Grid Code Liberia - (Ver Final) 11232022
Grid Code Liberia - (Ver Final) 11232022
OF
LIBERIA
November 2022
1
Table of Contents
Foreword .................................................................................................................................. 14
PART A: GENERAL PROVISIONS ......................................................................................... 15
SECTION 1: PREAMBLE ......................................................................................................... 16
1.1 Purpose and Scope of the Liberia Electricity Grid Code (LEGC) ............................. 16
1.2 Objectives of the LEGC .................................................................................................. 16
1.3 Application of the LEGC ................................................................................................ 16
1.4 Hierarchy.......................................................................................................................... 17
SECTION 2: ABBREVIATIONS ............................................................................................... 18
SECTION 3: ROLES AND RESPONSIBLITIES OF MAIN ACTORS ................................ 21
3.1 Background ..................................................................................................................... 21
3.2 Roles of Main Actors ...................................................................................................... 21
3.3 Responsibilities of the TSO ........................................................................................... 21
Market Operator/TSO ............................................................................................................ 22
3.4 Responsibilities of a Transmission GCP ..................................................................... 23
3.5 Responsibilities of a Generation GCP.......................................................................... 23
3.6 Responsibilities of a Distribution GCP or Large Consumer GCP (Demand GCPs) 24
3.7 Responsibilities of the GCAC........................................................................................ 24
3.8 Other Responsibilities of a GCP ................................................................................... 24
Compliance with laws and industry standards ...................................................................... 24
SECTION 4: TRANSITIONAL PROVISIONS AND DEROGATIONS ................................ 26
4.1 Purpose and Scope ........................................................................................................ 26
4.2 Configuration of Equipment and Installations ............................................................ 26
4.3 Service Performance Standard During Transition Period ......................................... 27
4.4 Management Systems .................................................................................................... 27
4.5 Capacity Building (Human Resource Development) .................................................. 27
4.6 Existing Contracts .......................................................................................................... 27
4.7 LERC Right to Review Scope of Derogations ............................................................. 28
SECTION 5: GOVERNANCE OF THE GRID CODE ........................................................... 29
5.1 Purpose and Objectives ................................................................................................. 29
5.2 Conduct of the TSO ........................................................................................................ 29
5.3 Establishment of the GCAC........................................................................................... 29
5.4 Mandates of GCAC ......................................................................................................... 30
5.5 Meetings of GCAC .......................................................................................................... 31
2
5.6 Grid Code Review and Revision Procedures .............................................................. 32
5.7 Complaints and disputes ............................................................................................... 33
5.8 Unforeseen Circumstances ........................................................................................... 33
5.9 Grid Code Violations and Sanctions ........................................................................ 34
PART B: TRANSMISSION LICENSE CONDITIONS ........................................................... 35
SECTION 6: TRANSPARENCY AND NON-DISCRIMINATION REQUIREMENTS ....... 36
6.1 Background, purpose and scope.................................................................................. 36
6.2 Publication of Procedures ............................................................................................. 36
6.3 Equal application of the Grid Code............................................................................... 36
6.4 Transparency criteria ..................................................................................................... 36
6.5 Delegation and Outsourcing of functions ................................................................... 37
6.6 Exercise of discretion by the TSO and other officials................................................ 37
6.7 Charges for LITS services ............................................................................................. 38
SECTION 7: PLANNING SUB-CODE..................................................................................... 39
7.1 Background, Purpose and Scope ................................................................................. 39
7.2 Grid planning responsibility .......................................................................................... 39
7.3 Grid Development Plan (GDP)....................................................................................... 40
7.4 Grid planning criteria...................................................................................................... 41
7.5 Grid Planning Studies .................................................................................................... 42
7.6 Grid Planning Data.......................................................................................................... 43
SECTION 8: CONNECTION SUB-CODE .............................................................................. 44
8.1 Background, Purpose and Scope ................................................................................. 44
8.2 Connection Principles .................................................................................................... 45
Obligations and Responsibilities .......................................................................................... 45
8.3 General ............................................................................................................................. 45
8.4 Obligations of the TSO ................................................................................................... 45
8.5 Obligation of Transmission GCP .................................................................................. 46
8.6 Obligations of Generation GCP..................................................................................... 47
8.7 Obligations of Demand GCP (Distribution or Large Consumer GCP)...................... 47
8.8 Investment Responsibilities ...................................................................................... 48
8.9 Connection Point ........................................................................................................ 48
8.10 Ownership Boundary.................................................................................................. 49
8.11 Operating and Maintenance Boundary..................................................................... 49
8.12 Requirement for Connection Agreement ................................................................. 49
8.13 Grid Impact Studies................................................................................................. 49
3
8.14 Application for new connection or modification..................................................... 50
8.15 Processing of application for a new connection or modification ..................... 51
Technical Requirements for Connected Equipment........................................................... 52
8.16 General Requirements for GCP’s Equipment........................................................... 52
Unintended and Unscheduled back-energization ................................................................. 53
8.17 Power System Control................................................................................................ 53
8.18 Protection Requirements ........................................................................................... 53
General principles .................................................................................................................. 53
Minimum requirements/Protection philosophy ...................................................................... 54
Back-up protection................................................................................................................. 55
Protection bypass/disconnection ........................................................................................... 55
Additional protection requirements........................................................................................ 55
Network stability and integrity................................................................................................ 56
8.19 Short Circuit Current and Fault Clearance Time..................................................... 56
8.20 Telecommunications Requirements for Monitoring and Control ......................... 57
8.21 SCADA System for Monitoring and Control ............................................................ 57
Process Signals Interface to RTU ......................................................................................... 57
8.22 Data Registration ........................................................................................................ 58
Data to be Registered............................................................................................................ 58
Stages of data registration..................................................................................................... 59
Data forms ............................................................................................................................. 59
8.23 Submittals prior to the Commissioning Date .......................................................... 60
8.24 Commissioning ........................................................................................................... 60
Procedure for Commissioning of equipment and physical connection to the LITS .............. 60
Requirement to inspect and test equipment during commissioning ..................................... 61
Coordination during commissioning ...................................................................................... 61
Commissioning program........................................................................................................ 62
Commissioning Tests ............................................................................................................ 62
8.25 Electrical Diagram and Connection Point Drawing Requirements ....................... 63
Responsibilities of TSO and GCPs ....................................................................................... 63
Preparation of Electrical Diagram and Connection Point Drawing ....................................... 63
Changes to Electrical Diagrams and Connection Point Drawings........................................ 64
Validity of Electrical Diagrams and Connection Point Drawings .......................................... 64
8.26 Equipment Identification and Nomenclature ........................................................... 64
8.27 Compliance with Connection Requirements by Generation GCP ........................ 65
4
8.28 Inspection and testing ................................................................................................ 66
Right of entry and inspection ................................................................................................. 66
Right of testing ....................................................................................................................... 67
8.29 Routine Testing of Protection Equipment by GCPs ............................................... 68
8.30 Power System Tests ................................................................................................... 68
8.31 Disconnection and Reconnection ............................................................................. 69
Voluntary disconnection ........................................................................................................ 69
Decommissioning procedures ............................................................................................... 69
Involuntary disconnection ...................................................................................................... 70
Disconnection to implement regulatory order ....................................................................... 70
Obligation to reconnect.......................................................................................................... 70
PART C: RULES OF PRACTICE ............................................................................................ 72
SECTION 9: OPERATIONS SUB-CODE............................................................................... 73
9.1 Background, Purpose and Scope ................................................................................. 73
Purpose.................................................................................................................................. 73
Scope ..................................................................................................................................... 73
9.2 TSO Obligations.............................................................................................................. 73
System Reliability and Safety ................................................................................................ 74
System Security ..................................................................................................................... 75
Operational Measures ........................................................................................................... 75
9.3 Operational Planning and Management....................................................................... 75
Operations Plan ..................................................................................................................... 76
Annual Operations Plan requirements .................................................................................. 76
9.4 Operations Planning Criteria......................................................................................... 77
General principles .................................................................................................................. 77
Generation management ....................................................................................................... 77
Voltage management............................................................................................................. 77
Time management and frequency control ............................................................................ 78
Interchange management...................................................................................................... 78
9.5 Operating Reserves Criteria .......................................................................................... 78
Types of reserves .................................................................................................................. 78
Quick Reserve ....................................................................................................................... 79
Emergency Reserve .............................................................................................................. 79
Slow Reserve......................................................................................................................... 80
Negative Reserve .................................................................................................................. 80
5
Determination and allocation of operating reserves ............................................................. 80
9.6 System voltage and reactive power criteria .................................................................. 81
Coordination of reactive power compensation ...................................................................... 81
Basic reactive power compensation...................................................................................... 82
Supplementary reactive power compensation ...................................................................... 82
Compliance of Generation GCPs with TSO instructions ...................................................... 83
9.7 Transmission Operations Planning Studies................................................................ 83
9.8 Power System Operating States ................................................................................... 84
Normal state........................................................................................................................... 84
Alert state ............................................................................................................................... 84
Emergency state .................................................................................................................... 85
Extreme state......................................................................................................................... 85
Restorative state .................................................................................................................... 85
9.9 Power System Operations Criteria ............................................................................... 85
9.10 Power System Frequency Control ............................................................................ 86
Restriction of governor action................................................................................................ 87
9.11 Power System Voltage Control ................................................................................. 88
9.12 Protection Coordination............................................................................................. 89
Remedial Action Schemes .................................................................................................... 89
9.13 Ancillary Services ....................................................................................................... 90
Standards for ancillary services ............................................................................................ 90
Operating reserves & frequency control................................................................................ 90
Quick (or spinning) Reserves ................................................................................................ 91
Slow (or non-spinning) Reserves .......................................................................................... 91
Voltage and reactive power control ....................................................................................... 92
Black start capability .............................................................................................................. 92
Reliability Must-Run requirements ........................................................................................ 92
9.14 Demand Management ................................................................................................. 93
Automatic Frequency Load Shedding (AFLS) ...................................................................... 93
Demand management in an Emergency operating state ..................................................... 94
9.15 Power System Restoration ........................................................................................ 94
Restoration plan..................................................................................................................... 94
Restoration process ............................................................................................................... 95
9.16 Outage/Maintenance Planning .................................................................................. 95
General .................................................................................................................................. 95
6
Requirements and exceptions to prior approval for outages ................................................ 96
Responsibility for preparation of outage plans ...................................................................... 97
Outage planning process....................................................................................................... 97
Initial/Provisional outage Plans ............................................................................................. 98
Revised outage needs ........................................................................................................... 98
Committed outage Plan ......................................................................................................... 98
Outage/maintenance coordination ........................................................................................ 99
Restoration or return of equipment into service .................................................................... 99
Outage records and reporting ............................................................................................... 99
9.17 Equipment Testing.................................................................................................... 100
9.18 Testing of Generating Units by TSO ....................................................................... 101
9.19 Tests by GCPs of Own Plant Requiring Changes to Normal Operation ............ 102
9.20 Communication Systems and Facilities ................................................................. 103
9.21 TSO Communication Procedures ........................................................................... 103
Guidelines and requirements for notification....................................................................... 103
Notification of planned TSO operations .............................................................................. 104
Notification of GCP operations ............................................................................................ 104
Notification of Alert conditions and events .......................................................................... 104
9.22 System Disturbance Events / Faults Monitoring and Recording ........................ 105
Purpose................................................................................................................................ 105
Disturbance monitoring requirements ................................................................................. 105
Monitored data ..................................................................................................................... 106
9.23 Operations Monitoring Reporting Requirements.................................................. 107
Reporting of emergency, automatic or unplanned TSO operations ................................... 107
Routine monthly reporting ................................................................................................... 107
Quarterly and Annual reports .............................................................................................. 107
9.24 Incident/Fault Reporting and Investigation ........................................................... 108
General ................................................................................................................................ 108
Reporting of major incident or Significant Incident by a GCP............................................. 108
Reporting of major incident or Significant Incident by the TSO .......................................... 108
Guidelines for written reports .............................................................................................. 109
Investigation of incidents ..................................................................................................... 109
Investigation of major or Significant Incidents..................................................................... 109
SECTION 10: SCHEDULING AND DISPATCH OF GENERATION & ANCILLARY
SERVICES .................................................................................................................... 111
7
10.1 Background, Purpose and Scope ........................................................................... 111
Purpose................................................................................................................................ 111
Scope ................................................................................................................................... 111
10.2 Responsibilities of the TSO ..................................................................................... 111
10.3 Responsibilities of Transmission GCP .................................................................. 112
10.4 Responsibilities of Generation GCPs..................................................................... 113
10.5 Responsibilities of Demand GCPs.......................................................................... 113
10.6 Demand Forecast and Forecasting Process ......................................................... 113
10.7 Generation Margin .................................................................................................... 115
10.8 Scheduling and Dispatch Criteria ........................................................................... 115
10.9 Scheduling and Dispatch Data ................................................................................ 115
10.10 Merit Order Operation ........................................................................................... 116
10.11 Merit Order Table ................................................................................................... 117
10.12 Generation Scheduling Procedure ...................................................................... 117
10.13 Preparation of the Generation Schedule ............................................................ 118
Adjustments to Generation Schedule.................................................................................. 119
10.14 Revision of Generation Schedule ........................................................................ 120
10.15 Issuing of Generation Schedule .......................................................................... 120
10.16 Dispatch Instructions ............................................................................................ 120
Action Required by Generation GCPs ................................................................................ 122
Instruction to Distribution GCPs and other Demand GCPs ................................................ 123
10.17 Reactive Power Dispatch...................................................................................... 123
10.18 System Emergency Conditions ........................................................................... 124
10.19 Ancillary Services Agreement.............................................................................. 124
10.20 Dispatch, Monitoring and Testing of Ancillary Services .................................. 125
SECTION 11: SAFETY SUB-CODE ..................................................................................... 126
11.1 Background, Purpose and Scope ............................................................................ 126
Purpose................................................................................................................................ 126
Scope ................................................................................................................................... 126
11.2 Preparation of Safety Rules ...................................................................................... 126
11.3 General Guiding Principles for Safety Coordination ............................................. 127
11.4 Safety Coordination Procedure............................................................................... 128
Safety Coordinators ............................................................................................................. 128
11.5 Operating Instructions............................................................................................... 129
11.6 Isolation and Grounding Principles ......................................................................... 129
8
11.7 Authorization for Testing .......................................................................................... 130
PART D: STANDARDS OF PERFORMANCE .................................................................... 131
SECTION 12: BENCHMARKS AND INDICES FOR STANDARDS OF SUPPLY ......... 132
12.1 Background, Purpose and Scope ........................................................................... 132
Purpose................................................................................................................................ 132
Scope ................................................................................................................................... 132
12.2 Standards for Power Quality and Reliability.......................................................... 133
12.3 Voltage Variations ..................................................................................................... 133
Voltage limits – Normal State .............................................................................................. 133
Voltage limits - Alert State ................................................................................................... 134
Voltage limits - Emergency State ........................................................................................ 134
Voltage unbalance ............................................................................................................... 134
Voltage harmonics & limits .................................................................................................. 134
Voltage flicker ...................................................................................................................... 134
12.4 Reactive Power and Power Factor ........................................................................... 135
12.5 System Frequency Limits ........................................................................................ 135
Frequency withstand capability ........................................................................................... 135
Load shedding scheme ....................................................................................................... 136
12.6 Protection Relays ....................................................................................................... 136
12.7 Monitoring and Reporting of LITS Performance ................................................... 136
Reliability performance indices............................................................................................ 137
Quality performance indices ................................................................................................ 138
Voltage & Power factor........................................................................................................ 138
Frequency ............................................................................................................................ 138
Efficiency performance indices............................................................................................ 138
Equipment loading reporting ............................................................................................... 138
Event inclusions and exclusions for performance reporting ............................................... 138
SECTION 13: METERING SUB-CODE................................................................................ 139
13.1 Background, Purpose and Scope ............................................................................ 139
Purpose................................................................................................................................ 139
Scope ................................................................................................................................... 139
13.2 General Metering Principles ..................................................................................... 139
13.3 Positioning of Main and Check Metering Systems ................................................ 140
Generating station meter locations...................................................................................... 141
Distribution GCP’s network meter locations........................................................................ 141
9
Other Demand GCP system meter locations ...................................................................... 141
International Interconnection line meter locations .............................................................. 141
13.4 Ownership of Metering Systems & Associated Responsibilities......................... 142
13.5 Metering Facility Features......................................................................................... 143
13.6 Use of Meters.............................................................................................................. 143
13.7 Minimum Requirements for Metering Facility Equipment .................................... 144
Voltage Transformers .......................................................................................................... 144
Current transformers............................................................................................................ 144
Meters .................................................................................................................................. 144
Integrating Pulse recorders ................................................................................................. 145
13.8 WAPP Interconnections ........................................................................................... 145
13.9 Metering Register...................................................................................................... 145
13.10 Certification of Meter and Metering Equipment................................................. 146
13.11 Meter and Metering Equipment Testing.............................................................. 147
Instrument transformer testing ............................................................................................ 147
Meter testing and calibration ............................................................................................... 147
Request for tests.................................................................................................................. 148
Test failure ........................................................................................................................... 148
13.12 Maintenance of Metering Equipment ................................................................... 148
13.13 Metering Equipment Security, Meter Reading and Metering Data Access...... 149
Sealing ................................................................................................................................. 149
Meter reading and access to metering data........................................................................ 150
On-Site meter reading ......................................................................................................... 150
Electronic data transfer capability ....................................................................................... 150
Restriction of unauthorized access to metering data .......................................................... 150
Audit of Databases .............................................................................................................. 151
13.14 Billing and Settlement Procedure......................................................................... 151
13.15 Settlement Audit Procedure ...................................................................................... 151
Allocation of audit cost......................................................................................................... 151
Audit results ......................................................................................................................... 151
Audit appeals ....................................................................................................................... 151
13.16 Confidentiality ......................................................................................................... 151
SECTION 14: DATA AND INFORMATION EXCHANGE SUB-CODE............................ 152
14.1 Background, Purpose and Scope ........................................................................... 152
Purpose................................................................................................................................ 152
10
Scope ................................................................................................................................... 152
14.2 Information Exchange Interface .............................................................................. 152
14.3 Implementation Principles for Data and Information Exchange ......................... 152
14.4 Information Exchange Categories .......................................................................... 153
Provision of Information to the TSO .................................................................................... 153
14.5 Planning Information ................................................................................................ 153
14.6 Operational Information ........................................................................................... 154
Commissioning information ................................................................................................. 154
Network information exchange ............................................................................................ 154
Generating plant performance data .................................................................................... 154
Demand GCP performance data......................................................................................... 154
SCADA infrastructure .......................................................................................................... 155
14.7 Post-Dispatch Information ....................................................................................... 155
General post-dispatch information ...................................................................................... 155
Generation settlement ......................................................................................................... 155
Ancillary Services settlement .............................................................................................. 155
Additional unit post-dispatch Information ............................................................................ 155
14.8 Time Standard ........................................................................................................... 156
14.9 Data Retention and Archiving ................................................................................. 156
14.10 Operational Communication and Data Retention Requirements........................ 156
Telephone/fax ...................................................................................................................... 157
Computer equipment ........................................................................................................... 157
File Transfers ....................................................................................................................... 157
14.11 LITS Performance Data .......................................................................................... 157
14.12 Events Reporting .................................................................................................... 158
14.13 Confidentiality Obligations................................................................................... 158
Exceptions to confidentiality of information ......................................................................... 159
Disclosure of confidential information ................................................................................. 159
PART E: RENEWABLE ENERGY PROVISIONS ............................................................... 160
SECTION 15: RENEWABLE ENERGY SUB-CODE.......................................................... 161
15.1 Background, Purpose and Scope ............................................................................... 161
Purpose................................................................................................................................ 161
Scope ................................................................................................................................... 161
15.2 Technical Connection Conditions........................................................................... 161
General ................................................................................................................................ 161
11
Frequency range of operation ............................................................................................. 162
Voltage Range of Operation ................................................................................................ 162
Power Quality....................................................................................................................... 163
Voltage variations and Voltage unbalance.......................................................................... 163
Flicker................................................................................................................................... 164
Harmonics............................................................................................................................ 164
Reactive Power Capability................................................................................................... 164
15.3 Reactive Power Control and Voltage Control Requirements .............................. 166
General ................................................................................................................................ 166
Voltage droop control........................................................................................................... 167
Reactive power control (Q control)...................................................................................... 167
Power factor control (cosφ-control) ..................................................................................... 168
15.4 Active Power Curtailment of a VRPP Output ......................................................... 168
High frequency active power reduction requirement for VRPPs ........................................ 169
Primary and secondary frequency control .......................................................................... 169
15.5 Behavior of VRPP During Abnormal Voltage Conditions ................................... 170
Fault Ride-through Requirements ....................................................................................... 170
Remain-connected voltage conditions ................................................................................ 170
Active power provision and reactive current flows during fault........................................... 171
Reactive current support of voltage during LVRT/HVRT situations ................................... 171
Active and reactive power recovery after fault .................................................................... 172
15.6 Automatic Synchronization Capability................................................................... 172
15.7 Protection and Fault Levels ..................................................................................... 173
15.8 VRPP Impact on System Reserve Requirements.................................................. 173
15.9 Communication and Control.................................................................................... 174
Requirement for VRPP SCADA communication capability ................................................ 174
PART F: DEFINITIONS ........................................................................................................... 175
PART G: TECHNICAL SCHEDULES ................................................................................... 192
........................................................... 193
.................. 194
................................................ 195
........................................................... 201
............. 202
................................. 203
12
............................... 204
.................................................................................................................... 205
........................................... 206
............... 208
........................................... 209
............................................... 211
.... 216
................................................................ 220
..................... 221
PART H: APPENDICES .......................................................................................................... 222
.................................................. 223
....................................... 233
B.1. Introduction.................................................................................................................... 233
B.2. Measurement Transformers......................................................................................... 233
B.2.1 Current transformer (CT) ........................................................................................... 233
B.2.2 Voltage Transformer (VT) .......................................................................................... 233
B.2.3 Combined VT/CT ....................................................................................................... 233
B.3. Meters ............................................................................................................................. 234
B.3.1 Type tests ................................................................................................................... 234
B.3.2 Routine tests .............................................................................................................. 235
B.3.3 Acceptance tests ........................................................................................................ 235
............................................ 236
C.1. Sealing Procedure at the Laboratory .......................................................................... 236
C.2. Sealing Procedure at the Point of Installatio ............................................................. 236
C.3. Sealing Procedure at the Point of Maintenance, Recalibration, Inspection etc. ... 236
C.4 Seal Specifications......................................................................................................... 237
C.5 Sealing Points ................................................................................................................. 237
13
Foreword
The Liberia Electricity Grid Code (LEGC) specifies the framework for connection and
usage of the grid, system services, grid expansion and procedures for the planning and
operation of the transmission system during normal and exceptional conditions. It is a live
working document which will be continuously subjected to revisions and amendments to
comply always with existing policy, legislation, and good industry practices.
