6abha09 Abha 08 MBL Ev Itp 00002

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

P6 Abha Entertainment Complex

Client: Contractor: Assistant Engineer and Supervision Project Management Consultant


Consultant: and Engineer:

6ABHA09-INSPECTION TEST PLAN (ITP) AND CHECK LIST FOR INSTALLATION AND TESTING OF FIRE ALARM
SYSTEM
Review Sheet
Ref: 6ABHA09-ABHA-08-MBL-EV-ITP-00002 Revision 00 Date & Time 05 February 24
Client: Saudi Entertainment Ventures
Project Management Consultant and Engineer Saudi Consolidated Engineering Company - Khatib & Alami
Assistant Engineer and Supervision Consultant DAR International for Engineering Consultancy
Contractor Modern Building Leaders
Area / Location
Discipline:
☐ Civil ☐ Structural ☐ Architectural ☐ Mechanical ☐ GM ☐ Electrical ☐ HV ☒EV ☐ Plumbing ☐ Quality ☐ BIM
☐ Project Control ☐ Quality Management ☐ FLS/Safety ☐ General ☐ Other (specify if other):

Assistant Engineer and Supervision Consultant: DAR Engineering


Comments:
1- ITP and checklist can be modified when required as per site condition. 2- ITP inspection responsibility assignments
can be modified when required as per site condition. 3- Fire alarm system and procedures shall be as per project
specification, manufacturer recommendation, and last updated Saudi BUILDING code & Civil defense guide line. 4-
Delivered Fire alarm system and all its components will be properly packaged and adequately protected from
damage/deterioration during shipment, transportation, handling and storage. 5- Pre-testing: After installation,
align, adjust, and balance the system and perform complete pre-testing. Determine, through pre-testing, the
compliance of the system with requirements of the Drawings and Specification. Correct deficiencies observed in
pre-testing. Replace malfunctioning or damaged items with new ones,and retest until satisfactory performance and
conditions are achieved. Prepare forms for systematic recording of acceptance test results. 6- Report of Pre-testing:
After pre-testing is complete, provide a letter certifying the installation is complete and fully operable, including the
names and titles of witnesses to preliminary tests. 7- Final Test Notice: Provide a minimum of 10 days' notice in
writing when the system is ready for final acceptance testing. 8- Minimum System Tests: Test the system according
to procedures outlined in NFPA 72. 9- Strict compliance with project specification and all other project contractual
documentations. 10- Fire alarm system shall comply with the latest editions of the requirements of applicable local
codes, and the following standards (EIA & TIA & IEEE & ISO & ANSI & IEC & EN-50174, NFPA). 11- Safety
measurements and precautions shall be covered.
Eng. Name: Ashraf Abdalrahim Signature: Date: 05 February 24
Submittal Status:

☐ A- Approved ☒ B- Approved with Comments ☐ C- Revise & Resubmit


Project Management Consultant and Engineer: Khatib and Alami
Comments:
- Compliance Sheet for ITP of Fire Alarm System for Rev.0 is attached / comply.
Kindly proceed as commented.
Eng. Name: Nicolas Abboud Signature: Nicolas Abboud Date: 05 February 24
Submittal Status:

☐ Reviewed ☒ Reviewed with Comments


Client: Saudi Entertainment Ventures – SEVEN (IF REQUIRED)
Page 1 of 2
P6 Abha Entertainment Complex
Client: Contractor: Assistant Engineer and Supervision Project Management Consultant
Consultant: and Engineer:

Comments:

Eng. Name: Signature: Date: 05 February 24


Submittal Status:

☐ Reviewed ☐ Reviewed with Comments


IMPORTANT: Permission to proceed does not relieve the Contractor from full compliance with contractual obligations, responsibility, and the Local Authorities requirements.

