Quality in Construction Projects
Quality in Construction Projects
PROJECTS
What is Quality?
Chung (1999) states, “Quality may mean different things to different people. Some take it
to represent customer satisfaction, others interpret it as compliance with contractual
requirements, yet others equate it to attainment of prescribed standards” (p. 3). As
regards quality of construction, he further states, “Quality of construction is even more
difficult to define. First of all, the product is usually not a repetitive unit but a unique piece
of work with specific characteristics. Secondly, the needs to be satisfied include not only
those of the client but also the expectations of the community into which the completed
building will integrate. The construction cost and time of delivery are also important
characteristics of quality” (p. 3).
“Construction project quality is the fulfillment of the owner’s needs per defined scope
of works within a budget and specified schedule to satisfy the owner’s/user’s
requirements”. Per Chung (1999)
In the context of quality management, quality is not an expression of excellence in a
comparative sense. It is just an abbreviation for ‘desired quality’ that should be laid
down as explicitly as possible.
Crosby’s quality definition is “conformance to requirements” and that of Oakland is
“meeting the requirements.”
Philip B. Crosby’s philosophy is seen by many to be encapsulated in his five “Absolute
Truths of Quality Management.” These are
Quality Control
Quality control refers to the activities that are carried out on the production line to
prevent or eliminate causes of unsatisfactory performance. In the production of
ready-mixed concrete and fabrication of precast units, the major functions of quality
control are control of incoming materials, monitoring of production processes and
testing of the finished product.
Before production is commenced, an assessment is made of the minimum quality
needed to satisfy the stated requirements and how that quality can be consistently
achieved.
During production, the strength of the concrete is continuously monitored via routine
testing and statistical analysis of the test results, so as to detect at the earliest possible
moment when either the mean strength or the variability of strength shows a significant
change.
The quality of the finished works is controlled by way of inspection and testing as
construction proceeds. For example, the quality of concrete and other materials on site
is judged by random sampling and testing, and a thorough inspection of the finished
works is performed without exception before final acceptance. The major drawback of
this ‘inspectorial system’ of quality control is that it identifies the mistakes after the
event. Even high strength concrete can be defective if it is not properly compacted and
cured, and the potential hazard of steel corrosion will not surface until some years later.
1. Scope of work
2. Time
3. Budget
Cost of quality refers to the total cost incurred during the entire life cycle of construction
project in preventing nonconformance to owner requirements (defined scope). There are
certain hidden costs that may not directly affect the overall cost of the project; however,
it may cost the consultant/designer to complete the design within the stipulated
schedule to meet owner requirements and conformance to all the regulatory
codes/standards, and for the contractor to construct the project within the stipulated
schedule meeting all the contract requirements. Rejection/non approval of
executed/installed works by the supervisor due to noncompliance with specifications
will cause the contractor loss in terms of
● Material
● Manpower
● Time
The contractor shall have to rework or rectify the work, which will need additional
resources and will need extra time to do the work as specified. This may disturb the
contractor’s work schedule and affect execution of other activities. The contractor has
to emphasize the “Zero Defect” policy, particularly for concrete works. To avoid rejection
of works, the contractor has to take the following measures:
● Rework
● Rectification
● Rejection of checklist
● Corrective action
Appraisal Costs
● Design review/preparation of shop drawings
● Preparation of composite/coordination drawings
● On-site material inspection/test
● Off-site material inspection/test
● Pre-checklist inspection
Prevention Costs
● Preventive action
● Training
● Work procedures
● Method statement
● Calibration of instruments/equipment
Quality System
A company’s quality system is its blue-print for quality management. It is a means of
ensuring the quality of the product.
The quality system is to be fully documented in the corporate level by the Quality
Manual which contains the Quality Policy, Organizational structure, Quality Procedures,
Work Instructions and other documents. The quality procedures and work instructions
together ensure consistency of operations.