The LEGC is prepared using a functional rather than an organisational approach , so that
it will remain robust and require minimal changes as the Liberia electricity industry evolves
and the reforms proceed. It identifies and defines the responsibilities of two key
independent functional entities in the Liberia electricity market, the Transmission Network
Asset Owner (NGC) and the Transmission System Operator (TSO). These functional
entities, together with other GCPs connected to the transmission network, and including
electricity traders operating within the Electricity Market must comply with the provisions
of the LEGC and the Market Operation Rules (MOR) which is yet to be developed by the
TSO for approval by the LERC. The LEGC development approach further allows for a
consistent improvement of the quality of electricity supply levels and the associated
performance standards and benchmarks for the TSO and the transmission network
service provider or the NGC (referred to as the TGCP in the LEGC) as their expertise
develops.
Proposals for changes to the LEGC will be received by a Grid Code Advisory Committee
(GCAC). The GCAC is a stakeholder representative committee, and its composition is
laid out in the LEGC. The roles and responsibilities of the GCAC are prescribed in the
LEGC among which includes proposition of recommendations to the LERC for changes
to the Code.
This LEGC provides a general framework for the revision of existing Technical Standards
and Procedures thereby ensuring harmonization for the safe, secure, and reliable
operation of the Liberia Interconnected Transmission System (LITS). It will work in
conjunction with other legal and regulatory documents, including but not limited to the
2015 Electricity Law of Liberia (ELL), the Liberia National Energy Policy as of May 2009
(or any other policy thereafter approved), the Liberia Distribution Code and other codes,
rules and regulatory guidelines issued by the LERC.
14
Part A: General Provisions
Part A, General Provisions, establishes the guiding principles and purpose of the Liberia
Electricity Grid Code (LEGC); defines the scope of the principal actors involved under the
LEGC; provides the definition of roles and responsibilities, derogations, and transitional
measures to assist actors in meeting their obligations under the Code; and elaborates
arrangements for the governance and management of the LEGC. This Part also
establishes the hierarchy of the LEGC relative to the Law, the Regulations, other codes,
and rules, and contains a Section that provides meaning of acronyms (or terminology)
used in the LEGC.
15
Section 1: Preamble
1.1 Purpose and Scope of the Liberia Electricity Grid Code (LEGC)
1.1.1 The Liberia Electricity Grid Code (LEGC) is formulated to ensure efficient
coordinated operation and maintenance of the Liberia Interconnected
Transmission System (LITS). The LEGC is a dynamic document that is revised
periodically in accordance with laid down procedures, considering the reasonable
interests and views as expressed by the stake holding entities in the light of new
developments and the experience gained in the actual implementation of the Code.
1.1.2 This LEGC is approved by the Liberia Electricity Regulatory Commission (LERC)
following extensive deliberations by stakeholders and it is based on the provisions
of Sections 3.3: A. 5, 6, 8, 9, B.4 and 3.4 of the 2015 Electricity Law of Liberia
(ELL) that together mandate the LERC to establish the LEGC to ensure the
coordinated technical operation, maintenance, and performance monitoring of the
high voltage transmission system within Liberia.
16
(i) Ancillary service provider; and
(j) The Market Operator (MO) [regulation 50 of the Electricity Licensing
Regulations (ELR) mandates the TSO to assume this role in the interim].
1.3.2 Except for the TSO and the MO, all the parties listed under sub-section 1.3.1 shall be
referred to in this LEGC as “Grid Code Participants” or “GCPs”.
1.3.3 A GCP shall be a legal entity either:
(a) with an Asset Vesting Agreement with the TSO granting the TSO operational
control of all Connection points in the LITS – in the case of a Transmission GCP,
or
(b) having a valid Connection Agreement with the TSO for the purposes of:
(i) constructing, owning and providing LITS infrastructure or ancillary services;
(ii) injecting, wheeling, or off-taking power for its own use or for retail; or,
(iii) exchanging power either with the electricity networks of neighboring
countries or within the WAPP.
1.3.4 The TSO and all GCPs shall comply with the provisions of the ELL, the terms and
conditions of the ELR and issued licenses (where applicable) as well as the approved
LEGC and any other applicable regulations, rules and legislation.
1.3.5 A breach of any of the instruments mentioned in sub-section 1.3.4 could result in the
sanctioning, suspension, or withdrawal of the applicable License.
1.4 Hierarchy
1.4.1 For guidance of the parties to this Code, it is noted that the hierarchy of
documents related to the Code is as follows, from the highest to the lowest:
(a) The ELL;
(b) The ELR issued by the LERC;
(c) The Electricity Tariff Regulations and Methodology issued by the LERC;
(d) The Customer Service and Quality of Supply Regulations as issued from
time to time by LERC;
(e) The Operating License of the connected entity;
(f) This LEGC and any other codes, rules, regulations, or procedures issued
by the LERC; and
(g) Any codes, rules, procedures, and protocols issued by the WAPP.
1.4.2 In the event of conflict, the document highest in the hierarchy takes precedence. Where a
GCP encounters conflict between any of the documents listed in sub-section 1.4.1, the
GCP should seek advice from the TSO, the Grid Code Advisory Committee (GCAC) and
ultimately the LERC.
17
Section 2: Abbreviations
18
IEC International Electro-technical Committee
IEEE Institute of Electrical & Electronic Engineers
IHD Individual Harmonic Distortion
ITU International Telecommunication Union
kVar Kilovar, or one thousand volt-amperes of reactive power
kW Kilowatt or one thousand watts of active electric power
kWh Kilowatt-hour or one thousand watt-hours of electrical energy
LCTDMP Least Cost Transmission Development Master Plan
LEC Liberia Electricity Corporation
LERC Liberia Electricity Regulatory Commission
LEGC Liberia Electricity Grid Code
LITS Liberia Interconnected Transmission System
LV Low Voltage
LVRT Low Voltage Ride Through
MD Maximum Demand
MDF Main Distribution Frame
MO Market Operator
MOR Market Operation Rules
MOU Memorandum of Understanding
MVar Megavar, one million volt-amperes of reactive electric power
MW Megawatt, one million watts of active electric power
NGC National Grid Company
NOx Nitric oxide gases
PLC Power Line Carrier
PPA Power Purchase Agreement
PoC Point of Connection
PSA Power Supply Agreement
PSS Power System Stabilizer (or stabilization)
PV Photo Voltaic
Plt Long term flicker Perceptibility
Pst Short term flicker Perceptibility
RAS Remedial Action Schemes
RETs Renewable Energy Technologies
19
RMR Reliability Must-Run
RMS Root Mean Square
RTU Remote Terminal Unit
SCADA Supervisory Control And Data Acquisition
SFRS Secondary Frequency Regulation System
SO2 Sulphur dioxide
20
Section 3: Roles And Responsibilities Of Main Actors
3.1 Background
The open-access transmission service that is envisaged for the LITS requires extensive
coordination of the roles and responsibilities of the several actors (listed in Section 1.3 of the
LEGC) to successfully deliver the required service.
22
3.3.6 Until the Market Operation Rules are established and the market operation functions (of
the TSO) are clearly delineated, the TSO is mandated under this LEGC to perform the
critical functions of the MO as provided for particularly under the Metering Sub-code
including the following:
(a) administering of power supply and power purchase agreements;
(b) determination of Generation GCP and power pool energy and ancillary service
offers; and
(c) the performance of accounting, billing, and settlement functions for LITS supply
services or transactions.
23
(e) operating its plant and equipment in accordance with dispatch instructions of the
TSO to meet system performance and reliability requirements and in a manner
that is consistent with the reliable operation of the LITS; and
(f) providing accurate and timely data, information, and reports to the TSO.
24
3.8.3 Despite the separation, the different Parts of the LEGC are intended to be consistent
and complementary for the satisfactory and efficient delivery of transmission operational
services and nothing in this Code precludes the application of evolving technologies and
processes as they become available.
25
Section 4: Transitional Provisions And Derogations
4.1 Purpose and Scope
Section 4 provides:
(a) the rationale for derogations,
(b) how derogations are to be made, and
(c) the duration of these exemptions.
26
compliance which has been identified and included in the “Non -compliance
Listing”.
4.2.8 A request for derogation made by a GCP or the TSO from any provision of the
LEGC shall contain the following:
(a) the version number of the LEGC;
(b) identification of the Plant and/or Apparatus in respect of which a derogation
is sought;
(c) identification of the provision which the GCP or TSO is, or will be, unable
to comply with;
(d) the extent of the non-compliance;
(e) the reason for the non-compliance; and
(f) the date by which compliance will be achieved (if remedy of the
noncompliance is possible)
27
4.6.3 The TSO in consultation with the Transmission GCP shall endeavor to negotiate
for new contracts or amend existing contracts which shall conform to all the
provisions of the LEGC within one year from Effective Date of coming into force
of this LEGC.
4.6.4 Neither a GCP nor the TSO shall enter a new contract or extend any existing
contract that is not in accordance with the LEGC.
28
Section 5: Governance Of The Grid Code
5.1 Purpose and Objectives
This Section 5 of the Code defines the arrangements for the management and
governance of the implementation of the LEGC for the provision of transmission
services for the benefit of the electricity supply industry.
5.3.2 The GCAC shall comprise the following persons knowledgeable in the electricity
supply industry:
(a) One member of the LERC’s Electricity Technical Committee who shall
serve as Chairperson
(b) Head of Technical Regulation, LERC;
(c) Chief Executive Officer of the TSO;
(d) A representative each of the following:
(i) the Transmission GCP (Transmission Licensee);
29
(ii) the national generation GCP (LEC-Generation);
(iii) other generation GCPs connected to the LITS;
(iv) WAPP operator/suppliers connected to the LITS;
(v) Distribution GCPs connected to the LITS;
(vi) Large Consumers (Demand GCPs)
(vii) the Ministry of Mines and Energy;
(viii) the Electrical Engineering Academia;
(ix) the Engineering Society of Liberia; and
(e) One independent and unaffiliated person with technical expertise in
generation, transmission and distribution operations
5.3.3 LERC shall appoint the members of the committee upon their nomination by the
relevant entity or institution, where applicable.
5.3.4 A member of the GCAC, except a representative from the LERC, shall hold office
for a three-year term subject to re-nomination and re-appointment.
5.3.5 Any changes of representation by entity or institution shall be communicated in
writing to LERC which shall confirm the appointment within thirty (30) days.
5.3.6 The representative of the LERC shall be the Secretary to the GCAC and shall
publish the latest list of members of the GCAC within 14 days of any change.
5.3.7 The LERC shall house the GCAC Secretariat and provide all administrative and
secretarial personnel, logistics and support for the Committees’ work and
meetings.
5.3.8 All members shall have a designated backup replacement to serve on the GCAC
in case of unforeseen circumstances. Such nominations shall be made in writing
to the GCAC Secretariat and shall be approved by LERC. The constituency of
representatives may replace members at any given time, provided they give 14
days’ written notice to the GCAC and the LERC.
5.3.9 The LERC may request the replacement of members by their constituency upon
recommendation of the GCAC, if they have not attended three consecutive
meetings.
30
(d) review and make recommendations to LERC regarding proposals for
derogations in relation to compliance with the LEGC;
(e) analyze any major grid disturbances within fourteen (14) calendar days
after occurrence and evolve any consequent revision to the LEGC;
(f) review and make recommendations regarding proposals for amending the
LEGC; and
(g) recommend to LERC, changes to the LEGC together with the reasons for
the changes and any objections, if applicable.
31
5.5.11 The GCAC, at its discretion, may invite experts or any oth er organization such as
Government Departments, Local Authorities, or academic/ technical institutions, to
attend the GCAC meeting depending on the agenda. Such invited members can
express or offer advice on the matter under consideration but shall act as
observers only in the final determination.
32
5.6.12 The GCAC Secretariat shall make hard copies of the latest version of the LEGC
available to requesting entities, for which a nominal fee may be charged to recover
reproduction costs.
33
5.8.5 The normal operations of a GCP should never be disrupted by any situation or
dispute. The majority decision of the meeting of GCPs or the considered
determination of the TSO shall be implemented unless and until the GCAC issues
a different ruling; and the ruling of the GCAC shall be in force unless and until a
different decision is issued by LERC (if the issue is referred to LERC).
5.8.6 The decision of LERC is ultimate and shall be implemented by all GCPs.
34
Part B: Transmission License Conditions
This Part of the LEGC defines the Conditions of the licenses for the transmission segment of the
electricity supply industry comprising the TSO License and the Transmission License. It
contains the sub-codes that deal with the requirements, processes and procedures for planning
and development of the Grid, the technical requirements, processes and procedures for
connection to the LITS and the rights and requirements for transparency and nondiscrimination
in the provision of services from the LITS.
35
Section 6: Transparency And Non-Discrimination Requirements
6.1 Background, Purpose, and Scope
Section 6 of the LEGC defines the requirements and actions which will inter alia provide
fair, transparent, and non-discriminatory access to the LITS for use by GCPs and any
other duly licensed or permitted entity for whom open access is to be provided.
6.4.5 Despite provisions under Section 5.5 and in furtherance of the transparency
objective, the following rules shall apply to the performance of the functions of the
GCAC relating to meetings:
(a) the agenda for meetings of the GCAC shall reflect the priorities of all the
stakeholders and shall be announced and made public well in advance;
(b) the dates and places of meetings shall be announced;
(c) any interested GCP shall be allowed to be physically present at any
meeting (except when discussing individuals or appointments) to observe
the proceedings where decisions are taken; and
(d) the minutes of meetings and documentation shall be published within 10
working days.
37
6.6.4 The principles and rationale for any discretion exercised or decision taken by the
TSO shall be published and made available to any person upon request.
6.6.5 A person aggrieved by a discretionary decision taken by the TSO may request for
a review by the GCAC, as necessary.
6.6.6 The GCAC shall consider the complaint and uphold or recommend a
reconsideration of the TSO decision.
6.6.7 A discretionary decision once approved by the GCAC shall be considered as a
precedent which shall be applied uniformly and equally to all similar situations
unless explicitly reversed or revised in writing.
38
Section 7: Planning Sub-Code
7.1 Background, Purpose, and Scope
7.1.1 The Planning Sub-code specifies the planning responsibility for grid developments
and the policy, standards or criteria and organizational procedures to be applied.
Grid development includes the construction or refurbishment of power lines,
transformers, substation equipment, reactive compensating devices, auxiliaries,
and control systems.
7.1.2 Transmission system planning accounts for new connection requirements,
development of existing transmission system and apparatus due to changes in
factors such as demand, generation , reliability, and environmental requirements.
7.1.3 The primary aim of transmission planning is the maintenance of the integrity of the
bulk transmission system. The adequacy and security of supply to any particular
load or area is secondary to this primary aim.
7.1.4 The objective of the Planning Sub-code is to define processes and standards to
ensure that:
(a) the configuration of new transmission infrastructure is optimized and in
accordance with projected long-term needs;
(b) the development of infrastructure facilities and apparatus is well
coordinated in terms of technical arrangement and characteristics;
(c) system congestion of existing facilities and apparatus is adequately
anticipated, and reinforcement schemes are designed to overcome
constraints to electrical power transfer and overall power system
performance; and
(d) all GCPs provide from time to time, the planning data that is required.