Page 2 of 2
Client PMC LDC Contractor
Saudi Entertainment Ventures Khatib & Alami Dar International Engineering Consultancy Modern Building Leaders
Project name: Program 6: Abha Entertainment Complex
Location: Abha Contract No.:

INSPECTION TEST PLAN


6ABHA09-INSPECTION TEST PLAN (ITP) AND CHECK LIST FOR INSTALLATION AND TESTING OF FIRE ALARM SYSTEM

New Submittal Submittals NO Submittals date Revision Previous submittal date

Resubmit 6ABHA09-ABHA-08-MBL-EV-ITP-00002 23-Jan-2024 00

Document purpose For Information For Notes For Approval

DECPLINE Sewage Struc. BIM Electronic Services/ELV

(Quality) (Method statement) (Time Schedule) (Safety)

Document type (Soil Report) (Policies) (Monthly Report) (General Report)

Weekly Report) INSPECTION TEST PLAN

Attachments 1 2 3

Sr. Document TITLE Document NO Document Status Notes

6ABHA09-INSPECTION TEST PLAN (ITP) AND CHECK


1 LIST FOR INSTALLATION AND TESTING OF FIRE 6ABHA09-ABHA-08-MBL-EV-ITP-00002 For Approval
ALARM SYSTEM

Sr.Project Manger (Contractor) Sr. Engineer (Contractor)

Name: Eng. Mohamed KotbTahoun

Signature: Technical Office Manager

Date: 23-Jan-24

Remarks:

Supervision Consultant representative PMC representative

Name: Ashraf AbdalRahim Signature: Name: Signature:

Position: Resident Engineer Date: Position: Date:

Document Status

(A) Approved As Submitted (B) Approved with Comments (C) Revise and Resubmit (D) Rejected

Issued by the contractor: Signature: From the consultant: Signature:


Date: Date:

FR-QC-CW0091-01 Issue Date 14 November 2021 Rev.00


ITP Submittal
Internal Review Checklist
Project Name: ABHA-P6 Entertainment Complex ITP no.: 6ABHA09-ABHA-08-MBL-EV-ITP-00002
Contract No: P6 Rev. no.: 0
Contractor: MBL Date: 23-JAN-24
Sub-Contractor: ICAD Discipline: ELV

ITP description : INSTALLATION & TESTING OF FIRE ALARM SYSTEM

No. Item Yes No N/A Comment

1 Has the scope of inspections & tests been well defined?

Has the mock-up inspection tests with frequency of the mock-up inspection tests been
2
included with Respecting W and H points?

3 Has the samples inspection tests been included with Respecting W and H points?

Are items to be inspected and tested including test stages identified and presented in a
4
logical construction order?

Are controlling documents such as test procedure, method statement, project


5
specification, related standards been included?
Are all Quality Control requirements including, pre-task quality brief, calibration, Shop
6 drawings,Redline drawing monitoring, clearance from other disciplines, and turn-over
review detailed as required?

Are acceptance criteria with a clear tolerance for each inspection and test been
7
specified?

8 Has the frequency of inspection and testing been included?

Are verifying documents has been identified with clear reference to applicable
9
checklists and forms?

Does the ITP include notification requirements for “Work Inspection Request” (WIR)/
10 Material inspection request (MIR)?(Minimum (24) hours for site work and (1) week in
advance for inspections requested during holidays and Fridays.

Does the ITP include specific code/ standard to be used for each inspection/ test in
11
accordance with the requirements of SEVEN List of Codes & Standards?

12 Are responsibilities related to inspection and test been included?

13 Are there references to Applicable procedures for testing & inspection.?

Are the 3rd party, MBL, LDC, PMC ,and SEVEN hold, witness review points been
14
established among all parties with a clear definition in the legend?

15 Does the ITP specify the percentage of tests to be done/ sampling plan?

16 Has SEVEN Project number been speicifed?

17 Are the reporting forms & checklist been included as an attachment to the ITP?

18 Are previous submittal comments have been addressed and replied?

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


ITP Submittal
Internal Review Checklist
Project Name: ABHA-P6 Entertainment Complex ITP no.: 6ABHA09-ABHA-08-MBL-EV-ITP-00002
Contract No: P6 Rev. no.: 0
Contractor: MBL Date: 23-JAN-24
Sub-Contractor: ICAD Discipline: ELV

ITP description : INSTALLATION & TESTING OF FIRE ALARM SYSTEM

No. Item Yes No N/A Comment

Has the inspection & test plan been signed off by designated competent preparer,
19
reviewer and approver?

