flowsheet is shown in Figure 5-6. In this

optimization design, the entire CO2 solvent flow is contacted with the H2S absorber

overhead stream in the pre-contacting stage, which can unloads the CO2 absorber. The

heat of absorption is removed from this pre-contacting stage in a refrigeration chiller. The

relatively high temperature of this stream allows setting high temperature refrigeration,

which reduces the power consumption of the refrigeration system. The solvent is cooled

to optimum absorption temperatures when the pressure is reduced in the flash

regeneration portion of the facility. A portion of the rich CO2 solvent is returned to the

H2S absorber as pre-saturated solvent. The remainder of the solvent is flash regenerated

which will be presented below. The top bed of the tower uses lean solvent from the H2S

regeneration facility to contact the syngas. This allows for the CO2 to be removed to

levels lower than could be achieved using only flash regenerated (semi-lean) solvent.

145
Figure 5 - 6 Optimized Selexol process for CO2 absorption

Rich CO2 is flash regenerated as shown in Figure 5-7. The flash regeneration uses

one sump tank, one or two power recovery turbines, and three stages of flash. The CO2

rich solvent leaving the bottom of the CO2 absorber is let down to the sump tank at a

reduced pressure, where most H2 and a tiny amount of CO2 captured in the Selexol are

released and recycled back to the pre-contacting stage.

Then the CO2 rich solvent with high pressure is let down to one or two hydraulic

power recovery turbines to recover the pressure energy before it is fed into three flash

drums, where CO2 is released at staged pressures to reduce the power consumption of

CO2 compression later.

146
Figure 5 - 7 Optimized Selexol regeneration through CO2 flash

A key limitation of Selexol systems is the operating temperature requirement. The

operating temperature for Selexol systems is typically approximately 100°F. Hence a

reasonable location of Selexol process in an IGCC system is at the down stream of

syngas cooling section.

5.4. Performance model of Selexol process

As a patented commercial solvent, the detailed characteristics of the Selexol solvent

are not available. Hence in this section, a semi-analytical, semi-regression performance

model of Selexol systems for CO2 capture is presented.

147
5.4.1. Performance model of Selexol process for CO2 capture

This section discusses the methodology of setting up a performance model of

Selexol process for CO2 capture. A cost model of the Selexol process is further developed

on the basis of this performance model.

Temperature effect on solubility of gases in Selexol

The solubility of a gas in Selexol depends on its partial pressure and temperature.

The solubility of CO2 as a function of temperature is regressed based on published data

[Doctor 1996, Black 2000] and given by,

χ CO = 0.0908 − 0.0008 ⋅ T
2 (R2=0.95) (5-1)

where χ CO2 = the solubility of CO2 in the Selexol (SCF/gallon-psia)

T = the temperature of solvent with a range of 30~77 °F

The solubility of other gases at different temperature is not available. Here the

relative solubility of other gases to CO2 at different temperature is assumed to be

constant.

Solvent flow rate of the Selexol process

The input and output parameters of this model are given in Table 5-4. For the

performance simulation, the first step is to calculate the flow rate of the solvent. In order

to do this calculation, the whole Selexol process can be simplified as Figure 5-8. Stream

1 is the syngas fed into the absorber at a given temperature, and α percent of CO2 is

removed from the syngas. Stream 4 is the lean solvent at a design temperature. Due to

148
heat transfer between the solvent and syngas and the absorption heat, the temperature of

the rich solvent (stream 3) will be increased by ∆T . For the given CO2 removal

percentage α , the flow rate of solvent, fuel gas and CO2 can be calculated as follows.

Table 5 - 4 Input and output parameters of Selexol model

Input parameter Output parameter


Flow rate Flow rate
(mole/s) f1 (mole/s) f2
Pressure p1 Pressure p2
Temperature T1 Temperature T2
[CO]1 [CO]2
[CO2]1 [CO2]2
Syngas Fuel gas
input [H2]1 output [H2]2

Molar [CH4]1 Molar [CH4]2


concentrations [H2S]1 concentrations [H2S]2
[COS]1 [COS]2
[NH3]1 [NH3]2
[H2O]1 [H2O]2
Flow rate
CO2 flow (mole/s) f5
CO2 removal percentage Pressure P5
Refrig. Comp.
power Power recovery power

149
Figure 5 - 8 Simplified Selexol process

As mentioned in the above section, the solubility of gases in Selexol is a function of

temperature. For calculating the flow rate of solvent, the first step is to estimate the

temperature change of solvent in the absorber. Assuming the flow rate of solvent is ω lb-

mol/hr, the temperature increase of solvent in the absorber is given by

∆T = ∆T1 + ∆T2 (5-2)

where ∆T = the temperature increase of solvent in the absorber (°F)

∆T1 = solvent temperature increase caused by the heat transfer (°F)

∆T2 = solvent temperature increase due to the solution heat of gases (°F)

According to the amount of heat transferred between the syngas and solvent, and

the specific heat of the solvent, the temperature increase due to heat transfer is calculated

by

150
Q1
∆T1 = (5-3)
ω ⋅ MWSel ⋅ C p ,s

where MWSel = the molar weight of Selexol (280 lb/lb-mol)

C p , s = the specific heat of Selexol (0.49 Btu/lb °F)

Q1 = the heat released by the syngas, which can be estimated according to the

energy balance and given by,

Q1 = (TSG ,i − TSG ,o )f SG ,i {2.02 ⋅ [H 2 ]1 ⋅ C p ,H 2 + 16 ⋅ [CH 4 ]1 ⋅ C p ,CH 4


+ 28 ⋅ [CO]1 ⋅ C p ,CO + 44 ⋅ [CO 2 ]1 ⋅ (1 − α) ⋅ C p ,CO 2 } (5-4)
+ 44 ⋅ (TSG ,i − TSG ,o − ∆T) ⋅ f SG ,i ⋅ α ⋅ [CO 2 ]1 ⋅ C p ,CO 2

where TSG ,i = the syngas temperature at the inlet of the absorber (°F)

TSG ,o = the syngas temperature at the outlet of the absorber (°F)

f SG ,i = the molar flow rate of syngas at the inlet of the absorber (lb-mole/hr)

[i ]1 = the molar concentration of species i in syngas at the inlet of the absorber

C p ,i = the specific heat of species i (Btu/lb °F), which is given in Table 5-5.

Table 5 - 5 Specific heat of gases in the syngas

Gas CO CO2 H2 CH4 Ar N2 H2S NH3


Specific heat 0.248 0.199 3.425 0.593 0.125 0.249 0.245 0.52
(Btu/lb F)

151
In Eq. 5-2, ∆T2 is caused by the solution heat. Here only the solution heat of CO2 is

calculated. The solution heat of other gases is negligible because the amount of other

gases captured by Selexol is much less than that of CO2.

44f SG ,i ⋅ [CO 2 ]1 ⋅ α ⋅ ψ CO 2
∆T2 = (5-5)
ω ⋅ MWSel ⋅ C p ,Sel

where f SG ,i = total flow rate of syngas entering the absorber (lb-mole/hr)

α = CO2 removed from the syngas (%)

ω = Selexol flow rate (lb-mole/hr)

MWS = Selexol molecular weight (lb/lb-mole)

[CO2 ]1 = CO2 molar concentration at the inlet of absorber

ψ CO 2 = solution heat of CO2 in Selexol (Btu/lb-solute), and the solution heat of

several gases is given in Table 5-6 [Korens, 2002].

Table 5 - 6 Solution heat (Btu/lb-solute) of gases in the Selexol

Gas CO2 H2S CH3


Heat of solution (Btu/lb-solute) 160 190 75

In the flash tanks, the residual time is long enough to assume that equilibrium can

be achieved in these tanks. In the last flash tank, the solvent temperature is about

(30+ ∆T1 ), hence the volume and mass flow rate of the residual CO2 in the lean solvent

(S4 stream in Figure 5-8) can be given by:

152
VCO 2 ,res (SCF / hr ) = SVsel ⋅ ω ⋅ p CO 2 χ CO 2 (5-6)

VCO 2 ,res
m CO 2 ,res (lb ⋅ mol / hr ) = (5-7)
SVCO 2

where SVsel = the specific volume of Selexol (32.574 gallon/lb-mol);

SVCO2 = the specific volume of CO2 (377.052 SFC/lb-mol);

ω = the flow rate of Selexol (lb-mol/hr);

pCO2 = the partial pressure of CO2 (psia);

χ CO 4 = the solubility of CO2 in Selexol at temperature of 30+ ∆T1 .


2,

According to the CO2 capture percentage in the absorber, the amount of CO2 that

need be captured by the solvent is,

VCO2 ,abs ( SCF / hr ) = SVCO2 ⋅ f SG ,i ⋅ [CO2 ]1 ⋅ α (5-8)

In the absorber, the equilibrium cannot be achieved due to the limited residual time.

The flow rate of solvent used in the absorber is larger than that of the solvent required to

capture α percentage of CO2 at equilibrium. The ratio of the actual flow rate to the

equilibrium flow rate of the solvent was regressed based on published data [Doctor, 1994,

1996, Sciamanna, 1988].

1.26
γ = − 0.0002 p1 ( R 2 = 0.8 ) (5-9)
(1 − α ) 0.07

153
where p1 = the pressure of syngas at the inlet of absorber (psia).

Then the flow rate of Selexol for capturing α percentage of CO2 is given by

γ (VCO ,res + VCO ,abs )


ω (lb ⋅ mol / hr ) = 2 2
(5-10)
SVsel ⋅ p1 ⋅ [CO2 ]1 ⋅ χ CO ,1
2

VCO2 ,res
where = volume flow rate of residual CO2 in the lean solvent (lb-mole/hr)

VCO2 ,abs
= volume flow rate of CO2 captured in the absorber (lb-mole/hr)

χ CO 1 = the solubility of CO2 in Selexol at temperature of 30+ ∆T (°F)


2,

Based on the above discussion, the calculation process for the flow rate of Selexol

is concluded as in the following. First assuming the temperature of the Selexol solvent in

the absorber is increased by ( ∆T1 + ∆T2 ), then the solubility of CO2 at this increased

temperature can be calculated. Second the solubility of CO2 at the solvent in the last flash

tank is calculated at the temperature (30+ ∆T1 ). Given the amount of CO2 needed to be

required, the flow rate of the solvent is calculated based on the solubility difference

between the solvent in the absorber and in the last stage flash tank. Then the new values

of ∆T1 and ∆T2 are computed using the calculated solvent flow rate of solvent. Such

calculation process continues until the flow rate of the solvent is convergent. This

calculation process is represented by Figure 5-9:

154
Figure 5 - 9 Calculation process for the flow rate of Selexol

Composition and flow rate of fuel gas

After CO2 capture, the syngas is converted into the fuel gas, the main component of

which is hydrogen. The composition and flow rate of the fuel gas can be calculated as

follows.

With knowing the Selexol flow rate and solubility of gases, the volume and mass

amount of species i which is captured by the solvent is:

Vi (SCF / hr ) = SVsel ⋅ ω ⋅ p i ⋅ χ i (5-11)

Vi
m i (lb ⋅ mol / hr ) = (5-12)
vi

where Vi = the volume flow rate of species i captured in the Selexol (SVF/hr);

SVsel = the specific volume of Selexol (gallon/lb-mol);

vi = the specific volume of CO2 (SFC/lb-mol)

ω = the flow rate of Selexol (lb-mol/hr);

pi = the partial pressure of species i in the syngas (psia);

χ i = the solubility of species i in Selexol at temperature of 30+ ∆T °F;

155
In the sump tank, most of the H2, CH4 captured in the Selexol are released and

recycled to the absorber again. Because of the much higher solubility, only a tiny amount

of CO2 is released in the sump tank. The operating pressure of the sump tank is a design

parameter. For this study, the operating pressure is determined to keep the loss of H2 to

Selexol solvent no more than 1% of H2 in the syngas. The calculation process for the

sump tank is as the follows: assuming the operating pressure is p sump , the volume of

species i released from the sump tank is Vi ' , then the partial pressure p i ,sump can be given

by Eq. (5-13). According to mass conservation, the total volume of species i captured in

the absorber equals the volume released in the sump tank plus the volume retained in the

solvent in the tank, expressed as Eq. (5-14). Now recalling the Eq. (5-11), the volume of

species is retained in the solvent in the tank can calculated as Eq. (5-15). Iteratively

calculating Eq (5-13), (5-14), and (5-15) until the partial pressures are converged. If at

the given operating pressure, the H2 volume retained in the solvent does not meet the

design value, then the operating pressure is adjusted and the calculation is run again. The

calculation procedure is given by Figure 3-10.

Vi'
p i ,sump = p sump (5-13)
∑ Vi'
i

Vi = Vi ,sump + Vi' (5-14)

Vi ,sump (SCF / hr ) = 32.574ω ⋅ p i ,sump ⋅ χ i (5-15)

156
Figure 5 - 10 Calculation process for the operating pressure of the sump tank

Composition and flow rate of CO2 rich flow

At each stage of the flash tanks, the flash pressure is given. At this pressure, the

residual gases in the lean solvent can be calculated based on their solubility. Based on

mass conservation, the composition and flow rate of CO2 rich flow from the flash tanks

can also be calculated, and the calculation procedure is similar to that shown in Figure 5-

10.

5.4.2. Power consumption model of Selexol process

There is no heat duty in the Selexol process because the solvent is regenerated

through pressure flashing, but the power input is required to compress the recycling gas

from the sump tank, the lean solvent from the flash tank 3, and the CO2 rich product. At

the same time, some electricity can be generated through the power recovery hydro

turbine. The total power consumption is the difference between the power input and the

recovered power from the turbine.

Power recovery

In this performance model, the pressure of the high-pressure rich solvent from the

absorber is reduced and the energy is recovered through one or two hydro turbines.

157
According to the designs in other studies [Doctor, 1994, 1996, Sciamanna, 1988, Black,

2000], a thumb rule of design is concluded here. If the pressure of CO2 rich Selexol flow

is larger than 240psia, two power recovery turbines will be used. Otherwise, only one

power recovery turbine will be used. Generally, this outlet pressure ( Po ,1 , psia) of the

turbine can be determined based on the system pressure as following:

Po ,1 = 0.0402Pi1,1.415 (5-16)

where Po ,1 = the outlet pressure of power recovery turbine 1 (psia).

Pi ,1 = the pressure of the CO2-rich Selexol at the inlet of turbine 1 (psia),

(150 ≤ p i ,1 ≤ 1000) .

If the pressure of the CO2 rich Selexol flow is larger than 240 psia, then the outlet

pressure of the second turbine is given by,

p o , 2 = 35.619 ln(p i ,1 ) − 169.88 (240 ≤ p1 ≤ 1000) (5-17)

where Po , 2 = the outlet pressure of power recovery turbine 2 (psia)

Pi ,1 = the pressure of the CO2-rich Selexol at the inlet of turbine 1 (psia),

(240 ≤ p i ,1 ≤ 1000)

The power recovered from the liquid solvent is calculated from the following

expression [Doctor, 1994],

158
f Sel2
hp tur = H Sel ⋅ ⋅ η tur (5-18)
1714

where hptur = the power recovered through the power turbine (hp)

H Sel = the total dynamic head (lb/in2)

f Sel2 = the flow rate of CO2 rich Selexol entering the turbine (gal/min)

η tur = the efficiency of the turbine

The temperature change of the solvent in the turbine can be calculated based on the

change in enthalpy, which equals flow work, ∫ vdp . For the default efficiency of turbines,

78%, the temperature can be given by,

dTtur = 0.0047 ⋅ dPtur − 0.0715 (5-19)

where dTtur = the decreased temperature of the Selexol in the power recovery

turbine (°F);

dPtur = the decreased pressure of the Selexol in the power recovery turbine (°F)

CO2 compression

There are three flashing pressure levels for CO2 release. The design of the flashing

pressures in the three flashing tanks is an optimal problem, but a preliminary study

showed that the effect of flashing pressures on the power consumption of the Selexol

processes is not considerable. Hence, some default values are adopted here for the

159
process design. If the system pressure is larger than 240 psia, the first flashing pressure

equals the outlet pressure of the second turbine. If the system pressure is less than 240

psia, the first flashing pressure is set to be 25 psia. The second flashing pressure is set to

be 14.7 psia, and the last flashing pressure is set to be 4 psia.

In each flashing tank, the gases released from solvent are calculated. CO2 released

from flash tank 2 and tank 3 is compressed to the flashing pressure of tank 1. The CO2

stream is finally compressed to a high pressure (>1000psia) for storage using a multi-

stage, inter-stage cooling compressor. The power required by the CO2 compressors is

estimated by [Doctor, 1994],

0.00436 k Pcomp.,o ( k gas −1) k gas


hp comp. = ⋅ VFgas ⋅ Pcomp,i ⋅ ( ) ⋅ [( ) − 1] (5-20)
η comp. k −1 Pcomp.,,i

where hp comp. = the power consumption of the CO2 compressor (hp)

η comp. = the overall efficiency of the compressor

VFgas = the inlet rate of the CO2 stream (ft3/min)

Pcomp.,i = the inlet pressure of the compressor (psia)

Pcomp.,o = the outlet pressure of the compressor (psia)

C p ,gas
k gas = .
C v ,gas

160
Solvent compression work

The CO2-lean solvent is pumped back to the absorber operating pressure by a

circulation pump. The power required by the circulation pump is estimated in a similar

way as Eq. (5-18),

f Sel
hp pump = H s (5-21)
1714η pump

where H s = the total dynamic head (psia)

f Sel = the flow rate of CO2 lean Selexol (gal/min)

η pump = the efficiency of the pump

Recycle gas compression work

The gases from the sump tank are recycled to the absorber. A compressor is used to

compress the gases to the operating pressure of the absorber. The power of the

compressor is estimated using Eq. (5-20).

Solvent refrigeration

Before the CO2-lean solvent fed into the absorber, it has to be cooled down to the

absorber operating temperature (30F) by refrigeration. The refrigeration power is

estimated by [Doctor, 1994],

refrigeration load(Btu / hr )
Wref . = (5-22)
T
1000(9 + evap )
10

161
where Wref . = the power consumption of the solvent refrigeration process (kW)

Tevap = the evaporation temperature of the refrigerant (°F)

Makeup of the Selexol solvent

The vapor pressure of the Selexol solvent is1.35 × 10 −5 psia at 77F, which is very

low. The real vapor pressure is even lower because the operating temperature is usually

lower than 77F. Hence, the loss of solvent due to evaporation is negligible. On the other

hand, due to leakage, especially in the start on and turn off processes, a certain amount of

solvent is lost. Here the annual loss of solvent is assumed to be approximate 10% of the

total solvent in the system [UOP, 2003].

5.5. Cost model of the Selexol process

Similar to the cost model of the WGS reaction system discussed in Chapter 4, the

outputs of this cost model include the process facility cost, total plant cost, total plant

investment, total capital requirement, and O&M cost.

5.5.1. Process facility costs of the Selexol system for CO2 capture

The major process facility costs of the Selexol system for CO2 capture are

considered as in the following.

CO2 absorption column

Using the data in Table 5-7, the process facility costs of the absorption column is

regressed as a function of the operating pressure, the flow rates of the solvent and syngas,

PFC abso . = N T , abso . ⋅ [ − 1375 . 356 + 16 . 536 Pabso ,i

+ 0 . 127628 ( 0 . 5 f Sel + 0 . 5 f SG )] (R2=0.90) (5-23)

162
where PFC avso = the process facility cost of the absorber(US k$ in 2000)

N T ,abso = the total train number of absorbers

Pabso.,i = the inlet pressure of absorber (atm)

f Sel = the flow rate of the Selexol(lb-mole/hr)

f gas = the flow rate of the syngas (lb-mole/hr)

Table 5 - 7 Absorber cost data adjusted to the dollar values in 2000 [Doctor, 1996]

PFC (2000$) P(atm) Flow rate of syngas(lb- Selexol flow rate(lb-


mol/h) mol/hr)
6.3E+05 30.35 11771.88 11815.53
9.2E+05 10.21 12418.46 20802.84
1.5E+06 16.88 17614.58 23000
1.3E+06 68.05 17614.58 6900

Power recovery turbine

Based on the data in Table 5-8, the process facility cost of the power recovery

turbine is given by,

PFC tur = 219.086 + 0.080912 ⋅ hp tur + 0.020086Ptur


2
,o (R2=0.91) (5-24)

where PFCtur = the process facility cost of power recovery turbine (US k$ in 2000)

hptur = power output of the turbine (hp)

Ptur ,o = the outlet pressure of the turbine (atm)

163
Table 5 - 8 Power recovery turbine cost data adjusted to the dollar value in 2000
[Doctor, 1996]

PFC (2000 k$) Outlet pressure Power output(hp)


277.23 13.60 649
235.64 3.40 404
246.66 5.10 293
263.21 3.40 451
246.66 1.70 293
317.14 51.03 567
317.14 6.80 567

Sump tank

The process facility cost of the sump tank is regressed as a function of the solvent

flow rate,

f Sel
PFC slump = 2.0049 ⋅ N T ,slump ⋅ ( ) 0.7446 (R2=0.87) (5-25)
N O ,slump

where PFC sump = the process facility cost of the sump tank (US k$ in 2000)

N T ,sump = the total train number of sump tanks

N O ,sump = the operating train number of the sump tanks

f Sel = the flow rate of the CO2-rich Selexol entering the sump tank (kg/s),

400~800/train

164
Table 5 - 9 Sump tank cost data adjusted to the dollar value in 2000 [Doctor, 1996]

PFC (2000 k$) Selexol flow rate (kg/s)


179.04 416.85
272.83 733.92
205.11 811.44
205.22 811.44

Recycle compressor

The process facility cost of the recycle compressor is given by,

0.7784
PFC RC = 4.45519 hp RC (R2=0.98) (5-26)

where PFC RC = the process facility cost of the recycle compressor (US k$ in 2000)

hp RC = the power consumption of the recycle compressor (hp)

Table 5 - 10 Recycle compressor cost data adjusted to the dollar value in 2000
[Doctor, 1996]

PFC (2000 k$) Compressor capacity (hp)


576.64 537
361.19 259
212.55 151
212.55 151.3

Selexol pump

The process facility cost of the Selexol pump is given by,

0.7164
PFC SP = 1.2286hp SP (R2=0.92) (5-27)

where PFCSP = the process facility cost of the Selexol pump (US k$ in 2000);

hp SP = the power consumption of the Selexol pump (hp).