7.1.5 The Planning Sub-code therefore specifies the information to be supplied by GCPs
to facilitate the evaluation of the impact of the connection of new facilities,
identification of congestion and the planning of expansion , reconfiguration,
reinforcement, or development of the transmission network regarding its adequacy
to meet the needs of all existing and prospective GCPs.
39
7.2.2 The planning activities leading to the GDP shall be undertaken sufficiently in
advance so that all prudent and required steps for coordination, design,
construction, and commissioning of the needed facilities are performed without
disturbing the delivery of power over the LITS and so that all stakeholders have an
opportunity to contribute to all the steps.
7.2.3 The planning process shall also provide sufficient time for the preparation of
designs and proposals so that all interested persons have an adequate non-
discriminatory opportunity to participate in any invitation to build or supply the
facilities.
7.3.4 The GDP and any subsequent revisions or updates shall be submitted to the
GCAC for review and then to the LERC for approval prior to any commitments
being made for its implementation.
7.3.5 Subject to sub-section 7.3.1, the GDP shall include, as a minimum, the following
main contents, for the planned period:
(a) a transmission network expansion planning methodology;
(b) an evaluation of the current technical situation of the transmission network;
(c) forecast of demand (minimum of up to 5 succeeding years) and impact on
existing transmission capacity;
(d) list of generation projects to be connected, and details of the connection
point, and connection contract for each such generation project;
(e) a list of newly proposed demand connections with details of the connection
point and the corresponding connection contract for each such new
demand connection;
(f) a list of any new connections proposed, th at are not included in the annual
list, and details of the connection point and connection contract for such
new connections;
40
(g) calculation of the system’s power distribution load profile, the expected
peak and average power flows at steady state in the dry and wet seasons;
(h) analysis of the LITS’ steady state and dynamic stability;
(i) calculation of the short circuit current at all 225kV, 66kV buses and those
33kV (or 22kV) buses that are directly connected to high voltage buses;
(j) an analysis defining the transmission network’s reactive power
compensative requirements during the planned period;
(k) analysis of the areas that the TSO or the Transmission GCP considers that
black start capability will be required;
(l) analysis of whether the transmission network can continue to meet network
performance criteria as provided under Section 12, and Technical
Schedules TS – K and TS – L of the LEGC;
(m) analysis of the least cost investment required to:
(i) support the current approved GDP, regional power development plan,
and any current connection contracts; and
(ii) meet the network performance criteria as provided under Section 12
and Technical Schedules TS – K and TS – L of the LEGC;
(n) a proposed development plan to meet the above requirements over the
planning period; and
(o) a proposed expenditure plan for the next financial year consistent with the
proposed development plan.
41
(c) unacceptable overloading of transmission elements - (i.e., Line loading
limits not to be exceeded);
(d) prolonged operation with system frequency outside the specified
performance and reliability limits; and
(e) system instability.
42
(c) electromagnetic transient (EMT) studies - to assess the effect of very short
duration current and voltage transients (e.g., lightning and switching
effects) on equipment.
43
Section 8: Connection Sub-Code
8.1 Background, Purpose, and Scope
8.1.1 To maintain stable and secure operation of the LITS to provide the expected
standard of service for the benefit of all GCPs, certain minimum technical, design
and operational criteria are to be met by all applicants seeking connection of plant
and equipment to the LITS.
8.1.2 This Section 8, the Connection Sub-code, provides protection for the transmission
system and all connected plant and equipment with an assurance of secure and
reliable operation of the LITS for efficient service delivery.
8.1.3 The purpose of the Connection Sub-code is to:
(a) provide the framework, rules and guidelines for connection to the
transmission network to facilitate the harmonious and coordinated access
to the LITS by GCPs in a fair, transparent and non-discriminatory manner;
(b) specify the minimum technical, design and operational criteria at the
connection point of a GCP and to ensure maintenance of acceptable
reliability and quality service;
(c) establish the process to be followed to set up a new connection or modify
an existing connection to the transmission network without adverse effects
to the LITS; and
(d) define the data exchange requirements between the TSO and GCPs.
8.1.4 The scope for this Sub-code covers the responsibilities and grid connection
requirements for the following:
(a) the TSO;
(b) the Transmission GCP,
(c) other transmission network operators (either within or outside Liberia) that
are connected or intending to be connected to the TSO system (LITS);
(d) Distribution GCPs connected (or intending to be connected) directly to the
LITS;
(e) Generation GCPs connected or intending to be connected to the LITS;
(f) Large Consumers connected to (or intending to be connected) directly to
the LITS; and
(g) Ancillary services providers to the LITS.
44
8.2 Connection Principles
8.2.1 The Connection Sub-code is based on the following principles relating to
connection to the LITS:
(a) Provided they satisfy all requirements in this Sub-code, all Generation
GCPs including VRPPs, Distribution GCPs and Large Consumers that
seek to connect directly to the network of the Transmission GCP shall have
the opportunity to connect to the LITS and have fair and equitable access
to the services provided by the TSO;
(b) The terms and conditions under which connection to the LITS and provision
of service is to be granted shall be set out in a commercial agreement
designated as the Connection Agreement entered between the TSO and
the GCP;
(c) The processes and operations under this Sub-code should result in the
achievement of
I) long term benefits to GCPs in terms of costs and reliability of the LITS,
and
ii) open communication and information flows between the TSO and
GCPs while ensuring the security of confidential information
belonging to GCPs; and
(d) No facilities shall be connected without a minimum arrangement for
communications, metering and protective relaying being in place.
8.2.2 The TSO shall not assume any responsibility for the protection of a GCP’s plant or
equipment or any other portion of the GCP’s electrical equipment. A GCP shall be
responsible for protecting its equipment in such a manner th at faults or other
disturbances within the LITS do not cause damage to the GCP’s equipment.
8.3 General
A GCP shall construct, operate, and maintain all equipment that are part of its facility in
accordance with:
45
(c) enter into a Connection Agreement for a connection to the LITS with any
applicant that seeks to connect to the grid and meets the specified
requirements;
(d) advise a GCP or any other person who may be affected about any
expected service interruption so that the GCP may make alternative
arrangements during such interruption;
(e) make recommendations to the Transmission GCP and the other GCPs
regarding the reinforcement or expansion of their facilities to meet reliability
requirements; and.
(f) coordinate the planning and development of the LITS in accordance with
the terms and conditions of the TSO License and the LEGC.
46
availability and reliability such that electricity may be transmitted efficiently
and continuously to the agreed capability;
(l) employ its best efforts to restore equipment and service as soon as
practicable following any interruption at a Connection Point; and
(m)comply with applicable regulatory provisions and all relevant provisions of
the LEGC.
A Generation GCP that seeks connection of its generating facility to the LITS has an
obligation to:
(a) submit to the TSO an application in respect of a new or an altered
equipment owned, operated or controlled by it and which it desires to
connect to the LITS;
(b) have in force a valid Connection Agreement with the TSO prior to the
facility being connected to the LITS;
(c) comply with the requirements of the TSO and the relevant Transmission
GCP in respect of design requirements of equipment proposed to be
connected to the LITS;
(d) at all times, comply with applicable requirements and conditions of
connection for generating units as stipulated in the LEGC and in
accordance with its Connection Agreement with the TSO;
(e) provide generating unit technical characteristics, data and Availability
Declaration information to the TSO in accordance with the relevant
provisions of the LEGC;
(f) permit and participate in the inspection and testing or commissioning of
facilities and equipment to be connected to the LITS;
(g) permit and arrange for the witnessing and participation of the TSO and
the relevant Transmission GCP in the commissioning or re-
commissioning of facilities and equipment to be connected to the LITS;
(h) commit to operate its facilities and equipment in accordance with the
instructions of the TSO, so long as it remains connected to the LITS; and
(i) give prior notice of any intended voluntary disconnection in accordance
with the provisions of this Sub-code.
A Demand GCP that seeks connection to the LITS has an obligation to:
(a) submit to the TSO an application in respect of any new or altered
equipment or network that it owns, operates or controls and which he
desires to connect to the LITS;
(b) have in force a valid Connection Agreement with the TSO prior to its
equipment or network being connected or re-connected to the LITS;
47
(c) comply with the requirements of the TSO and the relevant Transmission
GCP in respect of the design and technical standards of equipment or
networks proposed to be connected to the LITS;
(d) ensure that all facilities which are owned, operated or controlled by it and
associated with a Connection Point at all times comply with applicable
requirements and conditions of connection for GCPs as stipulated in the
LEGC and in accordance with the Connection Agreement with the TSO;
(e) provide to the TSO information on energy and power demand forecasts as
specified in the relevant sections of the LEGC;
(f) permit and participate in inspection and testing of facilities and equipment
in accordance with the provisions of the LEGC;
(g) permit and arrange for the witnessing and participation of the TSO and the
relevant Transmission GCP in the commissioning or re-commissioning of
facilities and equipment which are to be connected to the LITS;
(h) commit to operate its facilities and equipment in accordance with the
instructions of the TSO, so long as it remains connected to the LITS; and
(i) provide prior notice of any intended voluntary disconnection in accordance
with the provisions of this Sub-code.
8.8.2 The details of the investment boundary shall be as agreed between the GCP and
the Transmission GCP, in accordance with the principles stated in sub-section
8.8.1, and recorded in detailed drawings, diagrams and documentation as part of
the Connection Agreement.
8.8.3 For clarity, it is noted that the investment boundary may not necessarily be the
Connection Point.
8.9.2 The Connection Point shall be described with detailed drawings, diagrams and
documentation in the Connection Agreement.
48
8.10 Ownership Boundary
8.10.1 The Connection Point shall be the ownership boundary between the Transmission
GCP and any other GCP.
8.10.2 The assets for each party at the ownership boundary shall be listed with detailed
drawings, diagrams and documentation provided in the Connection Agreement.
49
8.13.2 The TSO shall specify which of the planning studies described in Section 7 of the
LEGC will be carried out to evaluate the impact on the Grid for a proposed
development.
8.13.3 A prospective GCP may request additional technical studies to be undertaken by
the TSO as part of the Grid Impact Studies and shall bear the cost of the additional
studies requested.
8.13.4 An applicant for a new connection or a modification of an existing connection to
the LITS shall take all the necessary steps to ensure that the proposed
development will not result in the degradation of the LITS.
8.13.5 The TSO may disapprove an application for connection or a modification to an
existing connection if the Grid Impact Studies show that the proposed development
will result in unacceptable degradation of the LITS.
8.13.6 To enable the TSO carry out the necessary detailed Grid Impact Studies, a GCP
may be required to provide data as specified in the relevant sections of the
Planning Sub-code, the Connection Sub-code and any additional data that may be
specified by the TSO.
8.13.7 The TSO shall maintain an up-to-date fault level database that should be made
available to a GCP on request. The TSO shall inform the GCP, if fault levels at a
Connection Point are likely to impact adversely on a GCP’s equipment that is
connected to the Grid. The TSO shall also provide information and
recommendations on mitigation measures (e.g., a special protection system) as
may be needed.
8.15.2 The TSO, in consultation with the Transmission GCP, shall evaluate the
application and inform the applicant whether the proposed development is
acceptable or not within sixty (60) days from the date of submission of the
completed application.
8.15.3 If the application is acceptable the TSO shall, in consultation with the Transmission
GCP, approve the Connection Proposal or the Connection Modification Proposal
and sign a Connection MOU or a Connection Modification MOU, (as the case may
be,) with the applicant.
8.15.4 If the application is not acceptable, the TSO shall notify the applicant stating why
the application is not acceptable. The TSO shall include in its notification,
suggestions on how the application could be improved and made acceptable.
8.15.5 Where an applicant’s connection requirement is rejected because it is not covered
by the existing approved GDP, the applicant may request for a modification of the
approved GDP through the TSO or Transmission GCP for consideration and
approval by the LERC.
8.15.6 When the appropriate modification of the GDP has been approved in accordance
with the procedures as issued from time to time by the LERC, then the TSO and
the relevant Transmission GCP may arrange to connect the applicant, provided
the applicant agrees to pay for costs arising directly from the proposed connection.
8.15.7 The applicant may revise and resubmit the application as it deems appropriate,
and the TSO and Transmission GCP shall consider the resubmission.
8.15.8 If the TSO/Transmission GCP and the applicant cannot reach agreement on the
proposed connection or the modification to an existing connection, either party may
bring the matter to the attention of the LERC for resolution.
51
8.15.9 If a Connection MOU or Connection Modification MOU is signed, the applicant
shall, within thirty (30) days from signing (or a mutually agreed longer period),
submit to the TSO the Detailed Planning Data pertaining to the Connection
Proposal or the Connection Modification Proposal in accordance with the
requirements stated in Section 7.6 of the Planning Sub-code.
8.15.10 The applicant seeking connection shall undertake to build and operate its network
or installed equipment in compliance with th e LEGC and other existing regulations,
rules, standards and procedures.
8.15.11 The applicant may at any time thereafter commence construction of the facility
subject to having deposited copies of the Connection MOU or the Connection
Modification MOU with the LERC and any other relevant regulatory authority (as
may be required).
8.15.12 In consultation with the Transmission GCP, the TSO and the applicant shall
negotiate and execute a Connection Agreement or Amended Connection
Agreement, (as the case may be,) before the construction is completed after
making any relevant corrections and amendments to the MOU to reflect what has
been constructed and/or installed at the Connection Point.
8.15.13 The Connection Agreement or the Amended Connection Agreement shall only
come into force after the satisfactory construction and commissioning of the facility
and the issuance of a Certificate of Approval to Connect by the TSO.
8.15.14 The TSO shall lodge copies of a Connection Agreement or Amended
Connection Agreement with the LERC within fourteen (14) days after its
execution.
8.16.2 All other equipment directly connected to the connection point must also be
capable of withstanding the maximum short circuit current expected at the
connection point.
8.16.3 A Transmission GCP must annually advise the maximum short circuit current that
may occur at each connection point. This shall be calculated considering power
system development potential consistent with the targets specified in section 8.19
of the LEGC.
8.16.4 For a Generation GCP including VRPPs, the circuit breaker to be used for
connection switching must be equipped with a synchro-check system and
52
disconnectors to ensure safety, unless otherwise agreed with the relevant
Transmission GCP and TSO.
8.17.3 Each Generation GCP (including the VRPP GCPs) shall have its own control
center facility well equipped to effectively schedule the power interchange with the
TSO’s LITS Control Centre.
53
8.18.2 Equipment protection relates to the selective and rapid detection of a fault and
disconnection of the faulty equipment or circuit.
8.18.4 Protection schemes are considered adequate when the protection relays perform
correctly in terms of:
(a) Dependability,
(b) Security,
(c) Speed of operation,
(d) Selectivity, and
(e) Sensitivity.
8.18.6 The TSO and each GCP shall implement the prevailing protection philosophy,
standards and preventive maintenance procedures that shall improve the reliability
performance of their respective systems and result in the least adverse effects on
the LITS.
8.18.7 The Transmission GCP and other GCPs are responsible for designing, installing,
and testing protection system in their networks so that they comply with the
protection adequacy requirements in sub-section 8.18.4 as determined by the TSO
and specified in relevant Connection Agreements. Protection schemes shall be
secured against unwanted operation for out-of-zone faults, brief overloads,
transient surges, or power swings etc.
8.18.8 Electrical lines connecting a GCP's network to the transmission network, and the
transmission network itself, must be equipped with protection system in
accordance with the latest version of standards published by the Transmission
GCP periodically.
8.18.9 The coordination of protections at connection points must be agreed between the
TSO, Transmission GCP and other GCPs and the protection system settings must
be technically coordinated and graded in accordance with values approved and
issued by the TSO.
54
8.18.10 All Generation GCPs with facilities connected to the transmission network shall
provide protection against
(a) loss of excitation on the generating unit, and
(b) pole slipping on the generating unit.
8.18.11 All GCPs shall ensure correct and appropriate settings of protection to achieve
effective removal of faulty equipment within the clearance time specified in section
8.19 of this LEGC.
Back-up Protection
8.18.12 Backup protection facilities shall be provided in accordance with the prevailing
protection standards in case of failure of the main protection to operate.
8.18.13 All circuit breakers connecting to a Connection Point must be equipped with
breaker failure protection. If the protection system fails to interrupt fault current
within fault current interruption time, the circuit breaker failure protection shall be
capable of initiating tripping of all the necessary electrically adjacent circuit
breakers to interrupt the fault current as provided under section 8.19.
8.18.14 In the circumstances cited in sub-section 8.18.13 that involve faults on the GCP's
network, the GCP's protection may be allowed to trip necessary circuit breakers
on Transmission GCP’s network (inter-tripping of protection equipment), subject to
consensus of the Transmission GCP and the TSO, and this must be described in
the Connection Agreement.
Protection Bypass/Disconnection
8.18.15 Protection settings at the connection point shall not be altered, or protection
bypassed and/or disconnected without consultation and agreement of the TSO and
the GCP.
8.18.17 If an agreement as required under sub-section 8.18.16 has not been reached the
electrical equipment should be removed from service forthwith.
8.18.19 Additional protection functions required for a VRPP are specified in section 15.7
under the Renewable Energy Sub-code of the LEGC.
55
Network Stability and Integrity
8.18.20 High speed relays, high speed circuit breakers and automatic re-closing facilities
shall be used where studies show that their application will enhance network
stability. Automatic re-closing under out-of-step conditions shall be prevented by
blocking relays.
8.18.22 The target performance for the protection system of a GCP measured in terms of
Dependability Index shall be as specified in sub-section 12.6.3 of the LEGC.
8.19.5 A Transmission GCP may propose to LERC a maximum fault level or fault
clearance time different from that specified in the TSO’s System Operations
Manual for specific substations where it reasonably considers such alternative fault
level or clearance time would result in a lower overall cost of supply to consumers.
Such a proposal should demonstrate the overall cost benefit to consumers of such
a different fault level or clearance time.
8.19.6 LERC shall duly consider any such proposal (stated in sub-section 8.19.5) in
consultation with the GCAC, the TSO and all affected GCPs.
8.19.7 Where the LERC considers that such a proposal would result in a lower overall
cost to consumers without compromising on system integrity, a fault level or
56
clearance time different from the specified default fault level or clearance time for
a specific substation may be approved.
57
equipment to the interface cable to the Main Distribution Frame (MDF) shall be the
responsibility of the GCP.
8.21.7 Measured quantities/values and indications to be supplied by GCPs to the TSO
shall be in the formats as specified by the TSO or as agreed between TSO and
GCP. Where the required signals become unavailable or do not comply with
applicable standards for reasons within the control of the provider of the
information, the GCP shall report the deficiencies to the TSO and restore or correct
the signals and/or indications to what was agreed.