On the project basis, the quality system is implemented through a quality plan. A quality
plan is a document setting out the specific quality activities and resources pertaining to
a particular contract or project. Among other things, it makes reference to an
assortment of documented procedures of the quality system. It may also contain
project-specific procedures or work instructions which only apply to the particular
project. While the quality manual is intended to apply across the company’s entire
organization, the quality plan is prepared specifically for the project in question. It is
virtually the quality manual of the project.
Training
All personnel carrying out quality-related functions should have the skills and
experience necessary for the tasks. It is the responsibility of management to identify
training needs and to provide appropriate training.
Training is also essential in the use of quality procedures and work instructions,
including the correct way of filling in the related forms. Such training is preferably made
a regular event. Training programs range from on-the-job training to short courses
offered by professional bodies. There should be some means of assessing the skills of
the trainees completing the training program. For certain trades, such as welding and
nondestructive testing, the level of competence is normally demonstrated by
certification.
Records of training should be maintained. This is conveniently done by updating the
personal record to include the achievement attained in the training program.
Quality Control in Design Phase
● To have best use of the money, that is, to have maximum profit or services at a
reasonable cost
● On time completion, that is, to meet the owner’s/user’s schedule
● Completion within budget, that is, to meet the investment plan for the facility
Feasibility Study
Once the owner’s need is identified, the traditional approach is pursued through a
feasibility study or an economical appraisal of owner needs or benefits, also taking into
account the many relevant moral, social, environmental, and technical constraints. The
feasibility study takes its starting point from the output of the project identification
need.
The flow chart illustrates a preliminary appraisal and the steps in the project
identification.
Steps in project identification
Time Schedule
The duration of a construction project is finite and has a definite beginning and a
definite end, therefore during the conceptual phase the expected time schedule for the
completion of the project/facility is worked out. The expected time schedule is
important from both financial and acquisition of the facility by the owner/end user. It is
the owner’s goal and objective that the facility is completed in time. Figure below
illustrates a time schedule for a typical construction project.
Typical time schedule
Identification of project team
Most construction projects involve three major groups or parties:
1. Owner: A person or an organization that articulated the need for the facility and
responsible for arranging the financial resources for the creation of the facility.
2. Designer/consultant: This consists of architects, engineers, or consultants. They are the
owner’s appointed entity accountable for converting the owner’s conception and need
into a specific facility with detailed directions through drawings and specifications,
within the economic objectives and schedule. They are responsible for the design
process and assist the owner in preparation of tender and contract documents. The
owner may engage the designer to supervise construction.
3. Contractor: A construction firm engaged by the owner to complete the specified facility
by providing the necessary staff, workforce, materials, equipment, tools, and other
accessories to complete the project to the satisfaction of the owner/end user in
compliance with the contract documents.
The owner is the first member of the project team. The owner’s relationship with other
team members and his or her responsibilities depend on the type of deliverable system
the owner would prefer to go with. There are many types of contract delivery systems;
however, design/bid/ build is the most predominantly used contracting system preferred
by the owners.
For the design/bid/build type of contract system, the first thing the owner has to do is
select design professionals/consultants. Generally, the owner selects a
designer/consultant with whom he or she has worked before with satisfactory results.
The owner can use his or her preferred designer/consultant or select one by obtaining
proposals from several design professionals/consultants. The owner may contract a
designer or A&E to provide site supervision during the construction process. Thus, the
designer or A&E firm acts as the prime professional to design the project and also
supervises the construction.
The table below illustrates the contribution of various participants during all the phases
of the construction project life cycle for the design/bid/build type of contracting system.
