DAILY ACTIVITIES REPORT

Improvement Emergency Access Installation at Wayang Windu Power Station Control Room

PROJECT NAME : Improvement Emergency Access Installation at Wayang Windu REPORT NO : BST/EAI-WW/I-033
LOCATION : Power Station Control Room DAY / DATE
CONTRACT NO : 4200003155 PREPARED BY : Nadia Nur Islami
CLIENT : Star Energy Geothermal Wayang Windu Limited SUBMITTED TO : SEGD Representative
CONTRACTOR : PT. Bagus Sarana Teknik
1. Weather Condition :
Time 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 C : Clear TR : Tiny Rain
C C C C C C C C C C CL : Cloudy HR : Heavy Rain
2. Construction Highlights :
A. This Day Construction: B. List of next day contruction priority:
1 Fabrication Railing 1 Continue Fabrication Railing
2 2
3 3
4 4
5 5
4. HSE Performance: (Describe HSE activities summary performed by Contractor)
Activities Total Activities Total
1 Toolbox meeting 1 4
2 5
3 6

5. Daily Resources Record :


1 HSE 1 Person 7 Fitter 2 Person
2 Project Control 1 Person 8 Mekanik 1 Person
3 Helper 2 Person 9 Person
4 Material control 1 Person 10 Person
5 Supervisor 1 Person 11 Person
6 Welder 2 Person 12 Person
Total Present Today 11 Person
6. Project Photo Records: (inserts photo of relating project including HSE activities, constructions, installation, etc)
DAILY ACTIVITIES REPORT
Improvement Emergency Access Installation at Wayang Windu Power Station Control Room