Does the inspection & test plan format & language is as per project requirements and
20
easy to understand?

Does the inspection & test plan include the repair stage or contain a reference to a
21
separate Special Procedure for repairs?

Does the inspection and test plan require an activity for the protection of completed
22
work? If yes is the approved Method/procedure mentioned in the Reference?

Conclusion/ Remarks

Prepared by: Reviewed by: Accepted by:

Name Eng Rami Baydown Junaid Ahmad Mohammed Imaduddin

Designation Sr. Tech Engr. MBL QA/QC Elect Engg Sr. QA/QC Eng.

Signature

Date 23-JAN-24 23-JAN-24 23-JAN-24

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Compliance Sheet for ITP of Fire Alarm System

Sr. No. Comments Response

The contractor should include all inspection major activity


for installation of Fire Alarm system. like 1.1- for item 5.1 -
Fire alarm system submission of As-Built drawings Include
Complied. Separate Checklists
1 item to be as a WIR 1.2- Include item 5.2 - Grounding of
included in SEC 3 of ITP.
equipment and cable shield. 1.3- Include item 5.3-
Identification of components, wiring cabling and
terminals, 1.4- Include item 5.4- Functional testing of FACP

The contractor should define and provide acceptance


2 criteria for every inspection activity for installation of Fire Complied
Alarm system.

The contractor should define and provide exact checklist


Complied. Separate Checklists
3 for every inspection activity for installation of Fire Alarm
Provided
system.

For testing and commissioning for Fire alarm separate Noted. The detailed procedure will
4 detailed manufacture recommended procedure to be be submitted in Method Statement
submitted. of Testing of Fire Alarm System

Noted. The detailed procedure will


5 All interface testing should be done and verified. be submitted in Method Statement
of Testing of Fire Alarm System
Test for Cause and Effect should be carried out as per Noted. Cause and Effect Matrix will
6 approved matrix, and it should be mentioned in the be included in Method Statement for
procedure. Testing.
The Applicator EST /Installer should submit Warranty
7 certificate for materials and completed works at site that Noted
satisfy project requirements.
Noted. Manufecturer
The contractor/Installer shall follow manufacturer
recommendations included in
8 installations manuals and recommendations during
Method Statement for installation of
installation the system components.
fire alarm system.

Prior to start implementation Installation, The Contractor


9 should coordinate with the other Trades after approving Noted
reflected ceilings, and all other site activities.

Use only properly color coded, stranded wire. Install wire


10 Noted
sizes as approved in the shop drawing.
The Contractor should only use the product system after
11 approval of the Engineer on the specific application Noted
requested.

The Contractor should strictly follow the instructions,


12 Approved shop drawing, and recommendations of the Noted
Manufacturer in all stages of application.

Noted. All Material has been stored


The Contractor to establish a storage area with follows the
13 properly following specifications and
instructions, and recommendations of the Manufacturer.
manufecturer recommendations.

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)

Utilized By
Document Number Document Type Contract Number
Document Title Inspection Test Plan Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Activity INSTALLATION & TESTING OF FIRE ALARM SYSTEM


ITP Number 6ABHA09-ABHA-08-MBL-EV-ITP-00002 Discipline ELV ITP Approval Date

Project Title ABHA-P6 Entertainment Complex


WIR No
INSPECTION

CONTRACTO
Third Party
ITEM Reference

Seven
PMC
Task / Activity Acceptance Criteria Frequency Check List Recording Document REMARKS