● Code Analysis
● Zoning Analysis
● Topographical Survey
● Boundary Survey
● Existing Utility Survey
● Geotechnical Survey
● Environmental Survey
● Space Planning
● Alternative Layouts
● Alternative Cost Analysis
● Traffic Impacts
Preliminary Engineering and Design
Preliminary design is mainly a refinement of the elements in the conceptual design
phase. Preliminary design is also known as schematic design. During this phase, the
project is planned to a level where sufficient details are available for the initial cost and
schedule. This phase also includes the initial preparation of all documents necessary to
implement the facility/construction project. The central activity of preliminary design is
the architect’s design concept of the owner’s objective, which can help make the
detailed engineering and design for the required facility. Preliminary design is a
subjective process transforming ideas and information into plans, drawings, and
specifications of the facility to be built
Preliminary design is the basic responsibility of the architect (designer/ consultant or
A&E). In the case of building construction projects, a preliminary design determines
● Layout Refinement
● Available Utility Service Analysis
● Architectural and Engineering Systems Definition
● Preliminary Plans, Elevations, Sections, Schedules
● Discipline Coordination
● Outline Technical Specifications
● Preliminary Analyses and Calculations
● Preliminary Construction Schedule
● Preliminary Staging Plans
● Preliminary Cost Estimate
● Completion of Site Surveys
● Finalize Geotechnical Investigations
● Finalize Environmental Investigations
General Scope of Works/Basic Design
The purpose of a general scope of works is to provide sufficient information to identify
the works to be performed and to allow detail design to proceed without significant
changes that may adversely affect the project budget and schedule.
At the preliminary design stage, the scope must define deliverables, that is, what will be
furnished. It should include a schedule of dates for delivering drawings, specifications,
calculations and other information, forecasts, estimates, contracts, materials, and
construction. The designer develops a design concept with the plan, elevation, and other
related information that meet the owner’s requirements. The designer also develops a
concept of how various systems such as heating and cooling systems, communication
systems, etc., will fit into the system.
Budget
Based on the preliminary design, the budget is prepared by estimating the cost of
activities and resources. The preparation of the budget is an important activity that
results in a timed phased plan summarizing the expected expenses toward the contract
and also the income or the generation of funds necessary to achieve the milestone. The
budget for a construction project is the maximum amount the owner is willing to spend
for design and construction of the facility that meets the owner’s need. The budget is
determined by estimating the cost of activities and resources and is related to the
schedule of the project. If the cash flow or resulting budget is not acceptable, the
project schedule should be modified. It is required that while preparing the budget, the
risk assessment of the project is also performed.
Schedule
After the preliminary scope of works, the preliminary design and budget for the
facility/project are finalized; the logic of the construction program is set. On the basis of
logic, a critical path method (CPM) schedule (bar chart) is prepared to determine the
critical path and set the contract milestones.
Contract Terms and Conditions
Normally it is the consultant/designer team that is responsible for developing a set of
contract documents that meets the owner’s needs, and specifies the required level of
quality, budget, and schedule. At this stage, a contract exists between the consultant
and the client for the development of the project, and any good management test will
demand that the contract be clearly understood by all parties associated with it. There
are numerous combinations of contract arrangements for handling the construction
projects; however, design/bid/build is predominantly used in most construction project
contracts. This delivery system has been chosen by owners for many centuries and is
called the traditional contracting system. In the traditional contracting system, the
detailed design for the project is completed before tenders for construction are invited.
The detailed engineering is carried out by the consultant/design professional to make
the project qualitative and economical.
Based on the type of contracting arrangements with which the owner would like to
handle the project, necessary documents are prepared by establishing a framework for
execution of the project. Generally, FIDIC’s model conditions for international civil
engineering contracts are used as a guide to prepare these contract documents.
Preliminary specifications and documents are prepared in line with model contract
documents
Value Engineering Study
In the construction industry, the definition of value engineering (VE) is the method used
to solve problems, identify and eliminate unwanted costs and improve function and
quality. VE is a systematic, multi-disciplined approach designed to optimize the value of
money spent on the project.
It is the method that the project team employs to improve the value of the project by
examining the function of each item or element and its associated cost. By weighing the
function-to-cost ratio, the project team can make suggestions for alternate construction
methods, designs, or materials that improve the value of the project.
