PM CW1 Assignment Explanation
PM CW1 Assignment Explanation
BM522
A C F
Start Finish
B D E G
A 0 7 C 7 19 F 26 32
7 2 9 12 14 26 6 26 32
Start Finish
B 0 9 D 9 17 E 17 26 G 26 31
9 0 9 8 9 17 9 17 26 5 27 32
Forward Pass
• A has no dependences (this is a scenario of no dependencies on the forward
pass)so its EST will be 0, or right away. Since it has 7 weeks to be completed, its
EFT will be 0+7=7 (EF=ES+t)
• B has also EST of 0, and with an activity time of 9 it will have an EFT of 0+9=9
• C needs A to be completed (this is a scenario of 1 dependence) before it can start.
Since the EFT of A is 7, then the EST C can start is 7, and with an activity time of
12 weeks C will have an EFT of 12+7=19.
• D needs both A and B to finish (this is a scenario of more than one dependences
on the forward pass). Since the EF time for A and B are 7 and 9 respectively, and
D needs both of them to finish, in order to start, the EST of D is 9 (We pick the
highest, when we do the forward pass). In other words, the highest of the EF
times preceding an activity will be the activity’s EST. So D finishes at 8+9=17.
Forward Pass Cont.
• E, since it depends on D, so can start at 17 and finish at 17+9=26.
• F depends on C and E, since the higher EF time is 26, F can start
earliest at 26, and finishes at 26 +6=32.
• G can also start earliest at 26 since it has only one
dependence/predecessor, E and G can finish at 26+5=31. Although G
is the last letter, does not have the highest EF time (31<32), so we say
that the project completion time is 32 weeks. In essence, the project’s
competition time, is the highest of the EF times.
Backward Pass
• Since the project completion time is 32 weeks, the LFT for the activities at
the finish node (be careful, it might be only one node and not 2) F and G
has to be 32. That is F and G cannot be completed in longer than 32 weeks.
Next we obtain the LST by subtracting the activity times from the LFT
(LS=LF-t).
• For G, the LST will be 32-5=27.
• For F, LST=32-6=26.
• E has 2 dependencies, F and G. The LST of these activities are 26 and 27
respectively. As a result, the LST of E has to be 26, in order for F to start. In
essence, when doing the backwards pass, the LFT of an activity, must be
the minimum of the LST of its successors. Thus, the LST for E=26-9=17.
Backward Pass Cont.
• D has only one successor, E. So the LFT will be the LST for E, which is
17-9=9
• Activity C has one successor, F. Therefore the LFT will be 26 for C, and
the LST will be 14.
• A has two successors, C and D. The minimum of their latest starting
time is 9. So, the LFT for A will be 9 and the LST will be 2.
• Activity B has one predecessor, D, with LST of 9. So the LFT for B will
be 9, and its LST will be 0.
• The backward pass is now complete.
Slack Calculation
• Slack for an activity is defined as how long the activity can be delayed
without extending or increasing the projects completion time and is
calculated as: slack=LS-ES or slack=LF-EF (Be careful, any of those 2
calculations must result on the same number. If not, it means you have
done a mistake on your calculations).
• So the slack for A=2-0=2 or 9-7=2
• For B=0, for C=7, for D=0, for E=0, for F=0 and G=1
• For example, activity C, can begin any time between week 19 and 14and
can finsigh between week 19 and 26. Thus C can be delayed for up to 7
weeks and the project will still be completed in week 32. Activities B,D,E,F
on the other hand, cannot be delayed at all, without extending the
project’s competition time. So, if D is delayed by 2 weeks, then the project
will be delayed by 2 weeks, from 32 to 34.
Critical Activities and Critical Path
• The activities with 0 slack are called critical activities and they form
the critical path, which is the longest path in the network. So, the
critical path here is B-D-E-F.
Gantt Chart
• After you finish with all calculations, you should create a Gantt chart,
in MS Project.
(3) How to make Gantt Chart using MS Project 2016 - YouTube
Part 3
Task 3 Example
Stakeholders Analysis
Task 3 Requirements
Task 3:
Undertake a stakeholder analysis for this project. This should
clearly
• identify internal and external stakeholder,
• group stakeholders according to their interest and power i.e.
stakeholder management matrix, communication strategies.
(20 marks)
Internal & External Stakeholders
Create a list of stakeholders and divide them as internal and external
Internal & External Stakeholders Example
Portfolio Interest, Influence, and information Needs
Stakeholders
Risk Description of the Risk Probability Impact Risk Risk Owner Risk Actionee Proposed risk management
Category level Status strategy
Security Risk During the festival, someone enters Low High Medium Project Manager Specialised security The project manager has assigned the risk to a
with a gun and begins shooting in team specialised security team and they will be
all directions. responsible to take action upon it. The following
will be applied.: Searching (body and bag as
appropriate)
Patrolling and boundary / car park security
Entrance and exit security
Part 6
Quality Expectations
Task 6 Requirements
Task 6:
You are required to DETERMINE what
• the quality expectation,
• acceptance criteria,
• quality specification,
• and what measures would be put in place to control the event.
In other words your write up in this section must cover these heading.
(15 marks)
Part 7
Assignment
Recommended Structure
Assignment Structure
- Cover page – Add: Bucks Students’ Union Music Festival Project
BM522 Project Management CW1 Assignment
Buckinghamshire New University
BA (Hons) Business Management Degree
Semester XXXXXX
Word count : XXX