LDC
NO. /Controlling Document

R
1.0 DOCUMENTATION

Document Review (Spec)28 Document Review (Spec) Approved


1.1 Pre-Qualification of Sub Contractor As required N/A N/A H R R R
46 21.11 28 46 21.11 Prequalification
Document Approved IFC Shop Drawing
1.2 Shop Drawing Approval Each Shop Drawing N/A N/A H R R R
Review(IFC/Spec) drawings/Spec Transmittal
Approved Method
1.3 Method Statement Approval Document Review Prior to Start of Activity N/A As per Specification N/A H R/H R R
Statement
As per Specification /
Document Review (Spec)28 Material Sample Form /
1.4 Sample & Mockup Approval Prior to Start of Activity N/A Approved Material Submittal / N/A H R/H H H
46 21.11 Mockup WIR
Method Statement

2.0 RECEIVING INSPECTION

2.1 Check the Material as per approved submittal. Approved MTS/ MIR Per Delivery MBL-CL-ELV-Fire Alarm System-005 Approved MTS MIR N/A H H S R

3.0 INSTALLATION INSPECTION

As per approved Approved Shop Drawing


3.1 Installation of Cables of Fire Alarm System Prior to Commissioning MBL-CL-ELV-Cabling-001 WIR N/A H H S R
(Check List) and Method statement

As per approved Approved Shop Drawing


3.2 Identification & Grounding of Fire Alarm System Prior to Commissioning MBL-CL-ELV-Identification & Grounding-002 WIR N/A H H S R
(Check List) and Method statement

As per approved Approved Shop Drawing


3.3 Installation of Fire Alarm System (Devices, Panels) Prior to Commissioning MBL-CL-ELV-FIRE ALARM SYSTEM-003 WIR N/A H H S R
(Check List) and Method statement

4.0 TESTING & COMMISSIONING

As per Approved Approved Shop Drawing WIR with Attached


4.1 Testing of Fire Alarm System Prior to Commissioning MBL-CL-ELV-TESTING OF FIRE ALARM SYSTEM-004 H H H S R
Specification and Method statement Test report

5.0 AS BUILT DRAWING

WIR & Redline Drawing


After prepared based on
Requirements set forth in Specification:
5.1 Maintain site as built drawing Completion of All N/A Approved TQ and Field N/A W R R R
Contract Documents Section 01 77 00 - 2
Works Change Document
Approved

6.0 CLOSE OUT

6.1 Handover to main Contractor As per contract Document At End of Work N/A As per contract Document Contract Document H H R R R

GENERAL NOTES
1 The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Consultant may adjust the levels of SEVEN participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant
LEGEND
H Hold Point for QC Inspection/Test R Review of Documents
Page 1 of 1
W Witness Inspection/Test
S Surveillance

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-CABLING
Activity: INSTALLATION OF FIRE ALARM CABLES ELV
INSTALLATION-001
Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR
WIR No
ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
Project specs.
C1 Conceal fire alarm system wiring in raceway.
28 46 21-43 3.2 ( B )
Fire alarm circuits and equipment control wiring associated with the fire alarm Project specs.
C2
system shall be installed in a dedicated raceway system. 28 46 21-43 3.2 ( B.1)
Cables and raceways used for fire alarm circuits, and equipment control
Project specs.
C3 wiring associated with the fire alarm system, may not contain any other wire
28 46 21-43 3.2 ( B.2)
or cable.
Wiring within Enclosures: Separate power-limited and non-power-limited
conductors as recommended by the manufacturer. Make all connections with Project specs.
C4
approved crimp-on terminal spade lugs, pressure-type terminal blocks, or plug 28 46 21-43 3.2 ( C )
connectors.
Cable Taps: Use numbered terminal strips in junction, pull and outlet boxes, Project specs.
C5
cabinets, or equipment enclosures where circuit connections are made. 28 46 21-43 3.2 ( D )
Color-Coding: Color-code fire alarm conductors in red differently from the normal Project specs.
C6
building power wiring. 28 46 21-43 3.2 ( E )
Project specs.
C7 No joints are allowed in the fire alarm cabling.
28 46 21-43 3.2 ( F )
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-
IDENTIFICATION &
Activity: IDENTIFICATION & GROUNDING OF FIRE ALARM SYSTEM ELV
GROUNDING
INSTALLATION-002