8.21.8 The TSO shall notify a GCP of additional measured quantities and/or indications
in relation to a GCP plant and equipment that are needed to meet a Transmission
GCP’s system requirement. The costs related to the GCP’s modifications for the
additional measured quantities and/or indications shall be for the account of the
providing GCP.
8.21.9 Within seven (7) days of receipt of TSO’s notification specified in sub-section
8.21.8, the GCP shall ensure that such measured quantities and/or indications are
made available at the RTU.
8.21.10 The TSO and the GCP shall agree on the timeous provision of operational data
items as per the relevant Power Purchase Agreement (PPA) and/or Power Supply
Agreement (PSA) or TSA.
8.21.11 The TSO and a GCP shall jointly verify all measured quantities and/or indications
for functionality and accuracy once every three (3) years, so as to achieve overall
accuracy of operational measured quantities within the limits agreed.
8.21.12 The data formats to be used and the fields of information to be supplied to the
TSO by the GCP shall be as per the relevant PPA, PSA or TSA and Connection
Agreement.
8.21.13 The TSO shall provide periodic feedback to a GCP regarding the status of
equipment and systems installed at the Connection Point. The feedback shall
include, but not be limited to, results from tests, condition monitoring, inspections,
audits, failure trends and calibration. The frequency of the feedback shall be
determined in the operating agreemen t/service level agreement.
58
(a) Forecast Data - includes demand and active energy, and shall contain the
GCP's best estimate of the data being projected for five (5) successive
years
(b) Estimated Equipment Data – contains the GCP's best estimate of the
values of parameters and information about the equipment for five (5)
successive years; and
(c) Registered Equipment Data – shall contain validated actual values of
parameters and information about the equipment that are submitted by the
GCP to the TSO at the Connection Date.
Stages of Data Registration
8.22.2 The data relating to a Connection Point and a GCP development that are submitted
by an applicant for a new connection, or an amended connection shall be
registered in three stages and classified accordingly as:
(a) Preliminary Project Planning Data;
(b) Committed Project Planning Data; and
(c) Connected Project Planning Data.
8.22.3 The data that are submitted at the time of application shall be considered as
Preliminary Project Planning Data. These shall contain the Standard Planning Data
and the Detailed Planning Data specified in Section 7.6 of the Planning Sub-code.
8.22.4 Once a Connection MOU or Connection Modification MOU is signed, the
Preliminary Project Planning Data as may have been amended during the
consideration of the relevant proposal shall become the Committed Project
Planning Data and shall be utilized in the evaluation of other similar applications
and in preparation of the GDP.
8.22.5 The Committed Project Planning Data shall be updated, confirmed, and replaced
with validated actual values of parameters and information about the connected
equipment or facility at the time of commissioning and shall be transformed to
become the Connected Project Planning Data.
8.22.6 The Connected Project Planning Data shall be registered to replace the
Committed Project Planning Data in accordance with the categories specified in
sub-section 8.22.1 and shall hitherto be utilized in the evaluation of other
applications for a new connection or modification of existing connection and in
preparing the GDP.
Data Forms
8.22.7 The applicant, in consultation with the TSO, shall complete and submit the forms
for all data requirements in fulfilment of either a Connection MOU or Connection
Modification MOU.
59
8.23 Submittals Prior to the Commissioning Date
Pursuant to the terms, conditions and schedules specified in the Connection Agreement,
the following shall be submitted by the applicant prior to the commissioning date:
(a) Specifications for major equipment not included in the Standard Planning
Data and Detailed Planning Data;
(b) For distribution network connections and connections for other
equipment or networks that will not form part of the LITS, details of
switching, protection and control arrangements and equipment settings for
connection to the network of a Distribution Company, a Large Consumer
or any other Demand GCP system that will be extracting power from the
LITS;
(c) For assets that will form part of the LITS, electrical diagrams and drawings
of the applicant’s equipment at the LITS node;
(d) Information that will enable the TSO to prepare the Connection Point
drawings;
(e) Copies of all safety rules and local safety instructions applicable to the
applicant’s equipment and a list of Safety Coordinators;
(f) A list of the names and telephone numbers of authorized representatives,
including confirmation that they are fully authorized to make binding
decisions on behalf of the applicant, in relation to operations of the LITS;
(g) Proposed maintenance program; and
(h) Commissioning and test procedures at the Connection Point and for the
connected facility.
8.24 Commissioning
Procedure for Commissioning of Equipment and Physical Connection to the LITS
8.24.1 Upon completion of construction, erection or installation of the proposed facility,
commissioning of the applicant’s development including work at the Connection Point, the
equipment at the Connection Point or the GCP development shall be subjected to the
required commissioning and test procedures.
8.24.2 The procedure for any tests which may require, result in, or involve a temporary connection
to the LITS shall be jointly agreed, scheduled and performed by the applicant or GCP and
the TSO in collaboration with the Transmission GCP.
8.24.3 Where the tests are successful and the installation ready for operation, the applicant or
GCP shall submit to the TSO, a statement of readiness to connect, which shall include the
test results and the commissioning report.
60
8.24.4 The TSO may within fourteen (14) days after the receipt of the statement of
readiness to connect, perform at its sole discretion any tests it deems necessary
to accept or decline the statement of readiness to connect.
8.24.5 Upon acceptance of the statement of readiness to connect received from an
applicant or GCP, the TSO shall issue a Certificate of Approval to Connect and
arrange with the Transmission GCP to connect the facility at the convenience of
the applicant or the GCP as may be appropriate.
8.24.6 The physical connection to the LITS shall be made only after the Certificate of
Approval to Connect has been issued by the TSO.
Requirement to Inspect and Test Equipment During Commissioning
8.24.7 Any new or replacement equipment to form part of or to be connected to the LITS
shall be inspected and tested by the TSO to demonstrate that it complies with the
relevant standards, the provisions of the LEGC and any relevant Connection
Agreement prior to (or within an agreed time after) being connected to the LITS.
The Transmission GCP is entitled to witness such inspections and tests.
8.24.8 When the TSO or Transmission GCP notifies the GCP that the status of a
Connection Point or any equipment of the GCP does not meet the conditions for
energizing, the GCP shall complete the necessary adjustments and modifications
required and agree a new inspection schedule with the Transmission GCP and the
TSO.
8.24.9 During inspection, the GCP shall prove that equipment in its own system or side
of the Connection Point comply with the current technical standards, regulations,
and procedures.
8.24.10 Valid test certificates shall be produced upon demand (or within an agreed time
thereafter) by any affected GCP, showing that the equipment has passed the tests
and complies with the required standards before connection to a network.
Coordination During Commissioning
8.24.11 A GCP seeking to connect a facility to the LITS shall cooperate with other GCPs
and the TSO to develop procedures that will ensure that the commissioning of the
connection and the connected facility is carried out in a manner that:
(a) does not adversely affect other GCPs or affect power system security or
quality of supply; and
(b) minimizes the threat of damage to any other GCP’s equipment.
8.24.12 Not less than four (4) months prior to the proposed commencement of
commissioning of a new or replacement equipment (other than replacement by
identical equipment) that could reasonably be expected to alter performance of the
power system, the GCP shall submit to the TSO sufficient design information
including proposed parameter settings to allow critical assessment and analytical
61
modelling of the effect of the new or replacement equipment on the performance
of the power system.
8.24.13 The TSO shall consult with other relevant GCPs as appropriate and within twenty
(20) days of receipt of the design information , notify the GCPs for any comments
on the proposed parameter settings of the new or replacement equipment.
8.24.14 The TSO and affected GCPs shall consult and agree on the parameter settings.
Commissioning Program
8.24.15 Not less than three (3) months prior to the proposed commencement of
commissioning by a GCP of any new or replacement equipment that could
reasonably be expected to alter performance of the power system, the GCP shall
inform the relevant Transmission GCP and the TSO in writing of the commissioning
program including test procedures and proposed test equipment to be used in the
commissioning.
8.24.16 The relevant Transmission GCP and the TSO shall, within fifteen (15) days of
receipt of such information notify the GCP that it either agrees with the proposed
commissioning program and test procedures or that it requires changes in the
interest of power system security, safety or quality of supply.
8.24.17 If the Transmission GCP or the TSO require changes, then the parties shall co-
operate to reach agreement and finalize the commissioning program within a
reasonable period.
8.24.18 A GCP shall not commence commissioning until the commissioning program has
been finalized and agreed with the Transmission GCP and the TSO.
8.24.19 The Transmission GCP and the TSO shall not unreasonably delay finalizing a
commissioning program.
Commissioning Tests
8.24.20 The TSO may, at its sole discretion, witness commissioning tests relating to new
or replacement equipment that could reasonably be expected to alter performance
of the power system or the accurate metering of energy.
8.24.21 The Transmission GCP and the TSO shall, within a reasonable period after
receiving advice of commissioning tests, notify the (requesting) GCP [whose new
or replacement equipment is to be tested] whether or not it wishes to witness or
observe the commissioning tests and if it finds the proposed commissioning times
to be suitable.
8.24.22 A GCP whose new or replacement equipment is tested under this provision shall
submit to the Transmission GCP and the TSO the commissioning test results
demonstrating that the new or replacement equipment complies with the provisions
of the LEGC or the relevant Connection Agreement or both to the satisfaction of
the Transmission GCP and the TSO.
62
8.24.23 If the commissioning tests conducted in relation to a new or replacement item of
equipment demonstrates non-compliance with one or more requirements of the
LEGC or the relevant Connection Agreement then the GCP whose new or
replacement equipment was tested shall promptly meet with the TSO to agree on
a process aimed at the achievement of compliance of the relevant equipment with
the provisions of the LEGC.
8.24.24 The TSO may independently or at the request of a GCP direct that the
commissioning and subsequent connection of the equipment must not proceed if
the relevant equipment does not meet the technical requirements and applicable
standards.
63
8.25.8 The title block of the Electrical diagram and Connection Point drawing shall
include the names of authorized persons together with provisions for the details of
revisions, dates, and signatures.
Changes to Electrical Diagrams and Connection Point Drawings
8.25.9 The TSO and other affected GCPs shall be provided with a revised Electrical
diagram and Connection Point drawing by the Transmission GCP or the relevant
GCP, at least one month prior to a proposed addition to or change of equipment
connected to or forming part of any LITS Node.
8.25.10 If the modification involves the replacement of existing equipment, the revised
Electrical diagram and Connection Point Drawing shall be provided to the TSO or
other party in accordance with the requirements of the Amended Connection
Agreement.
8.25.11 The revised Electrical diagram and Connection Point drawing shall incorporate
the new equipment to be added, the existing equipment to be replaced or the
change in Equipment Identification.
Validity of Electrical Diagrams and Connection Point Drawings
8.25.12 The composite Electrical diagram and Connection Point drawing prepared by the
TSO in accordance with the provisions in sub-section 8.25.5 shall be the Electrical
diagram and Connection Point drawing to be used for all operation and planning
activities associated with the Connection Point.
8.25.13 If a dispute involving the accuracy of the composite Electrical diagram or
Connection Point drawing arises, a meeting between the TSO and the GCP or any
other relevant parties shall be held as soon as possible, to resolve the dispute.
65
8.27.6 If the TSO or a GCP either:
(a) is not satisfied that a generating unit does comply with one or more
technical requirements, or
(b) does not have evidence demonstrating that a generating unit complies with
the technical requirements, or
(c) holds the reasonable opinion that there is or could be a threat to the power
system security,
the TSO may independently or upon the advice of a GCP, direct the relevant
Generation GCP to operate the relevant generating unit at a particular generation
output or in a particular mode until the Generation GCP submits evidence
reasonably satisfactory to the TSO or the GCP that the generating unit is
complying with the relevant technical requirement.
8.27.7 A Generation GCP shall maintain records for five years on each of its generating
units and power stations setting out details of the results of all technical
performance and monitoring tests conducted under the provisions of the LEGC
and make these records available to the relevant GCP and the TSO on request.
8.28.3 A GCP may not carry out an inspection under this section 8.28 on more than two
occasions in any month, except for the purpose of verifying the performance of
corrective actions claimed to have been carried out in respect of non-conformance
observed and documented on a previous inspection or for the purpose of
investigating an operating incident that has occurred.
66
8.28.4 At any time when the representative of a GCP is conducting an inspection , that
representative shall:
(a) not interfere with the operation of the facility except to the extent reasonably
necessary and approved by the Transmission GCP and the TSO (such
approval not to be unreasonably withheld or delayed); and
(b) observe all safety precautions, site access and clearance protocols of the
facility, provided that these are not to be used to delay or deny the granting
of the access for inspection.
8.28.5 Any representative of a GCP conducting an inspection under this section must be
appropriately qualified to perform the relevant inspection.
8.28.6 The cost of inspections under this section shall be borne by the GCP requesting
the inspection.
8.28.7 The TSO or any of its authorized representatives may, at any time and without
notice, inspect a facility of a GCP and the operation or maintenance of that facility
to:
(a) assess compliance by the GCP with its operational obligations under the
LEGC or an ancillary service agreement;
(b) investigate any possible past or potential threat to power system security;
or
(c) conduct any periodic familiarization or training exercise associated with the
operational requirements of the LITS.
8.28.8 A GCP who undertakes an inspection under this section shall within seven (7)
days of first entry submit to the TSO and the Transmission GCP a report that
provides the findings and results of the inspection carried out.
Right of Testing
8.28.9 A GCP who has reasonable grounds to believe that equipment or facilities owned
by itself or by others may not comply with the LEGC or the Connection Agreement
may request testing of the relevant equipment by giving notice in writing to the
TSO.
8.28.10 The TSO shall notify the Transmission GCP and may conduct, either by itself or
by contract or otherwise arrange for, the relevant test(s) required at a time suitable
to the TSO and the Transmission GCP, if the Transmission GCP’s involvement is
necessary.
8.28.11 The costs of such tests shall be borne by the GCP that requested for the test,
unless the target equipment is determined by the tests to be non -compliant with
the relevant Connection Agreement or the LEGC, in which case all reasonable
costs of such tests shall be borne by the owner of that facility.
67
8.28.12 Tests shall be conducted using standard test procedures agreed between the
relevant parties, which agreement shall not be unreasonably withheld or delayed.
8.28.13 Tests shall be carried out only by persons with the relevant skills and experience.
8.28.14 A GCP shall give the TSO adequate prior notice of the intention to conduct a test
in respect of equipment within the GCP’s facility.
8.28.15 The GCP who requests a test under this section may appoint a representative to
witness the test and the representative so appointed shall be provided with all the
necessary information, schedules, and procedures to enable that representative
to follow the stages of the test as it is being conducted.
8.28.16 An accredited testing officer or expert who conducts a test shall submit a report
to the GCP who requested the relevant test, the TSO, the Transmission GCP and
to any other GCP that is likely to be affected by the results of the test within a
reasonable period after the completion of the test, but in any case, not exceeding
two (2) weeks except for stated reasons.
8.28.17 The TSO may, at the request of a GCP and subject to the other provisions of this
Sub-code regarding entry and inspection, instruct a Transmission GCP to arrange
and attach a test or monitoring equipment to its plant.
8.28.18 In carrying out a monitoring directive, the performance of the monitored plant or
equipment shall not be constrained in any way.
8.28.19 Notwithstanding any provisions in this section, the TSO may undertake
equipment testing at any time it deems necessary in accordance with procedures
prescribed under section 9.17.
68
(b) a new facility of the LITS is commissioned;
(c) a new generating unit of a Generation GCP or equipment of any other GCP is
commissioned that is expected to substantially alter the power transfer capability
of the transmission network; and
(d) settings or changes are made to any power system stabilizers.
8.30.2 The TSO shall develop a program and coordination arrangements for the tests including
criteria for continuation with the tests and operational procedures.
8.30.3 Operational conditions for each test shall be arranged by the TSO and the test procedures
shall be coordinated by an officer nominated by the TSO who has the authority to stop the
test or any part of it or vary the procedure within pre-approved guidelines if that officer
considers any of these actions to be reasonably necessary.
8.30.4 Each GCP shall cooperate with the Transmission GCP and the TSO when required during
the planning, preparation and conduct of tests on the LITS to assess the technical
performance of the transmission network and, if necessary, conduct coordinated activities
to prepare for power system-wide testing or individual on-site tests of a GCP’s facility or
plant, including the disconnection of a generating unit.
8.30.5 The TSO may direct changes in operation of generating units during power system tests
if this is deemed necessary to achieve operational conditions on the LITS which are
reasonably required to achieve valid test results.
8.30.6 The TSO shall plan the timing of tests so that the variation from scheduled dispatch that
would occur is minimized and the duration of the tests is as short as possible and
consistent with test requirements and power system security.
69
8.31.5 The Transmission GCP shall notify the TSO and any other GCP with whom the
TSO has a Connection Agreement, if it believes in its reasonable opinion, that the
terms and conditions of such a Connection Agreement will be affected by the
procedures for disconnection or the proposed procedures agreed with any other
GCP. The parties shall negotiate any amendments to the procedures for
disconnection or any amendments to the Connection Agreement that may be
required.
Involuntary Disconnection
8.31.6 The TSO or a Transmission GCP may without the prior consent of any affected
GCP, disconnect a GCP’s facilities from the LITS under any of the following
conditions:
(a) during an emergency in accordance with the provisions of the LEGC;
(b) in accordance with applicable laws or order of the law courts; or
(c) in accordance with the provisions of the GCP’s Connection Agreement.
8.31.7 In all cases of disconnection by the TSO during an emergency, the TSO shall
undertake a review and thereafter provide a report to the GCP and the GCAC
advising of the circumstances requiring such action.
8.31.8 In carrying out its obligations under sub-section 8.31.6 (a), where there is more
than one GCP involved, the TSO shall, to the extent practicable,
(a) implement an equitable sharing of the reconnection of facilities up to the
power transfer capability of the network, and,
(b) in performing these obligations, both the TSO and the relevant
Transmission GCP shall, to the extent practicable, give priority to
reconnection of sensitive loads.
8.31.9 All disconnections of a GCP’s facilities other than those required during an
emergency, shall be undertaken in an orderly manner and include a request to the
relevant GCP to reduce the power transfer level at the proposed point of
disconnection to zero prior to disconnection at the appointed time.
Disconnection to Implement Regulatory Order
8.31.10 The TSO or a Transmission GCP may, pursuant to a directive given by a
regulatory or legal authority in accordance with the laws of Liberia or following the
withdrawal of the GCP’s License or Permit in accordance with the Regulations or
permitting guidelines, disconnect a GCP’s facilities from the LITS without the
GCP’s prior consent.