165
Table 5 - 11 Selexol pump cost data adjusted to the dollar value in 2000 [Doctor,
1996]

PFC (2000 US k$) Pump capacity (hp)


301.52 2205
207.29 1282
326.63 2388
326633.3 2388

CO2 compressor

The process facility cost of the CO2 compressor is regressed as,

0.6769
PFC comp1 = 7.0321hp comp
(R2=0.83) (5-28)

where PFC comp1 = the process facility cost of the CO2 compressor (US k$ in 2000)

hp comp = the power consumption of the compressor (hp)

Table 5 - 12 CO2 compressor cost data adjusted to the dollar value in 2000 [Doctor,
1996]

PFC (2000, US k$) Compressor capacity (hp)


323.1754 600.41
311.5061 255
216.2418 155.52
190.1031 120.54
1026.139 1086
576.6455 539.71

CO2 final product compressor

The process facility cost of the multi-stage CO2 compressor is given by,

0.64
PFC comp 2 = 13.0969hp comp (R2=0.85) (5-29)

166
where PFC comp 2 = the process facility cost of the compressor (US k$ in 2000)

hp comp = the horse power consumption of the compressor (hp)

Table 5 - 13 CO2 final compressor cost data adjusted to the dollar value in 2000
[Doctor, 1996]

PFC (2000 US K$) Compressor capacity (hp)


2162.421 2582
2851.544 2913
2565.347 3369
2382.109 3217

Refrigeration

The process facility cost of the refrigeration unit is regressed as,

f Sel 0.3618
PFC refr = 1.0019 ⋅ N T ,refr ⋅ [16.4796 ⋅ ( ) (∆TSel ) 0.4064 ] (R2=0.97) (3-30)
N O ,refr

where PFC refr = the process facility cost of the refrigeration unit (US k$ in 2000);

N T ,reft = the total train number of the refrigeration unit;

N O ,reft = the operating train number of the refrigeration unit;

f Sel = the flow rate of the solvent entering the refrigeration unit (lb-mol/h),

70000~23000 /train;

∆TSel = the Selexol temperature difference between the inlet and outlet of the

refrigeration unit (°C ), 1~5 °C.

167
Table 5 - 14 Refrigeration unit cost data adjusted to the dollar value in 2000 [Doctor,
1996]

PFC (2000 k$) Solvent flow rate (lb-mol/h) Temperature


difference (C)
657.73 12000 2.171
613.81 20802 1.017
771.71 7016 4.706
771.71 23397 1.667

168
Flash tank

The process facility cost of flash tanks is given by,

f Sel 0.8005
PFC tan k = 0.9832 ⋅ N T , tan k ( ) (R2=0.89) (5-31)
N O, tan k

where PFC tan k = the process facility cost of the flash tank (US k$ in 2000);

N T , tan k = the total train number of the flash tank;

N O , tan k = the operating train number of the flash tank;

f Sel = the flow rate of the Selexol entering the flash tank (kg/s), 400~800 /train.

Table 5 - 15 Flash tank cost data adjusted to the dollar value in 2000 [Doctor, 1996]

PFC (2000 $) Solvent flow rate (kg/s)


129745.5 416.85
197707.4 733.92
205227.8 811.44

5.5.2. Total Capital Requirement of the Selexol process

169
Here the default values for the capital cost calculation of the Selexol process for

CO2 capture are given by the following Table 5-16.

Table 5 - 16 Parameters for TCR of Selexol process

Total process facilities cost (PFC) Sum of PFC of the major units in the process
Engineering and home office 10% PFC
General facilities 15% PFC
Project contingency 15% PFC
Process contingency 10% PFC
Total plant cost (TPC) = sum of the above values
Interest during construction Calculated
Royalty fees 0.5% PFC
Preproduction fees 1 moth fee of VOM&FOM
Inventory cost 0.5% TPC
Total capital requirement (TCR) = sum of above values
Fixed O&M cost (FOM)
Total maintenance cost 2% TPC
Maintenance cost allocated to labor 40% of total maintenance cost
Administration & support labor cost 30% of total labor cost
Operation labor 2 jobs/shift
Variable O&M cost (VOM)
Selexol solvent $ 1.96/lb

170
REFERENCES (CHAPTER 5)

1. Black W.B., Pritchard V., Holiday A., Ong J.O. and Sharp C., 2000: Use of
SELEXOL Process in Coke Gasification to Ammonia Project By Presented at the
Laurance Reid Gas Conditioning Conference, The University of Oklahoma, Norman,
Oklahoma

2. Doctor R.D., 1994: Gasification combined cycle: carbon dioxide recovery, transport,
and disposal, ANL/ESD-24

3. Doctor R.D., 1996: KRW oxygen-blown gasification combined cycle carbon dioxide
recovery, transport, and disposal, ANL/ESD-34, 1996

4. Dow Chemical Company, 2004: Selexol solvent for gas treating, www.dow.com

5. Epps R., 1994: Use of Selexol Solvent for Hydrocarbon Dewpoint Control and
Dehydration of Natural Gas, presented at the Laurance Reid Gas Conditioning
Conference, Norman, OK

6. Gas Processes, 2002: Hydrocarbon Processing, UOP LLC, Des Plaines, Illinois.

7. IEA, 2003: Potential for improvement in gasification combined cycle power


generation with CO2 capture, Report number PH4/19

8. Newman S. A., 1985: Acid and sour gas treating processes: latest data and methods
for designing and operating today’s gas treating facilities, Gulf Publishing Co.

9. Kohl A.L. and Riesenfeld F.C., 1985: Gas Purification, Fourth Edition, Gulf
Publishing Company

10. Korens N., Simbeck D.R., Wilhelm D.J., 2002: Process Screening Analysis of
Alternative Gas Treating and Sulfur Removal for Gasification, Revised Final Report,
December 2002, Prepared by SFA Pacific, Inc. Mountain View, California

11. Personal communication with UOP, 2003

12. Sciamanna S. and Lynn S., 1988: Solubility of hydrogen sulfide, sulfur dioxide,
carbon dioxide, propane, and n-butane in poly(glycol ethers), Ind. Eng., Chem. Res.,
27

13. Shah V.A., 1988: Low-cost ammonia and carbon recovery, Hydrocarbon Process.,
67(3)

14. UOP, 2002: Use of SELEXOL Process in Coke Gasification to Ammonia Project,
UOP report

171
Chapter 6. GREENFIELD IGCC POWER PLANT WITH AND WITHOUT CO2
CAPUTRE

Table 6 - 1 Technical design assumption of the IGCC power plant

Parameter Value
Design ambient temperature 59 °F
Design ambient pressure 14.7 psia
ASU oxygen purity 95%
Steam cycle 1400 psi/1000°F/1000°F
Condenser pressure 0.67 psia
Syngas sulfur removal efficiency 99%
NOx control fuel gas moisturization
Gasifier operation conditions 615 pisa/2450 °F
Spare gasifier number 1
Fuel type Pittsburgh #8

Table 6 - 2 Economic and financial assumption of the IGCC power plant

Capacity factor 75%


Fixed charge factor 14.8%
Cost year 2000
Construction period 4 years
Lifetime 30 years
Fuel price 1.26 $/MBtu
For CO2 capture plant
CO2 capture efficiency 90%
CO2 product final pressure 2100 psia
CO2 transport and storage 10 $/tonne

This section applies the IGCC models in Aspen Plus to investigate factors

influencing the performance and costs of IGCC power plants with and without CO2

capture. At first, the effects of the quality of coals are studied. Then effects of CO2

172
capture, plant size, and capital structures are also studied. The general technical design

assumptions are given in Table 6-1 and the economic and financial assumptions are given

in Table 6-2

6.1. The effects of coal types on IGCC performance

For a Texaco gasifier, coal is prepared in a slurry form. The composition of the

slurry (for a given type of coal, the water percentage in the slurry by weight), may

influence the gasifier efficiency and the efficiency of a whole IGCC power plant. To

investigate the effects of water percentage in the slurry, an IGCC system with two GE

7FA gas turbines and two operating gasifiers was studied.

As an important factor determining the actual operation, as well as the economic

feasibility of using a gasifier system, the gasification efficiency is defined as,

Hg ⋅ Qg
ηgasifier = ⋅ 100 (6-1)
Hs ⋅ Ms

where η gasifier = gasification efficiency (%)

Hg= is heating value of the gas (kJ/m³);

Qg = is volume flow of gas (m³/s);

Hs = is the heating value of gasifier fuel (kJ/kg);

Ms = is the gasifier solid fuel consumption (kg/s).

173
If the lower heating values of the syngas and the fuel are used in the above

equation, the gasification efficiency is the lower heating value gasification efficiency.

Otherwise, it is the higher heating value efficiency.

Texaco gasifiers require the coal to be prepared in a slurry form for transport. The

amount of water added depends on the composition of a coal, especially the carbon, ash

and moisture percent in the coal. At first, the effects of total water percent in slurry on the

performance of IGCC systems are studied. For Pittsburgh #8 coal, Figure 6-1 gives the

effects of water percentage in slurry by weight on the gasification efficiency, the net plant

thermal efficiency and the heat rate of the IGCC plant. The gasification efficiency is as

low as 45% if no extra water is added to the coal, because at a given gasification

temperature there is not enough oxygen to partially oxidize all the carbon in the

feedstock. With the increase of the water percentage in the slurry, the gasification

efficiency increases, and reaches the peak point, approximately 79%, at a total water

percentage of 27% in the slurry by weight. The gasification efficiency decreases with

further increasing the water percentage due to the increase of water content in the syngas.

The thermal efficiency of the whole IGCC system shows the same trend as the

gasification efficiency, which also shows that the gasification efficiency is a major factor

influencing the performance of IGCC systems.

174
80 16000

70
Gasification

Heating rate (Btu/kWh)


14000
efficiency (%,
Efficiency (%) 60 Coal: App MS, 5.05% H2 O
HHV)
T exaco quench Gasification
50 T : 2450 F P: 615 psia 12000 efficiency (%,
LHV)
40 T hermal
10000 efficiency (%,
30 HHV)
Heating rate
20 8000
5 10 15 20 25 30 35 40 45 50
Water (moisture+added) in slurry by weight (% )

Figure 6 - 1 Effect of water percentage in slurry on IGCC performance

The effects of the water percentage in the slurry by weight on the total capital

requirement and the cost of electricity are given by Figure 6-2. It is not a surprise to find

that the there is an optimal water percentage for the COE and TCR of an IGCC power

plant, because COE and TCR are heavily depends on thermal efficiency. However, the

optimal value of water percentage in the slurry in this case is pure hypothetical and

without considering the requirement of the slurryability. The slurryability of a given type

of coal has a minimum requirement of water percentage in the slurry for transportation in

pipes and pumps. For instance, in order to ensure the slurryability for transportation, the

total water percentages in the slurry for Pittsburgh #8, Illinois #6, PRB and ND Lignite

should be no less than 34%, 37%, 44% and 50%, respectively [Breton, 2002]. The

hypothetical testing of all the four types of coal shows that the amount of water added in

the slurry should based on the minimum requirement of the slurryability to avoid that the

slurry composition is far away from the optimal value.

175
75 2000

70
COE ($/MWh) 1800
65

TCR ($/kW)
COE
60 1600 ($/MWh)
T CR
55 ($/kW)
1400
50
Coal: Pittsburgh #8
45 1200
5 15 25 35 45
Total wate r in slurry by we ight (%)

Figure 6 - 2 Effect of water percentage in slurry on TCR and COE

Although an entrained flow gasifier, like the Texaco gasifier, is able to gasify all

types of coals regardless of coal rank, caking characteristics, or amount of coal fines, coal

rank may influence the performance of gasifiers and IGCC systems. Here four coals are

used to investigate this influence. These four coals represent bituminous coal, sub-

bituminous coal, and lignite. The compositions of these coals are given in Table 6-3. The

major feedstock parameters are carbon content, ash content, and oxygen content. The

primary energy of coal is from the carbon content, which is reflected in the heating value

of coal. Ash content in coal is a heat sink in gasification, and the oxygen content

influences the oxygen requirement of gasification process. All results derived here are

based on Aspen simulations of the gasifier performance; at this time there is a lack of

empirical data for alternative (low rank) coals.

176
Table 6 - 3 Compositions of the four coals and their water percentage in slurry

Dry basis
Pittsburgh#8 Illinois#6 Wyoming PRB ND Lignite
Coal rank Bituminous Bituminous Sub-bituminous Lignite
HHV (Btu/lb) 13965 12529 11955 8989
MOISTURE 5.05 13.00 30.24 33.03
ASH 7.63 12.64 7.63 23.77
CARBON 77.74 70.34 69.07 52.32
HYDROGEN 5.14 4.83 4.74 4.00
NITROGEN 1.50 1.33 1.00 1.15
CHLORINE 0.06 0.20 0.01 0.13
SULFUR 2.24 3.74 0.53 1.73
OXYGEN 5.70 6.92 17.02 16.89
Wet basis
MOISTURE 5.05 13.00 30.24 33.03
HHV 13260 10900 8340 6020
LHV2 12761 10381 7722 5431
ASH 7.24 11.00 5.32 15.92
CARBON 73.81 61.20 48.18 35.04
HYDROGEN 4.88 4.20 3.31 2.68
NITROGEN 1.42 1.16 0.70 0.77
CHLORINE 0.06 0.17 0.01 0.09
SULFUR 2.13 3.25 0.37 1.16
OXYGEN 5.41 6.02 11.87 11.31
Water percentage in slurry
Water% 34 37 44 55

2
LHV calculation is based on the following formula given by [George Booras, 2004]: LHV

= HHV – (91.1436 * H + 10.3181 * H2O + 0.3439 * O), where H, H2O, and O are on an as-

received basis.

177
Figure 6-3, using Pittsburgh #8 coal as the reference case, compares the gasification

efficiency, thermal efficiency and heat rate of the IGCC power plant using the four types

of coal. From this figure, it is clear that the rank of coal significantly influence the

gasification efficiency and the thermal efficiency of the power plant, which increase with

the increase of the heating value of coal. The heat rate of the IGCC power plant using

lignite coal (ND lignite with a high heating value of 6020 BTU/lb) is about 33% percent

higher than that of the IGCC plant using bituminous coal (Pittsburgh #8 with a high

heating value of 13260 BTU/lb).

1.4 1.0

gasification efficiency
Relative heating rate

ND Lignite

Relative thermal &


Pittsburgh #8
1.3
Illinois #6 0.9
1.2 PRB

0.8
1.1

1.0 0.7
6000 7500 9000 10500 12000 13500
Coal HHV (Btu/lb)

Relative Heat Rate Relative Efficiency Relative Gasification Efficiency

Figure 6 - 3 Effect of coal rank on the efficiency and heat rate of IGCC plants

The rank of coal also influences the economic factors of IGCC power plants. Figure

6-4 shows that low quality coal significantly increases the capital cost of an IGCC power

plant. For instance, the total capital cost ($/kW) of an IGCC power plant using ND coal is

about 68% higher than that of an IGCC power plant using Pittsburgh #8. On the other

hand, the lower quality coal has the lower fuel price (except ND lignite), which offsets

the effect of coal quality on the cost of electricity. For instance, the cost of electricity of

178
an IGCC using the PRB coal is only 8.6% higher than that of an IGCC using the

Pittsburgh #8 coal.

1.7 ND Lignite
1.6
Relative TCR & COE

Relative TCR
1.5
Relative COE
1.4
PRB
1.3
1.2 Illinois #6
Pittsburgh #8
1.1
1.0
6000 7000 8000 9000 10000 11000 12000 13000 14000
Coal HHV (Btu/lb)

Figure 6 - 4 The effect of coal rank on the TCR and COE of IGCC plants (For the
COE calculation, the coal price ratios based on the actual mine month
coal price are: Pittsburgh #8: Illinois #6: PRB: ND
Lignite=1:0.667:0.2:0.265)

The relative feed rates of oxygen and coal per MWh output of an IGCC using the

four coals are compared in Figure 6-5. For a unit power output, the oxygen flow rate of

the lower rank coal is bigger. For instance, the oxygen flow rate per MWh output of

Illinois #6, PRB, and ND lignite are 1.2, 1.3 and 2.2 times of that of Pittsburgh #8. The

relative flow rate of coal per MWh output shows the similar trend. The relatively higher

feed rates of stock and oxygen require more capital cost and auxiliary power

consumption for an IGCC power plant, which explain why lower rank coal deteriorates

the performance of IGCC plants.

179
3 ND Lignite

2.6

Relative flow rate


2.2

PRB
1.8

Illinois #6
1.4
Pittsburgh #8
1
6000 7500 9000 10500 12000 13500

HHV of Coal

Relative O2 flowrate Relative coal flowrate

Figure 6 - 5 Relative oxygen and coal mass flow rate per MWh power generation

An IGCC power plant using the lower rank coal emits more CO2 because of its

lower energy efficiency Figure 6-6 shows that the CO2 emission rate (kg CO2/MWh) of

an IGCC plant using ND lignite coal is more than 1.3 times higher than that of an IGCC

using the Pittsburgh #8 coal.

1.4
Relative CO2 emission rate

ND
1.3

1.2

PRB
1.1
Illinious #6
Pittsburgh #8
1
6000 7500 9000 10500 12000 13500
HHV of Coal

Figure 6 - 6 Relative CO2 emission for per MWh power generation

180
6.2. Effects of CO2 capture efficiency

Many studies of CO2 capture from IGCC power plants typically assumed a constant

CO2 capture efficiency in a range of 75% to 92%. CO2 capture efficiencies used in these

studies were determined by the study authors, and no studies published investigate the

effect of different CO2 capture efficiency on the performance of IGCC power plants. In

this section, the performance of IGCC power plants, including the CO2 avoidance cost,

energy penalty, capital cost and cost of electricity, are studied with different CO2 capture

efficiencies. An optimal criterion is explored to determine the least-cost CO2 capture

efficiency for an IGCC power plant. The configuration of the IGCC system for this study

is based on one GE 7FA gas turbine and one operating gasifier.

This study is based on the two-stage Selexol process for sulfur removal and CO2

capture described in Chapter 5. At the first stage, 99% of sulfur content well as 7% of

CO2 is removal and vented into the atmosphere at the sulfur removing unit. After a two-

stage shift reaction, there is approximately 0.5% CO not converted into CO2, and this

additional amount is also emitted as CO2 when the fuel gas is burned in the combustor.

Hence, the maximum total CO2 removal efficiency is approximately 92.5%. Here the

total CO2 removal efficiency is defined as:

CO 2 captured(mole)
CO2 removal efficiency =
Total carbon in syngas from gasifier (mole)

For the CO2 captured, this study considers three situations: one is the CO2 captured

in the Selexol without compression; one is that the CO2 captured is compressed to 2100

181
psia; the last one is that the CO2 captured is compressed to 2100 psia, and transported and

stored with a cost of 10$/tonne CO2.

Figure 6-7 shows the power requirement and capital cost of the Selexol process for

CO2 capture. The power consumption for CO2 capture varies slowly when the total CO2

removal efficiency is lower than 80%. The power consumption rises quickly when the

total CO2 removal efficiency is higher than 80% because the total flow rate of Selexol

increases quickly for very high CO2 removal efficiency. Compared with the power

consumption for compressing the CO2 stream to 2100 psia, which is about 74 kWh/tonne-

CO2, the power consumption of the Selexol process with 90% total CO2 removal

efficiency is about 44% of the power consumption for CO2 compression.

The capital cost (k$/tonne-CO2 captured per hour) of the Selexol process (excluding

CO2 compression) reaches the lowest value of 49.2 when total CO2 capture efficiency is

in a range from 85% to 90%. Out of this range, the capital cost increases sharply.

36 54

53
Power requirement
(kWh/tonne CO 2)

Cost requirement

Power
(k$/tonne CO2)

34
Cost 52

51
32
50

30 49
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 capture efficiency

Figure 6 - 7 Power requirement and capital cost of Selexol process for CO2
capture

182
The thermal efficiency of an IGCC power plant with CO2 capture is given in Figure

6-8. The thermal efficiency decreases with the increase of the total CO2 removal

efficiency. Compared with the thermal efficiency without CO2 compression, compressing

the captured CO2 to 2100 psia reduces the thermal efficiency by 2 percent points when

the total CO2 removal efficiency is 90%.

0.35

0.34
Thermal efficiency

0.33 Efficiency with


compression

0.32
Efficiency w/o
0.31 compression

0.30
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 capture efficiency

Figure 6 - 8 Thermal efficiency of IGCC power plants with CO2 capture

Energy penalty is defined to study the influence of the CO2 capture on the energy

performance of an IGCC power plant as in the following,

reference plant efficiency − capture plant efficiency


EP =
reference plant efficiency

Figure 6-9 gives the energy penalty of an IGCC power plant with different total

CO2 removal efficiency. Without CO2 compression, the energy penalty is about 8% when

the total CO2 removal efficiency is 70%, and it rises to 10% when the total CO2 removal

efficiency is 90%. CO2 compression further increases the energy penalty. For instance,

183
when the total CO2 removal efficiency is 90%, the energy penalty including compression

is up 15%.