Value engineering (VE) studies can be conducted at various phases of a construction
project; however, the studies conducted in the early stage of a project tend to provide
the greatest benefit. In most projects VE studies are performed during the schematic
phase of the project. At this stage the design professionals have considerable flexibility
to implement the recommendations made by the VE team, without significant impacts
on the project’s schedule or design budget.
● Soil stability
● Alignment with road width, property lines
● Speed
● Intersections/interchanges
● No. of lanes, width
● Right-of-way lines
● Exits, approaches, and access
● Elevation datum
● Super elevation
● Clearance with respect to railroad, roadway, navigation (if applicable)
● High and low levels of water (if applicable)
● Utilities passing through the bridge length
● Slopes
● Number and length of span
● Live loads, bearing capacity
● Water load, wind load, earthquake effect (seismic effect)
● Bridge rails, protecting screening, guard rails, barriers
● Shoulder width
● Footings, columns, and piles
● Abutment
● Beams
● Substructure
● Super structure, deck slab
● Girders
● Slab thickness
● Reinforcement
● Supporting components, deck hanger, tied arch
● Expansion and fixed joints
● Retaining walls, crash wall
● Drainage
● Lighting
● Aesthetic
● Sidewalk, pedestrian and bike facilities
● Signage, signals
● Durability
● Sustainability
Highways
Designer should use relevant authorities’ design manual and standards and consider the
following point while designing highways. (Ex. AASHTO, ACI, ASTM etc.)
● Type of highway
● Soil stability
● Speed
● No. of lanes, width
● Shoulder width
● Gradation
● Type of pavement and thickness
● Right-of-way lines
● Exits, approaches, access, and ramp
● Superelevation
● Slopes, curvature, turning
● Median, barriers, curb
● Sidewalks, driveways
● Pedestrian accommodation
● Bridge roadway width
● Drainage
● Gutter
● Special conditions, such as snow and rain
● Lighting
● Signage, signals
● Durability
● Sustainability
Architectural Design for Building
● Intent/use of building/facility
● Property limits
● Aesthetic look of the building
● Environmental conditions
● Elevations
● Plans
● Axis, grids, levels
● Room size to suit the occupancy and purpose
● Zoning per usage/authorities requirements
● Identification of zones, areas, rooms
● Modules to match with structural layout/plan
● Number of floors
● Ventilation
● Thermal insulation details
● Stairs, elevators (horizontal and vertical transportation)
● Fire exits
● Ceiling height and details
● Reflected ceiling plan
● Internal finishes
● Internal cladding
● Partition details
● Masonry details
● Joinery details
● Schedule of doors and windows
● Utility services
● Toilet details
● Required electromechanical services
● External finishes
● External cladding
● Glazing details
● Finishes schedule
● Special equipment
● Fabrication of items, such as space frame, steel construction, retaining wall, having
special importance for appearance/finishes
● Special material/product to be considered, if any
● Any new material/product to be introduced
● Conveying system core details
● Ramp details
● Hard and soft landscape
● Parking areas
Concrete Structures for Buildings
● Type of foundation
● Energy-efficient foundation
● Design of foundation based on field and laboratory tests of soil investigation that give
the following information:
o Subsurface profiles, subsurface conditions, and subsurface drainage
o Allowable bearing pressure, and immediate and long-term settlement of footing
o Coefficient of sliding on foundation soil
o Degree of difficulty for excavation
o Required depth of stripping and wasting
o Methods for protecting below-grade concrete members against impact of soil and
groundwater (water and moisture problems, termite control, and radon where
appropriate)
o Geotechnical design parameters such as angle of shear resistant, cohesion, soil density,
modulus of deformation, modulus of subgrade reaction, and predominant soil type
o Design loads such as dead load, live load, wind load, and seismic load
● Grade and type of concrete
● Size of bars for reinforcement and the characteristic strength of bars
● Clear cover for reinforcement for
o Raft foundation
o Underground structure
o Exposed to weather structure such as columns, beams, slabs, walls, and joists
o Not exposed to weather columns, beams, slabs, walls, and joists
● Reinforcement bar schedule, stirrup spacing
● Location of columns in coordination with architectural requirements
● Number of floors
● Height of each floor