Obligation to Reconnect
8.31.11 The TSO shall reconnect a GCP’s facility to the LITS as soon as practicable if:
70
(a) it is reasonably satisfied that there no longer exists an emergency due to
which the GCP’s facility was disconnected under sub-section 8.31.6(a) of
the LEGC;
(b) it is reasonably satisfied that there no longer exists a reason for the
disconnection under applicable laws or the GCP’s Connection Agreement
as provided in sub-sections 8.31.6(b) and 8.31.6(c) respectively; or
(c) any of the following conditions are met:
(i) a code breach giving rise to disconnection has been remedied,
(ii) where the breach is not capable of remedy, compensation has been
agreed and paid by the GCP to the affected parties or, failing
agreement, the amount of compensation payable has been
determined in accordance with the dispute resolution procedure of
the LERC or GCAC and that amount has been paid,
(iii) where the breach is not capable of remedy and the amount of
compensation has not been agreed or determined, assurances for
the payment of reasonable compensation have been given to the
satisfaction of the TSO, the Transmission GCP and the affected
parties, or
(iv) the GCP has taken all necessary steps to prevent the re-occurrence
of the breach and has delivered binding undertakings to the TSO or
the Transmission GCP that the breach will not re-occur.
71
Part C: Rules Of Practice
Part C, the Rules of Practice, covers the arrangements for system operations, scheduling
and dispatch and safety procedure. This Part details the principles, procedures, and
processes for secure power system operation s; defines the roles and responsibilities of
actors in system operation including the planning and coordination of generation and
transmission outages and resolution of faults to ensure secure operation of the LITS. It
also provides for the ancillary service procurement procedures, the roles and
responsibilities of all the actors in producing the demand forecast data used in operational
planning, the generation scheduling and dispatch process, and safety coordination
procedures.
72
Section 9: Operations Sub-Code
9.1 Background, Purpose, and Scope
9.1.1 Section 9 of the LEGC contains the provisions and rules governing all the relevant
aspects of power system operation. The Operations Sub-code governs the day-to-
day control, management and short-term planning functions needed to ensure the
satisfactory performance of the LITS.
9.1.2 The LITS is operated in parallel as an interconnected grid with the CSLG
transmission system which is part of the regional WAPP interconnected system.
In pursuance of harmonized interconnected operation s, the WAPP has developed
operating guidelines that are subscribed to by all operating members including
Liberia represented by the TSO. The TSO and LERC commit to harmonize the
LITS operations under the LEGC to the requirements as provided in the WAPP
operating guidelines.
Purpose
9.1.3 The purpose of the Operations Sub-code is to define the general arrangements,
obligations, policies, criteria and procedures needed to ensure the coordinated
provision of system services, network switching, demand /supply balancing,
operational planning and events reporting related to the operation of the LITS in a
manner consistent with the security of supply and reliability requirements as set
out in Technical Schedules TS – K and TS – L, taking into account any expected
or real constraints on the generation and transmission systems.
Scope
9.1.4 The Operations Sub-code shall apply to the TSO and all GCPs and their agents
and shall deal with issues relating to the following:
(a) Operational planning and management;
(b) Power system operating states and criteria;
(c) Real-time system monitoring and control;
(d) Facilities and procedures for communication during normal and emergency
conditions;
(e) Outage and maintenance planning, coordination and execution;
(f) Ancillary services; and
(g) System disturbance monitoring, analysis and reporting.
9.1.5 All entities to whom this Sub-code applies shall always adopt Prudent Utility
Practice to ensure reliable and satisfactory operation of the LITS.
74
System Security
9.2.12 The LITS shall be operated as far as practical so that instability, uncontrolled
separation, or cascading outages do not occur as a result of the most severe single
contingency. Multiple outages of a credible nature shall be examined and,
whenever practical, the LITS shall be operated to protect it against instability,
uncontrolled separation, and cascading outages.
9.2.13 The TSO is responsible for efficient restoration of the LITS after supply
interruptions.
9.2.14 The TSO shall operate and maintain primary an d emergency facilities to ensure
continuous operation of the LITS.
Operational Measures
9.2.15 The TSO shall establish operating instructions, procedures, standards and
guidelines in a System Operations Manual to cover the operation of the LITS under
all system conditions.
9.2.16 The LITS shall, as far as reasonably possible, be operated within defined technical
standards and equipment ratings.
9.2.17 The TSO shall manage constraints on the LITS through the determination of
operational limits, and scheduling of sufficient generation required for the demand
and ancillary services to relieve constraints.
9.2.18 To achieve a high degree of service reliability, the TSO shall ensure adequate and
reliable communications between all control centers, generating units and
substations. Communication facilities to be provided and maintained by the various
GCPs are specified in Section 13 – Data & Information Exchange Sub-code.
9.2.19 The TSO shall be responsible for the determination of the LITS protection
philosophy (as contrasted and supplementary to Equipment Protection philosophy
elaborated under section 8.18) through the conduct of applicable analytical
studies.
9.2.20 The TSO shall determine, and review on a regular basis, relay settings for main
protection and back-up protection on the LITS.
75
(c) coordination of maintenance outages with all GCPs including Large
consumers.
9.3.2 The purpose of operational planning shall be to ensure that short-term and
medium-term events such as maintenance and repair work on equipment and
apparatus, constructional activities in the transmission system and schedules
registered with the TSO by Generation, Transmission, Distribution and other
connected GCPs are handled efficiently by taking them into consideration in the
planning of daily operational activities.
Operations Plan
9.3.3 Operations plan for the LITS shall cover at least the following:
(a) Normal Operations - where each Generation GCP, Transmission GCP,
Distribution GCP or other Demand GCP, working with the TSO, shall plan
its future operations so that normal interconnected operation can proceed
in an orderly consistent manner with each Demand GCP providing its best
estimate of demand to the TSO to develop the total demand forecast.
76
9.4 Operations Planning Criteria
General Principles
9.4.1 Operational planning for the LITS shall be based on operations criteria that are
designed to maintain the security, reliability, safety and continuity of electricity
supply within the LITS at least cost.
9.4.2 In performing the operational planning function to provide system services
essential for the proper functioning of the LITS, the TSO shall:
(a) take into account the maintenance cycle of plant and equipment and
prepare annual, monthly, weekly and daily operational plans to achieve the
required objectives;
(b) at all times have a set of current plans, which are based on evaluated
options and implement these plans to ensure that supply quality and
reliability of the LITS are maintained;
(c) measure, record and account for all power and energy flowing or
interchanged over the LITS; and
(d) install and operate devices of acceptable accuracy at each input and output
node or feeder of the LITS for the purposes stated in sub-sections 9.4.3 to
9.4.11.
Generation Management
9.4.3 The TSO shall operate sufficient generation capacity under automatic control to
meet its obligation to continuously balance power demand and supply in real -time
in accordance with the stipulated reliability and quality of supply standards.
Voltage Management
9.4.4 The TSO, in operating the LITS, shall schedule generating unit reactive power
outputs and procure reactive compensation as necessary to maintain the voltages
at all LITS nodes and substations within established limits as stipulated in
Technical Schedules TS–L and TS–V.
9.4.5 Each generating plant shall be capable of continuous operation within the
stipulated power factor range to support voltages under normal and contingency
conditions.
9.4.6 The TSO shall employ both static and dynamic methods to maintain voltage
stability, maintain voltages at the LITS nodes within the prescribed limits and
minimize system losses using power system voltage control procedures
prescribed in Section 9.11 and methods that include but not limited to the following:
(a) Transformer tap changing;
(b) Reactor and capacitor switching;
(c) Static Var Compensators;
(d) Generating unit reactive power capability;
(e) Demand management; and
(f) Transmission lines charging capacitance.
77
Time Management and Frequency Control
9.4.7 The TSO shall control and operate all relevant LITS equipment and devices to
maintain system frequency within the stipulated performance and reliability limits,
as stipulated in Technical Schedule TS – L.
9.4.8 Each Generation GCP shall, to the extent possible, contribute to frequency
regulation to achieve the required balance. The TSO shall employ Automatic
Generation Control (AGC) and manual actions for secondary frequency control in
accordance with procedures prescribed in section 9.10. GCP’s generating units
that are required to be under AGC shall be specified in the Connection Agreement
and those not operating under AGC shall continue to follow dispatch instructions
from the TSO. The AGC shall meet the frequency and tie-line standards defined
by CLSG/WAPP.
9.4.9 Operating limits for frequency deviation and time error shall be established with
LITS reliability as priority. Each Generation GCP shall participate in time error
correction procedures and the TSO shall coordinate the time error correction
procedures.
Interchange Management
9.4.10 Each Generation GCP shall, through daily schedule verification and the use of
reliable metering equipment, accurately measure, control and account for all
energy and power interchanges.
9.4.11 Recognizing variations in generation and load patterns, each Generation GCP
(including tie-line operator) shall be active in preventing inadvertent interchange
accumulation.
78
equipment forced outages and scheduled outages. Operating reserves consist of
Quick Reserves and Slow Reserves.
Quick Reserve
9.5.3 Quick Reserve is used for balancing supply and demand when an unexpected
system event occurs within one dispatch period. Quick reserves provide capacity
that the TSO can call up at short notice to correct any imbalance and can come
from the supply side (generating units) or from the demand side (load
management).
9.5.4 During normal operation, Quick reserves can come in the forms classified as
Primary, Secondary or Tertiary reserve as follows:
(a) Primary Reserve is an automatic increase or decrease in active power
output of a generating unit in response to a system frequency fall or rise,
in accordance with the primary control capability and additional
mechanisms for controlling active power. This change in active power
output must be in accordance with the technical characteristics and loading
of the generating unit, without any time delays other than those necessarily
inherent in the design of the governor control system. Primary reserve
(positive and negative) must respond immediately and must be fully active
within 10 seconds and sustained for at least one hour.
(b) Secondary Reserve is the automatic response to frequency changes that
is fully available within 30 seconds from the time of frequency change to
take over from the Primary reserve, and which is sustainable for a period
of at least one hour.
(c) Tertiary Reserve is required to balance supply and demand for changes
within a one-hour dispatch interval and is used to restore Secondary
reserve when required. Tertiary reserve must be fully activated within 10
minutes from the instruction of the TSO and shall be sustained for at least
two hours.
9.5.5 Pursuant to sub-section 9.5.4(a), all online generating units must have their turbine
governors in service and unblocked to meet (mandatory) regulating reserve
requirements as specified in the sub-section 9.6.1(b) of the LEGC.
Emergency Reserve
9.5.6 Emergency reserve is typically made up from contracted interruptible load, gas
turbines and emergency generation facility. Emergency reserve is a less frequently
used reserve though it can be relied upon as a Quick reserve during abnormal
LITS conditions for returning the LITS to normal operating conditions while slower
reserves are being activated. Emergency Reserve can be used by the TSO for
supply-demand balancing, and for addressing network stability and voltage
constraints. Emergency Reserve shall be fully active within ten minutes from an
instruction of the TSO and shall be sustained for at least two hours.
79
Slow Reserve
9.5.7 Slow reserve (or non-spinning reserve) is the component of Operating reserve that
is not operating or synchronized to the system, but which is available to serve
demand within a specified time. Slow reserve is used to restore Quick reserve
when required usually for compensating imbalance resulting from day-ahead
prediction errors or unexpected generating unit trips.
9.5.8 A Slow (or non-spinning) reserve shall comprise the steady output available from
a generating unit that can be synchronized to the LITS and loaded up within thirty
minutes of being requested to respond to an unexpected demand increase or loss
of generation or transmission capacity and must be sustained for at least 4 hours.
Actual times for activation and sustained availability are subject to bilateral
agreements.
Negative Reserve
9.5.9 Negative reserve is the ability of generating units to reduce their active power
output for balancing the system in the case of excess of generation (i.e.
situations of high frequency) and can be of the following types:
(a) Negative Primary reserve - Generating units providing Primary reserve
must always be capable of providing the same amount of Negative
reserve without breaching the operating limits of the generating Unit;
(b) Negative Secondary &Tertiary reserves - Generating units providing
Secondary & Tertiary reserves must be capable of providing Negative
Secondary & Tertiary reserve; and
(c) Negative Emergency reserve - All generating units in operation must
provide negative Emergency reserve, meaning that they must follow the
instructions of the TSO for reducing their loading if required.
Determination and Allocation of Operating Reserves
9.5.10 The TSO shall determine and have adequate operating reserves available at all
times to ensure the security and reliability of power supply within the LITS and in
accordance with the Operating reserves allocation policy in Technical Schedule
TS–O of the LEGC.
9.5.11 Quick reserve at any time shall be set large enough to cover the net impact of the
largest single contingent event among the following, whichever is the largest:
(a) the loss of the generating unit currently producing the highest amount of
power within the LITS;
(b) the loss of generation capacity that could result from any single
transmission equipment failure, fault, or other contingency; or
(c) the loss of any power in-feed from an interconnected system.
9.5.12 The TSO shall allocate and distribute the required Quick (or spinning) reserves
among the generating units operating within the LITS such that the grid is able to
withstand any single contingency.
80
9.5.13 The TSO shall determine the amount of Slow (or non-spinning) reserve that is
required within the LITS and shall allocate and distribute this requirement among
any available generating units provided the generating unit has not been already
identified as part of the Quick reserve providers and can be synchronized and put
on-line within the stipulated time of thirty minutes (ref. sub-section 9.5.8).
9.5.14 The security of supply from the LITS especially under certain contingency
conditions, depends on the reliable and prompt start-up of Slow reserves whenever
required. Accordingly, a generating unit designated or allocated as part of the Slow
reserve providers shall ensure its readiness to start-up and generate its full
allocated power within the stipulated period.
9.5.15 A generating unit that fails to meet its operating reserve obligation shall be in
breach of the LEGC and shall be liable for penalties as may be provided for under
the Electricity MOR.
9.6.2 Operations planning for the LITS shall ensure that voltages are maintained within
the stipulated range, provided loads, and generating plants abide by the
requirements prescribed under sub-section 9.6.1.
9.6.3 Where the inherent characteristics and design of a generating unit are such that it
is reasonably able to operate beyond the prescribed requirements, the Generation
GCP will declare such capabilities of the unit to the TSO.
Coordination of Reactive Power Compensation
9.6.4 Based on the expected power flows, the TSO shall predict the voltage profile of
the LITS, the reactive power generation and reactive power reserve capacity
requirements for each section of the system and the respective quantities expected
from each generating unit to ensure satisfactory voltage levels.
9.6.5 The TSO shall instruct the use of voltage control devices and dispatch the reactive
power output of generating units to meet the requirements as economically as
possible in accordance with Section 10 of the LEGC.
81
Basic Reactive Power Compensation
9.6.6 All Demand GCPs connected to the LITS shall install devices in their respective
networks that provide sufficient reactive power compensation to maintain their
operations within the stipulated average power factor of not lower than 0.9 lagging.
9.6.7 In addition to the requirement in sub-section 9.6.1(b), generating plants shall have
reactive reserve capacity to operate with power factor at 0.90 leading for up to
thirty minutes and remain within the generating unit capability chart for temporary
sustenance of system voltage under contingency conditions.
9.6.8 The TSO shall co-ordinate with each Generation GCP on the setting of generating
unit operating points and the use of voltage control equipment to maintain
transmission voltages as specified in Technical Schedule TS–L.
9.6.9 The normal provision of reactive power requirements by any generating unit
operating at any power factor within the required limits shall be without
compensation but dispatch instructions for operation beyond the standard
requirement shall attract compensation payments from the TSO as provided under
the Electricity MOR.
9.6.10 Failure of a Generation GCP to provide the normal operational requirement for
voltage control upon the instructions of the TSO shall constitute a breach of the
LEGC for which penalties may be assessed and applied in accordance with the
Customer Service and Quality of Supply Regulations (or the Electricity MOR).
9.6.11 Provided Demand GCP’s loads and Generation GCP’s generating units have
complied with the normal reactive power compensation requirements, it shall be
the responsibility of the TSO to provide any additional reactive power
compensation that is required to maintain system voltages within the stipulated
range. Such reactive power compensation generally referred to as the “Basic
Reactive Power Compensation” shall be to the account of the TSO as part of
the general costs of operating the LITS.
Supplementary Reactive Power Compensation
9.6.12 Demand GCPs connected to the LITS shall not depend on the TSO for reactive
power support; but shall provide reactive power compensation for their systems
and ensure that customers having inductive load install capacitors so that the
power factor at the interface with the transmission system is not less than 0.95.
9.6.13 Where a Demand GCP fails to maintain its reactive power requirements or power
factor within the stipulated range, the TSO may procure or provide supplementary
reactive power compensation to ensure that the voltage standards are achieved at
the LITS node. Such non-compliant GCPs shall be liable to pay compensation to
the TSO, in addition to penalties that may be imposed by the LERC in accordance
with the Customer Service and Quality of Supply Regulations (or the Electricity
MOR), which are commensurate with either the level of their reactive power needs
that are in excess of their limits or the level of supplementary reactive
82
compensation deemed to have been procured by the TSO due to their failure to
comply with the standards.
9.6.14 The TSO shall schedule, provide, procure and/or dispatch supplementary
reactive power compensation as may be necessary to maintain system voltage
within the specified limits during normal operations as well as during grid
contingency conditions.
Compliance of Generation GCPs with TSO instructions
9.6.15 A Generation GCP shall comply with the instructions of the TSO and operate its
generating units accordingly to provide reactive power compensation and maintain
voltage levels.
9.6.16 Generation GCPs shall inform the TSO of any difficulties in operating their units to
meet the standard voltage levels or in providing their reactive power compensation
requirements. The Generation GCPs shall in addition ensure that automatic
voltage regulators and other similar devices are continuously in service and inform
the TSO accordingly whenever a generating unit is operating without its automatic
voltage regulator or any such devices.
9.6.17 The inability or unwillingness of a Generation GCP to comply with the valid
instructions of the TSO to operate at any point within the mandated limits shall
constitute a breach of the LEGC for which penalties may be assessed and applied.
84
(c) directing those specific parts of the LITS to be returned to service, as
required; and
(d) operating at security limits appropriate for an Alert state.
Emergency State
9.8.5 The LITS shall be in an Emergency state when a multiple contingency system
condition has occurred without resulting in a total system collapse, in addition to
the existence of any one of the following conditions:
(a) there is a generation deficiency;
(b) LITS transmission voltages are outside the limits of ±10% of the nominal
value; or
(c) the loading level of any transmission circuit or substation equipment is
above 110% of its continuous rating.
9.8.6 The TSO shall declare the power system to be in an Emergency state when any
of the above conditions specified for an Emergency state exists on the LITS or
when the TSO determines that there exists a situation which has an adverse effect
on electricity supply, or which poses a significant threat to system security.
9.8.7 During an Emergency state, all GCPs shall coordinate their actions to restore the
LITS to the Normal state.
9.8.8 When an Emergency state is declared, the TSO shall operate within the security
limits appropriate for an Emergency state which shall include taking such
necessary action as the following:
(a) cancelling all maintenance or other planned work affecting the security of
the LITS;
(b) cancelling, denying requests for or deferring approved planned outages;
(c) directing that transmission or generation facilities be returned to service;
and
(d) operating to security limits that is appropriate for an Emergency State.
Extreme State
9.8.9 The LITS shall be in an Extreme state when corrective measures taken by the
TSO during an Emergency state have failed to maintain the security of the LITS
and that has resulted in either cascading trips, islanding and/or system collapse.
Restorative State
9.8.10 The LITS shall be in a Restorative state when generating units, transmission
lines, substation equipment and loads are being energized and synchronized to
restore the LITS to its Normal state.