18

16
Energy penalty (%)

Energy penalty
14 with CO2
compression
12
Energy penalty
10
w/o CO2
8 compression

6
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 removal efficiency

Figure 6 - 9 Energy penalty for CO2 removal (The thermal efficiency of the IGCC
reference plant without in this case is 0.371)

The capital cost of an IGCC power plant is also significantly influenced by CO2

capture. Figure 6-10 gives the total capital requirement (TCR) of an IGCC power plant

with CO2 capture. When the total CO2 removal efficiency is lower than 0.9, the total

capital requirement increases slowly with the increase of the CO2 removal efficiency.

When the total CO2 removal efficiency is 0.9, the total capital requirement without CO2

compression is about 1800 $/kW, and it’s approximately 11% higher when CO2

compression is considered.

184
2050

TCR with
1950
TCR ($/kW)

compression

1850
TCR w/o
compression

1750
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 capture efficiency

Figure 6 - 10 Total capital cost of an IGCC power plant with CO2 capture

Figure 6-11 shows the TCR increase percentage between the capture plant and the

reference plant. Without CO2 compression, the TCR is increased by 16% when the total

CO2 removal efficiency is 90%. The TCR would be increased by about 30% when the

captured CO2 is compressed up to 2100 psia after capture.

35

30 TCR increse
TCR increase (%)

percen w/o
25 compression

TCR increse
20 percen with
compression
15

10
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 capture efficiency

Figure 6 - 11Total capital cost increase percentage of IGCC power plants with CO2
capture (The total capital requirement of the reference plant is 1547
$/kW in this study)

185
Cost of electricity (COE) is an essential factor to evaluate the economic

performance of a power plant. Figure 6-12 shows the COE increase percentage under the

three different situations. Compared to the COE of the reference plant, when the total

CO2 removal efficiency is 90%, the COE increase percentage without CO2 compression,

with CO2 compression, and with CO2 transportation and storage is 15%, 25% and 41%,

respectively.
COE increase percentage (%)

45
40
35
With S&T
30
With compression
25
W/O compression
20
15
10
0.70 0.75 0.80 0.85 0.90 0.95
Total CO2 removal efficiency

Figure 6 - 12 COE increase percentage of IGCC plants with CO2 capture (In this
case, the COE of the reference plant is 56 $/MWh)

CO2 avoidance cost is used to evaluate the price paid for CO2 capture, which is

defined as:

COE of capture plant − COE of reference plant


reference plant CO 2 emission rate − capture plant CO 2 emission rate

Figure 6-13 shows the CO2 avoidance cost of an IGCC power plant. When the total

CO2 removal efficiency is 0.9, comparing to the case without CO2 compression, the CO2

avoidance cost with CO2 compression is increased by 1.7 times. When the transportation

and storage cost is included, the CO2 avoidance cost is 2.7 times of the cost without

186
compression. It is also noticed that no matter with CO2 compression or storage and

transportation, the avoidance cost always reaches the lowest point when the total CO2

removal efficiency is around 90%.

35
CO2 avoidance cost ($/tonne)

30

25

20

15

10
0.65 0.70 0.75 0.80 0.85 0.90 0.95
CO2 capture efficiency

With S&T With compression W/O compression

Figure 6 - 13 CO2 avoidance cost of IGCC plants

Figure 6-14 compares the CO2 emission rates of the capture plant. The relative CO2

emission rate quasi-linearly decreases with the increase of the total CO2 removal

efficiency. When the total CO2 removal efficiency is 0.9, the CO2 emission rate of the

capture plant is 0.091kg/kWh for the capture only case and, it goes up to 0.097 kg/kWh

for the capture and compression case, which is about the 11.7% of the emission rate of

the reference plant.

187
0.40

CO2 emission rate (kg/kWh)


0.30

0.20

0.10 With compression


W/O compression
0.00
0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95
CO2 capture efficiency

Figure 6 - 14 CO2 emission rate of the capture IGCC plant

6.3. Effects of plant size

Generally, the performance and cost of a power plant will vary with a change in the

size of the plant because in a certain range, relatively large plants will be benefit from

economy of scale and higher efficiency. This section shows the influence of the plant size

on IGCC systems and CO2 capture.

Here three sizes are investigated: one gasifier with one GE 7FA gas turbine, two

gasifiers with two GE 7 FA gas turbines, and three gasifiers with three GE 7FA gas

turbines. There is one spare gasifier for each plant. For the capture plant, the CO2 capture

efficiency is 90%, and the final CO2 product is compressed to 2100 psia.

The cost of electricity, thermal efficiency, total capital requirement and the net

output of each plant without CO2 capture are shown in Figure 6-15. The plant size has

notable influence on the total capital requirement. The capital requirement of the biggest

plant is about 280 $/kW less than that of the smallest one. Beside of the effect of

economy of scale on the equipment, the lower capital cost percentage of the spare gasifier

188
in the bigger IGCC plant is also a major reason for the lower capital cost. The thermal

efficiency is also improved with the increase of the plant size. For instance, the efficiency

of the biggest plant is about 0.5 percentage points higher than that of the smallest one.

Hence the cost of electricity also decreases with the increases of the plant sizes due to the

lower capital requirement and higher efficiency.

The effects of the plant size on the cost of electricity, thermal efficiency, total

capital requirement and net power output of IGCC plants with CO2 capture, which are

given in Figure 6-16, are similar to the effects shown in Figure 6-15.

60 1600
COE ($/MWh) & Effieicncy (%)

55
1500

TCR ($/kW)
50
1400
45

1300
40

35 1200
250 350 450 550 650 750 850
Net Output (MW)

COE ($/MWh) Thermal efficiency TCR ($/kW)

Figure 6 - 15 Cost of electricity, thermal efficiency and total capital requirement of


different size IGCC plants without CO2 capture

189
80 2000

70 1900

COE ($/MWh) &


Effieiency (%)

TCR ($/kW)
60 1800

50 1700

40 1600

30 1500
200 300 400 500 600 700 800
Net Capacity (MW)

COE ($/MWh) Thermal efficiency TCR ($/kW)

Figure 6 - 16 Cost of electricity, thermal efficiency, and total capital requirement of


different size IGCC plants with CO2 capture (the COE of the capture
plant includes the CO2 transportation and storage cost at a value of 10
$/tonne-CO2)

The CO2 avoidance cost, as shown in Figure 6-17 slightly decreases with the

increase of the plant size. For example, the avoidance cost of the biggest plant is 29

$/tonne-CO2 captured, which is approximately $2 lower than that of the smallest one.
CO2 Avoidance Cost ($/tonne )

32
31
30
29
28
27
26
25
200 300 400 500 600 700 800
Net Capacity of IGCC (MW)

Figure 6 - 17 Effect of plant size on the CO2 avoidance cost

6.4. Finance analysis of IGCC systems

Although IGCC systems show advantages in energy efficiency and emissions,

investments to design and build commercial IGCC power plants in the world have not

190
solidly stepped forward due to financing, cost and risk concerns [Rosenberg, 2004]. One

of the major issues hindering the application of IGCC is difficulty with financing. A key

challenge with financing IGCC technology is that there is not enough information on

which to make comparisons, or not enough experience bases in the marketplace.

Due to the large capital investment required by an IGCC power plant, typically,

neither the manufacturer nor the owner can self-finance, or secure adequate financing

using their non-project assets. So, project financing with an affordable capital structure is

often the only way that IGCC technology can be built.

The term capital structure refers to the mix of debt and equity that is used to finance

projects. A typical capital structure for a utility company is given in the following Table

6-4.

Table 6 - 4 Capital structure of a typical power plant project (source: IECM


manual)

Title Units Value


Percent Debt % 45
Percent Equity (Preferred Stock) % 10
Percent Equity (Common Stock) % 45

Cost of capital refers to the weighted costs of common stock, preferred stock

(equity returns) and long term debt (debt interests) used to finance a project. For a project

financed by debt and equity, the average capital cost is given by [Ross, 2005],

S B
r WACC = ( ) × rs + ( ) × r B × (1 − T C )
S+ B S+ B

191
where rWACC = average cost of capital after tax for the project

S = the amount of equity

B = the amount of debt

rS = the cost of equity

rB = the cost of debt (borrowing rate)

TC = the tax rate

Both the cost of equity and the cost of debt depend on the perceived risk of a

project. As an emerging technology for power generation, IGCC is generally viewed to

have higher risk than more mature power generation systems, such as PC power plants.

Hence IGCC faces higher financing cost in the absence of incentive policies.

In order to stimulate deployment of IGCC technology, a 3-Party Covenant has been

proposed, which is a financing and regulatory program aimed at reducing financing costs

and providing a technology risk-tolerant investment structure [Rosenberg, 2004]. The 3-

Party Covenant would be an arrangement between the federal government, state Public

Utility Commission (PUC), and equity investors. The proposal would work as follows

First, Federal legislation authorizes a federal loan guarantee to finance IGCC projects.

The terms of the federal guarantee require that a proposed project obtain from a state

PUC an assured revenue stream to cover return of capital, cost of capital, taxes and

operating costs. The state PUC provides this revenue certainty through utility rates in

states with traditional regulation of retail electricity sales. The equity investors (electric

192
utility or an independent power producer) negotiate performance guarantees to develop,

construct, and operate the IGCC plant. A fair equity return is determined and approved by

the state PUC before construction begins [Rosenberg, 2004].

In short, the function of this 3-Party Covenant is to adjust the capital structure (debt

to equity ratio) and reduce the interest rate of debt through federal guarantee. For

instance, a typical interest rate of a mid-grade utility debt ranked as BBB was 6.5 percent

in early 2004. With the federal guarantee, the debt would be ranked as AAA, and its

interest would be reduced to 5.5 percent [Rosenberg, 2004].

Six different capital structures are used here to investigate the influence of the

proposed 3-Party Covenant on the capital costs and energy costs of IGCC power plants,

which are given in Table 6-5. The capital structures and resulting cost of capital from

Case A to Case E reflect different debt-to-equity ratios. Case F gives a conventional

capital structure for a power plant project.

Table 6 - 5 Capital structures and cost of capital for IGCC financing

Title Unit Case A Case B Case C Case D Case E Case F


Real Bond Rate % 5.5 5.5 5.5 5.5 5.5 6.5
Real Equity Return % 11.5 11.5 11.5 11.5 11.5 11.5
Percent Debt % 50 60 70 80 90 45
Percent Equity % 50 40 30 20 10 55
Debt/Equity Ratio 1.0 1.5 2.3 4.0 9.0 0.8
Federal Tax Rate % 35 35 35 35 35 35
State Tax Rate % 4 4 4 4 4 4
Property Tax Rate % 2 2 2 2 2 2
Cost of Capital
(Before Taxes) % 8.50 7.90 7.30 6.70 6.10 9.25
Fixed Charge Factor (FCF) % 13.00 12.04 11.12 10.22 9.35 13.88

193
In the following simulation cases, the IGCC system has two GE 7FA gas turbines

and two operation gasifiers. For comparison, the performance and costs of a PC power

plant and a NGCC plant are also calculated using the IECM computer model. The PC

power plant is super-critical with in-furnace NOx control, cold-side ESP for particulate

control, and a flue gas desulfurization system for SOx control. The gross output of the PC

plant is 500 MW. The fuel for the PC plant is also the Pittsburgh #8 coal with a price of

1.27 $/MBtu. The NGCC power plant uses two GE 7FA gas turbines, and its steam cycle

heat rate is 9496 kJ/kWh. The natural gas price is 3.797$/GJ. The capacity factors for all

these three type plants are 75%.

Figure 6-18 shows the total capital requirement of the reference IGCC power plant

with the A to F capital structures and the total capital requirement of the PC plant with

the F capital structure. With the same capital structure F, the total capital requirement of

the IGCC plant is about 11% higher than that of the PC power plant. With the incentive

3-Party Covenant capital structures, the total capital cost of the IGCC plant reduces with

an increasing debt-to-equity ratio, because higher debt percentage in the capital structure

lowers the Allowance for Funds during Construction (AFDC).

194
1300

1250

1200

TCR ($/kW)
1150

1100

1050

1000
A- B- C- D- E- F - F -PC
IGCC IGCC IGCC IGCC IGCC IGCC

Figure 6 - 18 Total capital requirement of the IGCC and PC plant based on


different capital structures

The effect of the capital structure on the cost of electricity is show in Figure 6-19.

Among the IGCC, PC and NGCC plants with the same conventional capital structure

(Case F), the IGCC power plant has the highest COE, and NGCC has the lowest one.

However, the COE of the IGCC with the capital structure of Case A is 43.9 $/MWh,

which is almost break-even with that of the PC plant. When the debt-to-equity ratio in the

capital structure increases from Case A to Case B, the COE of the IGCC plant is even

lower than that of the NGCC plant.

195
50

45

COE ($/MWh)
40

35

30

25

20
A- B- C- D- E- F- F -PC F-
IGCC IGCC IGCC IGCC IGCC IGCC NGCC

Figure 6 - 19 Cost of electricity of IGCC plant with different capital structures

The IGCC plant shows its advantage if CO2 capture is included. From Figure 6-20,

it is clear that even with the common capital structure, the total capital requirement of the

IGCC capture plant is still lower than that of the PC capture plant.

2000

1900
TCR ($/MWh)

1800

1700

1600

1500

1400
A- B- C- D- E- F -IGCC F -PC
IGCC IGCC IGCC IGCC IGCC

Figure 6 - 20 Total capital requirement of IGCC and PC capture plants under


different capital structures

With the same conventional capital structure, the COE of the IGCC capture plants,

as shown in Figure 6-21, is about 22 percent lower than that of the PC power plant, and

about 12 percent higher than that of the NGCC plant. When the debt-to-equity ratio

196
increases to 2.3, the COE of IGCC is the same as that of NGCC plant. However, it should

be noticed that the natural price used here is a relatively low value based on recent U.S.

gas prices. If the nature gas price goes up to 4.66 $/MJ, calculation shows that with the

same conventional capital structure, the COE of the NGCC capture plant will be same as

that of the IGCC capture plant. Considering the highly volatile price of natural gas in the

foreseeable future, even without any incentive policies an IGCC capture plant could be

competitive with an NGCC capture plant.

90

80
COE ($/MWh)

70

60

50

40
A- B- C- D- E- F- F -PC F-
IGCC IGCC IGCC IGCC IGCC IGCC NGCC

Figure 6 - 21 COE of IGCC, PC and NGCC capture plants with different capital
structures

In conclusion, many factors influence the performance and cost of IGCC power

plants. For the current commercial gasifier designs that employ slurry coal feeding, the

use of low rank coal significantly reduces the thermal efficiency of an IGCC plant. The

plant size also is an important factor influencing the total capital cost of an IGCC plant

due to the economy of scale. For CO2 capture, there is an optimal CO2 capture efficiency

that minimizes the CO2 avoidance cost. Based on the current CO2 capture procedure, this

optimal CO2 capture efficiency is in a range from 85% to 90%. Finally, without an

197
incentive financing approach, the IGCC power plant without CO2 capture is less

competitive than the PC and NGCC power plants in terms of both the total capital

requirement and the COE. An incentive financing policy for IGCC power plants, like the

3-Party Covenant proposed by Rosenberg [2004], can help IGCC power plants enter into

commercial operation more widely. Due to the advantages of IGCC plants for CO2

capture, even without incentive financing policies IGCC capture plants are competitive

with PC and NGCC capture plants.

198
REFERENCES (CHAPTER 6)

1. Booras G., and Holt N, 2004: Pulverized Coal and IGCC Plant Cost and
Performance Estimates, Gasification technologies, Washington, DC, October 3-6,
2004

2. Breton D. L. and Amick P., 2002: Comparative IGCC cost and performance for
domestic coals, gasification technology conference, Oct., 2002, San Franscio

3. Rosenberg W.G., Alpern D.C., and Walker M.R., 2004: Deploying IGCC in This
Decade With 3-Party Covenant Financing, ENPR discussion paper, discussion
paper 2004-7, Harvard University, Cambridge, MA

4. Jaffe R.W., 2005, Corporate Finance, Seventh Edition, McGraw-Hill

5. IECM User Manual, 2005, Department of Engineering and Public Policy, Carnegie
Mellon University, Pittsburgh, PA

199
Chapter 7. IGCC REPOWERING WITH CO2 CAPTURE

North America has over 320,000 MWe of existing coal-fired power plants, which

accounts for 35% of the total installed capacity and 49.8% of the total annual power

generation in North America [Simbeck, 2001; Smock, 1990, EIA, 2004]. Most of the

existing coal-fired power plant capacities are pulverized coal (PC) boilers that are 25-35

years old. These existing coal-based power plants have the highest CO2 emission rate,

due to the use of high carbon fuel (coal) and a relatively low thermal efficiency. What is

the technical and economic potential to reduce CO2 emissions from these existing power

plants in the event that new environmental regulations place limits on carbon emissions?

One recent study looked at retrofitting plants with an amine scrubber, and found this to be

a costly measure that would substantially degraded plant performance [Rao, 2002].

However, IGCC repowering with CO2 capture offers a substantially different option to

this problem.

IGCC repowering can be defined as the integration of gasification units, gas turbine

generator units and heat recovery units into an existing steam power plant. Compared to

other repowering technologies, IGCC repowering without CO2 capture is usually

considered to be less attractive due to the expense of the gasification units [Brander,

1992]. However, it does present several advantages. IGCC repowering can substantially

increase the capacity and thermal efficiency of an old PC plant. The net output of a

repowered IGCC plant can be up to three times or more of the original PC plant’s output.

At the same time, the emissions of NOx, SOx, Hg and solid waste can be dramatically

reduced [Daledda, 1995; Bajura, 1995]. Shorter construction time and re-use of existing

equipment (cooling system, steam turbine/generator units), infrastructure (road/railroad

200
connections, office building), and existing transmission capacity will reduce the capital

cost relative to a new IGCC plant. Furthermore, re-use of the existing plant land can

simplify the complicated site studies and authorization procedures [Makansi, 1994]. If the

purpose of repowering is to mitigate CO2 emissions, IGCC repowering can reduce CO2

emissions while also improving capacity and efficiency.

This section provides an overview of the available options of using IGCC

technology for repowering PC power plants. Then the decision factors which should be

considered for an IGCC repowering project are discussed. Finally, the cost and

performance of IGCC repowering are preliminarily analyzed, and results are summarized

to show how IGCC repowering might be an attractive option for improving the

performance of existing power plants.

7.1. IGCC repowering options

There are four major approaches for IGCC repowering, which are site repowering,

feedwater heating repowering, boiler hot windbox repowering and heat recovery

repowering [Sullivan, 1994; Najjar, 1994; Stenzel, 1995]. Each of them is discussed

below.

7.1.1. Site Repowering

Site repowering is the simplest repowering option. It is to reuse the existing site to

construct a new IGCC power plant or other types of power plants after demolishing

existing units, except for keeping some reusable facilities, such as the cooling water

system, switchyard and buildings. Site repowering has the advantage of being able to

utilize the best available combined-cycle technology without having to make

201
compromises to match the older existing components or systems. When compared to

constructing a new unit on a new site, there can be savings in the permitting process,

transmission access, and socioeconomic considerations for the local area that can make

the site repowering a preferred option. The repowered plant performance would usually

be identical to a new unit.

7.1.2. Feedwater heating repowering

Feedwater heating repowering uses the gas turbine exhaust to heat feedwater in an

existing PC power plant. The steam previously extracted from steam turbines for

feedwater heating is used to generate more power in steam turbines if the existing steam

turbine design limits are not exceeded, or used to augment power output in the

combustion turbine. In order to increase the availability, existing feedwater heaters can be

retained to allow conventional operation when the combustion turbine or the gasifier is

out of service. Feedwater heating repowering can improve the efficiency of the steam unit

by about 15% [Brander, 1992].

7.1.3. Boiler windbox repowering

Windbox repowering utilizes the gas turbine exhaust as the combustion air for the

existing boiler. Boiler windbox repowering technologies can add up to 25% additional

capacity to the unit, improve the efficiency by 10-20%, improve the part load efficiency

and cycling capability, and reduce NOx emissions, but windbox repowering appears to be

the highest degree of technical complexity of all the combustion-turbine-based

repowering options [Stenzel, 1995].

202
A variant to the boiler windbox repowering approach includes a HRSG to reduce

the temperature of the combustion turbine exhaust and produce additional steam. With

this approach the existing windbox can be retained but will need to be enlarged, or the

boiler will not produce the full steam output. This repowering configuration is commonly

known as warm-windbox repowering and is used primarily to achieve heat rate

reductions.

7.1.4. Heat recovery repowering

In the heat recovery repowering, the plant’s existing boiler is replaced by a gasifier,

combustion turbine and Heat Recovery Steam Generator (HRSG). Heat recovery

repowering uses the gas turbine exhaust to generate steam in a HRSG. High efficiency is

obtained by exchanging condensate, feedwater, and steam between the gasification

system and the heat recovery steam generator.

7.1.5. Evaluation of repowering options

The site repowering is somewhat like building a greenfield IGCC power plant,

which can be roughly estimated based on the performance and cost of a greenfield IGCC

plant. For the feedwater heating and boiler windbox repowering, the existing boilers have

to be kept, and it is necessary to control CO2 emissions from the existing boilers as well

as from the gasifier. Therefore, these two approaches do not fully take advantage of the

low CO2 capture cost of the gasification process. In the heat recovery repowering, the

existing boiler is completely replaced by a gasifier, which is the only source of CO2.

