New Product and Process Development SOP
New Product and Process Development SOP
Project Committee:
New Product Technical Committee is responsible for designing and documenting inputs and outputs
of design and development activities.
3. Head / GM (Procurement)
1
Initiation of Ideas
New product ideas are derived from either one or more of the following groups:
• Customer requirements
Idea Screening
These ideas and requirements are reviewed by the ED (Technical) and VP (Marketing), recorded on
Project Initiation Form approved by the MD and is forwarded to EDT for further working.
Preliminary Elimination:
1. Promising Ideas
2. Marginal Ideas
3. Rejected Ideas
Screening:
Basis of screening
2. Product Price
4. Manufacturing Costs
5. Rate of Return
2
Concept Development and Testing
Design & Development Planning: Executive Director Technical [EDT] prepares Design and
Development Plan for the project indicating the design phases, departmental interfaces during the
design process, tentative planned duration of each design phase, etc. The tentative durations are
only minimum projected durations and may vary depending on the availability of resources and
personnel. The plan is forwarded to Manager Product Development along with the Project Initiation
Form for execution.
4. Time of consumption
Overall:
1. Target Market
3. Product Positioning
4. Sales
5. Market share
6. Profit Goals
1. Planned price
2. Distribution
3. Marketing Budget
3
Literature survey and innovator/competitive product development analysis
Literature survey of available methods, similar applications, similar products, related testing, etc.
with references if prepared by Manager Product Development and submitted to EDT.
Manager Product Development checks innovator / competitor’s product or technology and submits
report to EDT.
Product Development Team (PD Team) under the supervision of Head/Manager - Product
Development starts working on the tentative design of the intended product with 3D
Concept/Visuals and required inputs for Design and Development.
1. Material properties
2. Loading criteria
3. Environmental criteria
7. Formwork criteria
NPTC approves design inputs from Product Development Team and supports in necessary data
capturing.
4
Design and Development
Product Development Team (PD Team) shall consider the following and prepare a design report:
2. duration required,
3. nature of complexity,
9. design controls,
13. level of control expected from other departments, customers and other interested parties
5
Advanced Production and Quality Planning
Once the product design is reviewed, verified and validated, the NPTC takes decision on order of
formwork and proceeds for the Advanced Production and Quality Planning (APQP Process).
Inspection method,
Design review Design verification plan Quality Planning
equipment and tools
6
Design and Development Documented Output
1. Design Report
2. Specifications
3. Raw material
To be completed….
Stability study
1. GM (Operations) prepares a stability protocol for the first 3 samples of products. An SOP may
be developed.
2. Stability study may be carried out and reported every 6 months. Any deviations/failures may
be recorded, and the results maybe intimidated to EDT.
3. EDT holds a Design Review Meeting with Team where probable causes of deviation / failures
are discussed and modification in the product are proposed and approved.
4. The decisions / modifications in the intended product are implemented through Process
revision Form.
Minimum 3 reviews: