PROJECT : 3 VILLAS OF ALI ABDULLAH ABDULGHANI @ WAKRAH

WORK SCHEDULE OF PROJECT

MEP WORKS

ROOM ACTIVITY STATUS COMPLETION REMARKS


VILLA 01
BASEMENT FLOOR
BS01 STAIR 100%
BS23 ELECTRICAL ROOM DB DRESSING PENDING
BS03 GYM LIGHT MARKING PENDING
BS05 HAIR DRESSING 100%
BS06 GYM BATH 100%
BS02 LOBBY 100%
BS18 GENERAL STORE 100%
BS17 LAUNDRY LIGHT MARKING PENDING CEILING WORK PENDING
BS16 KITCHEN STORE 100%
BS25 COLD STORE 100%
BS15 SERVICE ENTRANCE LIGHT MARKING PENDING CEILING WORK PENDING
BS14 KITCHEN AC GRILL ALLIGNMENT CEILING WORK PENDING
BS13 SERVICE STAIR 100%
BS08 LOBBY 100%
BS11 HANDWASH AND SHOWER 100%
BS09 SITTING 100%
BS10 MAIDS ROOM 100%
BS24 GARDEN STORE 100%
BS25 STORE 100%
BS20 DRIVER ROOM 100%
BS21 LOBBY 100%
BS22 BATH 100%
ENGLISH COURT 1 100%
ENGLISH COURT 2 100%
GROUND FLOOR
GR04 ENTRANCE HALL 100%
GR10 GUEST BEDROOM LIGHT MARKING PENDING CORNICHE IS PENDING
GR06 LOBBY 100%
GR08 BATH INSTALLATION OF ABLUTIION MIXER MATERIAL NOT RECEIVED YET
GR05 MALE MAJLISS 100%
DB DRESSING
GR11 STAIR MAIN CABLE PULLING PENDING
GR12 ARABIC MALE SITTING MAIN CABLE PULLING PENDING
GR20 FEMALE MAJLISS LIGHT MARKING CORNICHE IS PENDING
GR13A MAIN HALL 100%
GR16 KITCHEN AC GRILL ALLIGNMENT CEILING WORK PENDING
GR14 SILVER ROOM 100%
GR15 LOBBY AC DRAIN PIPE GOT DAMAGED BY CIVIL TEAM
GR19 LOBBY
GR21 BATH 100%
GR18 HALL 100%
GR13B MAIN HALL 100%
ELECTRICAL CABLE
GR23 GUARD HOUSE PENDING
PULLING,DB INSTALLATION
GR24 PANTRY 100%
GR25 BATH 100%
LANDSCAPE 100%
FIRST FLOOR
FR01 STAIR DB DRESSING PENDING
FR20-21 DINING ROOM 100%
FR24 STORE 100%
FR23 BATH DRAINAGE PIPE LAYING PENDING NEED CLEARENCE FROM WATER PROOFING TEAM

FR22 HALL 100%


FR25 BEDROOM 1 100%
FR16 HALL 100%
FR18 BEDROOM 2 100%
FR17 BATH DRAINAGE PIPE LAYING PENDING NEED CLEARENCE FROM WATER PROOFING TEAM

FR02 FAMILY LIVING ROOM 100%


FR13 HALL 100%
FR15 BABY ROOM 100%
FR14 BATH DRAINAGE PIPE LAYING PENDING NEED CLEARENCE FROM WATER PROOFING TEAM

FR05 HER DRESSROOM 100%


FR03 SITTING AREA 100%
FR04 HIS BATH DRAINAGE PIPE LAYING PENDING NEED CLEARENCE FROM WATER PROOFING TEAM

FR07 LOBBY 100%


FR06 HIS DRESSING ROOM 100%
FR08 MASTER BEDROOM LIGHT MARKING PENDING CORNICHE IS PENDING
FR09 TERRACE 100%
FR26 ROOF DECK 100%

FR26 TERRACE 100%

PENTHOUSE FLOOR
PH01 STAIR SPLIT AC INSTALLATION,COPPER PIPING ONGOING 95% ONLY PRESSURE TESTING PENDING
PH03 DRESSING ROOM SPLIT AC INSTALLATION,COPPER PIPING ONGOING 95% ONLY PRESSURE TESTING PENDING
PH09 BEDROOM SPLIT AC INSTALLATION,COPPER PIPING ONGOING 95% ONLY PRESSURE TESTING PENDING
SPLIT AC INSTALLATION,COPPER PIPING ONLY PRESSURE TESTING PENDING
PH04 SECRET ROOM MAIN CABLE PULLING ONGOING 95%
PRESSURE TESTING & DB DRESSING PENDING
PH02 SERVICE ROOM SPLIT AC INSTALLATION,COPPER PIPING,DB DRESSING ONGOING 90%
PH00 STORE SPLIT AC INSTALLATION,COPPER PIPING ONGOING 95% ONLY PRESSURE TESTING PENDING
COPPER PIPING FINISH;POWER CABLE PULLING
PH13 ROOF DECK OUTDOOR AC COPPER PIPING & CABLING ONGOING 50% PENDING
VILLA 3 COPPER PIPE INSTALLATION VILLA 3 COPPER PIPE INSTALLATION VILLA 3 COPPER PIPE INSTALLATION
VILLA 3 COPPER PIPE INSTALLATION VILLA 3 INDOOR SPLIT AC WORK VILLA 3 INDOOR SPLIT AC WORK
VILLA 3 CONCEALED FLUSH TANK VILLA 3 SHIFTING OF POINTS VILLA 1 LIGHT POINT FINALISING
VILLA 1 BOUNDARY WALL LIGHT POINTS VILLA 1 BOUNDARY WALL LIGHT POINTS VILLA 1 BOUNDARY WALL LIGHT POINTS
VILLA 1 FF TOILET VILLA 1 COPPER PIPE INSTALLATION VILLA 1 COPPER PIPE INSTALLATION
VILLA 1 COPPER PIPE INSTALLATION VILLA 1 COPPER PIPE INSTALLATION VILLA 1 KITCHEN DRAINAGE
VILLA 1 KITCHEN DRAINAGE