Hence, for the goal of CO2 capture, only the heat recovery repowering approach is an

attractive choice for IGCC repowering with CO2 capture.

203
7.2. Decision factors for IGCC repowering

Evaluations for repowering projects must include a wide range of business aspects,

load growth forecasts, financial parameters, environmental regulations, fuel cost ranges,

fuel availability, legal issues and many other factors. A repowering analysis usually

follows steps similar to those summarized below [Stenzel, 1995; Weinstein, 1999]:

• Determining the generation system goals; e.g., the amount and value of the

needed additional power, emission reductions, fuel availability and costs,

transmission requirements and/or limitations, forecasted generation load

schedules, target electricity market price and/or other requirements and goals.

• Determining the existing plants that can be repowered to meet the generation

goals by identifying the important site restrictions (e.g., emission limits),

conditions of the existing equipment, and other important information.

• Identifying candidate repowering technologies and perform an initial analysis to

reduce the repowering options to the most competitive technologies.

• Developing the design, operation parameters, capital costs, schedules and

economics (the saving potential and simple pay-out time) for applicable

repowered plants and optional new plants.

• Selecting the best option(s) based on economics and other factors.

There are a number of significant differences in considering IGCC repowering

applications, which include the following.

204
Available space: Reusing old sites is one of the advantages of repowering, but

IGCC repowering with CO2 capture needs more equipment than other repowering

approaches. For an IGCC repowering, the area for new units, the distance from gas

turbine to existing steam turbines are important factors to consider. Hence, site space

could be at a premium for some locations, and installation costs may be increased due to

fitting new units in available space and more complicated layouts. Based on the space

availability, for heat recovery repowering, the existing boilers can be demolished to

provide more space for new units, or retired in place, or retained in standby for increased

reliability states [Weinstein, 1999].

Heat rejection capability: Although the heat rejection from the steam turbine cycle

is almost the same before and after the repowering, the low-energy, non-recyclable waste

heat from the air separation unit and gasification process increases the total amount of

heat rejection. In some cases this additional heat generated by gasification could exceed

the heat rejection limitation permitted for a plant where condenser cooling is provided

from a river, ponder or estuary. For cooling tower installations, this will result in an

increase in condenser pressure, circulation water temperature, and tower evaporation.

This system should be checked to assure that any cooling tower makeup water flow

limitations are not exceeded and that certain critical auxiliary cooling water users, such as

the generator coolers, do not exceed maximum temperature limits. Any such permitting

limitations should be evaluated [Sullivan, 1994].

Transmission constraint on bulk transmission system: IGCC repowering can triple

the capacity of an existing plant and the total capacity of the repowered plant may surpass

the capacity of the original switchyard and transmission system.

205
Demineralized water availability: For IGCC repowering, power augmentation from

the gas turbine and steam turbine is desired, steam or water is available with an

associated increase in the demineralized water requirements.

Air emissions: Emissions from IGCC systems are typically controlled to meet strict

environmental standards. Emissions limitations for the existing boiler can vary

significantly depending on the control technology used, local permitting requirements,

the age of the boiler, and other site specific conditions. Typically, IGCC emissions will

be less than that of the boiler being replaced. This reduction in total emissions will also

benefit the utility by allowing offsets in emissions at other sites.

Steam turbine capabilities: the conditions, capabilities, and limitations of the

existing steam turbine are the most significant factors in determining the feasibility of

IGCC repowering. Optimizing the existing steam turbine performance with the new

combined-cycle components is important for the repowered unit to be able to compete

with a new unit, even if it has lower capital costs. Selecting an appropriate size

combustion turbine to match an existing steam turbine is a key factor to reach the optimal

result. The following section will discuss this key issue: how to select and match a

combustion turbine to an appropriately sized steam turbine for IGCC repowering with

and without CO2 capture.

7.3. Heat recovery repowering design

For a PC power plant, steam is generated in a one, two, or three-pressure boiler for

delivery to a steam-generator. The boiler feed water is heated by steam extracted from the

steam turbine. Figure 7-1 gives the schematic process of a PC power plant with a single-

206
pressure, non-reheat system cycle. This is the simplest steam cycle that can be applied in

a PC plant. It results in a low installed cost. Although it does not produce the highest

combined-cycle thermal efficiency, it is a sound economic selection when fuel is

inexpensive.

Figure 7 - 1 One-pressure, non-reheat steam cycle with steam extraction for


feedwater heating

Multi-pressure (two or three) steam cycles are used to maximize energy recovery

from the boiler. Two or three-pressure steam cycles achieve better efficiency than the

single pressure systems, but their installed cost is higher. They are the economic choice

when fuel is more expensive or if the duty cycle requires a high load factor. Figure 7-2

shows a two-pressure, non-reheat steam cycle. Three-pressure, reheat steam cycle is

shown in Figure 7-3. This cycle can achieve the highest energy efficiency, but the capital

cost is also higher than other steam cycle options.

207
Figure 7 - 2 Two-pressure, non-reheat steam cycle with steam extraction for
feedwater heating

Figure 7 - 3 Three-pressure, reheat steam cycle with steam extraction for


feedwater heating

For a combined cycle power plant, like an IGCC plant or a NGCC plant, its steam

cycle is similar to the PC power plant. Depending on the design criteria, the steam cycle

could be a simple one-pressure style if the capital cost is more concerned than the thermal

208
efficiency (or fuel cost). It can also be a three-pressure, reheat style if the thermal

efficiency is more concerned than the capital cost.

Unlike steam turbines, gas turbines are only available in discrete sizes. For the

IGCC heat recovery repowering option, the capacity of the gas turbines and steam turbine

should match well to fully utilize the waste heat from the gasification process and the gas

turbine. For a greenfield power plant, it is not a problem to product a steam turbine with

an appropriate size to match a given gas turbine. For a repowering project, however, a

steam turbine has existed with a fixed maximum flow capability (power generation

capacity). Once this is reached, no further output capability exists at the site.

There is a range of the steam turbine power output that that can be repowered with a

given gas turbine. The range depends on the temperature and flow rate of the gas turbine

exhaust, the throttle pressure and loading limitation of the existing steam turbine, and the

heat recovery process employed. The low boundary of the range is achieved under the

most restrictive condition—the steam turbine limitations are so severe that the

repowering is only simple replacement of a non-reheat boiler by a gasifier, a gas turbine,

and a HRSG with no modification to either the steam turbine or the feedwater heating

system. This configuration is illustrated in Figure 7-4, which shows the repowered plant

configuration with all existing feedwater heaters in service. This represents the minimum

capital cost approach, which also results in the lowest output, lowest thermal efficiency

alternative.

209
Figure 7 - 4 IGCC repowering with all feedwater heaters (minimum repowering )

If sufficient steam turbine low-pressure section flow passing capability is available,

the low pressure feedwater heaters or all feedwater heaters can be removed from service

as shown in Figures 7-5. These systems require additional heat transfer surface to be

installed in the HRSG to heat the feedwater, which increases the capital cost. The

increased plant output and efficiency may justify the added expense [Brander, 1992].

The maximum power output is achieved under the most ideal condition---the

existing steam turbine has sufficient design margins, and the temperature of a gas turbine

exhaust is high enough so that it can incorporate a three-pressure, reheat HRSG and

eliminate all the feedwater heaters, as shown in Figure 7-6.

210
Figure 7 - 5 IGCC repowering with removing some feedwater heaters (medium
repowering)

Figure 7 - 6 IGCC repowering without feedwater heaters (maximum repowering


case)

7.4. IGCC repowering economic and performance analysis

As discussed above, a wide range of factors have to be considered when evaluating

the performance and cost of a repowering project at a given site. Due to the variability

211
from site-to-site, it is clear that there will be a wide range in the results of economic

evaluation. As an example, consider using a Texaco quench oxygen-blown gasifier and a

GE MS7001F gas turbine to repower an old PC plant using a steam turbine operating at

1400 psig throttle condition. Two simulation models are set up in Aspen Plus to evaluate

the repower range of this configuration. One model simulates the most restrictive

condition, or the minimum case—replacing the existing boiler with a gasifier, a gas

turbine and a HRSG and no modification to the steam turbine and the feedwater system.

In this case, the heat recovered from syngas cooling is only used to reheat and saturate

the syngas fed into the gas turbine. Another model simulates the most favorable

condition, or the maximum case—the steam turbine has sufficient design margins so that

it can be incorporated into a three-pressure reheat HRSG, and remove all the feedwater

heaters. In this case, part of the heat recovered from syngas cooling is used to reheat and

saturate syngas, and the left heat is used for steam generation. The two models are

further revised to incorporate the CO2 capture function.

For the cost analysis, all existing equipment is assumed to be fully amortized, and

the reusable utilities are assumed to be the coal handling facility, the dematerialized water

unit, the boiler feed water system, the steam turbine and the generator. Other assumptions

are given in Table 7-1.

Table 7 - 1 Economic and financial assumption for repowering studies

Fixed charge factor 14.8% Years of construction (yr) 3.5


Capacity factor 75% Lifetime (yr) 30
Fuel type Pittsburgh #8 Fuel price ($/MBtu) 1.27
CO2 transport and
storage ($/tonne) 10 CO2 final pressure (psia) 2100

212
The performance of the repowering cases is given in Table 7-2. A Texaco quench

gasifier and a GE MS7001F gas turbine without CO2 capture can satisfy the steam

requirements of a 60 MW steam turbine if a straight boiler replacement is done. If the

cycle can be optimized using three-pressure reheat HRSG, the corresponding steam

turbine size is approximately 110 MW. The total capital cost of the repowered plants

without CO2 capture ranges from $1201/kW (maximum case) to $1410/kW (minimum

case) as compared to $1547/kW of the greenfield plant. For the repowering plants with

CO2 capture, the capital costs range from $1656/kW (maximum case) to $2108

(minimum case) as compared to $1995/kW of the greenfield plant.

Table 7 - 2 Study results of IGCC repowering with and without CO2 capture

Net
ST plant Thermal CO2
TCR COE power output efficiency emission
Case ($/kW) ($/MWh) (MW) (MW) (HHV) (kg/kWh)
Min. case 1410 57.5 60.1 225.5 31.1 0.986
Without Max. case 1201 48.8 110.3 274.4 36.7 0.835
CO2
capture Greenfield 1547 55.7 112.1 276.1 36.9 0.830
Min. case 2108 92.7 60.5 192.1 24.2 0.126
With Max. case 1656 72.5 120.4 251.6 31.3 0.098
CO2
capture Greenfield 1995 78.3 122.3 253.4 31.5 0.097

The repowering option with lower capital cost also has worse energy efficiency.

The energy efficiencies of the repowering plants without CO2 capture range from 31.1%

(minimum case) to 36.7% (maximum case) as compared to 36.9% of the greenfield plant.

Without CO2 capture, the COE of the minimum repowering case is slightly higher

than that of the greenfield IGCC power plant. However, the COE of the maximum

213
repowering case is around 12.3% lower than that of the greenfield plant. For the capture

plant, the maximum case also has the lowest COE, but the COE of the minimum

repowering case is much higher than the other two cases.


CO2 avoidance cost ($/tonne)

60 53
50
40 37
31
30 23 24
20
20
11 12
10 3
0
Full capture W/O T&S W/O com p.

Minimum case Maximum case Greenfield

Figure 7 - 7 CO2 avoidance cost of IGCC repowering plants (the greenfield IGCC
plant without CO2 capture is used as the reference plant to calculate
the CO2 avoidance cost. Full capture refers to CO2 capture,
compression, transport and storage; W/O T&S refers to CO2 capture
and compression without transport and storage; W/O comp. refers to
CO2 capture without transport, compression and storage)

Using the greenfield IGCC without CO2 capture as the reference plant, as shown in

Figure 7-7, the maximum repowering IGCC plant with full CO2 capture (capture,

compression, storage and transportation) reduces the CO2 avoidance cost from $31/tonne

to $23/tonne. On the other hand, the minimum repowering case raises the avoidance cost

to $53/tonne. For CO2 capture only without compression, the CO2 avoidance cost is only

$3/tonne.

According to the above discussion, IGCC repowering with and without CO2 capture

may be an economically attractive option for existing PC power plants. Compared to

building greenfield IGCC plants, IGCC repowering is less capital intensive and has a

214
shorter construction period. Hence it also provides an option for introducing new power

generation technology with lower risk to utilities. Under suitable conditions, IGCC

repowering may be a cost-effective and attractive option for reducing CO2 emissions

from existing coal-fired plants. However, the cost and feasibility of repowering is very

site specific. Hence, further research is needed to identify the most promising

applications of IGCC repowering based on detailed site-specific assessments.

215
REFERENCES (CHAPTER 7)

1. Simbeck D.R., CO2 Mitigation Economics for Existing Coal-Fired Power Plants,
the Eighteenth Annual International Pittsburgh Coal Conference, 4 December,
2001, Newcastle, NSW, Australia

2. Robert Smock, Performance improvement of old plants gains favor, Power


engineering, Nov. 1990

3. Rao, A.B. and Rubin, E.S. (2002). “A Technical, Economic and Environmental
Assessment of Amine-based Carbon Capture Technology for Power Plant
Greenhouse Gas Control,” Environ. Sci. Technol. 36(20), 4467-4475.

4. J. A. Brander, D. L. Chase, Repowering application considerations, Journal of


Engineering for Gas Turbines and Power, Oct. 1992, Vol. 144

5. Kenneth Daledda, Repowering cuts air pollution, improves station’s efficiency,


Power, April 1995

6. Rita A. Bajura and J. Christopher Ludlow, Repowering with coal gasification and
gas turbine systems: an acid rain control strategy option, Morgantown Energy
Technology Center, DOE

7. Jason Makansi, Repowering: options proliferate for managing generation assets,


Power, June 1994

8. T.M. Sullivan and M.S. Briesch, Repowering: a ready source of new capacity,
Energy Engineering, Vol. 91, No.2 1994

9. Y.S. H. Najjar and M. Akyurt, Combined cycles with gas turbine engines, Heat
recovery systems & CHP, Vol. 14, No.2, 1994

10. William C. Stenzel, Dale M. Sopocy, and Stanley E. Pace, Repowering Existing
Fossil Steam Plants

11. Richard E. Weinstein, Robert W. Travers Advanced Circulating Pressurized


Fluidized Bed Combustion (APFBC) Repowering Considerations

216
Chapter 8. PERFORMANCE AND COST UNCERTAINTY ANALYSIS OF
IGCC SYSTEMS

An IGCC plant is a complex chemical treatment and energy conversion system.

Large scale, commercial experience with IGCC and Selexol systems for CO2 capture is

still limited. Consequently, there are substantial uncertainties associated with using the

limited performance and cost data available to predict the commercial-scale performance

and cost of a new IGCC plant. There are several types of uncertainty associated with a

developing technology, such as the IGCC technology. These uncertainties include

statistical errors, systematic errors, variabilities, and the lack of an empirical basis for

concepts that have not been tested [Frey, 1994]. Uncertainties may apply to different

aspects of the process, including performance variables, equipment sizing parameters,

process area capital costs, requirements for initial catalysts and chemicals, indirect capital

costs, process area maintenance costs, requirements for consumables during plant

operation, and the unit costs of consumables, byproducts, wastes, and fuel. Model

parameters in any or all of these areas may be uncertain, depending on the development

state of the technology, the level of the performance and cost estimates, future market

conditions for new chemicals, catalysts, byproducts, and wastes, and so on.

Given limited performance and cost data, as well as uncertainties associated with

the complexity of IGCC systems, this chapter undertakes a systematic evaluation of

performance and cost uncertainties and a ranking of the importance of different factors in

terms of their potential contribution to the total uncertainty. In this study, the term

uncertainty is used loosely to include variability (for example, in nominal process design

values) as well as true uncertainty in the value of a particular parameter.

217
8.1. Methodology for uncertainty analysis

In this study, the parameter uncertainty analysis assumes that the total uncertainty

can be calculated from an estimate of uncertainty in each of the parameters used in the

performance and cost models. The technique of parameter uncertainty analysis provides a

quantitative way to estimate the uncertainty in model results. The general approach to

perform the parameter uncertainty analysis is given in the following steps [IAEA, 1989]:

• Define the assessment endpoint.

• List all uncertain parameters (include additional parameters if necessary to

represent uncertainty in model structure).

• Specify maximum range of potential values relevant for uncertain parameters.

• Specify a subjective probability distribution for values occurring within this

range.

• Determine and account for correlations among parameters.

• Using either analytical or numerical procedures, propagate the uncertainty in the

model parameters to produce a probability distribution of model predictions.

• Derive quantitative statements of uncertainty in terms of a subjective confidence

interval for the unknown value.

• Rank the parameters contributing most to uncertainty in the model prediction by

performing a sensitivity analysis.

218
• Present and interpret the results of the analysis.

According to the above procedure, to perform a quantitative uncertainty analysis,

the first step is to estimate uncertainties in specific process parameters, which involves

the following several steps:

• Review the technical basis for uncertainty in the process

• Identify specific parameters that should be treated as uncertain

• Identify the source of information regarding uncertainty for each parameter

Depending on the availability of information, the estimate of a parameter

uncertainty can be based on published judgments in the literature, published information

that can be used to infer a judgment about uncertainty, statistical analysis of data, or

elicitation of judgments from technical experts.

8.2. Probability distribution estimation of uncertainty parameters

For this study, reviewing the technical basis for uncertainty and identifying specific

parameters that should be treated as uncertain had been completed along with the

development of the technical and economic models. Then a probability distribution must

be assigned to each of the uncertain parameters. Some of the probability distributions of

parameters came directly from published judgments in the literature. Most of the other

probability distributions were estimated through statistical analysis of data from

reviewing published information. We note that using histograms of published literature

values can sometimes provide a misleading estimate of uncertainty because some

published literature values may have little bearing on how a system actually performs

219
once it has been deployed. With this in mind, much more attention was paid to collect

data from project reports and papers published by industrial companies with real-world

experience.

8.2.1. Data visualization

After data collection, the data set for each parameter was visualized through

plotting the data in figures. Specific techniques for evaluating and visualizing data

include calculating summary statistics, plotting empirical cumulative distribution

functions, representing data using histograms, and generating scatter plots to evaluate

dependencies between parameters. The purposes of visualizing data sets include [Frey,

2002]:

• evaluating the central tendency and dispersion of the data;

• visually inspecting the shape of empirical data distribution as a potential aid in

selecting parametric probability distribution models to fit to the data;

• identifying possible anomalies in the data set (such as outliers);

• identifying possible dependencies between variables.

8.2.2. Probability distribution selection

In choosing a distribution function to represent an uncertainty parameter, besides

the data visualization, prior knowledge of the mechanism that impacts a quantity plays an

important role. Probability distribution selection in this work was done in three steps.

220
As the first step, most of the probability distributions were represented by uniform

distributions or triangular distributions to screen the most important parameters. Uniform

probability is useful when it is possible to specify a finite range of possible values, but no

information is available to decide which values in the range are more likely to occur than

others. Triangular distributions also specify a range, but a mode is also specified. It is

useful when we can specify both a finite range of possible values and a most likely

(mode) value. For instance, for some input parameters, values toward the middle of the

range of possible values are considered more likely to occur than values near either

extreme. When this is the case, the triangular distribution provides a convenient means of

representing uncertainty [Morgan, 1998]. Uniform and triangular distributions are

excellent for screening studies and relatively easy to obtain judgments for relevant

values. In addition to being simple, the shape of the uniform and triangular distributions

can be a convenient way to send a signal that the details about uncertainty in the variable

are not well known. This may help to prevent over-interpretation of results or a false

sense of confidence in subtle details of model results [Morgan, 1998].

Once a particular distribution for an uncertainty parameter has been selected, a key

step is to estimate the parameters of the distribution. The most widely used techniques for

estimating the parameters are the method of maximum likelihood estimation (MLE), the

method of least squares, and the method of matching moments [Morgan, 1998]. MLE

was used in this study when a distribution more complicated than uniform and triangle is

employed.

The fitted parametric distributions may be evaluated for goodness of fit using

probability plots and test statistics. In this study, the empirical distribution of the actual

221
data set was compared visually with the cumulative probability functions of the fitted

distributions to aid in evaluating the probability distribution model that described the

observed data.

8.2.3. Distribution functions of uncertain parameters

During the model development process of IGCC system with CO2 capture, a

number of variables are determined as the uncertain parameters for preliminary

uncertainty screening, which are given in Table E-1, E-2 and E-3 of Appendix E. Several

of the parameters in the above tables were found to be correlated or expected to be

correlated. The probabilistic simulations were exercised both with and without

considering parameter correlations to determine if model results are sensitive to

parameter correlation. Simulations using parameter correlations produced only minor

effect on the results. Therefore, for convenience, the following case study presents the

results based on uncorrelated sampling.

After preliminarily investigating uncertainty ranges of these parameters and their

effects on performance and cost, this thesis focus on two key parameters, capacity factor

and fuel price, for the following reasons. First, preliminary study shows that the

uncertainties associated with these two factors have a significant influence on the CO2

avoidance cost and on the cost of electricity (which is arguably the most important

criterion for a power plant). Second, uncertainties (including variability) associated with

most of the parameters of the IGCC process and the capture process would disappear or

shrink after the specific plant is designed and installed, but during the operation period

the capacity factor and the fuel price may still change frequently and widely due to

changes in load requirements and fuel price volatility, as described below.

222
Capacity factor distribution

IGCC plants, as other coal-fired power plants, typically provide base load service,

with nominal design capacity factor of 85% assumed in many recent studies (vs. the

historical average of 67% for U.S. coal plants). To consider the possible range of capacity

factors over the lifetime of IGCC plants, historical capacity factor data for power plants

with capacity larger than 250 MW and age less than 30 years were collected from the

DOE/NETL coal-fired power plant database, for the year 2000, and used to simulate the

capacity factor uncertainty of an IGCC power plant.

Using the methodology expressed above, a distribution function for the capacity

factor of an IGCC power plant was represented as a Weibull distribution. Table 8-1

compares the statistic properties of the data points with that of the fitted Weibull

distribution. The empirical cumulative distribution function of the data points and the

cumulative distribution function of the Weibull distribution are compared in Figure 8-1.

These comparisons show that the Weibull distribution is a suitable presentation of the

uncertainty (variability) associated with the capacity factor.

Table 8 - 1 Statistical description of power plant capacity factor data and the fitted
Weibull distribution

Dataset Mean Median Standard Deviation Skewness


Coal Plant Data
(>250 MW, <30 years old) 0.762 0.771 0.104 -0.712
Weibull distribution 0.764 0.775 0.106 -0.568

223
1
Weibull Data

CDF of capacity factor 0.8

0.6

0.4

0.2

0
0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Capacity factor

Figure 8 - 1 Empirical cumulative distribution functions of the capacity factor


data and the distribution of the Weibull(8.5, 0.81) with Trunc(0, 1)

Fuel price distribution

Figure 8-2 represents the historical Central Appalachian coal prices in the New

York Mercantile Exchange (NYMEX). From 1990 to 2000, coal prices decreased, but

after 2000 coal prices began to increase and price volatility became notably larger. The

historical coal prices shows the importance of considering the risk of an IGCC power

plant exposed to volatile coal prices. Modeling and predicting the future coal prices are

beyond the scope of this thesis. Rather, this thesis focuses on analysis of the effect of

uncertainty of coal prices on IGCC systems based on the historical coal prices in the

recent 15 years.

224
2.2
2.0

Coal price ($/MMBtu)


1.8
1.6
1.4
1.2
1.0
0.8
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
Year

Figure 8 - 2 Central Appalachian coal price in the New York Mercantile Exchange
(The original coal prices were given for July of each year; the prices
shown here were inflation adjusted to the dollar value in 2000)

The distribution of coal prices is represented as a lognormal distribution. Table 8-2

gives the general statistical properties of the data points and the lognormal distribution.

The empirical cumulative distribution function of the data points and the lognormal

distribution are given in Figure 8-3.

Table 8 - 2 Statistic description of coal price data and the fitted lognormal
distribution

Dataset Mean Median Standard Deviation Skewness


Coal Price Data 1.14 1.02 0.38 2.35
Lognormal 1.17 1.14 0.27 0.64

225
1

CDF of coal price


0.8
0.6
Data
0.4
Lognormal
0.2
0
0.5 1 1.5 2 2.5
Coal Price ($/MMBtu)

Figure 8 - 3 Comparison of empirical cumulative distribution function of Central


Appalachian coal price data with the distribution of Lognormal(1.169,
0.273)

8.3. Uncertainty analysis results

In order to analyze uncertainties, a probabilistic modeling environment is required.

In this study, the uncertainty analysis was performed using the IECM computer model,

which employs Monte Carlo simulation for uncertainty analysis. In a Monte Carlo

simulation, a model is run repeatedly, using different values for each of its uncertain

inputs each time. The values of each of the uncertain inputs are generated based on the

probability distribution assigned to uncertain parameters, using Latin Hypercube

sampling.

The following simulation results are based on an IGCC capture plant with two GE

7FA gas turbines, two operation gasifiers and one spare gasifier. Other design parameters

and assumptions are the same as those in Chapter 6.

Figure 8-4 shows the uncertainties associated with the total capital requirement of

the IGCC capture plant. The deterministic total capital requirement in this case is 1714

$/kW. The value of the total capital requirement varies from 1660 to 1790 $/kW, with a

226
90% confidence interval of [1687, 1760] when the uncertainties due to the IGCC process

(parameters given in Table E-1) are taken into account. From this figure, it is clear that

most of the uncertainty in the total capital cost comes from the IGCC process, rather then

the capture process.

0.8
CDF of TCR

0.6 Det.

0.4 Unc. of cap.


process
Unc. of IGCC
0.2
All factors
0
1650 1700 1750 1800
TCR($/kW)

Figure 8 - 4 Cumulative distributions of the total capital requirement of the IGCC


plant (Unc. of cap. process is given by Table E-2; Unc. of IGCC is
given by Table E-1 in Appendix E; All factors take into account the
uncertainties from Table E-1 and E-2)

Then, the effect of uncertainties of capacity factor and coal price on the cost of

electricity is given in Figure 8-5. The deterministic value of COE is 69.9 $/MWh. The

uncertainties associated with the fuel price cause the COE to vary from 65 to 79 $/MWh,

with a 90 percentile range of 67~76 $/MWh. If other parameters are fixed, there is a 63%

possibility that the IGCC plants would have a higher COE than the deterministic estimate

due to the assumed variability of the fuel price. Compared to the uncertainty of fuel

prices, the assumed uncertainty of the capacity factor contributes more to the volatility of

the COE. The capacity factor distribution makes the COE change from 59 to 106 $/MWh,

with a 90 percentile range of 63~94 $/MWh. The combined uncertainty of fuel price and

227
capacity factor causes the COE to change from 58 to 108 $/MWh, with a 90 percentile

range of 62 to 96 $/MWh. In this scenario, the possibility that the COE will be higher

than that of the deterministic result is as high as 65%. In this scenario, the weighted

average COE, which takes into account the value of COE and its probability, is 75.5

$/MWh. The weighted average COE is 5.6 $/MWh higher than the deterministic result.

Because the weighted average COE takes into account the potential operating

uncertainties of an IGCC plant, it maybe a more suitable measure of performance of the

IGCC plant than the deterministic result based on a static situation.

0.8
CDF of COE

0.6 CF
0.4 Fuel
CF&Fuel
0.2
Deterministic
0
55 60 65 70 75 80 85 90 95 100
COE ($/WMh)

Figure 8 - 5 Cumulative distribution of the cost of electricity of the IGCC plant

The distributions of CO2 avoidance costs are given in Figure 8-6. The distribution

of the avoidance cost values are calculated based on the deterministic COE of the IGCC

reference plant, and the probabilistic COE values of the IGCC capture plant. If both the

fuel price and the capacity factor uncertainties are taken into account, the range of CO2

avoidance cost is from 13.4 to 78.6 $/tonne CO2, with a weighted average cost of $36.6

(weighted average 1 in the figure).

228
It is interesting to compared this weighed average costs with two other CO2

avoidance cost measures. One is the deterministic CO2 avoidance cost which is calculated

based on the deterministic COE values of the IGCC reference plant and the IGCC capture

plant. The other measure is a weighted average CO2 avoidance cost (weighted average

cost 2 in the figure) which is calculated based on the weighted average COE of the IGCC

reference plant and the IGCC capture plant. Hence, the difference between the three CO2

avoidance cost is that the deterministic cost is calculated without considering

uncertainties in both the reference plant and the capture plant; the weighted average 1

cost is calculated with considering uncertainties only in the capture plant; and the

weighted average 2 cost is calculated considering uncertainties in both the capture plant

and the reference plant. It is found that the deterministic CO2 avoidance cost has the

lowest value ($29.5/ton), the weighted average 1 cost has the highest cost ($36.6/ton),

and the weighted average 2 cost has an intermediate cost of $30.9/ton. Because the

weighted average 2 cost takes into account the uncertain operating conditions in both the

reference and the capture plant, this value is arguably the most realistic CO2 avoidance

cost. Not considering the uncertainty in the reference plant and the capture plant (or just

considering the uncertainty in one of the two plants) will lead to either higher or lower

estimates of the CO2 avoidance cost.

229
1

CDF of CO2 avoidance cost


0.8
CF
0.6 Fuel
CF&Fuel
0.4
Deterministic
0.2 Weighted average 2
Weighted average 1
0
10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
CO2 avoidance cost ($/tonne CO2)

Figure 8 - 6 Cumulative distribution of the CO2 avoidance cost

The uncertainty and variability in IGCC systems with CO2 capture come from the

limited experience in producing, constructing and operating IGCC power plants with CO2

capture. Most of the uncertainties associated with the capital cost of an IGCC capture

plant come from the IGCC process itself. Assumptions about the fuel price and the

capacity factor (especially the capacity factor) can change the estimated cost of electricity

and the CO2 avoidance cost significantly. Hence, using the most realistic capacity factor

estimates to evaluate the performance of IGCC plants and CO2 capture is especially

important.

230
REFERENCES (CHAPTER 8)

1. Frey C., 1994: Probabilistic Performance, Environmental, and Economic


Evaluation of an Advanced Coal Gasification System, Proceedings of the 87th
Annual Meeting, Cincinnati, OH, June 19-24, 1994

2. International Atomic Energy Agency (IAEA). 1989. Evaluating the Reliability of


Predictions Made Using Environmental Transfer Models. IAEA Safety Series 100.
Vienna, Austria

3. Rubin E.S. and A.B. Rao, 2002: Uncertainties in CO2 capture and sequestration
costs, GHGT-6 paper, 2002

4. Frey H.C. and J.Y. Zheng, 2002: Quantification of variability and uncertainty in air
pollutant emission inventories: method and case study for utility NOx emissions,
Journal of the air & waste management association, Vol. 52, Sep. 2002

5. Cullen A.C., H.C. Frey, 1999: Probabilistic techniques in exposure assessment—a


handbook for dealing with variability and uncertainty in models and inputs, Plenum
Publishing Corporation, 1999

6. Morgan M.G., M. Henrion, M. Small, 1998: Uncertainty—a guide to dealing with


uncertainty in quantitative risk and policy analysis, Cambridge University Press,
1998

7. Marco K., Carlo W., 2004: Fuel Flexibility, the European Gasification Conference,
May 2004

8. McDaniel J.E., Hornick M., 2003: Polk Power Station ICGG 7th year of
commercial operation, Gasification technologies, San Francisco, California

9. Keeler C.G., 2003: Operating Experience at the Wabash River Repowering Project,
Gasification technologies, San Francisco, California

10. Ignacio M.V., 2003: Elcogas Puertollano IGCC Update, Gasification Technologies,
San Francisco, California

11. Yamaguchi M., 2004: First Year Operation Experience with the Negishi IGCC,
Gasification Technologies 2004, Washington DC

12. JGC Corporation, 2003: NPRC Negishi IGCC Startup and Operation, Gasification
Technologies, San Francisco, California

13. Daslay C., BrkicBrkic C., 2003: The Experience of Snamprogetti’s Four
Gasification Projects, Gasification Technologies, San Francisco, California

231
14. Kaptur C.J., 2004: Trends in U.S. Domestic Coal Markets Are Higher Prices and
Higher Price Volatility Here to Stay? Pinecock Perspectives, Issue No.58, Sep,
2004

232
Chapter 9. IGCC SYSTEMS WITH ADVANCED TECHNOLOGIES

While current IGCC power plants show relatively high energy efficiency and low

environmental emissions, there is still much room for improvement in the performance

and cost of IGCC plants. There are substantial R&D programs in the U.S. to improve the

efficiency and cost-effectiveness of IGCC technology. During the next decade or so,

IGCC technology is expected to make significant improvement in the following five

areas [Todd, 2002; O’Brien, 2004]:

• Advanced gasifier concepts with higher efficiency, reliability, and higher

operating pressure for more economic CO2 capture;

• Advanced air separation units with better thermal integration with IGCC systems;

• Syngas cleanup process with less expensive particulate removal systems or hot

gas filtration;

• Advanced gas turbines with high energy efficiency and capacity of burning

syngas and hydrogen-rich fuels;

• Optimal integration with new technologies and components.

In particular, two research areas are likely to produce significant improvements in

the performance and capital cost of the next generation IGCC power plants: advanced air

separation processes and advanced gas turbines. The following sections discuss these

novel technologies and their influence on the development and application of IGCC

technologies in the near future.

233
9.1. Ion Transportation Membrane (ITM)-Based Air Separation Unit

The use of oxygen instead of air for gasification removes excess nitrogen from the

gasifier and results in higher gasification efficiency, higher syngas heat value, lower

capital costs (of gasifiers, heat recovery and downstream gas cleanup systems),

substantially lower NOx emissions, and better potential for CO2 capture. Cryogenic air

separation, pressure swing absorption, and polymeric membranes are common

commercially available technologies for oxygen production. After making numerous

refinements over a long time period, cryogenic air separation has now evolved as the

most efficient way to produce oxygen at large scale, and has become the typical air

separation process for oxygen-blown IGCC.

Current cryogenic air separation units of an IGCC system still account for about

15% of the plant capital cost, and consume about 10% of the gross power output [Stiegel,

2005]. Hence, reducing capital cost and increasing efficiency of ASU are important to

improve economic viability, and to stimulate commercial deployment of IGCC power

plants. However, the overall thermodynamic efficiency of cryogenic ASU is approaching

its theoretical limit. So few significant technical breakthroughs are expected that would

lead to dramatic oxygen cost reduction [Air Products, 2004].

A promising air separation alternative consists of highly selective and active

membranes with high flux and selectivity to oxygen. Oxygen can be recovered at high

temperatures by passing hot air over non-porous, mixed conducting ceramic membranes.

These membranes, known as ion transport membranes (ITM), utilize an oxygen partial

pressure differential across the membrane to cause oxygen ions to migrate through the

membrane [Air Products, 2002].

234
The separation mechanism of this technology is illustrated in Figure 9-1. Oxygen

molecules cling to the membrane surface on the high oxygen partial pressure side. Due to

the catalytic properties of the surfaces of specialized ceramic materials, oxygen atoms are

ionized by electrons. Then the oxygen ions diffuse across membrane due to the oxygen

partial pressure differential across the membrane. Oxygen ions diffused through the

membrane relinquish electrons and reform as oxygen molecules on the other side of the

membrane (low oxygen pressure) [Air Products, 2004].

Figure 9 - 1 Separation mechanism of membrane-based oxygen production


[Mathieu, 2002]

Due to the highly selective property of the membrane, impurities, such as nitrogen,

are rejected by the membrane. The product gas from the ceramic membrane systems is

virtually 100% pure oxygen. In addition, when ITM devices are built in practice, they

have three valuable properties from operating point of view. First, the ITM devices

require no moving parts, which lead to better reliability. Second, the ceramic membranes

are insensitive to supply air contaminants. All the other air separation technologies, such

as cryogenic air separation, suffer form sensitivity to moisture or the minor constituents

235
of air. Third, the deterioration and failure of a ceramic membrane can be readily detected

due to a fall-off in the pressure of the output oxygen pressure [Air Products, 2003].

Poly
Cryo PAS Mem ITM
100

80
Oxygen purity (%)

60

40

20

0
-200 25 40 800

Process temperature

Figure 9 - 2 Process temperature and oxygen purity of different air separation


technologies [Prasas, 2002]

When integrated with IGCC systems, ITM technology has another important

advantage to improve the energy efficiency of IGCC systems over other air separation

technologies. As shown in Figure 9-2, other air separation processes suffer from the lack

of thermal synergy between the low temperature oxygen production and the high

temperature gasifier operation. Oxygen produced from ITM is in the temperature range at

which coal gasifiers operate. Hence, IGCC processes can be developed so as to include a

significantly high level of thermal integration with air separation process. This will

increase the overall process efficiency and reduce the cost of electricity.

Presently, there is a keen competition among several manufacturers to develop the

membrane-based oxygen production technology. It is being developed under different

nametags by different players, such as ITM (Air Products), OTM (Praxair), COGS

236
(Litton Life Support). Currently, it appears that Air Products Inc. is holding a leading

position in this field.

With the support of the U.S. Department of Energy, Air Products has been leading a

R&D program for ITM process since 1998 [Richards, 2001]. The goal of the three-phase

program is to cut the cost of oxygen production by approximately one-third compared to

conventional technologies, and demonstrate all the necessary technical and economic

requirements for commercial scale-up. The research team has successfully addressed all

technical and economic requirements for scale-up ITM technology and demonstrated

over 2,300 hours of performance and stability of thin-film membrane structures in several

experiments [Air Products, 2004]. According to Phase III of this program, a pre-

commercial scale ITM process with approximately 25-50 ton-per-day (TPD) design

capacity will be demonstrated in year 2008. After Phase III, the process may be

introduced into the market at the 100’s-of-TPD scale. The technology is expected to be

ready for use in the large tonnage oxygen market (1000’s-of-TPD) within a decade [Air

Products, 2004].

9.2. GE H-class turbines

Improvement of the power block efficiency of IGCC system can further reduce the

cost of electricity. Hence, the next generation of gas turbines is expected to enhance the

economic competitiveness of IGCC plants. Key features of an advanced gas turbine

technology to improve economical power generation of IGCC plants are [Smith, 2001]:

low installed cost resulting from the capacity of the unit matching with a single large

gasifier; high efficiency which reduces fuel consumption and plant cost by reducing the

capacity of the gasification and cleanup system per unit of generation capacity

237
In 1995, GE introduced its new generation of gas turbines—the GE H System. This

H System technology is the first gas turbine to achieve 60% fuel efficiency (LHV basis).

Compared to the current gas turbines, like GE F-class turbines currently used in IGCC

plants, GE H system is a state-of-the-art turbine system. The H System’s pressure ratio is

23:1 which was selected to optimize the combined-cycle performance. This is a major

change from the GE F-class gas turbines, which used a 15:1 pressure ratio. The firing

temperature of H System is 2600 °F/1430 °C, which is about 200 °F/110 °C higher than

the firing temperature of F class turbines [Matta, 2000].

The unique feature of an H turbine is the integrated heat transfer system, which

combines the steam plant reheat process and gas turbine bucket and nozzle cooling

[Matta, 2000]. This feature allows the turbine to be operated at a higher firing

temperature and pressure ratio, which in turn produces dramatic improvements in fuel-

efficiency. However, higher temperatures in the combustor also increase NOx emission.

Using closed-loop steam cooling, GE H System solved the NOx problem, and is able to

raise firing temperature by 200 °F over the current GE F class of gas turbines and keep

the NOx emission levels at the GE F class levels.

In conventional gas turbines, the stage 1 nozzle is cooled with compressor

discharge air. This cooling process causes a temperature drop across the stage 1 nozzle of

up to 280 °F. In H System gas turbines, cooling the stage 1 nozzle with a closed-loop

steam coolant reduces the temperature drop across that nozzle to less than 80 °F [Matta,

2000]. This results in a firing temperature 200 °F higher, and with no increase in

combustion temperature.

238
An additional benefit of the H System is that the steam cooling the nozzle recovers

heat for use in the steam turbine, transferring the heat was traditionally waste heat into

usable output. The third advantage of closed-loop cooling is that it minimizes extraction

of compressor discharge air, thereby allowing more air to flow to the combustor for fuel

premixing [Matta, 2000].

Table 9-1 compares the performance of H class turbines and the F class turbines.

The technology improvements shown in the GE H turbines are expected to yield

substantial improvements in performance and significant reductions in the capital cost of

IGCC systems [Brdar, 2000].

Table 9 - 1 Performance characteristics of H-class and F-class turbines [Matta,


2000]

Gas turbine type 9FA 9H 7FA 7H


Firing Temperature, °F (°C) 2400 (1316) 2600 (1430) 2400 (1316) 2600 (1430)
Air Flow, lb/sec (kg/sec) 1376 (625) 1510 (685) 953 (433) 1230 (558)
Pressure Ratio 15 23 15 23
NGCC Net Output, MW 391 480 263 400
Net Efficiency, % (LHV basis) 56.7 60 56 60
NOx (ppmvd at 15% O2) 25 25 9 9

9.3. IGCC systems with ITM oxygen production

In this section, a model to simulate the performance and cost of IGCC systems with

ITM process is set up based on a simple ITM operation model.

9.3.1. ITM performance model

The performance of an ITM process can be simulated on the basis of a set of

operating equations [Air Products, 2002]. As shown in Figure 9-3, compressed, hot air at

239
an absolute pressure P, temperature T, and with the composition x feed , passes through an

ITM vessel. Oxygen permeates the membrane at the oxygen low pressure side and is

collected in the permeate stream at almost 100% purity and an absolute pressure, Pperm .

The oxygen-depleted non-permeate stream emerges out of the ITM unit with the

composition, x np , and at an essentially unchanged pressure P. The device operates

isothermally at a temperature T.

Figure 9 - 3 Simplified schematic process of an ITM unit

The oxygen-depleted non-permeate gas stream composition ( x np ) can be calculated

from an overall mass balance on the ITM unit. The overall recovery (R) is defined as the

available fraction of oxygen recovered from the feed stream, which is shown as the

following equation,

Fperm
R= (9-1)
x feed ⋅ F

where R= the overall recovery of the ITM unit

F perm = the molar flow rate of permeated oxygen (mole/hr)

F = the molar flow rate of air fed into the ITM unit (mole/hr)

240
x feed = the molar concentration of oxygen in the air

Theoretically, the overall recovery is ultimately limited by the driving force for

oxygen flux. The driving force is due to the partial pressure difference of oxygen on both

sides of the membrane. As the feed gas passes across the ITM device, the partial pressure

of oxygen decreases since the gas is depleted of oxygen. The theoretical overall recovery

is achieved when the oxygen partial pressure in the air falls as low as that in the permeate

stream. The theoretical overall recovery can be calculated as,

(1 − x feed )Pperm
RT = 1− (9-2)
x feed (P − Pperm )

where RT = the theoretical overall recovery of the ITM unit

Pperm = the pressure of the permeated oxygen stream (psia)

P = the pressure of the air stream fed into the ITM unit (psia)

x feed = the molar concentration of oxygen in the air feed

Consistent with many industrial separation processes, from an economical point of

view, a commercial ITM separation process is best operated at 25% -85% of theoretical

recovery. Hence, the practical overall recovery of an ITM unit is,

R = η⋅ RT (9-3)

where R = the practical overall recovery of an ITM unit

η = percentage of the theoretical recovery

241
According to experimental data from the Air Products, a useful heuristic for

calculating the separation performance of ITM is that the oxygen partial pressures in the

permeate and in the feed streams are related as,

PO 2 ≅ 7 Pperm (9-4)

where PO2 = the partial pressure of oxygen in the air at the inlet of the ITM unit

Pperm = the partial pressure of oxygen in the permeate side

According to the mass balance, the molar concentration of oxygen in the non-

permeate gas stream is given by,

x feed ⋅ F − Fperm
x O 2 ,np = (9-5)
F − Fperm

Substituting Eq. 9-1 into the above equation, the molar concentration of oxygen in

the non-permeate gas stream depending on recovery is given by,

x feed (1 − R )
x O 2 ,np = (9-6)
(1 − R ⋅ x feed )

Air Products has recommended the operating conditions of ITM units which are

summarized in Table 9-2.

