100% found this document useful (1 vote)
292 views4 pages

METHOD STATEMENT FOR Demolition

The document provides a method statement for demolition work at a bubble brewery project. It outlines the scope of work, references, work program, equipment used, methodology, responsibilities, quality assurance, and health and safety measures including risk identification and management.

Uploaded by

sarifullah khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
292 views4 pages

METHOD STATEMENT FOR Demolition

The document provides a method statement for demolition work at a bubble brewery project. It outlines the scope of work, references, work program, equipment used, methodology, responsibilities, quality assurance, and health and safety measures including risk identification and management.

Uploaded by

sarifullah khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

ENLIVEN BUBBLE BREWERY PROJECT KANAKAPURA ROAD

METHOD STATEMENT FOR DEMOLITION WORK


CONTENTS

Sr. No. TITLE

1 INTRODUCTION

2 SCOPE OF WORK

3 REFERENCES AND STANDARD

4 WORK PROGRAMME

5 MACHINERIES & EQUIPMENT

6 METHODOLOGY

7 RESPONSIBITIES

8 QUALITY ASSURANCE

9 HSE – HEALTH, SAFETY AND ENVIRONMENT

9.1 RISK IDENTIFICATION

9.2 RISK MANGEMENT

GINA PMC
Signature

Name
Date

Page 1 of 4
1.INTRODUCTION
This Method Statement describes the specific safe working methods which will be used to carry out
the work. It gives details of how the work will be carried out and what health and safety issues and
controls are involved.
2. SCOPE OF WORK:
The scope of work involves the following:
1. Record of levels before application of Demolition
2. Safety measures
3. Application as per specification .

3.REFERENCES AND STANDARD:


This document should be read in conjunction with technical specification and GFC
drawings issued from M/s LATITUDE PMC for execution of work at site
4. WORK PROGRAMME:
The filling work shall be carried out in accordance with the submitted program to M/s LATITUDE
PMC.
5. MACHINERIES & EQUIPMENT:
For Demolition work following equipment are proposed to be used for the given scope of work:
1. Crowbar
2. Breaker Machine
3. Concrete cutter machine
4. Spade
5. Mortar Span
6. Personal Protective Equipment, Safety helmet, Safety gloves, Safety shoes, eye protection or
goggles, approved respirator, and safety jacket.

6.METHODOLOGY:

PROCEDURES
1. Section Includes: All work necessary for the removal and disposal of structures, foundations,
piping, equipment and roadways, or any part thereof including masonry, steel, reinforced
concrete, plain concrete, electrical facilities, and any other material or equipment shown or
specified to be removed.
2. Basic Procedures and Schedule: Carry out demolition so that adjacent structures, which are
to remain, are not endangered. Schedule the work so as not to interfere with the day-to-day
operation of the existing facilities. Do not block doorways or passageways in existing
facilities.
3. Additional Requirements: Provide dust control and make provisions for safety
4. Site Inspection: Visit the site and inspect all existing structures. Observe and record any
defects that may exist in buildings or structures adjacent to but not directly affected by the
demolition work. Provide the Client or representative with a copy of this inspection record

Page 2 of 4
and obtain the ENGINEER's and the Client or representative approval prior to commencing the
demolition.

5. General Safety: Provide warning signs, protective barriers, and warning lights as necessary
adjacent to the work as approved or required. Maintain these items during the demolition
period.
6. Existing Services: Undertake no demolition work until all mechanical and electrical services
affected by the work have been properly disconnected. Cap, reroute or reconnect
interconnecting piping or electrical services that are to remain in service either permanently
or temporarily in a manner that will not interfere with the operation of the remaining
facilities.
7. Hazards: Perform testing and air purging where the presence of hazardous chemicals, gases,
flammable materials or other dangerous substances is apparent or suspected, and eliminate
the hazard before demolition is started.
DEMOLITION REQUIREMENTS
1. Explosives: The use of explosives will not be permitted.
2. Protection: Carefully protect all mechanical and electrical equipment against dust and debris.
3. Removal: Remove all debris from the structures during demolition and do not allow debris to
accumulate in piles.
4. Access: Provide safe access to and egress from all working areas at all times with adequate
protection from falling material.
5. Protection: Provide adequate scaffolding, bracing railings, toe boards and protective covering
during demolition to protect personnel and equipment against injury or damage. Properly
secure the covers to prevent accidental movement.
6. Lighting: Provide adequate lighting at all times during demolition.
7. Closed Areas: Close areas below demolition work to anyone while removal is in progress.
8. Material Drops: Do not drop any material to any point lying outside the exterior walls of the
structure unless the area is effectively protected.

DISPOSAL OF MATERIALS
1. Final Removal: Remove all debris, rubbish, scrap pieces, equipment, and materials resulting
from the demolition. Take title to all demolished materials and remove such items from the
site.

7. RESPONSIBILITIES:
1. Site-in-charge: He shall be responsible for overall management of construction activities.
2. Site Engineer: He shall be responsible for execution in safe work method as per drawings. He
shall guide the supervisors and work men regarding the execution of work.
3. QA/QC Manager/Engineer: He shall be responsible for ensuring the quality of work as per the
specifications and standards.
4. EHS Manager/Engineer:
a. He shall be responsible for assisting to engineer/supervisor to ensure the safety of
workers during the progress of work.
b. Safety inductions of each staff and workers shall be done and daily PPE check to be
done and tool box talk shall be carried out before the start of work.
c. General safety awareness as well as particular safety precautions and guidelines for
activity to be carried out in that particular day shall be discussed.

Page 3 of 4
8.QUALITY ASSURANCE
1. Limits: Exercise care to break concrete well for removal in reasonably small masses. Where
only parts of a structure are to be removed, cut the concrete along limiting lines with a
suitable saw so that damage to the remaining structures is held to a minimum.

9. HSE – HEALTH, SAFETY AND ENVIRONMENT:


a) All necessary precautions shall be taken in accordance with HSE Plan.
b) Safety
c) All works shall comply with the safety procedure or instruction as set out in project safety
plan and municipality rules and regulations.
d) Basic Personal Protective Equipment ( PPE ) shall be worn by all staff or laborers.
e) All operatives shall be inducted before entering the site.
f) Toolbox talk shall be conducted before the activity

9.1 RISK IDENTIFICATION:


During the whole process of work the following risks are foreseen:
a) The risk of accidents caused by machinery and equipment.
b) The risk of traffic accidents during mobilization and demobilization of equipment and
material.
c) The risk of accident between excavator and dump truck delivering earth work material and
public vehicle or persons.
d) The risk of accidents caused by improper arrangement of road sign.

9.2 RISK MANAGEMENT:


a) GINA shall comply with all the necessary mitigation measure as stated in Job safety analysis.
The risk management can be separated into general safety consideration and those that are
particularly applicable to the actual work at site.

Hazard Identification & Risk Assessment (HIRA) Register to be followed at site .

Page 4 of 4

You might also like