85
9.9.2 The LITS shall be operated and maintained to meet the operating limits and
performance benchmarks stipulated in Technical Schedules TS – K and TS – L
and other Reliability and Performance Standards under th e LEGC.
9.9.3 The security and reliability of the LITS shall, in accordance with Technical
Schedule TS – E, be determined based on a single contingency criterion which is
that the LITS shall continue to operate in the Normal state following the loss of any
one generating unit, a transmission line or a transformer.
9.9.4 The TSO shall operate the LITS at adequate security levels to reduce vulnerability
to transient instability, dynamic instability and voltage instability problems.
9.9.5 The system frequency shall be controlled by the Quick (or spinning) reserves
during the Normal state and by the timely use of Slow (non-spinning) reserves and
demand management practices during the Alert state and the Emergency state.
Adequate spinning reserve and non -spinning reserve shall be available to stabilize
the LITS and facilitate the restoration to the Normal state following a disturbance
leading to loss of generating capacity.
9.9.6 Following a contingency event or a significant change in power system conditions,
it is possible that the power system may no longer be in a condition which could
be considered secure on the occurrence of a further contingency event. The TSO
shall take all reasonable actions to adjust the operating conditions with a view to
returning the power system to the Normal operating state as soon as it is practical
to do so.
9.9.7 The TSO shall ensure that adequate load shedding facilities that could be initiated
automatically by frequency conditions are available and in service to facilitate the
restoration of the power system to a Normal state following significant contingency
events.
9.9.8 GCPs shall all be required to provide and maintain all required facilities consistent
with Prudent Utility Practice and to operate equipment in a manner to:
(a) assist in preventing or controlling instability within the LITS;
(b) assist in the maintenance of, or restoration of the LITS to a Normal state of
operation; and
(c) prevent uncontrolled separation of the power system, transmission break-
up, or cascading outages, following any system incident.
86
9.10.2 The following conditions shall assist with the effective control of power system
frequency by the TSO who has the mandate and authority to direct and control the
output of generating units:
(a) Generation GCPs are required to provide necessary protective devices or
systems to protect their plant and associated facilities against abnormal
and extreme frequency excursions on the power system;
(b) In order that adequate frequency control is always maintained on the LITS,
governor-controlled generating units are required to provide the Primary
reserve specified by the TSO, complying with the following requirements:
(i) when synchronized to the LITS, the units shall operate at all times
under the governor control system, unless otherwise specified by the
TSO, with all generating units operating within the appropriate ranges
as specified in section 9.13 and Technical Schedules TS–F, TS–P,
TS–K and TS–L of the LEGC;
(ii) no time delays other than those necessarily inherent in the design of
the governor control system shall be introduced; and
(iii) no frequency dead-bands shall be applied to the operation of
governor control systems.
(c) The TSO shall:
(i) arrange to have available and specifically allocate generating plant
as found appropriate that can be automatically controlled either
through AGC or directed by the TSO to ensure that normal load
variations do not result in frequency deviations outside the defined
limits for normal operation;
(ii) procure adequate ancillary services to cater for the impact of potential
power system disruptions on the power system frequency arising
from the most critical single contingency event; and
(iii) ensure that adequate facilities are always available and are under its
direction to allow for the managed recovery of the LITS to its Normal
state whenever required.
9.10.3 Non-dispatchable VRPPs are not required to provide Primary reserve; however, if
agreed between the VRPP GCP and the TSO, they may participate and will be
bound by the requirements in this section 9.10 of the LEGC as per generating
units.
Restriction of Governor Action
9.10.4 Subject to sub-section 9.10.2(b), a Generation GCP shall only restrict governor
action of a generating unit where the:
(a) action is essential for the safety of personnel and/or to avoid damage to
the plant; or
(b) reliability of the generating unit needs to be secured; or
87
(c) restriction has been agreed in advance between the TSO and the
Generation GCP; or
(d) restriction is in accordance with a dispatch instruction given by the TSO.
9.10.5 The TSO shall record the nature of the restriction, the reasons, and the time of
occurrence and duration of the restriction.
88
settings and levels, load-tap-change settings, reactive power flow and
status of reactive power supply resources; and
(d) The TSO shall arrange, coordinate, and supervise the conduct of
appropriate tests to assess the availability and adequacy of the provision
of reactive power to control and maintain power system voltages under
Normal, Alert and Emergency states.
89
9.12.9 RAS shall be subject to procedures detailing the operation and the conditions for
switching into service of the scheme. The effects of the automatic actions arising
from the operation of the RAS shall be subject to the specific agreement of all
GCPs involved.
9.12.10 The TSO shall monitor the status of all RAS and notify relevant GCPs of any
change of status.
91
Voltage and Reactive Power Control
9.13.12 Reactive power compensation which is required to maintain adequate system
voltages and to prevent power system failure through voltage collapse shall be
provided from generating units operating outside the reactive power limits defined
in the LEGC and from GCPs with the capability to supply additional reactive power
above their own requirements.
9.13.13 The TSO shall conduct technical studies based on the quantities, characteristics
and locations of forecast demand to determine the quantities and locations of
reactive power support required to maintain voltage levels and reactive power
margins at LITS nodes in accordance with the required standards.
9.13.14 Reactive power compensation and voltage control services shall be provided by
contractually committing to the TSO the ability to reserve and dispatch the reactive
power output of a generating unit and reactive power compensation devices.
9.13.15 Every generating unit including VRPPs shall provide a minimum amount of
reactive power to the TSO, in accordance with the relevant Connection
Agreements.
Black Start Capability
9.13.16 Generating plants with Black Start capability are required to enable restoration of
the LITS to Normal state following a complete or partial failure of the power system.
9.13.17 The TSO shall prepare an Emergency Power System Restoration Plan (EPSRP)
and determine the quantities and locations of black start generating units that are
required. The determination of black start requirements for the LITS shall be made
based on contingency studies performed during the preparation of the EPSRP
which studies shall, at a minimum, take into account the following:
(a) a range of reasonable initiating disturbances;
(b) the magnitude, extent and likelihood of the outage, the assumed status of
generation after the initiating disturbance and the system demand level at
the time of the disturbance;
(c) generating unit performance, including the probability that some resources
used to provide black start may fail to start; and
(d) the possibility that transmission system damage may prevent some of the
target black start resources from serving their intended loads.
9.13.18 The TSO shall secure adequate black start capacity by contractually committing
self-starting generating unit capacities which shall be used to restore service to the
LITS after a blackout.
Reliability Must-Run Requirements
9.13.19 The TSO shall contract Reliability Must-Run (RMR) generating units to cater for
situations where emergency reserve power is needed to keep the LITS secure.
9.13.20 The TSO shall:
92
(a) determine the needed RMR requirements by performing extensive
reliability studies on the LITS, taking the scheduled outages into account;
and
(b) quantify the LITS exposure to risk due to unanticipated outages and based
on its assessment, determine the additional RMR agreements that may be
required.
9.13.21 The TSO shall report on all RMR agreements by including the details in the
reliability assessment report on an annual basis to the LERC. The report shall
justify the rationale for each RMR agreement and the performance assessment of
each RMR generating unit.
94
9.15.4 The LITS Restoration Plan and associated procedures shall be developed by the
TSO in consultation with all GCPs and shall be reviewed and/or updated at least:
(a) annually;
(b) whenever changes are made in the power system configuration; or
(c) more frequently, if required.
9.15.5 Where an outside source of power is required for start-up, necessary switching
procedures shall be determined and reviewed periodically with the dispatch and
the operating personnel.
9.15.6 It shall be the responsibility of each GCP to ensure that any of its personnel who
may reasonably be expected to be involved in power system restoration are
familiar with and are adequately trained and experienced in the procedures to be
carried out and shall have sufficient authority to be able to implement the plan and
comply with any instructions issued by the TSO.
9.15.7 The TSO and all relevant GCPs shall verify the restoration procedure by actual
testing or through simulation.
Restoration Process
9.15.8 The TSO shall issue instructions to GCPs that have generating units with black
start capability to initiate a start-up.
9.15.9 Upon receipt of the instruction from the TSO, GCPs providing black start shall
startup immediately to energize a part of the LITS and/or synchronize to the LITS.
9.15.10 The TSO shall issue directions to GCPs and each GCP shall be responsible for
carrying out the directions in accordance with the provisions of the LITS
Restoration Plan.
9.15.11 The TSO shall coordinate the rate at which load is restored to prevent adding
load faster than generation and what transmission capabilities permit.
9.15.12 During total or partial collapse and as conditions are being brought back to
normal, the LITS may be operated outside normal voltage and frequency
standards.
9.15.13 The TSO shall inform all GCPs after the restoration of the LITS is completed that
(the Emergency state no longer exists and that) the LITS is back to Normal state,
and normal scheduling and dispatching operations shall then be resumed.
96
(b) thereafter notify the TSO in writing within 24 hours.
9.16.9 The TSO shall approve all schedules for equipment outages except for the
following generation facilities which do not need to be reported to or scheduled
with the TSO for outage unless the generation facility has been designated by the
TSO as affecting the reliability of the LITS:
(a) a non-registered generation facility; and
(b) a registered generation facility having a nameplate rating of less than 2
MW.
9.16.10 The TSO may, upon request, exempt certain additional facilities and equipment
from application of outage reporting and scheduling obligations set forth in sub-
section 9.16.5 where the TSO determines that the granting of such an exemption
is not inconsistent with the reliable and efficient operation of the LITS.
9.16.11 A GCP may submit an exemption request to the TSO at any time; however, it is
only after notification of the TSO’s approval of the request that the exemption shall
take effect.
Responsibility for Preparation of Outage Plans
9.16.12 The TSO has overall responsibility for assessment of the risk posed to the LITS
arising from maintenance and commissioning activities. The TSO shall therefore
coordinate maintenance activities, plan outages, administer the outage scheduling
process and shall prepare, among other things, the following outage plans:
(a) Initial Outage Plan covering the next one-year period;
(b) Provisional three-year Outage Plan (initial outage needs period inclusive);
and
(c) the annual Committed Outage Plan.
9.16.13 The TSO shall take the following into account during the preparation of outage
plans:
(a) forecast demand and the requirements of the LITS;
(b) needs for maintenance of grid components;
(c) actual maintenance program implemented;
(d) request by GCPs for changes in their maintenance schedules;
(e) the need to minimize total cost of the maintenance activity; and
(f) any other relevant factor.
Outage Planning Process
9.16.14 Each GCP shall determine its annual outage needs based upon its own criteria
and assessments and shall provide the TSO with the outage needs for the next
three years by June 15th of the preceding year.
97
9.16.15 The outage needs shall include the following information which shall also be
provided whenever a GCP wishes to request for an outage on its equipment or
facilities:
(a) the identification of the equipment and the capacity to be affected;
(b) a brief operational contingency and impact assessment report;
(c) the time it will take to restore the element in case of an emergency;
(d) a description of the maintenance work to be carried out;
(e) the expected duration of the maintenance work;
(f) an indication of the preferred start date for the outage and the expected
completion date for the work; and
(g) an indication of whether there is flexibility in dates, the earliest start and the
latest completion dates.
Initial/Provisional Outage Plans
9.16.16 Based on the outage needs information submitted, the TSO shall prepare an
Initial Outage Plan for the next year and a Provisional Outage Plan for a further
two years.
9.16.17 Whereas the TSO, in preparing the outage plans, shall endeavor to
accommodate GCPs’ requests for particular dates, the outage needs submitted by
a GCP only represent a preference which shall be subject to the scheduling
considerations of the TSO.
9.16.18 The Initial Outage Plan shall include all the outage needs provided by GCPs and
which shall be circulated to all GCPs not later than August 15th of the preceding
year.
Revised Outage Needs
9.16.19 Where the outage needs of GCPs are in conflict or are incompatible with the
service requirements of the LITS such that they cannot be accepted, the TSO shall
inform the affected GCPs and suggest, for their consideration, alternatives that
resolve the conflict following which the affected GCPs shall submit Revised outage
needs.
Committed Outage Plan
9.16.20 Upon receipt of the Revised outage needs, the TSO shall consult with affected
GCPs over any unresolved conflicts and prepare and issue by December 1st to all
GCPs, the Committed Outage Plan for the forth-coming year.
9.16.21 The Committed Outage Plan shall comprise a list indicating the planned outages
for each GCP and the associated facility or equipment that have received the
TSO’s planning approval. Outage needs that are not included in the approved
annual outage plan shall be deemed to have been denied by the TSO.
98
Outage/Maintenance Coordination
9.16.22 To ensure the coordinated implementation of the individual maintenance
programs, each GCP shall develop monthly outage requests that will specify the
details of the maintenance program for each week of the month, in accordance
with the Committed Outage Plan. The outage request for each month shall be
submitted to the TSO at least thirty (30) days before the start of the planned
maintenance.
9.16.23 The TSO shall approve all monthly outage requests that are in accordance with
the Committed Outage Plan unless unforeseen conditions make it unwise or
unacceptable from the system reliability, security or safety perspective for the
outage to proceed. In such cases, the TSO may deny, defer or cancel a previously
approved outage if it determines, in accordance with system reliability, security or
safety criteria that the planned outage poses a significant risk to the satisfactory
operation of the LITS such that it would not be prudent for the outage to proceed.
9.16.24 A GCP who no longer intends to proceed with a committed outage shall notify the
TSO and any withdrawn outages may only be added to the outage plans of
subsequent months at the sole discretion of the TSO.
9.16.25 Where the TSO cancels or denies a planned outage from proceeding, it shall
inform the affected GCP as soon as practical and cooperate with the GCP to
arrange for rescheduling of the activity at the GCP’s earliest convenience.
9.16.26 The TSO may, where necessary to maintain the reliability of the LITS in extreme
emergency conditions, recall a planned outage that has already commenced. The
TSO shall not recall an ongoing planned outage unless it has first cancelled,
deferred or rejected requests for approval of all other planned outages which
cancellation, deferral or rejection could eliminate the need to recall the ongoing
planned outage.
9.16.27 A GCP whose ongoing planned outage has been recalled shall arrange for the
accelerated return of the facility or equipment to service in accordance with the
TSO’s instructions.
Restoration or Return of Equipment into Service
9.16.28 GCPs shall coordinate with the TSO for the return to service of their facility or
equipment following an outage taking into account the observance of the
necessary safety requirements in accordance with Section 11 of the LEGC.
99
9.16.30 The TSO shall, within 15 days after the end of every quarter, provide a report
indicating the following with respect to outages and any related requests for
compensation and disputes occurring:
(a) a list of all forced outages that occurred during the period, including
planned outages that have been deemed as forced outages because they
exceeded their approved duration and differentiating the outage types and
provide the reasons for each outage;
(b) a list of all planned outages;
(c) a list of all outages where the approval was withdrawn by the TSO,
including recalled outages together with the reasons for such withdrawal,
and a record of whether the GCP submitted the matter to the dispute
resolution process;
(d) a list of all outages which were withdrawn by the GCP prior to
commencement of the outage; and
(e) such other outage-related information as may be requested by LERC.
9.16.31 In furtherance of sub-section 9.16.30(a) and for clarity, any planned outage that
takes place at a time (or times) other than the period approved by the TSO,
including outages that extend beyond the time approved by the TSO shall be
considered and reported as a forced outage and referred to the LERC.
100
(a) the rationale for the test;
(b) the equipment involved;
(c) the test method, system configurations or setup and relevant details of
contracts or agreements as they relate to the test activities;
(d) preferred and alternative dates and times for the conduct of the test;
(e) the expected impact of the test activities on power flows, voltage and
frequency, and of any other network characteristics that could affect the
stability and reliability of the LITS, including details of the steps or
precautions to be taken to minimize the negative impact on the LITS and
GCPs;
(f) details of special readings, curves, plots or observations, as available; and
(g) the names, designation and affiliation of personnel who will be involved in
the test activities and methods of communication with those who may be
contacted in this respect.
9.17.5 The request for the proposed test shall be made at least fourteen (14) days in
advance of the proposed test date to allow for the needed coordination and
assessment by the TSO to be done.
9.17.6 A test shall not commence without the specific approval of the TSO.
9.17.7 The TSO shall permit any of the tests referred to in sub-section 9.17.2 to be
performed unless the TSO determines that the performance of the test poses an
unacceptable level of risk to or will have an intolerable adverse impact on the LITS.
101
9.18.6 A Generation GCP shall bear its own costs associated with tests conducted under
this section and no compensation shall be payable for financial losses incurred as
a result of these tests or associated activities.
102
9.19.7 A GCP who conducts a test under this section shall ensure that the person
responsible for the coordination of the test promptly advises the TSO when the test
is complete.
9.19.8 If the TSO approves of a proposed test, the TSO shall use its best endeavors to
ensure that power system conditions reasonably required for the test are provided
as close as is reasonably practicable to the proposed start time of the test and
continue for the proposed duration of the test.
9.19.9 Within a reasonable period after any such test has been conducted, the GCP who
has conducted the test must provide the TSO with a report in relation to that test,
including full test results where appropriate or requested by the TSO.
103
9.21.6 Where there is insufficient time for notification to be given in writing before the
scheduled operation, then the notification shall be communicated by voice call to
enable the action to be taken without delay and this shall be followed by a written
confirmation of the notification soon after the action has been completed.
9.21.7 A notification shall include the name, position and other identification of the
individual issuing the notice. The individual issuing the notice shall be competent
and capable of discussing the technical merits, alternatives and implications of the
notice.
9.21.8 The recipient of the notification may ask questions to clarify the notification and the
issuing individual shall respond promptly and fully to any questions or requests for
clarification or additional information.
9.21.9 While in no way limiting the specific requirements for notification as set out in this
section 9.21, the TSO and GCPs shall from time to time review the operations and
events that require notification .
Notification of Planned TSO Operations
9.21.10 Prior to carrying out any operation such as switching or parameter adjustment on
a LITS equipment or device, the TSO shall inform all GCPs who may be affected
or their designated operators of the intended action.
9.21.11 The notification shall give details of the operation to be carried out, the intended
time and the expected or possible impact and effect to be experienced and suggest
the corresponding actions expected of the recipient of the notification, if any.
Notification of GCP Operations
9.21.12 A GCP shall notify the TSO of any operations within the GCP’s facility which will
or may have an operational effect on the LITS.
9.21.13 The TSO may use the information gathered from the GCP’s notification to notify
any other GCP whose facility or operations, in the reasonable opinion of the TSO,
is likely to be affected by the notification issued by the GCP.
Notification of Alert Conditions and Events
9.21.14 A GCP shall advise the TSO without delay, as soon as it becomes aware of any
condition that poses a risk to the smooth operation of the LITS, including the
following specific conditions:
(a) Security emergency - when civil or public order problems which may affect
grid operations exist;
(b) Operating reserves - when the Operating reserve is less than required;
(c) Overload - when there is critical loading or imminent overloading of
transmission lines or equipment;
(d) Weather disturbance - when weather conditions or activities pose a risk to
grid operations; and
104
(e) Act-of-God - any Act-of-God event or other relevant condition that poses a
threat to grid operations.