● Beam size and height of beam
● Superstructure:
o Columns
o Stairs
o Walls
o Beams
o Slabs
● Deflection that may cause fatigue of structural elements; cracks or failure of fixtures,
fittings, or partitions; or discomfort to occupants
● Movement and forces due to temperature
● Equipment vibration criteria
● Reinforcement bar schedule, stirrup spacing
● Shaft and pit for conveying system
● Building services to fit in the building
● Environmental compatibility
● Excavation
● Dewatering
● Shoring
● Backfilling
● Property limits/surrounding areas
External Works for Building Facility (Infrastructure and Road)
External works are part of the contract requirements of a project that involves
construction of a service road and other infrastructure facilities to be connected to the
building and also includes care of existing services passing through the project
boundary line. The designer has to consider the following while designing external
works:
● Grading material
● Asphalt paving for road or street
● Pavement
● Pavement marking
● Precast concrete curbs
● Curbstones
● External lighting
● Cable routes
● Piping routes for water, drainage, storm water system
● Trenches or tunnels
● Bollards
● Manholes and hand holes
● Traffic marking
● Traffic signals
● Boundary wall/retaining wall, if required
Contract Documents and Specifications
Preparation of detailed documents and specifications per master format is one of the
activities performed during this phase of the construction project. The contract
documents must specify the scope of works, location, quality, and duration for
completion of the facility.
As regards the technical specifications of the construction project, master format
specifications are included in the contract documents. The master format is a master
list of section titles and numbers for organizing information about construction
requirements, products, and activities into a standard sequence.
Design Reviews
A design review is a detailed, analytical, and unbiased approach used to verify that the
appropriate deliverables (e.g., studies, final drawings, technical specifications, and
construction bid documents) are being prepared and that the designer is maintaining
pace with the budget and project schedule.
Design reviews involve a formalized, structured approach to assure interdisciplinary
coordination and compliance with design criteria and environmental, site, and
operational constraints. Design reviews are conducted to assure quality of products in
design development. Design reviews generally occur at the following points in the
design process: design criteria, conceptual, preliminary engineering, or 30 percent, 60
percent, 90 percent, 100 percent, and bid documents.
The project manager coordinates and oversees reviews at the design criteria,
conceptual, preliminary engineering, 30%, 60%, 90%, 100%, and bid documents stages.
The percent refers to the approximate ratio of design budget spent over total design
budget. Reviews at these points in design are key control points to the design
management process.
For each design review, the design manager will ensure the following key objectives are
accomplished, as applicable to the particular review:
● 60-Percent Review – The project manager and/or design manager will make certain that
all major features of design are progressing in accordance with prior direction, major
engineering and VE decisions; and most drawings, specifications, and other documents
are well advanced. Usually a constructability review is conducted at this point or at the
latest before the 90 percent submittal.
● 90-Percent Review – The drawings and specifications provided by the design team are
to be nearly completed and checked. Therefore, the project manager and the design
manager will need to perform an extensive review since at this point in the design
development cycle, this will be the last major design review. In addition, you and the
design manager will verify that comments from the 60-percent review have been
addressed. When applicable these drawings should be sent to the permitting
Owner/Agency for a plan check. The construction cost estimate should also be verified
against the budget established for the project.
● 100-Percent Review – The drawings and specifications are to be finished by the design
team and checked. In addition, the project manager and/or design manager will verify
that comments from the 90-percent review have been addressed. Only incorporation of
comments arising from this review, plus sign-off and approval should be required to
complete the construction bid documents.