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No
ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
Identify system components, wiring, cabling, and terminals.Comply with
Project specs.
C1 requirements for identification specified in Division 26 Section "Basic Electrical
28 46 21-44 3.3 ( A )
Materials and Methods."
Project specs.
C2 Mark each terminal according to the system's wiring diagrams.
28 46 21-43 3.2 ( C )
Install framed instructions and zone layout in a location visible from the Project specs.
C3
MFACP/FACP. 28 46 21-44 3.3 ( B )
Fire alarm zone numbering scheme shall be in numbers not letters reflecting the floor Project specs.
C4
number. 28 46 21-44 3.3 ( D )
Project specs.
C5 Comply with Division 26 Section “Grounding and Bonding for Electrical Systems”.
28 46 21-44 3.4 ( A )
Ground fire alarm control panel and associated circuits; Install a ground wire Project specs.
C6
from main service ground to fire alarm control panel. 28 46 21-44 3.4 ( B )
Ground cable shields and equipment according to system manufacturer's written Project specs.
C7
instructions. 28 46 21-44 3.4 ( C )
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-Installation
Activity: INSTALLATION OF FIRE ALARM SYSTEM (DEVICES, PANELS) ELV
Of Fire Alarm System-003

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No
ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
Project specs.
C1 Connect the MFACP/FACP with a disconnect switch with lockable handle or cover.
28 46 21-42 3.1 ( A )
Project specs.
C2 Manual Stations: Mount semi flush in recessed back boxes.
28 46 21-42 3.1 ( B )
The Center point of a manual pull station should be mounted at 1200mm from floor Project specs.
C3
level. 28 46 21-42 3.1 ( C )
Ceiling-Mounted Smoke Detectors: Not less than 100mm from a sidewall to the near
Project specs.
C4 edge. For exposed solid-joist construction, mount detectors on the bottom of joists.
28 46 21-42 3.1 ( E )
On smooth ceilings, install not more than 9 m apart in any direction.
Wall-Mounted Smoke Detectors: At least 100mm, but not more than 300mm, below Project specs.
C5
the ceiling. 28 46 21-42 3.1 (F )
Smoke detectors where located above false ceiling shall be provided complete with
Project specs.
C6 LED indicator, this indicator shall be installed in an accessible location in the ceiling
28 46 21-27 2.8 ( 9 )
and shall be clearly labeled
Smoke Detectors near Air Registers: Locate detectors not closer than 910 mm (36 Project specs.
C7
inches) from air-supply diffuser or return-air opening. 28 46 21-42 3.1 ( G )
Install bells and horns on flush-mounted back boxes with the device-operating Project specs.
C8
mechanism concealed behind a grille. 28 46 21-43 3.1 ( K )
Project specs.
C9 Visible Alarm Devices: Install at least 150mm below the ceiling.
28 46 21-43 3.1 ( L )
Project specs.
C10 Device Location-Indicating Lights: Locate in public space near the device they monitor.
28 46 21-43 3.1 ( M )
MFACP/FACP: Surface mount with tops of cabinets not more than 1800mm Project specs.
C11
above the finished floor. 28 46 21-43 3.1 ( N )