Table 9 - 2 Recommended operating parameters for ITM oxygen process design


[Air Product, 2002]

Recommended operating parameters for ITM design Low High


T (°C) 800 900
Feed pressure, P (psia) 100 1000

242
Permeate pressure, Pperm (psia) 1.9 100
Feed O2 fraction 0.1 0.21
Percentage of theoretical recovery 25% 85%

As a new technology in the developing stage, there is no practical data available to

build up its capital cost model. Air products estimated that ITM would be 32% cheaper

than the conventional cryogenic technology [Air Products, 2004]. Hence the capital cost

of an ITM unit is estimated as 68% of the capital cost of a cryogenic ASU with the same

capacity.

9.3.2. IGCC designs with ITM air separation

Figure 9-4 represents a schematic of an IGCC system integrated with the ITM

oxygen production. In this design, the oxygen production process is fully integrated with

the gas turbine [Air Products, 2003]. Compressed air extracted from the gas turbine

compressor is heated by the oxygen-depleted non-permeated air from the ITM unit. Then

the compressed air is further heated by burning a portion of clean syngas to reach the

operating temperature of the ITM unit. The ITM unit is exothermically operated at an

essentially unchanged pressure. The oxygen stream from the ITM unit at a low pressure

and a high temperature is cooled down to produce steam for steam cycle, and then

compressed to a pressure suitable for gasifier operation. The heat from the hot oxygen-

depleted non-permeate air is used to pre-heat the inlet air of the ITM unit. The cooled

oxygen-depleted non-permeate air is then fed into the gas turbine combustor.

Figure 9-5 shows a revised design of IGCC system with ITM oxygen production. In

this design, the air fed into the ITM unit comes from a standalone compressor. This

243
design requires one more air compressor, but offers more flexible operation options. The

two designs are implemented in Aspen simulation model, and the design parameters of

the two cases are given in Table 9-3.

Table 9-3 gives the ITM operating conditions of two IGCC systems with the ITM

process. These two cases are used to investigate the influence of ITM on the performance

and cost of IGCC systems. Other technical and economic assumptions for these case

studies are the same as those given in Table 6-1 and 6-2.

Table 9 - 3 Design parameters of ITM units in the Aspen simulation models

ITM operating ITM air feed ITM percentage of


Case number Notes
temperature (F) pressure (psia) theoretical recovery
ITM-A 1500 250 80% Integrated with GT
ITM-B 1500 200 80% Standalone ITM

244
Ste a m

Hot O2-depleted air Cold O2-depleted air


Compressed air
Hot air
Wa ter Heat exchanger
Clean syngas

Cooler ITM Burner

Air
O2 compressor
GT
com pressor

Coal slurry Raw sy ngas LT sy ngas Acid gas


Gasification LTGC P ower
rem oval
GT
GT burner
Slag slurry Black water Ac id ga s
Exha ust

Exhua st to sta c k
Recy cle water Bla c k wate r Sulfur r ec ove r y
Slag treatment Ste a m c y c le
tr e atm e nt Ta il ga s tr e atm e nt Wa ter
Condensated water

Slag Water Sulfur

Figure 9 - 4 Overview of an IGCC system fully integrating with the ITM oxygen production

245
Ste a m

Heat exchanger
Hot O2-depleted air Cold O2-depleted air
Compressed air
Heated air
Wa ter
Cold O2 Hot Air Clean sy ngas Air
Hot O2
Cooler ITM Burner I TM c om pre ssor

Air
O2 compressor
GT
com pressor

Coal slurry Raw syngas LT sy ngas Acid gas


Gasification LTGC P ower
rem oval
GT
GT burner
Slag slurry Black water Ac id ga s
Exha ust

Exhua st to sta c k
Recy cle water Bla c k wate r Sulfur r ec ove r y
Slag treatment Ste a m c y c le
tr e atm e nt Wa ter
Ta il ga s tr e atm e nt
Condensated water

Slag Water Sulfur

Figure 9 - 5 Overview of an IGCC system with standalone ITM oxygen production

246
Table 9-4 shows the performance and cost of the two ITM cases and the

corresponding cryogenic ASU case. Comparing to the cryogenic ASU case, ITM cases

show significant improvement on the performance and cost of IGCC systems. For

example, the net efficiency of the IGCC plants with ITM increases approximately 2%

percentage points, an improvement of about 5.7% over the cryogenic case. The net power

output increases by 37 MW. The total capital requirement per kW reduces from $1311 to

$1240, and the cost of electricity also reduces by about 2.6 $/MWh. Corresponding to the

improvement of the net efficiency due to the ITM technology, the CO2 emission also

reduces by 5.5%.

Table 9 - 4 Performance and cost comparison of IGCC reference plants with ITM

Effic- Net ASU CO2 O2 ITM


TCR TCR COE
Case iency power TCR emission flowrate TCR
(M$) ($/kW) ($/MWh)
(HHV) (MWe) (M$) (kg/kWh) (TPD) (k$/TPD)
ITM-A 39.3 574.2 59.7 712.3 1240 45.71 0.78 3623.8 16.5
ITM-B 39.4 575.8 59.9 716.9 1245 45.84 0.78 3644.0 16.4
Cryo. 37.1 537.9 89.3 705.7 1311 48.40 0.83 3650.2 24.5

Next, the WGS reactor and Selexol process for CO2 capture are incorporated into

the Case ITM-B to study the effect of adopting ITM technology on the performance and

cost of the capture plant. Table 9-5 shows the performance improvement of IGCC power

plant with CO2 due to the ITM technology.

247
Table 9 - 5 Performance and cost comparison of IGCC capture plant with ITM

ITM Cryo. % Change


Net efficiency 33.6 32.0 5.2
Net power output (MW) 538.1 502.2 7.1
Plant TCR ($/kW) 1631 1714 -4.8
COE ($/MWh) 66.38 69.91 -5.0
CO2 emission (kg/kWh) 0.092 0.096 -4.8

9.4. IGCC systems using GE H turbine

Different from GE F gas turbine, GE H gas turbine uses a closed steam cooling

system, which requires a different gas turbine cooling and heat recovery system. Figure

9-6 shows an overview of the power block of an IGCC system using GE H turbine, which

is a three-pressure, reheat steam cycle and its integration with the gas turbine cooling

system. Gas turbine cooling steam is extracted from the high pressure steam turbine

exhaust to the closed circuit system that is used to cool the gas turbine stage 1 and 2

nozzles and buckets. The steam in the cooling circuit system is heated to approximately

the reheat temperature of the steam cycle, and returns to the immediate pressure steam

turbine.

A syngas heating system utilizes low grade energy from the HRSG to improve

combined-cycle thermal efficiency. Water extracted from the discharge of the HRSG IP

economizer is supplied to the syngas heater to pre-heat and saturate the syngas before it is

supplied to the combustion system. The water leaving the fuel heater is returned to the

cycle through the condensate receiver to the condenser.

248
Figure 9 - 6 Combined power block cycle with GE H turbine [Matta, 2000]

Due to the higher exhaust temperature from GE H turbine, the steam cycle can use

higher pressure and temperature to achieve better energy efficiency. The parameters of

this three-pressure, reheat steam cycle used in the simulation model are given in the

following table. The other general technical and economic parameters these case studies

are the same as those given in Table 6-1 and 6-2.

Table 9 - 6 Steam cycle parameters of the IGCC using GE H turbine

Parameter HP throttle Hot reheat LP admission


Pressure (psig/Bar) 2400/165 345/23.8 31/2.2
Temperature (°F/°C) 1050/565 1050/565 530/277

The capital cost of the H turbine is estimated with the gas turbine cost model

developed in Chapter 3, which is a function of the net power output the gas turbine.

Simulation results show that GE H gas turbines can greatly improve the performance of

IGCC power plants. As shown in Table 9-7, comparing to an IGCC with GE F turbine,

249
the utilization of GE H turbine can increase the net efficiency of IGCC systems by more

than 4 percentage points, reduce the capital cost per kilowatt by more than 4%, lower the

cost of electricity by more than 7%, and reduce the CO2 emission rate by about 10%. The

effects of the utilization of GE H turbine on the performance of CO2 capture plant are

given in Table 9-8.

Table 9 - 7 Performance and cost comparison of IGCC reference plants using


different gas turbines

Parameter H turbine F turbine % Change


Net efficiency 41.4 37.1 11.4
Net power (MW) 860.3 537.9 59.9
TCR ($/kW) 1256 1311 -4.2
COE ($/MWh) 44.82 48.40 -7.4
CO2 emission (kg/kWh) 0.74 0.83 -10.4

Table 9 - 8 Performance and cost comparison of IGCC capture plants using


different gas turbines

Parameter H turbine F turbine % Change


Net efficiency 36.2 32 13.1
Net power (MW) 814.6 502.2 62.2
TCR ($/kW) 1573 1714 -8.2
COE ($/MWh) 62.51 69.91 -10.6
CO2 emission (kg/kWh) 0.085 0.096 -11.7

9.5. IGCC system with ITM and H turbine

IGCC systems adopting ITM oxygen production and GE 7H turbine with and

without CO2 capture are also modeled and simulated. Table 9-9 presents the performance

of an IGCC employing both ITM and GE 7H gas turbine. This next generation IGCC

system with advanced technology expected to be available in the next decade, can

250
achieve a thermal efficiency as high as 42.3% on a higher heating value basis. The total

capital requirement of the IGCC plant with advanced technologies lowers to 1184 $/kW,

which is comparable to or lower than the capital cost of current PC power plants. Due to

the lower capital cost and higher energy efficiency, the cost of electricity of the next

generation IGCC power plant also is estimated to be slightly lower than that of the

current supercritical PC plants.

Table 9 - 9 Performance and cost improvement of the IGCC reference plant using
ITM and GE 7H turbine

Parameter ITM-H turbine Cryo-F turbine % Change


Net efficiency (%, HHV) 42.3 37.1 13.9
Net power (MW) 929.5 537.9 72.8
TCR ($/kW) 1184 1311 -9.7
COE ($/MWh) 42.30 48.40 -12.6
CO2 emission (kg/kWh) 0.73 0.83 -12.3

From Table 9-10, it is noticed that the energy efficiency of the next generation

IGCC system with CO2 capture is approximately 38.2%, which is higher than that of

current IGCC systems without CO2 capture. The total capital cost of the next generation

IGCC systems with CO2 capture is 1470 $/kW, which is only about 10% higher than that

of the current IGCC systems without CO2 capture.

The preliminary performance and cost analysis of IGCC systems with emerging

advanced technologies for oxygen production and gas turbine power generation are

expected to greatly improve the performance of IGCC systems. Simulation results show

that these new technologies will almost offset the influence of CO2 capture on the

performance and cost of current IGCC plants.

251
Table 9 - 10 Performance and cost improvement of the IGCC capture plant using
ITM and GE 7H turbine

Parameter ITM-H turbine Cryo-F turbine % Change


Net efficiency (HHV) 38.2 32.0 19.5
Net power (MW) 902.9 502.2 79.8
TCR ($/kW) 1471 1714 -14.2
COE ($/MWh) 58.6 69.9 -16.2
CO2 emission (kg/kWh) 0.081 0.096 -15.6

As with all cases involving advanced technologies, full-scale demonstrations and

commercialization are needed to verify the performance and cost assumptions employed

in this analysis. For example, while the H-class gas turbine is already offered

commercially, its design performance and cost when fired with syngas or hydrogen-rich

fuel gas (rather than natural gas) remain to be demonstrated and determined reliably.

Similarly, the scale-up and application of the ITM process to an IGCC also remains to be

demonstrated. Hence, the uncertainty characteristics discussed earlier in Chapter 8 apply

equally well to the advanced technologies discussed here.

252
REFERENCES (CHAPTER 9)

1. Air Products, 2002: Method for Predicting Performance of an Ion Transport


Membrane Unit-Operation, Advanced Gas Separation Technology, Allentown,
Pennsylvania

2. Air Products, 2003: The Development of ITM Oxygen Technology for Integration
in IGCC and Other Advanced Power Generation Systems

3. Air Products, 2004: ITM Oxygen for Gasification presented at: Gasification
Technologies 2004 Washington, D.C. 3-6 October 2004

4. Brdar R.D. and Jones R.M., 2000, GE IGCC Technology and Experience with
Advanced Gas Turbines, GER-4207

5. Matta R.K., Mercer G.D., and Tuthill R.S., 2000: Power Systems for the 21st
Century –“H” Gas Turbine Combined-Cycles, GER-3935B

6. Mathieu P., 2002: Private communication

7. O’Brien J.N., Blau J., Rose M., 2004: An Analysis of the Institutional Challenges
to Commercialization and Deployment of IGCC Technology in the U.S. Electric
Industry: Recommended Policy, Regulatory, Executive and Legislative Initiatives,
Final Report prepared for U.S. Department of Energy, National Energy Technology
Laboratory, Gasification Technologies Program and National Association of
Regulatory Utility Commissioners

8. Prasas R., Chen, J., Hassel, B., San, 2002: OTM-an advanced oxygen technology
for IGCC, Francisco, Oct 30, 2002, Gasification conference

9. Richards, R.E., 2001, Development of ITM Oxygen Technology for Integration in


IGCC & Other Advanced Power Generation Systems (ITM Oxygen), Technical
Progress Report for the period January – March 2001 for DOE

10. Stiegel, G.J., 2005: Overview of Gasification Technologies Global Climate and
Energy Project, Advanced Coal Workshop, March 15, 2005

11. Smith R.W., Polukort P., Maslak C.E., Jones C.M., and Gardiner B.D., 2001:
Advanced Technology Combined Cycles, GER-3936A

12. Todd D.M., 2002, The Future of IGCC, Gasification 5, Noordwijk, The
Netherlands

253
Chapter 10. CONCLUSION

The main objective of this research has been to perform a technical and economic

assessment of IGCC systems with and without CO2 capture. This chapter summarizes the

key points presented in this thesis.

10.1. Model development

Detailed engineering models of IGCC systems with oxygen-blown Texaco quench

gasifiers were developed in the Aspen Plus simulation software environment. A previous

cost model of this IGCC system developed at Carnegie Mellon was updated with more

recent data and coupled to the system performance model. To simulate CO2 capture,

performance models of the water gas shift (WGS) reaction system and the Selexol-based

CO2 capture process were derived using detailed chemical simulations, theoretical

analysis, and regression analysis. The cost models of the WGS reaction system and the

Selexol process for CO2 capture were coupled to (dependent upon) the input and output

parameters of the corresponding performance models. The CO2 capture system was

incorporated into the IGCC model in Aspen Plus with re-design of heat integration of the

whole plant. Since the cost models of IGCC systems with and without CO2 capture were

also linked with the plant performance model, all economic assessments reflected plant

design assumptions as well as economic and financial parameters.

The IGCC plant and the Selexol-based CO2 capture process models were also

implemented (in reduced form) in a general power generation modeling framework—

IECM. The probabilistic capability of the IECM was then applied to models of IGCC

systems with and without CO2 capture in IECM. Therefore, risk and uncertainty analyses,

which are important aspects of technical assessment and policy analysis, could be

254
performed. Thus, these models (performance and cost models in Aspen Plus and IECM)

provide an analytic environment and tools for technical and economic assessment of

gasification—based energy conversion systems with various CO2 capture options on a

systematic and consistent basis.

10.2. Model applications

As a developing technology, IGCC systems have shown advantages over traditional

combustion-based energy conversion technologies in terms of energy efficiency,

environmental emissions, and greenhouse gas control. First, the models developed in this

thesis were used to investigate the factors influencing the technical and economic

performance of greenfield IGCC systems with various CO2 capture options. Then the

technical feasibility and economic cost of repowering old PC power plants by IGCC

technology were investigated. The uncertainties associated with IGCC systems and with

the CO2 capture process were also studied. Finally, the models were extended to include

some emerging novel technologies, and used to assess the potential performance and

economic improvement of advanced IGCC systems in the near future.

10.2.1. Greenfield IGCC plants

Through case studies of an IGCC plant using an oxygen-blown Texaco quench

gasifier, the effect of factors including CO2 capture efficiency, coal type, plant size, and

capital structure were studied. Four coals, representing bituminous, sub-bituminous, and

lignite coals, were used to investigate the effects of coal quality on the performance and

cost of IGCC systems with and without CO2 capture. Although the Texaco gasifier

modeled in this study is able to gasify all coals regardless of coal rank, caking

characteristics, or amount of coal fines, the coal rank was found to significantly influence

255
the gasification efficiency, the thermal efficiency and capital cost of an IGCC power

plant. The water slurry feeding mechanism used in this plant design resulted in high (non-

optimal) total water input when utilizing low rank coal, like lignite. The relatively high

feed rates of coal and high oxygen requirements to maintain gasifier temperatures

resulted in increased capital cost and auxiliary power consumption relative to the nominal

plant design using bituminous coal.

The effect of different CO2 capture efficiencies on the power consumption, thermal

efficiency, capital cost, cost of electricity, and CO2 avoidance cost were studied. It was

found that the avoidance cost reaches the lowest point when the total CO2 removal

efficiency is in the range of 85%-90%. This indicates that the optimal CO2 capture

efficiency is also in this range.

Generally, the size of a plant will influence its performance and cost because a

relatively large plant will benefit from an economy of scale and higher efficiency. Three

IGCC systems with one, two, and three GE 7FA gas turbines, respectively, were studied

to show the influence of plant size on IGCC systems and CO2 capture. The plant size has

notable influence on the total capital requirement. The capital requirement of the biggest

plant is about 280 $/kW less than that of the smallest one. Thermal efficiency also

improves slightly with an increase of the plant size. The efficiency of the biggest plant is

about 0.5 percentage points higher than that of the smallest one. The CO2 avoidance cost

decreases slightly with an increase of the plant size. The avoidance cost of the biggest

plant is approximately $2/tonne lower than that of the smallest one.

256
One of the major issues hindering the application of IGCC is difficulty with plant

financing, since IGCC is perceived to be a riskier technology for power generation than

conventional combustion-based systems. Six different capital structures were studied to

investigate the influence of capital structures on the economic competitiveness of IGCC

power plants. Simulation results showed that the total capital requirement of the IGCC

plant reduces with an increase of the debt-to-equity ratio. Further study showed that

without an incentive financing approach, the IGCC power plant without CO2 capture is

less competitive than PC and NGCC power plants in terms of both the total capital

requirement and the cost of electricity (COE). An incentive financing policy for IGCC

power plants, like the 3-Party Covenant analyzed in this thesis, can improve the

competitive ability of IGCC power plants and accelerate their commercialization. Due to

the advantages of IGCC for CO2 capture, additional analysis showed that if CO2 capture

is required for power generation processes, IGCC plants without an incentive capital

structure would be competitive with PC and NGCC plants.

10.2.2. IGCC Repowering

In this thesis, two simulation models were set up in Aspen Plus to evaluate the

repowering cases. One model simulated the most restrictive condition, replacing the

existing boiler with a gasifier, a gas turbine and HRSG, and no modification to the steam

turbine and the feedwater system. Another model simulated the most favorable condition,

in which the steam turbine had sufficient design margins so that it could be incorporated

into a three-pressure reheat cycle with no feedwater heating. The two models were further

revised to incorporate the CO2 capture function. Simulation results showed that IGCC

repowering is less capital intensive and has a shorter construction period, but the

257
feasibility of repowering is very site specific. Under suitable conditions, IGCC

repowering with or without CO2 capture may be an economically attractive option for

existing steam power units. Repowering also provides an option for introducing new

power generation technology with lower risk to utilities.

10.2.3. Uncertainty analysis of IGCC systems

The uncertainty and variability in IGCC systems with CO2 capture come from the

limited experience in producing, constructing and operating IGCC plants with CO2

capture. This study investigated the influence of uncertainties and variability associated

with plants and process designs on the capital cost, cost of electricity and CO2 avoided

avoidance. After preliminary screening, this thesis focused on investigating the

uncertainties of two key parameters, capacity factor and fuel price. Considering the effect

of uncertainties of capacity factor and coal price, there was a significant possibility that

the COE of an IGCC capture plant could be higher than that of the deterministic

estimates found in many recent studies.

10.2.4. IGCC with advanced technologies

There are substantial R&D programs in the U.S. to improve the efficiency and cost

effectiveness of IGCC technology. This thesis studied the effects on performance and

cost of IGCC systems for two emerging advanced technologies—the ion transport

membrane (ITM) for oxygen production and the GE H-class gas turbine for power

generation.