● Bid Document Verification – After delivery of all completed, signed, and sealed original
drawings by the designer, the Project Manager and the design manager are to verify that
comments from the 100-percent review have been satisfactorily resolved, construction
cost estimates are in line with budgets, and appropriate Owner/Agency or individual
approvals can be given. Further comments that do not pertain to the 100percent review
should not be considered unless the design is in error because of an unsafe condition,
non-constructability of work as shown, or new work that was not previously shown. At
this point the Owner/Agency procurement staff will add the necessary contractual
provisions to the packages.
Constructability Reviews
Later in the design process, the design team will need to perform constructability
reviews as part of the design process. Constructability review is a project management
technique to review construction processes from start to finish during pre-construction
phase. It is to identify obstacles before a project is actually built to reduce or prevent
errors, delays, and cost overruns.
Constructability reviews are necessary prior to completion of final design and preferred
at 60 percent design to make certain what is depicted on the final drawings, technical
specifications, and construction bid documents can be built. Participants for
constructability reviews can come from within your Owner/Agency, the design team,
independent consultants, or contractors. The constructability reviews should be prior to
completion of 90 percent and preferably shortly after 60 percent of the design. The
purpose of constructability review is to:
1. Reference to contract drawings. This helps the A&E (consultant) to compare and review
the shop drawing with the contract drawing
2. Detail plans and information based on the contract drawings
3. Notes of changes or alterations from the contract documents
4. Detailed information about fabrication or installation of works
5. Verification of all dimensions at the job site
6. Identification of product
7. Installation information about the materials to be used
8. Type of finishes, color, and textures
9. Installation details relating to the axis or grid of the project
10. Roughing in and setting diagram
11. Coordination certification from all other related trades (subcontractors)
The shop drawings are to be drawn accurately to scale and shall have project-specific
information in it. They should not be reproductions of contract drawings.
Immediately after approval of individual trade shop drawings, the contractor has to
submit builder’s workshop drawings, composite/coordinated shop drawings taking into
consideration the following at a minimum.
B—Materials
Similarly, the contractor has to submit the following, at a minimum, to the
owners/consultants to get their review and approval of materials, products, equipment,
and systems. The contractor cannot use these items unless they are approved for use in
the project.
B—Samples
The contractor has to submit (if required) the samples from the approved material to be
used for the work. The samples are mainly required to
Procedure
A procedure is an established method for a specific process, describing step-by-step the
activities that constitute the process and indicating the persons responsible for these
activities.
Categories of Procedures:
1. Introduction
2. Purpose and Scope of Work
3. Reference Specifications and Standards
4. Responsibilities
5. Procedure
6. Records
1. Introduction
2. Purpose and Scope of Work
3. Reference Specifications and Standards
4. Responsibilities
5. Required Equipment/tools
6. Materials
7. Work Execution
8. Attachment
● ITP and Checklist are prepared and issued by the Quality Engineer
● Reviewed by the Quality Manager and Construction Manager
● Approved by the Project Manager
● Submitted to the Client or his Representative for approval
● QA/QC Engineer shall maintain a Register of all approved ITPs and Checklists
● Copy of the approved ITPs and checklists are provided to Quality Inspectors and
contractor for implementation
Any activity at any stage of the construction that contributes to quality assurance can
be specified within the ITP. For example, an ITP may include an item which specifies that
only competent persons are to undertake works and therefore would also summarize
how this will be checked (i.e. ‘inspected’) prior to works commencing such as checking
and recording qualifications.
Thus, the term ‘inspection’ may not only be a reference to the physical construction
works but could be a document, an item of equipment used for the works, a
qualification etc. which should be inspected.
Additionally, it is very important that an ITP details the evidence which will be provided
to demonstrate the ‘inspection’ or check has been satisfactorily completed and where it
will be filed for future reference or collected for inclusion in the building documentation
handed over at the end of the project.
In summary, the ITP provides a summary of the what, how, why, when, and who for
quality of an element of the works, ex.:
● Witness Point (W) – The activity will be verified by the party / individual in testimony to
the satisfactory completion of the item.
● Inspection (I) – The activity will involve a party or person undertaking a formal
verification and recording.
● Hold Point (H) – The next stage must not commence until the item is completed
satisfactorily.