9.21.15 The TSO shall assess the risks and potential impact on the LITS as soon as it
becomes aware of any condition described in sub-section 9.21.14. If it considers it
necessary, the TSO shall declare a state of Alert and notify all GCP’s who may be
affected accordingly. A GCP may be furnished with additional relevant information
upon request.
9.21.16 For the duration of the state of Alert, each GCP upon receipt of the Alert notice
shall take the necessary steps to place and maintain its plant or equipment in the
operational mode that it is best able to withstand the anticipated disturbance,
unless otherwise instructed by the TSO.
9.21.17 Subject to provisions under Section 10 of the LEGC, during the period while an
Alert notice is still in effect, the TSO may vary the scheduling and dispatch
instructions from those dictated by the merit order procedures prescribed in section
10.10 to manage the risks.
105
9.22.5 A Transmission GCP shall provide information to the TSO on the disturbance
monitoring equipment installed and operational within the LITS, and the
data/signals monitored at each location.
9.22.6 Data from transmission system disturbance monitoring equipment shall be in a
consistent time- synchronized format and following a disturbance, data from all
recorders shall be systematically retrieved, preferably automatically, and
correlated.
9.22.7 To ensure provision of a meaningful data, the recorders shall be synchronized to
standard time and equipped with GPS-synchronized clocks for time and date
stamping. Sequence-of-event recorders shall be provided with time resolution
between one and one hundred milliseconds which is necessary to determine the
sequence in which events occurred.
9.22.8 A Transmission GCP shall maintain a database of the disturbance monitoring
equipment and shall provide such information to the TSO on request.
9.22.9 The TSO, in consultation with GCPs, shall provide other details of minimum
technical specifications, data format and standards for disturbance monitoring
equipment, including any updates as may be found necessary.
Monitored Data
9.22.10 The basic data or signals to be monitored and recorded shall include, but not be
limited to the following:
(a) the transient and dynamic response of each generating unit in terms of real
and reactive power output;
(b) the voltage at the generating unit terminal;
(c) generating plant bus frequency;
(d) generating unit field voltage;
(e) generating unit field current;
(f) the system voltage at the high voltage side of the unit step-up transformer;
(g) power system stabilizer output;
(h) AGC pulses;
(i) active and reactive power flow at a Connection Point;
(j) substation busbar voltage and frequency;
(k) circuit breaker and protective device status; and
(l) required locations of recorders.
9.22.11 All major transmission substations and generating stations in the LITS shall be
equipped with disturbance monitoring equipment in addition to any other locations
determined and recommended by the TSO for installation of a recorder.
106
9.23 Operations Monitoring Reporting Requirements
Reporting of Emergency, Automatic or Unplanned TSO Operations
9.23.1 Under circumstances where the TSO needs to carry out an operation urgently or
it is not possible to provide notification prior to the execution of an operation, the
TSO shall proceed with the action and thereafter inform GCPs of the occurrence
of the operation without undue delay.
9.23.2 Immediately following an emergency, automatic or unplanned operation of LITS
equipment or devices, the TSO shall inform each GCP whose system may or could
have experienced an operational effect and give details of what has happened.
9.23.3 The TSO shall also inform the GCPs as to the likely duration of the LITS operating
condition and provide updates as appropriate, and when the condition has ended
the TSO shall inform the GCPs as soon as it is reasonably possible.
Routine Monthly Reporting
9.23.4 The TSO shall prepare and submit within fifteen (15) days of the succeeding
month, a monthly report on operations of the LITS for the previous month. The
report shall be submitted to the GCAC, the LERC and copies made available to all
GCPs.
9.23.5 The monthly LITS operations report shall include an evaluation of events and other
problems that occurred within the LITS for the previous month, the measures taken
to address them and the recommendations to prevent recurrence in the future.
9.23.6 In addition, the monthly report shall contain data and information on the following
performance characteristics of the LITS:
(a) Frequency profile;
(b) Voltage profile at selected LITS Nodes;
(c) Major generation and transmission outages;
(d) Transmission constraints; and
(e) Instances of persistent/significant non -compliance with the LEGC.
Quarterly and Annual Reports
9.23.7 Subject to the performance reporting requirements under Section 14 of the LEGC,
the TSO shall prepare and submit to LERC quarterly and annual reports on the
performance of the LITS. The quarterly and annual reports shall evaluate the
performance of the LITS against established targets, standards and benchmarks
for reliability, security and quality of service in accordance with Section 12 of the
LEGC.
9.23.8 The reports may also indicate constraints, if any, along with details of the GCPs
responsible for causing the constraints and any actions being taken by these GCPs
and the TSO to address each constraint.
107
9.24 Incident/Fault Reporting and Investigation
General
9.24.1 This section 9.24 provides procedures to be adopted for reporting faults, forced
outages and Significant Incidents which may occur in the LITS or a GCP’s network
or facility which may have an operational impact on others. It also describes the
procedure for setting up joint investigation of a Significant Incident.
Reporting of Major Incident or Significant Incident by a GCP
9.24.2 A GCP shall notify the TSO through a report, as soon as practicable and in any
event within twenty-four (24) hours of any forced outage, malfunction, fault or
Significant Incident to a LITS component or the GCP’s network or facility that may
have an impact on other GCPs or the quality, reliability or security of LITS services
and may include the following:
(a) Generation GCPs shall report loss of output and tripping of units and
governing control to the TSO within fifteen (15) minutes of the event
occurring;
(b) Demand GCPs shall report the loss of major loads (larger than 2 MW) to
the TSO within fifteen (15) minutes of the event occurring, and similarly,
warning of the reconnection of such loads shall be given with at least
fifteen (15) minutes advance notice;
(c) Incidents affecting any interconnected tie-line shall be reported to the TSO
and the Transmission GCP within the times specified in the relevant
Interconnection Agreements and Protocols; and
(d) Incidents on the LITS that involve sabotage or suspected sabotage, as well
as threats of sabotage shall be reported to the TSO.
9.24.3 The report mentioned in sub-section 9.24.2 shall include all the necessary
information on the circumstances of the incident to enable the TSO and the
Transmission GCP readily and correctly investigate and remedy any operational
deficiency.
9.24.4 Where the TSO determines that an incident which was reported by a GCP is
Significant, or has significantly impacted LITS services provision , the TSO may
request the GCP to submit a detailed written report of the event.
9.24.5 The TSO is not required to forward the GCP’s report to third parties but may use
the information obtained in preparing its report for other GCPs who may have been
affected by the incident.
Reporting of Major Incident or Significant Incident by the TSO
9.24.6 The TSO shall notify as soon as practicable, and in any event within twenty-four
(24) hours, the Transmission GCP or its designated representative of any forced
outage, disconnection, under- or over-voltage incidents, quality of supply
contraventions, malfunction, fault or Significant Incident to a LITS component.
108
9.24.7 The notice in sub-section 9.24.6 shall include all the necessary information on the
circumstances of the incident to enable the Transmission GCP readily and
correctly investigate and remedy any operational deficiency.
9.24.8 If a GCP determines that an incident which was reported earlier by the TSO is of
significance, the GCP may request the TSO to submit (or cause to be submitted)
a written report containing details of the incident.
9.24.9 The GCP shall not pass on the report to third parties unless the TSO’s permission
is sought and granted.
Guidelines for Written Reports
9.24.10 A report prepared under this section 9.24 may contain a confirmation of oral
notification with more details relating to the major incident/fault or Significant
Incident and shall, as a minimum, include the following details of the incident
(where applicable):
(a) time and date of event;
(b) location;
(c) plant and/or equipment directly involved;
(d) description and cause of event;
(e) conditions before the event;
(f) demand and/or generation (in MW) interrupted and duration of interruption;
(g) all relevant system data including copies of records of all recording
instruments including disturbance recorder, event logger, etc;
(h) sequence of tripping with time;
(i) details of relay operations; and
(j) remedial measures taken.
Investigation of Incidents
9.24.11 A Transmission GCP shall investigate the causes of any incident of forced outage
or equipment fault/failure reported by the TSO and immediately effect all advisable
temporary containment or remedial actions.
9.24.12 Upon completion of the immediate or remedial actions the Transmission GCP
shall submit its investigation report of the incident to the TSO.
Investigation of Major or Significant Incidents
9.24.13 Any major or Significant Incident that materially affects the quality of the LITS
service to a GCP shall be formally investigated. These may include interruptions
of supply, disconnections, under or over voltage incidents, quality of supply
contraventions, and others.
9.24.14 The TSO shall at its sole discretion initiate an investigation into a major or
Significant Incident that occurs on the LITS for the following purposes:
(a) to establish the probable causes of the incident;
(b) analyze the chronology and development;
109
(c) assess the impact;
(d) draw conclusions; and
(e) to outline the measures necessary for prevention or mitigating the impact
of similar incidents in the future.
9.24.15 The procedure to be followed by the TSO shall include the following:
(a) The TSO shall invite an affected GCP to make available all relevant
required information to the TSO subject to information exchange
confidentiality obligations described under Section 14 of the LEGC, where
necessary.
(b) A preliminary incident report shall be prepared and submitted within three
(3) days.
(c) The final report shall be submitted by the TSO to LERC through the GCAC
within three (3) months.
9.24.16 A GCP who is directly affected by a Significant Incident may request for a joint
investigation of the incident. The request for joint investigation shall be made in
writing to the TSO, giving reasons for the request. A joint investigation shall be
undertaken if warranted, in the opinion of the TSO.
9.24.17 A joint investigation shall be organized by the parties concerned and independent
experts may be invited to take part in the investigation by mutual agreement
between the parties.
9.24.18 The form and procedure of joint investigation of a particular incident shall be
agreed upon in advance by the parties concerned.
9.24.19 The results of the joint investigation shall be recorded in a report, copies of which
shall be lodged with the TSO who shall make copies available to LERC through
the GCAC within ten (10) days upon receipt of the final report.
110
Section 10: Scheduling And Dispatch Of Generation & Ancillary
Services
10.1 Background, Purpose, and Scope
10.1.1 Scheduling the operations of generating units and ancillary services is a major
component of the TSO’s operational activities. The optimal schedule is influenced
by factors on both the demand-side and supply-side as well as limitations and
constraints of the LITS.
Purpose
10.1.2 The purpose of the scheduling and dispatch process is to ensure that the
continuously changing demand on the grid is met in the most economic manner
bearing in mind the limitations on the transmission system, security requirements
and other constraints.
10.1.3 The TSO projects demand, considers the generating units that are available to
provide supply given the existing constraints within the LITS, and then schedules
generation in merit order to meet the projected demand at minimal cost and in
accordance with the LITS Performance and Reliability standards and Safety rules
and standards.
Scope
10.1.4 The Scheduling and Dispatch Sub-code defines, among others, the following:
(a) responsibilities of the TSO and GCPs in the scheduling and dispatch
process, including transactions of Import/Export Licensees on the CLSG
interconnected system;
(b) load forecasting obligations, procedures and methodologies;
(c) operational criteria for the preparation of the generation schedule;
(d) generation and ancillary services scheduling;
(e) pre-dispatch and post-dispatch planning; and
(f) the central dispatch procedures and issuance of dispatch instructions.
111
10.2.3 The TSO shall undertake the generation scheduling activity which requires
generating unit data as basis for preparing a merit order table for use in the
preparation and issuance of the generation schedule.
10.2.4 Subject to sub-section 10.2.2 the TSO shall be responsible for:
(a) collating and preparing the demand forecast on the LITS;
(b) determining the generating capacity needed to meet the demand
requirements of the LITS, including energy consumption, losses, internal
usage, operating reserves, etc.;
(c) preparation and issuance of the generation schedule in accordance with
the procedures described in this Sub-code;
(d) issuing of dispatch instructions for the scheduled generating units following
the procedures outlined in this Sub-code and the Operations Sub-code;
(e) ensuring that appropriately located generating units are available and
scheduled to provide ancillary services;
(f) rescheduling of generation during unplanned events in accordance with the
rules provided in this Sub-code;
(g) coordinating import/export transactions and other international
interconnection operations from the Liberian side in accordance with
regional Power Pool protocols and arrangements;
(h) keeping an electronic log of dispatch instructions and monitoring
compliance with dispatch instructions;
(i) reporting any non-compliance outside the tolerance band to the GCAC and
LERC, together with any explanation for the non -compliance as advised by
a Generation GCP; and
(j) fully documenting the operation of the generation scheduling process,
including the principles adopted in making the calculations required.
10.2.5 The TSO shall submit to LERC annually a recommended set of dispatch tolerance
bands for all classes of generating units considering the unit’s fuel source, physical
limitations on ability to control generation output, and any relevant locational
issues.
10.2.6 The LERC will consider the recommendations submitted under sub-section 10.2.5
and publish an approved set of dispatch tolerance bands.
10.2.7 For the avoidance of doubt dispatch tolerance bands for non-dispatchable
renewable generators (VRPPs) shall take into consideration the variability of their
fuel source (or primary resources) and reasonable efforts to forecast these
variations in formulating an offer.
10.3.3 A Transmission GCP shall follow, within dispatch tolerance bands, all dispatch
instructions properly issued by the TSO, except were doing so would endanger
people or equipment or breach its legal obligations.
113
10.6.2 A Demand GCP connected to the LITS shall forecast the total and the net (after
deducting embedded generation) energy and power demand that it expects to
impose at each nodal point of the LITS.
10.6.3 A GCP shall prepare and provide to the TSO, at least one (1) week in advance,
the forecast hourly load profiles for each day of the next two weeks. These
forecasts are to provide an indicative estimate of the total generation capacity and
the corresponding generation schedule needed to meet the forecast demand
requirements of the LITS over the relevant dispatch periods.
10 .6.4 The following factors shall be considered in the development of the demand
forecasts, to the extent that the factors are relevant to the particular forecast:
(a) historic demand data as recorded, including transmission losses and
station service consumption;
(b) growth patterns in the annual demand and load profiles of existing loads;
(c) load management expectations and expected energy output from
embedded generating facilities including non-dispatchable renewable
generation sources (VRPPs);
(d) demand forecasts for new connections or step increases in the
requirements of existing consumers;
(e) known weather patterns and forecasts;
(f) major events or anticipated activities which are likely to affect demand;
(g) expected changes in economic activity; and
(h) any other relevant information provided by GCPs.
10.6.5 The TSO shall collate all demand information provided by the relevant GCPs and
(the TSO) shall produce the following schedules and demand forecasts in
accordance with the timetable prescribed in Technical Schedule TS–T:
(a) dispatch schedule for each hour of the day ahead;
(b) hourly load forecasts for each of days 2 to 7 (inclusive) ahead;
(c) weekly demand forecast for 4 weeks ahead giving the daily energy forecast
as well as the peak and off-peak demand forecasts for each day; and
(d) monthly demand forecast for the period 12 months ahead of the current
month, giving for each month the energy forecast, peak and off-peak
demand forecasts, including also the typical hourly profiles of total system
load for working and non-working days in the first month only.
10.6.6 The TSO shall develop a methodology to collate the information obtained and
acquire the appropriate tools to create the indicative demand forecasts for the
entire LITS.
10.6.7 The demand forecasts produced by the TSO shall be indicative only as the TSO
has no direct influence over GCPs’ in the decisions about their levels of demand.
114
10.6.8 The demand forecast shall be adopted and used in operational planning and more
specifically, for the purposes of determining the dispatch schedules, operating
reserves, short- and medium-term capacity reserve requirements, in accordance
with the power system security and reliability standards.
115
10.9.2 The generation data and information to be submitted shall consist of the Capability
and Availability Declaration, generating unit scheduling and dispatch parameters,
and other relevant generation data and information including:
(a) details of any special factors which may have a significant impact on the
output of a scheduled generating unit;
(b) any temporary change to the registered data of the scheduled generating
unit indicating the duration of the temporary change; and
(c) any temporary change of a generating unit’s availability to provide ancillary
services and the duration of the temporary chan ge.
10.9.3 A Generation GCP shall without delay notify the TSO of any change in the
submitted Capability and Availability Declaration, generation scheduling and
dispatch parameters and other relevant generating plant data.
10.9.4 The Transmission GCP shall notify and provide details of any transmission system
constraints which may have a significant impact on the output of a scheduled
generating unit.
10.9.5 A Distribution GCP or any other Demand GCP shall notify the TSO of the following:
(a) its hourly demand forecast (i.e. requirements for power and energy) one
(1) day ahead of the dispatch Day;
(b) constraints on its distribution network or GCP system which may need to
be taken into account in the scheduling and dispatch process; and
(c) the requirements for the following which the TSO may need to consider for
reliability and stability of the LITS:
(i) control measures for voltage and reactive power (or MVar reserves),
and
(ii) ancillary services.
116
bases of each component of demand shall nevertheless be considered in
determining the settlement obligations of GCPs.
10.10.4 To meet the continuously changing demand on the LITS in the most economical
manner, generating units shall, as far as practicable, be stacked for dispatch by
the TSO in accordance with “the least variable cost of operation and maintenance
inclusive of cost of fuel (where applicable) and consumables (denoted as
“operating costs”) of producing electricity from each unit excluding the unit’s capital
cost and other fixed costs.
10.10.5 The generating units with the least operating costs shall be used to meet the
demand for power with the required margin for operating reserves.
10.10.6 Recognizing that the merit order for generation is dependent upon the chosen
timeframe for optimization, (i.e. the merit order that produces the least cost for one-
day only is different from that which results in the least cost for the week, the month
or the year), merit order dispatch within the LITS shall take into consideration the
various time frames.
10.10.7 The merit order Schedule for a hydro system is primarily based upon the annual
energy plan for the hydro units and the costs for hydro units are based upon:
(a) efficiency of the unit;
(b) the reservoir or pond level;
(c) run-of-river status; and
(d) Long-Run Marginal Costs (LRMCs).
10.10.8 For the purposes of merit order dispatch, generating units shall be listed in a Merit
Order Table according to the lowest to highest operating costs.
117
(a) collation of hourly demand forecasts for the next Dispatch Day by the TSO;
(b) submission to the TSO of the scheduling and dispatch data prescribed in
section 10.9;
(c) submission to the TSO of any revised generation scheduling data or
dispatch parameters for the following Availability Declaration period by
each Generation GCP; and
(d) use of the information provided by all GCPs in the preparation of a
Generation Schedule for the next Dispatch Day.
10.12.2 In preparing the Generation Schedule, the TSO shall take into account the criteria
and all other factors specified under sections 10.8 and 10.9 including any cross-
border power exchange or trade transactions as governed by sub-regional
interconnection protocols and other inter-utility bilateral agreements.
10.12.3 The Generation Schedule, as compiled by the TSO shall in addition be:
(a) in accordance with the Merit Order Table;
(b) sufficient to match the forecast system demand together with the required
reserve margins as defined by the Operations Sub-code; and
(c) sufficient to maintain system frequency within the required limits.
118
and at this stage, a day-ahead unconstrained Generation Schedule shall be
developed.