The net efficiency of an IGCC system using ITM increased approximately 2

percentage points, while the total capital requirement of the IGCC plant fell from $1311

258
to $1240. It was also found that GE H-class gas turbines could significantly improve the

performance of IGCC power plants. Compared to IGCC plants using GE F-class turbines,

the utilization of GE H turbines can increase the net efficiency by more than 4 percentage

points, reduce the capital cost per kilowatt by more than 4%, and reduce the cost of

electricity by more than 7%.

This preliminary analysis found that an IGCC plant employing both ITM and GE

7H gas turbines could achieve a thermal efficiency as high as 42.3% on a higher heating

value basis, and that the total capital requirement and the cost of electricity of such an

IGCC plant would be slightly lower than those of current PC power plants. It was also

predicted that the energy efficiency of such an IGCC system with CO2 capture is

approximately 38.2%, which is higher than that of current IGCC systems without CO2

capture. The total capital cost of the next generation IGCC systems with CO2 capture

would be about 1470 $/kW, which would be able to compete with current IGCC systems

without CO2 capture.

10.3. Some considerations about future work

This work may be furthered in several directions. First, the IGCC plant models

could be developed with greater consideration of optimal system design, especially when

the CO2 capture process is incorporated into IGCC plants. Studies of the optimal heat

recovery scheme, the optimal operation pressure and temperature of the gasifier and

HRSG, the optimal integration of oxygen production and the gas turbine system all would

provide a better understanding of the potential advantages of IGCC systems with CO2

capture.

259
Second, the models for the water gas shift reaction system and Selexol-based CO2

capture process could be refined with the availability of additional data. Another

direction of future work might be extending the CO2 capture process with different

commercial solvents, such as Rectisol and Ucarsol.

The IGCC models also could be extended by incorporating more technology

options. For instance, the models of IGCC systems with different gasifier types, such as

the Shell gasifier and E-Gas system. Different syngas cleanup processes, such as high

temperature cleanup processes, advanced CO2 capture systems, and options for combined

capture and sequestration of CO2 and H2S could be studied to provide a more

comprehensive set of options for technical and economic assessment of CO2 capture from

IGCC systems.

Finally, additional analyses of uncertainties and their effect on performance and

cost estimates could be carried out, especially for many of the advanced technologies

currently under development.

260
APPENDIX A. CO CONVERSION EFFICIENCY OF THE WGS
REACTION

Recall the WGS reaction equation given by:

CO + H 2 O ⇔ CO2 + H 2

Using the definition of the chemical equilibrium constant, the chemical equilibrium

constant (K) for the water gas shift reaction can be given by,

[CO 2 ][H 2 ]
K= (A-1)
[CO][H 2 O]

where [i] = the molar concentration of species i at the equilibrium state.

Substituting Eq. 4-3, 4-4, 4-5, and 4-6 into Eq. A-1, then the equilibrium constant in

the high temperature reactor (Kh) can be expressed as,

([CO2 ]0 + ξ h [CO]0 )([ H 2 ]0 + ξ h [CO]0 )


Kh = (A-2)
([CO]0 − ξ h [CO]0 )([ H 2 O]0 − ξ h [CO]0 )

Treating the CO conversion in the high temperature reactor ( ξ h ) as an unknown

parameter, noting that the above equation is parabolic in ξ h , and then solving Eq. A-2, the

CO conversion at the high temperature reactor can be obtained and given by:

u 1 − u 12 − 4 w 1 v1
ξh = (A-3)
2w 1

where,

u1 = K h ([CO ]0 + [ H 2 O ]0 ) + ([CO2 ]0 + [ H 2 ]0 )

261
v1 = K h ([CO]0 [ H 2 O]0 ) − ([CO2 ]0 [ H 2 ]0 )

w1 = K h − 1 (A-4)

In a similar way, the total CO conversion ( ξ total ) in the two reactors is given by

u 2 − u 22 − 4 w2 v 2
ξ tot = (A-5)
2 w2

where,

u 2 = K l ([CO]0 + [ H 2 O]0 ) + ([CO2 ]0 + [ H 2 ]0 )

v 2 = K l ([CO] 0 [ H 2 O] 0 ) − ([CO 2 ] 0 [ H 2 ] 0 ) (A-6)

w2 = K l − 1

Furthermore, the equilibrium constants in the high temperature and low temperature

reactors can be calculated as a function of temperature as follows (Davis, 1980):

8240
K h = exp( − 4.33) (A-7)
Th + dTh + 459.67

8240
K l = exp( − 4.33) (A-8)
Tl + dTl + 459.67

Where K h and K l are the equilibrium constants of shift reaction in the high and

low temperature reactors with taking into account of the approach temperatures; dTh and

dTl are the Aspen approach temperatures (F) for the high and low temperature reactors,

262
respectively. Th and Tl are the reaction equilibrium temperatures (F), which are the final

temperatures when the WGS reaction reaches equilibrium states, at the high and low

temperature reactors, respectively. The two temperatures, Th and Tl , can be calculated

using the following regression equations based on ASPEN Plus simulations,

Th = 0 . 0122 P0 + 0 .8668 T0 + 3297 . 049 [ CO 2 ] 0 − 21 .634 [ H 2 O ] 0 +


356 .234 [ H 2 ] 0 + 401 . 392 [ N 2 ] 0 + 2290 .608 [ CO ] 0 [ H 2 O ] 0

(R2=0.99) (A-9)

Tl = − 0 .00136 P0 + 0 .1031 T0 + 16608 .87 [ CO 2 ] 0 + 404 . 098 [ H 2 O ] 0


+ 331 .976 [ H 2 ] 0 + 258 .772 [ N 2 ] 0 − 1198 .036 [ CO ] 0 [ H 2 O ] 0 −
2105 .116 [ CO 2 ] 0 [ H 2 ] 0

(R2=0.99) (A-10)

Here T0 and P0 are the temperature (F) and pressure (psia) of the syngas fed into the

high temperature reactor. [i] 0 is the molar fraction of syngas composition i before fed into

the high temperature reactor.

According to the definition of CO conversion, the CO conversion in the low

temperature reactor is calculated from the CO conversion in the high temperature ( ξ h )

and the total CO conversion ( ξ tot ) as in the following equation.

1 − ξ total
ξl = 1 − (A-11)
1 − ξh

263
APPENDIX B. METHODOLOGY FOR CALCULATING THE CATALYST
VOLUME OF THE WGS REACTION

The volumes of catalyst, either clean shift catalysts or sour tolerance shift catalysts,

can be calculated as in the following steps.

The catalyst volume (Vcat, ft3 ) can be given by,

VF
Vcat . = (B-1)
SV

where SV is the space velocity (1/hr) ; VF is the volumetric flow rate of syngas

(ft3/hr).

For a well mixed, constant volume batch reactor, the space velocity is related to the

fraction conversion of reactant (x) and the reaction rate (r) by the following equation

(Polyanin, 2002):

x
dx
SV −1 = ∫ (B-2)
0
r

where x is the fraction conversion of CO to CO2.

The reaction rate of the WGS reaction can be given by (Doctor, 1994),

⎡ ([CO2 ]0 + x)([ H 2 ]0 + x) ⎤
r = k ⎢([CO ]0 − x)([ H 2 O]0 − x) − ⎥ (B-3)
⎣ K ⎦

where k is the reaction rate constant of the water gas shift reaction; [CO]0, [H2O]0,

[CO2]0, [H2]0 are the inlet molar concentration of CO, H2O, CO2 and H2, respectively; K

is the equilibrium constant of the water gas shift reaction at the equilibrium temperature.

264
Equation (B-3) can be substituted into Equation (B-2) to produce the following

equation,

k 2 K ⎧⎪ 2wx − u − q − u − q ⎫⎪
= ⎨ln[ ] − ln[ ]⎬
SV q ⎪⎩ 2wx − u + q − u + q ⎪⎭
(B-4)

where: w = K - 1

q = u 2 − 4 wv

u = K ([CO]0 + [ H 2 O]0 ) + ([CO2 ]0 + [ H 2 ]0 ) (B-5)

v = K ([CO]0 [ H 2 O]0 ) − ([CO2 ]0 [ H 2 ]0 )

Using the above equations, the volume of high temperature catalyst ( Vcat ,h ) is given

by:

VFh
Vcat .,h = (B-6)
SVh

where

kh K h ,real ⎧⎪ 2w 1 x 1 − u 1 − q 1 − u − q 1 ⎫⎪
= ⎨ln[ ] − ln[ 1 ]⎬ (B-7)
SVh q1 ⎪⎩ 2w 1 x 1 − u 1 + q 1 − u 1 + q 1 ⎪⎭

2
q 1 = u 1 − 4 w 1 v1

u1 = K h ,real ([CO ] 0 + [ H 2 O ]0 ) + ([CO 2 ]0 + [ H 2 ] 0 )

265
v1 = K h ,real ([CO ]0 [ H 2 O ] 0 ) − ([CO 2 ] 0 [ H 2 ]0 )

w1 = K h , real − 1 (B-8)

Recalling the equilibrium constant of the water gas shift reaction in Eq. (A-7), then

the equilibrium constant K h ,real calculated based on the equilibrium reaction temperature

in the high temperature reactor can be given by,

8240
K h , real = exp( − 4.33) (B-9)
Th + 459.67

In a similar way, the volume of the low temperature catalyst ( Vcat ,l ) is given by,

VFl
Vcat .,l = (B-10)
SVl

where

kl K l ,real ⎧⎪ 2w2 x 2 − u 2 − q 2 − u 2 − q 2 ⎫⎪
= ⎨ ln[ − ln[ ]⎬
SVl q2 ⎪⎩ 2w2 x 2 − u 2 + q 2 − u 2 + q 2 ⎪⎭

2
q2 = u 2 − 4w2 v2

u 2 = K l , real ([CO ]0 + [ H 2 O ]0 − 2 x1 ) + ([CO 2 ]0 + [ H 2 ]0 + 2 x1 )

v 2 = K l , real [([CO ] 0 − x1 )([ H 2 O ]0 − x1 )] − [([CO 2 ]0 + x1 )([ H 2 ]0 + x 2 )] (B-11)

w2 = K l , real − 1 (B-12)

266
Here, and the equilibrium constant K l , real is calculated based on the equilibrium

reaction temperature in the low temperature reactor as:

8240
K l , real = exp( − 4.33) (B-13)
Tl + 459.67

For the iron-based catalyst, the reaction rate constant (k) is given by [Doctor, 1994],

k 3830
log( ) = 6.947 − (B-14)
Ap 0.85Th + 0.15T0 + 459.67

where Th is the equilibrium temperature in the high temperature reactor (F); T0 is

the syngas temperature at the inlet of the high temperature reactor (F).

For the copper-based catalyst, the reaction rate constant (k) is given by [Campbell,

1970]:

k 3062
log( ) = 6.91 − (B-15)
Ap 0.85 ⋅ Tl + 0.15 ⋅ Tl ,i + 459.67

where Tl is the equilibrium temperature in the low temperature reactor (F); Tli is

the syngas temperature at the inlet of the low temperature reactor (F).

Here Ap is pressure-dependent activity factors, which can be given by [Doctor

1994],

P ≤ 400 psig , A p = 4 ⋅ 10 −8 P 3 + 10 −5 P 2 + 0.0092P + 0.9984

P f 400 psig , A p = 4 (B-16)

267
For a cobalt-based catalyst, the catalyst reaction rate constant is given by the

following equation, which is regressed using the published data [Park, 2000]:

10 7 95702
R ln k = 119.75 + 2 − (R2=0.996) (B-17)
T T

where R is the gas constant; T is the reaction temperature in the reactor.

268
REFERENCES (APPENDIX B)

1. Campbell, J. S., “Influences of Catalyst Formulation and Poisoning on the


Activity and Die-Off of Low Temperature Shift Catalysts”, Ind. Eng. Chem. Proc.
Des. Dev., 9(4), 1970, pp. 588-595.

2. A. D. Polyanin, A. M. Kutepov, et al., Hydrodynamics, Mass and Heat Transfer in


Chemical Engineering, Taylor & Francis, London, 2002.

3. Doctor R.D., Molburg, J.C. Thimmapuram, P., Berry, G.F., and Livengood, D.C.
“Gasification Combined Cycle: Carbon Dioxide Recovery, Transport Disposal,”
ANL/ESD-24, Argonne National Laboratory (Sept. 1994)

4. Park J.N., Kim, J. H., Lee, H. I., A study on the Sulfur-Resistant Catalysts for
Water Gas Shift Reaction IV. Modification of CoMo/-Al2O3 Catalyst with K,
Korean Chem. Soc. Vol.21, No.12 1239, (Oct. 2000)

269
APPENDIX C. CALCULATION PROCESS OF THE WGS REACTION
SYSTEM

This section illustrates the calculation process of the performance and cost model of

the WGS reaction system discussed in Chapter 4 through a case study. The input

parameters are as follows.

Table C - 1 Input parameters of the WGS model

Syngas to high temperature shift Molar Flow rate Volume


reactor concentration (lb-mol/hr) (cft/hr)
H2S 0.000 0.029 0.468
CH4 0.033 9.849 160.594
Ar 0.343 101.302 1656.494
COS 0.000 0.001 0.016
NH3 0.000 0.043 0.699
N2 0.429 126.627 2070.685
CO 19.841 5852.992 95708.543
H2O 60.179 17752.435 255451.049
CO2 4.197 1238.133 20003.158
H2 14.976 4417.884 71715.234
total 100.000 29499.294 446766.941
total flow rate (lb-mol/hr) 29499.295
Temperature(F) 450
Pressure(psia) 610

The first step is to calculate the CO conversion efficiency in the high and low

temperature reactor, which are given in Table C-2, and C-3.

270
Table C - 2 Calculation of the CO conversion efficiency in the high temperature
reactor

High temperature reactor Value Equations used


Equilibrium temperature at HT
reactor (F) 851.454 (A-9)
Equilibrium constant at HT reactor
temperature 7.062 (A-7)
Equilibrium constant at HT reactor
temperature taking into account
approach temperature 6.278 (B-9)

Middle variable u1 5.278


Middle variable v1 -5.216
Middle variable w1 0.743 (A-4)

CO conversion efficiency in HT
reactor 0.870 (A-3)
CO molar concentration change in
HT reactor 0.173

Table C - 3 Calculation of the CO conversion efficiency in the low temperature


reactor

Low temperature reactor Value Equations used


Equilibrium temperature at LT
575.040 (A-10)
reactor (F)
Equilibrium constant at LT
37.848 (A-8)
reactor temperature
Equilibrium constant at LT
reactor temperature taking into 33.777 (B-13)
account approach temperature

Middle variable u2 32.777 (A-6)


Middle variable v2 -27.220
Middle variable w2 4.027

Total CO conversion efficiency 0.971 (A-5)

271
With the CO conversion efficiency, the compositions of the syngas from the high

and low temperature reactors are given by Table C-4, and C-5.

Table C - 4 Syngas compositions from the high temperature reactor

Flow rate Volume


Molar
Syngas from HT reactor concentration (lb-mol/hr) (cft/hr) Equation used
H2S 0.000 0.029 0.677
CH4 0.033 9.849 232.447
Ar 0.343 101.302 2395.548
COS 0.000 0.001 0.023
NH3 0.000 0.043 1.011
N2 0.429 126.627 2994.502
CO 2.570 758.105 17927.399 (4-3)
H2O 42.908 12657.548 274474.925 (4-6)
CO2 21.468 6333.020 149086.154 (4-5)
H2 32.247 9512.770 223837.105 (4-4)
total 100.000 29499.294 670949.793
total flow rate (lb-
mol/hr) 29499.295
Temperature(F) 851 (A-9)
Pressure(psia) 604

272
Table C - 5 Syngas compositions from the low temperature reactor

Flow rate Volume


Molar
Syngas from HT reactor concentration (lb-mol/hr) (cft/hr) Equation used
H2S 0.000 0.029 0.547
CH4 0.033 9.849 187.747
Ar 0.343 101.302 1935.779
COS 0.000 0.001 0.019
NH3 0.000 0.043 0.817
N2 0.429 126.627 2419.791
CO 0.581 171.405 3275.385 (4-7)
H2O 40.919 12070.848 206971.530 (4-10)
CO2 23.457 6919.720 131153.762 (4-9)
H2 34.236 10099.471 191794.246 (4-8)
total 100.000 29499.294 537739.622
total flow rate (lb-
mol/hr) 29499.295
Temperature(F) 575.040 (A-10)
Pressure(psia) 591.882

273
Table C-6 and C-7 give the calculation steps of the catalyst volumes and the process

facility costs of the shift reactors.

Table C - 6 Calculation of catalyst volume and PFC of the high temperature reactor

Equation
Parameter Value used
Middle variable q1^0.5 3.721 (B-8)
Middle variable u1 5.843
Middle variable v1 0.837
Middle variable w1 6.062

Pressure-dependent activity
factors 4.000 (B-16)
Reaction reat in HT reactor 12584.716 (B-14)
SV in HT reactor 1625.458 (B-7)
Volume of HT catalyst 412.776 (B-6)
Volume of HT reactor 495.331
PFC of HT reactor 698.167 (4-23)
Initial HT catalyst cost 20.639
Table C - 7 Calculation of catalyst volume and PFC of the low temperature reactor

Parameter Value Equation used


Middle variable q2^0.5 16.240 (B-12)
Middle variable u2 17.750
Middle variable v2 0.348
Middle variable w2 36.848

Pressure-dependent activity factors 4.000 (B-16)


Reaction reat in LT reactor 23039.292 (B-15)
SV in LT reactor 2829.039 (B-11)
Volume of LT catalyst 67.795 (B-10)
Volume of LT reactor 81.354
PFC of LT reactor 277.444 (4-23)
Initial LT catalyst cost 16.949

274
The final step is to calculate the process facility costs of the heat exchangers, which

is given by Table C-8.

Table C - 8 Process facility costs of the heat exchangers

Parameter Value Equation used


Heat exchanger 1
Hot gas inlet T, F 851.454 (A-9)
Hot gas outlet T 450.000 Design value
Cold fluid inlet T 351.463 (4-20)
Cold fluid outlet T 580.153 (4-11)
Heat released by syngas, Btu/hr 53917730.708 (4-12), (4-13)
Heat released by syngas, kW 15797.895
Log mean temperature difference, C 94.768
PFC of heat exchanger 1 489.104 (4-24)
Heat exchanger 2
Hot gas inlet T, F 575.040 (A-10)
Hot gas outlet T 381.463 (4-17)
Cold fluid inlet T 57.000 Design value
Cold fluid outlet T 400.000 Design value
Heat released by syngas, Btu/hr 1.047E+08 (4-15), (4-16)
Heat released by syngas, kW 30687.447
Log mean temperature difference, C 134.508
PFC of heat exchanger 2 4605.725 (4-25)
Heat exchanger 3
Hot gas inlet T, F 381.463 (4-17)
Hot gas outlet T 100.000 Design value
Cold fluid inlet T 57.000 Design value
Cold fluid outlet T 351.463 (4-20)
Heat released by syngas, Btu/hr 2.416E+08 (4-18), (4-19)
Heat released by syngas, kW 70801.745
Log mean temperature difference, C 20.062
PFC of heat exchanger 3 3878.719 (4-26)

275
APPENDIX D. CALCULATION PROCESS OF THE SELEXOL SYSTEM
FOR CO2 CAPTURE

This section illustrates the calculation process of the performance and cost model

for the Selexol system discussed in Chapter 5 through a case study. The input parameters

are as follows.

Table D - 1 Selexol properties for calculation

Specific Vapor Specific CO2 Number Specific


Viscosity gravity Mole pressure heat solubility of volume
@25C,cp @25C, weight @25C, @25C SCF/US commerci (gallon/lb-
kg/m^3 mmHg Btu/lb F gal @25C al plants mol)
5.8 1030 280 0.00073 0.49 0.485 32 32.574146

Table D - 2 Properties of gases in syngas

Gas CO2 H2 CH4 CO H2S COS Ar NH3 N2


Relativly 1.000 0.013 0.067 0.028 8.930 2.330 0.000 4.870 0.000
Solubility
(scf/lb-mol) 377.05 379.50 378.46 379.17 376.08 374.53 379.01 375.88 379.23
Cp 0.199 3.425 0.593 0.248 0.245 0.125 0.520 0.249
(Btu/lb F)
Cv 2.440 0.450 0.172 0.399 0.176
(Btu/lb F) 0.152
K=Cp/Cv 1.310 1.400 1.320 1.410 1.310 1.310 1.600 1.310 1.400
Mole 44.010 16.043 28.010 34.082 60.074 39.948 17.031 28.013
weight 2.016
Solution 160.000 75.000 190.000
heat
(Btu/lb)

276
Table D - 3 Composition of syngas before CO2 capture

Syngas fed into heater exchanger Syngas out heater exchanger


Species
Molar flow rate Volume Molar flow rate Volume
conc. (lb-mol/hr) (cft/hr) conc. (lb-mol/hr) (cft/hr)
H2S 0.02 2.77 29.49 0.02 2.77 28.68
CH4 0.06 7.83 83.31 0.06 7.83 81.02
Ar 0.41 56.58 604.45 0.41 56.58 587.89
COS 0.01 1.39 14.81 0.01 1.39 14.40
NH3 0.00 0.00 0.00 0.00 0.00 0.00
N2 0.68 94.25 1006.95 0.68 94.25 979.36
CO 0.98 136.31 1456.26 0.98 136.31 1416.37
H2O 0.19 26.33 229.67 0.19 26.33 221.96
CO2 33.33 4619.95 47871.78 33.33 4619.95 46479.79
H2 64.32 8914.59 94165.06 64.32 8914.59 91555.39
total 100 13860 145462 100 13860 141365
Temperature (F) 70 70 70 55 55 55
Pressure (psia) 550 550 550 545 545 545

Table D - 4 Assumption for power consumption calculation

Efficiency Efficiency of Efficiency Efficiency


of power compressor of recycle Efficiency of three Evaporation
recovery for Selexol gas of CO2 stage CO2 temperature of
turibne compression compressor compressor compressor refrigeration(F)
0.78 0.8 0.82 0.82 0.82 10

Table D - 5 CO2 capture efficiency and flashing tank pressures

CO2 capture Flashing tank 1 Flashing tank Flashing tank3


efficiency pressure (psia) pressure 2 (psia) pressure (psia)
0.97 60 14.7 4

277
The calculation processes and output parameters of the Selexol system are as

follows.