● Surveillance (S) – A ‘surveillance’ is essentially a mini audit which reviews an aspect of
the works in more detail to verify compliance.
● Audit (AU) – periodic, independent, and documented examination and verification of
activities, records, processes, and other elements of a quality system to determine their
conformity with the requirements of a standard.
Construction Specifications,
Standards, and Tolerances
Specifications
The specifications are part of the contract documents that define the qualitative
requirements of the project that is to be built. The dictionary defines specification as “a
detailed description of requirements, dimensions, materials, etc., as of a proposed
building, machine, bridge, etc.,” and further as “the act of making specific.” The role of
the drawings is to define the geometry of a project, including dimensions, form, and
details. The specifications are intended to complement this by defining the nature of the
materials that are to be used and the description of the workmanship and procedures to
be followed in constructing the project.
Generally, most specifications can be divided into three main elements, or parts:
● Work that was not built as indicated in the approved issued For Construction Drawings
(FCD)
● Work that fails to meet specified tolerances as established in the project specifications
● Work that is being performed using non-approved methods or standards
● Failure to follow the approved testing and inspection plan
● Testing results demonstrate that the product does not meet established and approved
standards
● Material used that has not been approved as a substitute (equal or similar)
● Design is not accurate and does not represent actual field conditions
● Approved procedure was not followed, and quality defects have been identified by the
project team
Who Can Issue an NCR?
A non-conformance report can be issued by any of the project team members. The
report must present a non-debatable fact and include clear and sufficient backup
information that supports the claim. The NCR follows agreed-upon conditions for
tracking and closing the report after appropriate corrections are made.
Non-conformance reports often are used as training tools for team leaders to train other
employees to help prevent similar situations from happening again.
Non-Conformance Report must include at a minimum the following information:
● What is the main reason for the NCR or what went wrong
● Why the work doesn’t meet specifications
● What can be done to prevent the problem from happening again
● Explanation of corrective action taken or to be taken
● Key players involved in the NCR and specifications affected under the NCR
In the course of reviewing nonconforming work, the cause of the incident and the
situation leading to it are usually revealed. Corrective action is necessary to eliminate
the cause of nonconformance.
Corrective Action Report (CAR) – a report of action taken that ensure that the cause
which has resulted in a non-conformance is identified and corrected (i.e a
non-conformance has occurred)
Prompted by the actual nonconformity discovered, the investigation is usually extended
to similar situations in which potential nonconformities exist. (Potential
nonconformities may also be revealed) Appropriate steps have to be taken to prevent a
potential problem developing into a real one.
A report of action taken to ensure that the cause which may result in a nonconformance
is identified and corrected is a Preventive Action Report (PAR). (i.e. the potential for a
non-conformance to occur exist)
Recipient of an NCR, must act promptly and at a minimum follow these steps for a quick
resolution:
Quality Records
Quality records are intended to demonstrate conformance to specified requirements
and effective operation of the quality system. Accordingly, these records fall into two
categories which are filed separately.
1. Project-specific records: These records, which include pertinent records from the
subcontractors, provide evidence showing that the required standards of materials and
workmanship have been attained.
2. System-related records: These records should indicate that incidents of
non-conformance and client complaints diminish in number with maturity of the system
Quality records may be in the form of hard copy or electronic media. Proper
maintenance of quality records is an important aspect of a quality system. They should
be stored in such a manner as to facilitate retrieval yet preventing unauthorized access.
Hence, they should be suitably identified, indexed, secured against damage and
deterioration, filed and placed under the control of a designated personnel.
5S of Good Housekeeping
5S is a systematic approach for improving quality and safety by organizing a workplace.
It is a methodology that advocates
The contractor is responsible for providing all the resources to build the project/facility.