PROJECT NAME : Improvement Emergency Access Installation at Wayang Windu


OVERALL WORK PROGRESS
LOCATION : Power Station Control Room
CONTRACT NO : 4200003155 Previous Today
CLIENT : Star Energy Geothermal Wayang Windu Limited
26.09% 26.38%
CONTRACTOR : PT. Bagus Sarana Teknik
7. Progress ITP001-FE
No Desescription Work Item UoM Qty Plan Weight % Qty Actual2 Progress2
1 Mob & Demob Mob & Demob 4.75% 2.37%
1.1 Mob & Demob Mob & Demob Lot 1.00 4.75% 0.50 2.37%
2 Railing Railing 12.35% 3.15%
2.1 STEEL GRATING Ladder treads Kg 455.55 2.19%
2.2 STEEL GRATING Bordes Kg 852.35 4.34%
2.3 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Bordes Kg 443.88 3.00% 266.33 1.80%
2.4 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Diagonal Kg 400.95 2.71% 200.48 1.35%
2.5 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Elbow 90 Kg 7.00 0.12%
3 Structur Structur 41.91% 13.43%
3.1 WF BEAM VERTIKAL (300x150x9x6,5) WF BEAM VERTIKAL (300x150x9x6,5) Kg 2,011.16 9.68% 880.47 4.24%
3.2 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM 1 Kg 1,341.90 6.46% 496.50 2.39%
3.3 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM 2 Kg 656.04 3.16% 262.42 1.26%
3.4 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM EXTEND Kg 149.41 0.72% - 0.00%
3.5 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM BRACING Kg 66.90 0.32% - 0.00%
3.6 C BEAM (200x80x11x7,5) DIAGONAL Kg 811.80 3.91% 194.83 0.94%
3.7 C BEAM (200x80x11x7,5) BORDES Kg 378.84 1.82% 98.50 0.47%
3.8 C BEAM (100x50x7,5x5) ROOF H1 Kg 89.95 0.43% - 0.00%
3.9 C BEAM (100x50x7,5x5) ROOF H2 Kg 156.01 0.75% - 0.00%
3.10 L BEAM BRACING (80x80x6) LENGTH 2,9 Kg 211.70 1.02% 82.56 0.40%
3.11 L BEAM BRACING (80x80x6) LENGTH 3,3 Kg 96.36 0.46% 37.58 0.18%
3.12 ANCHOR VIBRATION DAMPER PAD/BEARING PAD/KARET JEMBATANEA
(RUBBER) 4.00 3.74% - 0.00%
3.13 RIB PLATE 16mm Kg 61.20 0.29% 28.15 0.14%
3.14 RIB PLATE 9mm Kg 40.17 0.19% 18.07 0.09%
3.15 RIB PLATE 6mm Kg 80.64 0.39% 36.29 0.17%
3.16 RIB PLATE GUSSET PLATE 9mm Kg 29.48 0.14% 14.74 0.07%
3.17 RIB PLATE COUPLE PLATE 16mm Kg 13.19 0.06% 6.59 0.03%
3.18 RIB PLATE END PLATE 16mm Kg 253.21 1.22% 126.60 0.61%
3.19 RIB PLATE END PLATE 12mm (Roof) Kg 4.24 0.02% 2.12 0.01%
3.20 RIB PLATE ADDITIONAL PLATE 5mm Kg 69.24 0.33% 34.62 0.17%
3.21 RIB PLATE PLATE 22mm Kg 48.36 0.23% 24.18 0.12%
3.22 RIB PLATE COVER PLATE 16mm Kg 239.14 1.15% 119.57 0.58%
3.23 RIB PLATE PLATE 16mm Kg 37.68 0.18% 18.84 0.09%
3.24 RIB PLATE PLATE 12mm Kg 29.51 0.14% 14.75 0.07%
3.25 RIB PLATE PLATE 9mm Kg 160.52 0.77% 80.26 0.39%
3.26 RIB PLATE PLATE 6mm Kg 54.78 0.26% 27.39 0.13%
3.27 BOLT BOLT 8-M20 x 65 Ea 240.00 1.14% 72.00 0.34%
3.28 BOLT BOLT 8-M20 x 65 BRACING Ea 112.00 0.53% 20.00 0.09%
3.29 BOLT BOLT 4-M20 x 65 Ea 16.00 0.08% 8.00 0.04%
3.3 BOLT BOLT 2-M20 x 45 Ea 28.00 0.13% 16.00 0.08%
3.31 BOLT BOLT 2-M22 Ea 40.00 0.22% 10.00 0.05%
3.32 BOLT BOLT 4-M22 Ea 48.00 0.26% 15.00 0.08%
3.33 BOLT BOLT 6-M16 x 45 Ea 72.00 0.34% 20.00 0.09%
3.34 STRUCTURE WF BEAM VERTIKAL (300x150x9x6,5) Kg 36.70 0.18% - 0.00%
3.35 STRUCTURE WF BEAM VERTIKAL (300x150x9x6,5) Kg 36.70 0.18% - 0.00%
3.36 STRUCTURE ANCHOR BOLT 1-M16 x 400L Ea 8.00 0.11% 8.00 0.11%
3.37 STRUCTURE BOLT 8-M20 x 65 Ea 16.00 0.09% - 0.00%