Table D - 6 CO2 capture amount required by capture efficiency

extra selexol ratio 1.5 Eq. (5-11)


CO2 capture in absorber
(SCF/hr) 1689702.3
CO2 solution heat(Btu/hr) 31555552.2 Eq. (5-7)
Heat released from syngas 1594624.8 Eq. (5-6)

Table D - 7 Calculating the flow rate of Selexol solvent

Estimated Estimated Estimated CO2 in


Selexol Selexol the lean Selexol at
Estimated temperature temperature the last stage (SFC
Selexol flow increase due to increase due to Selexol
rate(lb-mol/hr) CO2 solution heat syngas cooling
10578.96 21.74 1.10 112203.81
Adjusted Selexol Adjusted Selexol Estimated CO2 in
Adjusted Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat syngas cooling Selexol
9486.24 24.25 1.23 100457.65

Adjusted Selexol Adjusted Selexol Estimated CO2 in


Adjusted Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat syngas cooling Selexol

9859.17 23.33 1.18 104466.45


Adjusted Selexol Adjusted Selexol Estimated CO2 in
Adjusted Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat syngas cooling Selexol
9717.09 23.67 1.20 102939.17
Adjusted Selexol Adjusted Selexol Estimated CO2 in
Adjusted Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat syngas cooling Selexol
Eq (5-3) ~
9769.18 23.54 1.19 103499.12 Eq. (5-12)

278
Table D – 7 continued
Adjusted Selexol Adjusted Selexol Estimated CO2 in
Adjusted Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat syngas cooling Selexol
9749.80 23.59 1.19 103290.82 Eq (5-3) ~
Final Selexol Final Selexol Estimated CO2 in Eq. (5-12)
Final Selexol temperature temperature the lean Selexol at
flow rate(lb- increase due to increase due to the last stage (SFC
mol/hr) CO2 solution heat Syngas cooling Selexol
9756.97 23.57 1.19 103367.90

Table D - 8 Calculation of the operating pressure of sump tank

Operating pressure of sump tank (psia) 180.322


H2 in recycle gas (SCF/hr) 29179.53
Eq. (5-14)
CO2 in recycle gas 27737.39 ~Eq.(5-17)

Table D - 9 Calculation the temperature change of Selexol due to CO2 release from
flash tank

Adjusted amount Estimated heat(Btu) absorbed due Selexol temperature


of CO2 captured to CO2 released from Selexol decrease
SFC/hr 1074956.316 17036816 12.7268
lb-mol/hr 2850.952396
Adjusted amount Estimated heat(Btu) absorbed due Selexol temperature
of CO2 captured to CO2 released from Selexol decrease
SFC/hr 1033634.983 13410930 10.0182
lb-mol/hr 2741.361752
Adjusted amount Estimated heat(Btu) absorbed due Selexol temperature
of CO2 captured to CO2 released from Selexol decrease
SFC/hr 1042429.258 14182615 10.59466
lb-mol/hr 2764.685547

279
Table D – 9 continued
Adjusted amount Estimated heat(Btu) absorbed due Selexol temperature
of CO2 captured to CO2 released from Selexol decrease
SFC/hr 1040557.603 14018380 10.47197
lb-mol/hr 2759.721625
Final amount of Final heat(Btu) abosrbed due to Final Selexol
CO2 captured CO2 released from Selexol temperature decrease
SFC/hr 1040955.941 14053333 10.49808
lb-mol/hr 2760.778079

Table D - 10 Gases retained in the solvent at the flash tank 1

Amount of gases captured in Selexol CO2 H2 CH4 CO H2S


in first flash tank
SFC/hr 1040955.941 674.496 14.690 47.031 951.506
lb-mol/hr 2760.778 1.777 0.039 0.124 2.530

Table D - 11 Gases released from the solvent at the flash tank 1

Amount of gases released from CO2 H2 CH4 CO H2S


first flash tank
SFC/hr 752114.26 44303.92 188.06 1434.28 90.98
lb-mol/hr 1994.72 116.74 0.49 3.78 0.24
volume flow(cubic feet/hr) 180304.10 10551.23 44.93 342.25 21.87

Table D - 12 Gases retained in the solvent at the flash tank 2

Amount of gases captured in Selexol CO2 H2 CH4 CO H2S


in second flash tank
SFC/hr 293983.24 84.01 1.92 5.94 586.35
lb-mol/hr 779.68 0.22 0.005 0.015 1.55

280
Table D - 13 Gases released in the solvent at the flash tank 2

Amount of gases released CO2 H2 CH4 CO H2S


from second flash tank
SFC/hr 746972.69 590.48 12.76 41.08 365.14
lb-mol/hr 1981.08 1.55 0.03 0.11 0.97
volume flow(cubic feet/hr) 714322.91 561.06 12.159 39.07 350.10

Table D - 14 Gases retained in the solvent at the flash tank 3

Amount of gases captured in CO2 H2 CH4 CO H2S


Selexol in third flash tank
SFC/hr 103367.89 25.38 1.71 5.27 555.45
lb-mol/hr 274.15 0.07 0.004 0.01 1.47

Table D - 15 Gases released in the solvent at the flash tank 3

Amount of gases released CO2 H2 CH4 CO H2S


from third flash tank
SFC/hr 190615.34 58.62 0.22 0.66 30.90
lb-mol/hr 505.54 0.15 0.0006 0.002 0.08
volume flow(cubic feet/hr) 492358.34 162.83 0.60 1.85 86.59

Table D - 16 Final product of CO2 from Selexol

CO2 H2 CH4 CO H2S


SFC/hr 1689702.30 44953.03 201.04 1476.03 487.03
lb-mol/hr 4481.35 118.45 0.53 3.89 1.29
volume flow(cubic feet/hr) 433670.46 11463.08 51.43 377.10 125.39

281
Table D - 17 Power consumption calculation

Power recovery in turbine 1(hp) 594.74 Eq. (5-17)


Power recovery in turbine 2(hp) 586.43 Eq. (5-17)
Power consumption of solvent
compression(hp) 2105.39 Eq. (5-20)
Selexol temperature increase due to
compression 3.74 Eq. (5-21)
Power consumer of refrigeration(hp) 885.54 Eq. (5-22)
Calculation power of recycle gas
compressor
Average k=Cp/Cv 1.39
Power of recycle gas compressor(hp) 2965.07 Eq. (5-19)
Calcuation of power of CO2 compressor
in flash tank 2
Average k=Cp/Cv 1.31
Power of compressor(hp) 1555.53 Eq. (5-19)
Calcuation of power of CO2 compressor
in flash tank 3
Average k=Cp/Cv 1.31
Power of compressor(hp) 738.34 Eq. (5-19)
Calculation of power of CO2 product
compressor
Cold temperature(F) of CO2 product Design value
Average k=Cp/Cv 1.31
Power of compressor(hp) 6317.88 Eq. (5-19)
Total energy consumption of Selexol
(hp) 13386.61
total energy consumption (Kw) 9979.72

282
Table D - 18 Process facility cost of Selexol process

Cost model of Selexol


Cost of absorber per train(k$) 750.43 Eq. (5-23)
Cost of sump tank (k$) 155.24 Eq. (5-25)
Cost of recycle compressor (k$) 2246.19 Eq. (5-26)
Cost of power recovery turbine 1(k$) 275.75 Eq. (5-24)
Cost of power recovery turbine 2 ( k$) 266.87 Eq. (5-24)
Cost of flashing tank 1(k$) 107.33 Eq. (5-31)
Cost of flashing tank 2 (k$) 107.33 Eq. (5-31)
Cost of flashing tank 3 (k$) 107.33 Eq. (5-31)
Cost of CO2 compressor in flash tank 2 (k$) 1017.81 Eq. (5-28)
Cost of CO2 compressor in flash tank 3 (k$) 614.62 Eq. (5-28)
Cost of CO2 product compressor per stage (k$) 5263.78 Eq. (5-29)
Cost of refrigeration 3 (k$) 661.31 Eq. (5-30)
Cost of Selexol pump (k$) 295.29 Eq. (5-27)
Heat exchanger (k$) 1103.99 Eq. (5-32)

283
APPENDIX E. PRELIMINARY DISTRIBUTIONS OF UNCERTAIN
PARAMETERS

The basis of the probability distribution of model parameters (Table E-1, Table E-2,

and Table E-3) for the preliminary uncertainty screening in Chapter 8 is briefly explained

here. As mentioned in Chapter 8, these distributions take into account the data reported in

literatures, modeling approximations, and expert’s technical judgments. The parameters

and their distributions are given in Table E-1, E-2, and E-3.

Table E - 1 Distribution functions assigned to the parameters of the IGCC process


(the distribution functions in this table, except the distribution of the
fixed charge factor, mainly come from reference [1] and were updated
with data from reference [2] and [3])

Determinis
Parameter Unit Distribution function
tic value
Facility cost parameters
Fixed charged % 14.8 Triangular(7.1, 14.8, 17.4)

Engineering and
% of TPC 10 Triangular(7,10,12)
home office fee

Indirection
construction cost % of TPC 20 Triangular(15,20,20)
factor
Project uncertainty % of TPC 12.5 Uniform(10,15)
General facilities % of TPC 15 Triangular(10,15,25)
Process contingency
Oxidant feed % of PFC 5 Uniform(0,10)
Gasification % of PFC 10 Triangular(0,10,15)
Selexol % of PFC 10 Triangular(0,10,20)

Low temperature
% of PFC 0 Triangular(-5,0,5)
gas cleanup

Claus plant % of PFC 5 Triangular(0,5,10)


Beavon-Stretford % of PFC 10 Triangular(0,10,20)

284
Table E – 1 continued
Determinis
Parameter Unit Distribution function
tic value
Process condensate
% of PFC 30 Triangular(0,30,30)
treatment
Gas turbine % of PFC 12.5 Triangular(0,12.5,25)
Heat recovery
% of PFC 2.5 Triangular(0,2.5,5)
steam generator
Steam turbine % of PFC 2.5 Triangular(0,2.5,5)
General facilities % of PFC 5 Triangular(0,5,10)
Maintenance costs
Gasification % of TPC 4.5 Triangular(3,4.5,6)
Selexol for sulfur
% of TPC 2 Triangular(1.5,2,4)
remove
Low temperature
% of TPC 3 Triangular(2,3,4)
gas cleanup

Claus plant % of TPC 2 Triangular(1.5,2,2.5)


Boiler feed water % of TPC 2 Triangular (1.5, 2, 4)
Process condensate
% of TPC 2 Triangular(1.5,2,4)
treatment
Gas turbine % of TPC 1.5 Triangular(1.5,1.5,2.5)
Heat recovery
% of TPC 2 Triangular (1.5, 2, 4)
steam generator
Steam turbine % of TPC 2 Triangular(1.5,2,2.5)
Other fixed operating cost parameters
Labor rate $/hr 25 Triangle (17,25,32)
Variable operating cost parameters
Ash disposal $/ton 10 Triangular(10,10,25)
Sulfur byproduct $/ton 75 Triangular(60,75,125)

285
Table E - 2 Distribution functions assigned to Selexol-based CO2 capture process

Nominal
Performance parameter Unit value Distribution function
Mole weight of Selexol lb/mole 280 Triangular(265,280,285)
Pressure at flash tank 1 Psia 60 Uniform(40,75)
Pressure at flash tank 2 Psia 20 Uniform(14.7,25)
Pressure at flash tank 3 Psia 7 Uniform(4,11)
Power recovery turbine efficiency % 75 Uniform(70,80)
Selexol pump efficiency % 75 Uniform(70,80)
Recycle gas compressor efficiency % 75 Uniform(70,80)
CO2 compressor efficiency % 79 Triangular(75,79,85)
Cost parameter Unit Value Distribution function
WGS catalyst cost $/ft^3 250 Triangular(220,250,290)
Selexol solvent cost $/lb 1.96 Triangular(1.32,1.96,2.9)
% of
Process contingency of WGS system PFC 5 Triangular(2,5,10)
Process contingency of Selexol % of
system PFC 10 Triangular(5,10,20)
% of
Maintenance cost of WGS system PFC 2 Triangular (1, 2, 5)
% of
Maintenance cost of Selexol system PFC 5 Triangular(2,5,10)

Table E - 3 Distribution functions assigned to the fuel cost and capacity

Parameter Unit Deterministic Distribution function


Fuel price $/MBtu 1.3 Triangular(1.0,1.3,2.1)

Capacity factor % 75 Triangular(35, 75, 90)

The data sources of the parameters in the above tables are given in the following:

1. Fixed charge factor: Several studies reports different values, half of which range from
14.5% to 15%. Here a triangular distribution with a default mode value of 14.8% is

286
assigned to this parameter. Values of the fixed charge factor and their sources are
given in the following table.

Fixed charge factor (%) References


7.1 4
11.9 5
14.5~15 6, 7, 8
17.4 9

2. Fuel price: Fuel cost is the major variable operation cost of an IGCC power plant. The
lowest fuel price reported is 1.03 $/MBtu, and the highest price reported is 2.11
$/MBtu. For the uncertainty screening purpose, a rough triangular distribution is
assigned to the fuel price.

Fuel price ($/MBtu) References


1.03 8
1.3~1.5 2, 3, 5, 10
1.58 7
1.66 6
1.79 9
2.11 4

3. Capacity factor: For the uncertainty screening purpose, a triangular distribution with a
mode value of 75% is assigned to the capacity factor.

Capacity factor (%) References


35 11
51 12, 13
60~65 5, 6, 11, 12
65~70 11, 12, 14
70~75 11, 12, 15,
75~80 8, 11, 15
80~85 3, 9, 15
90 7, 16

287
4. Mole weight of Selexol: Selexol solvent is a mixture of dimethyl ethers of polyethylene
glycol with the formulation of CH3(CH2CH20)nCH3, where n is between 3 and 9. Mole
weight of Selexol influences the calculation of the flow rate of solvent. Different mole
weights are reported. A triangular distribution is assigned to this parameter.

Mole weight of Selexol (lb/mole) References


265 17
280 18, 19
285 20

5. Pressures of flush tanks: Three flush tanks are used to release CO2 captured in the
solvent at reduced pressures. The flash pressure in each flash tank is a design
parameter, which influences the power consumption of CO2 compression and CO2
capture efficiency. Due to limited data points, uniform distributions are assigned to the
three pressure parameters.

Flash pressure (psia) References


40 (flash tank 3) 21
75 (flash tank 3) 20
14.7 (flash tank 2) 21
25 (flash tank 2) 20
4 (flash tank 3) 21
11 (flash tank 3) 20

6. Power recovery turbine efficiency, Selexol pump and recycle compressor efficiency:
Power recovery turbine and pump are common mechanical devices used in industrial
fields. The efficiency of such devices may vary depending on the flow type and the
operating conditions. The efficiencies, typically, would be around 70-80%. Here a
uniform distribution (uniform(70,80)) is employed [22].

7. CO2 compressor efficiency: CO2 compressor is used to compress CO2 product to


desirable pressures. From the reported data, the compression efficiencies varies from
75% to 88%. Here a triangular is used for this parameter.

288
CO2 compressor efficiency (%) References
75 23
75~85 24
85 25
88 26

8. Selexol solvent cost: The cost of the sorbent depends on various market forces. Here a
triangle distribution is given to the solvent cost.

Selexol cost ($/lb) References


1.4 20
1.96 27
2.9 3

9. WGS catalyst cost: the deterministic value of the catalyst cost from reference [20].
Based on expert’s judgment, the range of the price fluctuation is around ± 20%, so a
triangle distribution is given to the catalyst cost.

10. Process contingency of WGS and Selexol system: The deterministic value of the
process contingency came from reference [3]. The value range of the contingency
came from the recommendation of reference [28].

11. Maintenance cost: the maintenance cost is usually expressed as a fraction of the total
plant cost. This parameter depends on some design parameters as well as the operating
conditions [22]. Based on the recommended range of reference [28], as well as
expert’s judgments, triangular distributions are assigned to the maintenance costs of
WGS and Selexol processes.

289
REFERENCES (APPENDIX E)

1. Frey, H.C., and N. Akunuri, "Probabilistic Modeling and Evaluation of the


Performance, Emissions, and Cost of Texaco Gasifier-Based Integrated
Gasification Combined Cycle Systems Using ASPEN," Prepared by North
Carolina State University for Carnegie Mellon University and U.S. Department of
Energy, Pittsburgh, PA, January 2001.

2. Shelton W., Lyons J., 2000: Texaco Gasifier IGCC Base Cases, Process
Engineering Division, NETL, PED-IGCC-98-001

3. Foster Wheeler Ltd, 2003; Potential for Improvement in Gasification Combined


Cycle Power Generation with CO2 Capture,” IEA Greenhouse Gas R&D
Programme, Report Number PH4/19, May 2003

4. Hendriks, C. A., 1994: Carbon Dioxide Removal from Coal-Fired Power Plants.
Kluwer Academic Publishers, Dordrecht, the Netherlands

5. Condorelli P., Smelser, S. C., McCleary G. J., 1991 Engineering and Economic
Evaluation of CO2 Removal from Fossil-Fuel-Fired Power Plants. Volume 2:
Coal Gasification Combined-Cycle Power Plants. Electric Power Research
Institute; Report # IE-7365

6. Doctor R. D.; Molburg J. C., Thimmapuram P. R., 1997: Oxygen-Blown


Gasification Combined Cycle: Carbon Dioxide Recovery, Transport, and
Disposal. Energy Convers. Mgmt. Vol. 38, Suppl.

7. IEA Greenhouse Gas R&D Programme and Stork Engineering Consultancy B.V.,
1999: Assessment of Leading Technology Options for Abatement of CO2
Emissions; December 1999.

8. Simbeck D., 1998: A Portfolio Selection Approach for Power Plant CO2 Capture,
Separation and R&D Options. Fourth International Conference on Greenhouse
Gas Control Technologies, Interlaken, Switzerland; 1998.

9. Chiesa P., Consonni S, 1998: Comparative Analysis of IGCCs With CO2


Sequestration. Fourth International Conference on Greenhouse Gas Control
Technologies, Interlaken, Switzerland; 1998.

10. IECM User manual, 2005, www.iecm-online.com

11. McDaniel J.E., Hornick M., 2003: Polk Power Station ICGG 7th year of
commercial operation, Gasification technologies, San Francisco, California

12. Marco Kanaar, Carlo Wolters, 2004: Fuel Flexibility, the European Gasification
Conference, May 2004

290
13. IgnacioMéndez-Vigo, 2003: Elcogas Puertollano IGCC Update, Gasification
Technologies, San Francisco, California

14. Yamaguchi M., 2004: First Year Operation Experience with the Negishi IGCC,
Gasification Technologies 2004, Washington DC

15. Keeler C.G., 2003: Operating Experience at the Wabash River Repowering
Project, Gasification technologies, San Francisco, California

16. Daslav C., BrkicBrkic C., 2003: The Experience of Snamprogetti’s Four
Gasification Projects, Gasification Technologies, San Francisco, California

17. Epps R., 1994: Use of Selexol Solvent for Hydrocarbon Dewpoint Control and
Dehydration of Natural Gas, presented at the Laurance Reid Gas Conditioning
Conference, Norman, OK, February 27-March 2, 1994

18. Sciamanna S. and Lynn S., 1998: Solubility of hydrogen sulfide, sulfur dioxide,
carbon dioxide, propane, and n-butane in poly(glycol ethers), Ind. Eng., Chem.
Res., 27, 1988

19. UOP, 2000: Use of SELEXOL Process in Coke Gasification to Ammonia Project,
UOP report

20. Doctor R.D., etc., 1996: KRW oxygen-blown gasification combined cycle carbon
dioxide recovery, transport, and disposal, ANL/ESD-34, 1996

21. Chiesa P. and Consonni S., 1999: Shift Reactors and Physical Absorption for
Low-CO2 Emission IGCCs, Journal of Engineering for Gas Turbines and Power,
Vol. 121

22. Rao A.B., 2003, A technical, environmental, and economic assessment of Amine-
based carbon capture systems for greenhouse gas control, Ph.D thsis, Carnegie
Mellon University

23. Price, B.C., 1984: Processing high CO2 gas. Energy Progress, 1984, 4(3)

24. Bolland, O. and H. Undrum, 1998: Removal of CO2 from gas turbine power
plants: evaluation of pre- and post-combustion methods. Fourth International
Conference on Greenhouse Gas Control Technologies, 30 Aug-2 Sep., 1998,
Interlaken, Switzerland

25. Hendriks, C., 1994: Carbon dioxide capture from power stations, a report
published by IEA Greenhouse Gas R&D Programme, UK

26. Alston, 2001: Engineering feasibility and economics of CO2 capture on an


existing coal-fired power plant. Final report prepared by Alstom Power Inc.
Report no. PPL-01-CT-09

291
27. Personal communication with UOP.

28. EPRI Technical Assessment Guide, 1993

292

You might also like