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Annunciator: Install with the top of the panel not more than 1800mm above the Project specs.
C12
finished floor. 28 46 21-43 3.1 ( O )
Project specs.
C13 Install sampling tubes so that they extend the full width of the duct.
28 46 21-42 3.1 ( I.2 )
The center point of a fire fighter telephone should be mounted at 1200mm from floor Project specs.
C14
level. 28 46 21-43 3.1 ( P )
Water-Flow detectors and valve supervisory switches: Connect for each sprinkler valve Project specs.
C15
station required to be supervised. 28 46 21-42 3.1 ( D )
Remove paint splatters and other spots, dirt, and debris. Touch up Project specs.
C16
scratches and marred finish to match original finish. 28 46 21-45 3.6 ( A )
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-Testing
Activity: TESTING OF FIRE ALARM SYSTEM of Fire Alarm System- ELV
004
Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR
WIR No
ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
Manufacturer's Field Service: Engage a factory trained and authorized service
Project specs.
C1 representative to inspect field-assembled components and connections and to
28 46 21-44 3.5 ( A )
supervise installation, pre- testing, testing, and adjustment of the system.
Pre-testing: After installation, align, adjust, and balance the system and perform
Project specs.
C2 complete pre-testing. Determine, through pre-testing, the compliance of the system
28 46 21-44 3.5 ( B )
with requirements of the Drawings and Specification
Report of Pre-testing: After pre-testing is complete, provide a letter certifying the
Project specs.
C3 installation is complete and fully operable, including the names and titles of witnesses
28 46 21-44 3.5 ( C )
to preliminary tests.
Minimum System Tests: Test the system according to procedures outlined in NFPA 72. Project specs.
C4
Minimum required tests are as follows: 28 46 21-44 3.5 ( E )
Project specs.
C5 Verify the absence of unwanted voltages between circuit conductors and ground.
28 46 21-45 3.5 ( E.1 )
Project specs.
C6 Test all conductors for short circuits using an insulation-testing device.
28 46 21-45 3.5 ( E.2 )
Verify that the control unit is in the normal condition as detailed in the manufacturer's Project specs.
C7
operation and maintenance manual. 28 46 21-45 3.5 ( E.4 )
Test initiating and indicating circuits for proper signal transmission under open circuit
conditions. One connection each should be opened at not less than 10 percent of Project specs.
C8
initiating and indicating devices. Observe proper signal transmission according to class 28 46 21-45 3.5 ( E.5 )
of wiring used.
Test each initiating and indicating device for alarm operation and proper response at Project specs.
C9
the control unit. Test smoke detectors with actual products of combustion. 28 46 21-45 3.5 ( E.6 )

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Test Both Primary and Secondary Power: Verify by test that the secondary power Project specs.
C10
system is capable of operating the system for the period and in the manner specified. 28 46 21-45 3.5 ( E.8 )
Test the system for all specified functions according to the approved operation and
maintenance manual.Observe indicating lights, displays, signal tones, and annunciator Project specs.
C11
indications. Observe all voice audio for routing, clarity, quality, freedom from noise 28 46 21-45 3.5 ( E.7 )
and distortion, and proper volume level.
Interface with other systems: Provide standard software protocol and required
hardware to communicate and interface all information to the Video Surveillance Project specs.
C12
System, Access Control, fire-fighting systems, PAS, etc. as detailed in Specification and 28 46 21-25 2.4 ( K )
in the Specifications of the interfaced systems.
Project specs.
C13 Interface with other building services systems and with the BMS.
28 46 21-5 1.5 ( C )
Report of Tests and Inspections: Provide a written record of inspections, tests, and Project specs.
C14
detailed test results in the form of a test log. 28 46 21-45 3.5 ( G )
Tag all equipment, stations, and other components at which tests have been Project specs.
C15
satisfactorily completed. 28 46 21-45 3.5 ( H )
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-Material
Activity : MATERIAL RECEIVING FOR FIRE ALARM SYSTEM Receiving of Fire Alarm ELV
System-005

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No
ITEM NO. Check Points Reference pass Fail N/A Remarks

CHECK MATERIAL AS PER APPROVAL


Project specs.
C1 Check the Material as per approved Material submittal.
28 46 21.11
Product Data: Submit data on LV Main distribution board(MDB's), LV Sub-main distribution Project specs.
C2
board(SMDB's) fittings and accessories. 28 46 21.11
Manufacturer's Certificate: Certify that products meet or exceed specified Project specs.
C3
requirements. 28 46 21.11
Project specs.
C4 Shop Drawings: Include plans, elevations, details,
28 46 21.11

C5 Delivery note Manufactory

Remarks:

SEVEN
MBL
Third Party (if applicable)
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00002 Rev#00 Date: 23-Jan-24