3.38 STEEL GRATING Grating A Kg 36.27 0.17% - 0.00%
3.39 STEEL GRATING Grating B Kg 36.27 0.17% - 0.00%
3.4 STEEL GRATING L 70.70.6 Kg 38.28 0.18% - 0.00%
3.41 STEEL GRATING DYNA BOLT M16x100 Ea 8.00 0.23% - 0.00%
Concrete, Roofing, Electrical, and
4 Concrete, Roofing, Electrical, and Modified works 22.33% 7.42%
Modified works
4.1 CONCRETE WORK DEMOLISH m3 1.00 0.29% 1.00 0.29%
4.2 CONCRETE WORK EXCAVATION m3 9.00 0.15% 9.00 0.15%
4.3 CONCRETE WORK REINFORCING CONCRETE MP25 m3 0.14 0.11% 0.14 0.11%
4.4 CONCRETE WORK FOUNDATION m3 5.76 4.34% 5.76 4.34%
4.5 CONCRETE WORK PATH STEP m3 0.40 0.30% 0.40 0.30%
4.6 ROOFING POLYCARBONAT/ALDERON ROOF m2 13.50 1.01% - 0.00%
4.7 MODIFIED EXISTING WINDOWS MODIFIED EXISTING WINDOWS Ls 1.00 3.39% - 0.00%
4.8 GUTTER AND DRAIN PIPE PVC 4INCH GUTTER AND DRAIN PIPE PVC 4INCH Ls 1.00 1.02% - 0.00%
4.9 ELECTRICAL WORKS (CABLING, LED LAMP,
ELECTRICAL
ETC) WORKS (CABLING, LED LAMP, ETC) Ls 1.00 9.49% - 0.00%
4.10 CONCRETE WORK DEMOLISH m3 0.37 0.11% 0.37 0.11%
4.11 CONCRETE WORK EXCAVATION m3 1.56 0.04% 1.56 0.04%
4.12 CONCRETE WORK REINFORCING CONCRETE MP25 m3 0.90 0.68% 0.90 0.68%
No Desescription Work Item UoM Qty Plan Weight % Qty Actual2 Progress2
4.13 CONCRETE WORK FOUNDATION m3 1.88 1.41% 1.88 1.41%
5 Coating Coating 18.66% 0.00%
5.1 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Bordes m2 16.62 0.77%
5.2 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Diagonal m2 15.62 0.73%
5.3 HANDRAIL TANGGA (Ø 1 1/2" sch 40) Elbow 90 m2 2.73 0.13%
5.4 WF BEAM VERTIKAL (300x150x9x6,5) WF BEAM VERTIKAL (300x150x9x6,5) m2 76.92 3.58%
5.5 WF BEAM HORIZONTAL (200x100x8x5,5)WF BEAM HORIZONTAL (200x100x8x5,5) m2 11.87 0.55%
5.6 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM 1 m2 57.74 2.69%
5.7 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM 2 m2 32.27 1.50%
5.8 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM EXTEND m2 9.65 0.45%
5.9 WF BEAM HORIZONTAL (200x100x8x5,5)BEAM BRACING m2 10.28 0.48%
5.10 C BEAM (200x80x11x7,5) DIAGONAL m2 30.32 1.41%
5.11 C BEAM (200x80x11x7,5) BORDES m2 16.36 0.76%
5.12 C BEAM (100x50x7,5x5) ROOF H1 m2 7.64 0.36%
5.13 C BEAM (100x50x7,5x5) ROOF H2 m 10.39 0.48%
5.14 L BEAM BRACING (80x80x6) LENGTH 2,9 m2 12.48 0.58%
5.15 L BEAM BRACING (80x80x6) LENGTH 3,3 m2 7.42 0.35%
5.16 RIB PLATE 16mm m2 0.49 0.02%
5.17 RIB PLATE 9mm m2 0.57 0.03%
5.18 RIB PLATE 6mm m2 1.71 0.08%
5.19 RIB PLATE GUSSET PLATE 9mm m2 0.42 0.02%
5.20 RIB PLATE COUPLE PLATE 16mm m2 0.11 0.00%
5.21 RIB PLATE END PLATE 16mm m2 2.02 0.09%
5.22 RIB PLATE END PLATE 12mm (Roof) m2 0.05 0.00%
5.23 RIB PLATE ADDITIONAL PLATE 5mm m2 1.76 0.08%
5.24 RIB PLATE PLATE 22mm m2 0.28 0.01%
5.25 RIB PLATE COVER PLATE 16mm m2 1.90 0.09%
5.26 RIB PLATE PLATE 16mm m2 0.30 0.01%
5.27 RIB PLATE PLATE 12mm m2 0.31 0.01%
5.28 RIB PLATE PLATE 9mm m2 2.27 0.11%
5.29 RIB PLATE PLATE 6mm m2 1.16 0.05%
5.30 WF BEAM VERTIKAL (300x150x9x6,5) WF BEAM VERTIKAL (300x150x9x6,5) m2 44.39 2.07%
5.31 WF BEAM VERTIKAL (300x150x9x6,5) WF BEAM VERTIKAL (300x150x9x6,5) m2 18.99 0.88%
5.32 ANCHOR BOLT 1-M16 x 400L ANCHOR BOLT 1-M16 x 400L m2 2.00 0.09%
5.33 BOLT 8-M20 x 65 BOLT 8-M20 x 65 m2 4.00 0.19%