These resources are mainly:
1. Manpower
2. Construction equipment, machinery, and tools
3. Material to be used/installed in the project
4. Consumables
The following points have to be considered while planning the layout for storage of
construction material:
Punchlist
A punch list is a document that is prepared close to the end of a construction project
and issued by the appropriate inspector (typically, the architect/engineer, project
engineer or employer’s agent). It lists any faults that are identified or works that do not
conform to the specifications, which should be rectified prior to a certificate of
substantial completion being issued.
Generally, punch list refers to a process that takes place prior to substantial completion
when an area is considered complete by a contractor and is offered ready for
inspection. It is a slang expression widely used in the construction industry to define the
process of inspection necessary to compile a list of minor defects or omissions in
construction projects for the contractor to rectify.
The process of inspection and going through a punch list is usually performed close to
the end, if not right at the end, of construction so that the work as a whole can be
reviewed and checked. The list of items to be completed or corrected is compiled by the
contractor and submitted to the employer’s representative.
Final Inspection
When the contractor believes that all punch list items have been taken care of, the owner is
notified that the project is ready for its final inspection. This inspection is less time as it involves
ascertaining only whether those items on the final punch list have been corrected. Fewer people
are likely to be involved, although the contractor, a member of the design professional team and
an owner’s representative will participate. Depending on the outcome of this inspection, the
owner and management team will declare the project to be either complete or substantially
complete and will issue an appropriate certificate.
As-Built Documentation
The project manager should assure the construction contract calls for the contractor to mark up
the changes on the drawings and specifications as they occur during construction and turn in a
set of marked up drawings and specifications. Under general direction of the project manager,
the construction manager verifies the construction contractor is keeping the drawings up to
date. The project manager should provide in the agreement with the designer of record scope
for the designer to review, approve, and produce the final as-built drawings.
Testing and Commissioning
Commissioning Plan
The commissioning plan is a living document and a supporting document to the Project
Management Plan. The plan should be started early in the design phase and further refined with
additional details as information becomes available at the completion of design and well in
advance of construction completion. Under the general direction of the project manager, the
commissioning manager will prepare the commissioning plan. The plan provides guidance and
details the key elements of the commissioning process including roles and responsibilities,
critical equipment list, OFE, integrated testing, safety and security and emergency preparedness,
O&M manuals, training, as-built drawings, and the warranty administration. The commissioning
plan is prepared with significant input from all internal and external stakeholders in close
coordination with the design and construction teams. Prepared properly and used as a living
document the plan will assure all requirements are properly incorporated in the design and
construction bid documents and executed during construction and commissioning.
As-Built Plan
The commissioning manager will use the as-built documentation as necessary to commission
the project. As-built drawings will save significant life cycle costs and avoid potential safety
hazards during operations and life of the facilities. The commissioning manager will review the
final as-built drawings and assure they are a part of the final commissioning report.
Testing
During services installation various tests will be undertaken known as ‘static
testing’. This testing is normally undertaken to prove the quality and workmanship of the
installation. Such work is undertaken before a certificate is issued to ‘enliven’ (i.e. to
make live) services whether electrically or otherwise. Examples of this sort of testing
are: Pressure testing ductwork and pipework, and undertaking resistance checks on
cabling.
All work is checked and inspected on a regular basis while the construction is in
progress; however, there are certain inspection and tests to be carried out by the
contractor in the presence of the owner/consultant. These are especially for
electromechanical systems, conveying systems, and electrically operated equipment,
which are energized after connection of permanent power supply. Testing of all these
systems starts after completion of installation works. By this time, the facility is
connected to a permanent electrical power supply, and all the equipment is energized.
Commissioning
Upon completion of static testing, dynamic/integrated testing can be undertaken, this is
called “commissioning”. Commissioning is carried out to prove that the systems
operate and perform to the design intent and specification.
This work is extensive and normally commences by issuing a certificate permitting the
installation to be made ‘live’, i.e. electrical power on. After initial tests of phase rotation
on the electrical installation and checking fan/pump rotation (in the correct direction),
the more recognized commissioning activities of balancing, volume testing, load bank
testing, etc. begin.