10.13.7 Following the development of the unconstrained Generation Schedule, the TSO
shall determine the feasibility of the unconstrained Generation Schedule,
considering any constraints within the LITS.
10.13.8 The unconstrained Generation Schedule shall be adjusted as may be necessary
to develop the final constrained Generation Schedule, after taking the constraint
factors into account.
10.13.9 Scheduled generating units that are not included in the Generation Schedule
shall be set aside for possible inclusion in the latter stage of the generation
scheduling process.
10.13.10 The Generation Schedule shall reflect the true operating characteristics of
generating units. If a scheduled generating unit becomes available at a different
capacity the relevant Generation GCP shall notify the TSO and provide a revised
Capability and Availability Declaration within the prescribed deadlines. If provided
within the prescribed deadlines, the TSO shall take the revised Capability and
Availability Declaration into account in the preparation of the final day-ahead
Generation Schedule.
Adjustments to Generation Schedule
10.13.11 The TSO may deem it necessary to adjust the output of the generation scheduling
process, before the issue of the Generation Schedule. Such adjustments may be
necessary due to the following factors:
(a) changes in offered availability and dispatch parameters of generating units,
brought to the attention of the TSO after the commencement of the generation
scheduling process;
(b) changes to system demand forecasts;
(c) changes in transmission network configuration and equipment availability,
resulting in constraints not previously foreseen; and
(d) any other condition which in the opinion of the TSO would result in additional
risk to the security of the LITS including:
(i) volatile weather situations giving rise to low confidence in demand
forecasts;
(ii) severe (unpredicted) weather conditions imposing high risk to the LITS;
(iii) impending strikes or political unrest posing a high risk to the LITS or parts
thereof; and
(iv) limitations or deficiencies of computational algorithms of the TSO
scheduling process.
10.13.12 Any of the factors listed in sub-section 10.13.11 may result in a generating unit being
chosen out of merit. Any deviation from the use of the Merit Order Table for dispatch shall
be reported by the TSO, including details of the reasons or those responsible for the
deviation. These reports shall be consolidated into a weekly report by the TSO to all GCPs,
the GCAC and the LERC.
119
10.14 Revision of Generation Schedule
10.14.1 If a revision in the availability declaration, generation scheduling and dispatch
parameters or other relevant generation data is received by the TSO prior to 15:00h on
the day preceding the relevant scheduled Day, the TSO shall, if there is sufficient time
prior to the issue of the generation schedule, take into account the revised availability
declaration, generation scheduling and dispatch parameters or other relevant generation
data in preparing the generation schedule.
10.14.2 If a revision in availability declaration generation scheduling and dispatch parameters or
other relevant generation data is received by the TSO at or after 15:00h on each day but
before the end of the next following scheduled Day, the TSO shall, if it has to re-schedule
the units available to generate, take into account the revised availability declaration,
generation scheduling and dispatch parameters or other relevant generation data in that
re-scheduling.
10.14.3 If an event on the LITS occurs which requires substantial amendment in the data being
used in preparing the Generation Schedule, the TSO may issue a revised Generation
Schedule to the extent necessary, because of such events.
120
10.16.2 Dispatch instructions shall take into account the Capacity and Availability Declaration,
generation scheduling and dispatch parameters, and other relevant generating plant data
supplied to the TSO.
10.16.3 The dispatch instruction shall contain, at the minimum, the following:
(a) the specific generating unit to which the instruction applies;
(b) the active power (MW) and reactive power (MVar) output required;
(c) notice and change in notice to synchronize or de-synchronize scheduled
generating units in a specific timescale;
(d) target time of ramp-up and ramp-down rates for generating units; and
(e) the time of issue of a dispatch instruction.
10.16.4 The dispatch instruction may also include:
(a) details of the type of reserves to be carried by each generating unit, including
specifications of the duration in which that reserve may be dispatched;
(b) an instruction for generating units to provide ancillary services and other
operational requirements;
(c) target voltage levels at instructed generating capacity level or the individual
reactive power output at the bus or Connection Point;
(d) requirements for changes in AGC mode; and
(e) an instruction to carry out tests as specified in the Operations Sub-code.
10.16.5 The TSO shall maintain records of the following dispatch instructions in an electronic
format or a written logbook or both:
(a) synchronizing and de-synchronizing instructions; and
(b) active power (MW) and reactive power (MVar) dispatch instructions.
10.16.6 For each of the instructions listed in sub-section 10.16.5, the required action, time of
issuance of the instruction and the time the action is to be implemented shall be recorded.
10.16.7 The TSO shall issue to all Generation GCPs (including Import/Export licensees) through
an appropriate means of communication (telephone and confirmed by email or fax), the
dispatch instruction regarding their day-ahead hourly Generation Schedule.
10.16.8 The hourly loading as defined by the Generation Schedule and issued to scheduled
generating units shall remain valid, unless superseded by another dispatch instruction
from the TSO.
10.16.9 A generating unit/plant shall be deemed to have complied with a dispatch instruction
when it achieves an output within the allowable tolerance of its declared available capacity
for both active and reactive power and within the time for the change according to its
registered operating parameters and characteristics.
10.16.10 In the event of two or more generating units having the same price, the TSO shall
dispatch the generating unit that will result in a smaller system loss.
10.16.11 Dispatch instructions may be subsequently cancelled or varied. Generating units that are
declared to be available but not included in the Generation Schedule may be issued with
dispatch instructions.
121
10.16.12 A generating unit that has been declared as available shall be ready to provide power
within 30 minutes of being instructed.
10.16.13 Where a Generation GCP has received a dispatch instruction to change the output of a
synchronized generating unit, it shall carry out the instruction to achieve the new target
within the unit’s registered operating parameters and characteristics and within the time
specified by the TSO.
10.16.14 The form of instructions and terms to be used by the TSO in issuing of instructions are
to be mutually agreed by all the relevant parties.
10.16.15 A dispatch instruction for operating reserves shall specify the type of reserve that the
generating unit is required to provide.
10.16.16 A dispatch instruction for emergency load reduction shall contain the quantity and
magnitude of load to be dropped and the time the load reduction is to be implemented.
10.16.17 In the event that while carrying out a dispatch instruction, an unforeseen problem arises,
the TSO shall be notified without delay by telephone.
10.16.18 Where a Generation GCP is unable to comply with a dispatch instruction correctly issued
by the TSO, it shall inform the TSO by telephone without delay and the Generation GCP
shall follow up to provide a new declaration.
10.16.19 The dispatch instruction to shut down a generating unit shall specify the shutdown time.
10.16.20 Where a Generation GCP has not informed the TSO of its inability to comply with a
dispatch instruction, but the TSO ascertains that the GCP is not in compliance with a
dispatch instruction, the GCP shall be deemed to have breached the LEGC and the
prescribed sanctions or penalties shall apply.
Action Required by Generation GCPs
10.16.21 A Generation GCP shall comply with all dispatch instructions issued by the TSO.
10.16.22 If an unforeseen problem arises, which affects the safety of the unit, plant or personnel,
the Generation GCP may disregard dispatch instructions and take necessary corrective
actions and shall notify the TSO.
10.16.23 De-synchronization may take place without the TSO’s prior approval if it is done solely
on the grounds of safety of the plant or personnel.
10.16.24 De-synchronization because of low-frequency-relay operation shall be reported to the
TSO immediately.
10.16.25 A Generation GCP shall, without delay, notify the TSO of any changes to or loss
(temporary or otherwise) of operational capability of its unit that is synchronized or
instructed to be synchronized or designated for operation as Operating reserve.
10.16.26 Where a Generation GCP or a particular generating unit fails to respond to a dispatch
instruction within a tolerable time and accuracy (in accordance with generating unit’s
declared technical characteristics and Prudent Utility Practice), the generating unit shall
be declared and identified as non-conforming and the relevant Generation GCP may face
financial penalties or other sanctions imposed under its License for breach of the LEGC.
122
Instruction to Distribution GCPs and other Demand GCPs
10.16.27 The TSO shall issue instructions directly to a Distribution GCP or other Demand GCP
for special actions relating to:
(a) demand management,
(b) load transfer,
(c) disconnection, or
(d) restoration of load.
123
10.17.9 MVar dispatch instructions issued by the TSO shall reflect the limits contained in the
applicable registered generating unit parameters and characteristics.
10.17.10 Under system fault conditions, where reactive power output is driven outside its declared
operating characteristic limits, the Generation GCP shall immediately inform the TSO of
the situation. However, if the Generation GCP reasonably believes that the situation may
be dangerous to personnel or plant, then appropriate action may be taken to remedy the
situation.
124
10.19.7 When justifiable in terms of power system security, the TSO may direct any GCP to
provide an ancillary service where the GCP’s plant can do so.
10.19.8 The TSO shall offer compensation to a GCP in respect of the ancillary services provided
where:
(a) the TSO directs a GCP to provide ancillary services and the GCP provides the
ancillary services; and
(b) there is no Ancillary Services Agreement in place with that GCP in respect of the
required ancillary service.
10.19.9 If compensation offered by the TSO for provision of ancillary services is not accepted by
the GCP and the level of compensation cannot be agreed between the parties, the GCP
may seek a determination of a reasonable level of compensation in accordance with the
dispute resolution procedures of the LEGC.
125
SECTION 11: SAFETY SUB-CODE
11.1 Background, Purpose and Scope
11.1.1 The electromechanical systems that have been interconnected to form the LITS are
designed so that when operated normally they are safe, but they contain inherent dangers.
Personnel of the TSO, GCPs and their agents often must work on or in proximity to the
LITS facilities or equipment connected to the LITS. To ensure safe working conditions for
these situations, it is necessary for the TSO and GCPs to operate in accordance with
standard Safety Rules and Procedures.
Purpose
11.1.2 The Safety Sub-code provides standard operating procedures for coordination,
establishment and maintenance of necessary safety protocols and guidelines that ensure
safe working conditions for personnel working on or in proximity to LITS equipment or
GCP’s equipment at Connection Points. The general arrangement involves making
electrical equipment dead and providing secure isolation and grounding such that the
equipment cannot be inadvertently made live.
Scope
11.1.3 The Sub-code does not impose a particular set of safety rules to be adopted by the TSO
or GCPs but sets out the principles and arrangements which govern the interface between
the parties. Each GCP shall develop and adopt its own safety rules which shall be guided
by the principles in the Sub-code.
11.1.4 This Safety Sub-code applies to:
(a) the TSO;
(b) Transmission GCPs;
(c) Generation GCPs including VRPPs;
(d) Distribution GCPs; and
(e) Other Demand GCPs.
126
(iv) adopting specialized procedures and appropriate tools required to be
applied when the work must be done on equipment which remains
energized;
(c) authorizing the commencement of work;
(d) receiving the authority to commence work and executing the work;
(e) supervising safety during the work and clearing the authority when the work is
terminated;
(f) cancelling the authority on termination of the work; and
(g) restoring the system to normal operation.
11.2.4 Safety procedures for personnel working on or in proximity to the LITS shall in addition be
governed by the TSO’s requirements for safety coordination, as may from time to time be
in force.
127
11.3.11 The TSO shall coordinate the activities of persons responsible for the testing, monitoring
and maintenance of facilities or equipment connected to the LITS, in order to ensure that
testing and maintenance are carried out in a safe manner.
128
11.4.13 Contact between safety coordinators of the TSO and GCP(s) will be made via normal
operational channels, and accordingly telephone numbers for each safety coordinator
shall be registered and available at the TSO and GCP(s) premises at all times.
11.4.14 If work is to be carried out on the LITS which necessitates the provision of safety
precautions in accordance with the provisions of this section 11.4, the requesting safety
coordinator who requires safety precautions to be provided shall contact the relevant
implementing safety coordinator(s) to coordinate the establishment of safety precautions
throughout the work.
(b) an adequate physical separation in accordance with the local safety instructions
of the Transmission GCP or other GCP in addition to placing a safety tag at the
switching points.
129
11.6.3 Where isolation is achieved by means of an isolating device, the device shall allow the
isolating position to be maintained in a manner that minimizes the risk of inadvertent,
accidental or unauthorized operation and that when put in this position, a notic e or “tag”
to that effect shall be attached.
11.6.4 Grounding shall be implemented by any of the following:
(a) a grounding switch secured in a closed position by a lock and with a safety tag
affixed to it or secured by such other method in accordance with the local safety
instructions of the Transmission GCP or other GCP as the case may be; or
(b) an adequate physical connection which shall be in accordance with the methods
set out in the local safety instructions of the Transmission GCP or other GCP, in
addition to a safety tag which shall be placed at this point of connection and all
related switching points.
11.6.5 Where grounding is achieved by means of a grounding device, the grounding position
shall be maintained in such a manner as to minimize the risk of inadvertent, accidental or
unauthorized operation and that when put in this position, a notice or “tag” to that effect
shall be attached.
11.6.6 The confirmation of grounding shall be recorded in the respective safety logs of the
requesting safety coordinator and implementing safety coordinator.
11.6.7 The implementing safety coordinator shall ensure that the established safety precautions
are maintained until requested to be removed by the relevant requesting safety
coordinator.
(b) All safety precautions other than the current safety precaution have been
cancelled; and
(c) The other safety coordinators or the other GCPs agree for the conduct of testing
in that part of the system.
130
PART D: STANDARDS OF PERFORMANCE
Part D, the Standards of Performance, sets out the performance indicators and benchmarks for
quality and reliability of supply. It also contains the sub-code for metering which describes the
metering requirements of electricity flows injected into or off-taken from the LITS including the
applicable standards and installation arrangements for metering. This Part further stipulates
standards and requirements for data and information exchange among the various actors and
outlines guidelines and requirements for periodic reporting to the LERC and other relevant
authorities.
131
SECTION 12: BENCHMARKS AND INDICES FOR STANDARDS OF
SUPPLY
12.1 Background, Purpose and Scope
12.1.1 Power system performance and reliability encompasses all aspects of providing reliable
electricity supply to customers efficiently. The concept of reliability is described as “the
degree to which the performance of the elements of the system result in power being
delivered to customers within accepted standards and in the amount desired”. This
definition contains the concepts of adequacy and security.
12.1.2 Adequacy is “the ability of the system to supply the aggregate power and energy
requirements of the consumers at all times” and Security is “the ability of the system to
withstand sudden disturbances”.
12.1.3 Reliability of a power system pertains to its ability to satisfy the load demand under the
specified operating conditions and policies. A reliable power system, therefore, is one
which only allows few interruptions to customers’ services.
12.1.4 Pursuant to sub-section 12.1.3, reliability as regards the LITS is a measure of the ability
of the LITS to adequately perform its designated functions given the conditions within
which it must operate.
Purpose
12.1.5 The purpose of the Standards of Performance Sub-code of the LEGC is to:
(a) specify the various indices that are used to monitor the performance of the TSO
and GCPs;
(b) define the minimum level of quality of electric power supply within the LITS;
(c) define the minimum reliability standards, benchmarks and performance targets for
the LITS; and
(d) to provide GCPs with the basis to design, operate and maintain their systems and
equipment to fit the environment within which they operate.
12.1.6 The reliability of the LITS shall be quantified in terms of the probability or frequency of
encountering an outage or an inadequate state, or the period that a system spends in
these states. Reliability may be evaluated in terms of the frequency, duration, and
magnitude or severity (in terms of impact on load curtailment) of any adverse events or
deviations from the stipulated service standards.
12.1.7 Maintaining acceptable reliability of the LITS means that the LITS is dimensioned and
operated so that:
(a) the impacts of disturbance situations are minimized;
(b) there are provisions for restoring the LITS to the Normal state; and
(c) disturbance incidents are cleared as quickly as possible.
Scope
12.1.8 The performance standards prescribed in this Sub-code apply to the TSO and the
following GCPs:
132
(a) a Generation GCP;
(b) a Transmission GCP;
(c) a Distribution GCP; and
(d) any other Demand GCP directly connected to the LITS.
12.1.9 The TSO shall monitor and report to the GCAC and the LERC on the performance of the
LITS in terms of quality and reliability (i.e., adequacy and security) of supply.
133
Voltage limits - Alert State
12.3.3 When the power system is in the Alert State, the voltages within the LITS shall be
regulated to within ±10% of the nominal voltages and this situation shall not persist for
more than ten (10) minutes.
Voltage limits - Emergency State
12.3.4 When the power system is determined to be in an emergency state, voltage levels within
the LITS shall be regulated to within ±10% and this situation shall not persist for more than
thirty (30) minutes.
Voltage unbalance
12.3.5 The phase voltages of a 3-phase supply at a LITS Node shall nominally be of equal
magnitude and 120 degrees apart in phase angle. Deviations will result in decreased
efficiency, negative torque, vibrations and overheating and when severe, voltage
unbalance could lead to malfunctioning of some equipment.
12.3.6 Phase voltage unbalance shall not exceed one percent (1%) when the LITS is in the
Normal State and two percent (2%) when in the Alert State.
Voltage harmonics & limits
12.3.7 Harmonics are sinusoidal voltages and currents having frequencies that are integral
multiples of the fundamental frequency. Voltage harmonic distortions are grouped into
three categories: odd triplens (multiples of the third harmonic), other odd harmonics, and
even harmonics, with different severity levels and effects on equipment for each category.
12.3.8 The maximum permissible harmonic limits shall be as defined in IEC/TR3 61000-3-7
standard or the IEEE Standard 519-1992 -” Recommended Practices and Requirements
for harmonic control in the electrical power system”.
12.3.9 A GCP shall take preventive or corrective action, where necessary, to mitigate harmonic
distortions and comply with the specified standard.
Voltage flicker
12.3.10 “Voltage Flicker” is a rapid change or fluctuation in voltage (typically caused by consumer
equipment) that distorts or interferes with the normal sinusoidal voltage waveform of the
transmission system due to a relatively large current inrush when customer equipment,
such as a large motor, is suddenly switched on, or from the sudden increased demand
from a welding equipment, for example. The current inrush acting over the network
impedance is the mechanism that produces the voltage dip (sudden fall) and the
corresponding voltage swell (sudden rise) when the equipment concerned is off -loaded. If
the fluctuation is of a magnitude and frequency perceptible to the eye, it becomes flicker
which could range from annoying to complete interference of normal activity.
12.3.11 Since voltage fluctuation on the LITS affects other users of the system, the TSO shall
direct the management of flicker on its lines and station buses.
12.3.12 The maximum permissible voltage flicker limits shall be as defined in IEC/TR3 61000-3-
7 standard or the IEEE Standard 519-1992 - “Recommended Practices and Requirements
for harmonic control in the electrical power system”.
134
12.3.13 A GCP shall promptly identify the sources of voltage flicker and voltage depressions that
are more than the maximum permissible limits and implement corrective actions
accordingly.
135
12.5.7 A Generation GCP shall be responsible for providing adequate protection for its generating
units against damage for frequency excursions outside the range specified in sub-section
12.5.5.
Load shedding scheme
12.5.8 All GCPs off-taking power from the LITS including Distribution GCPs and Large Consumer
GCPs shall cooperate with the TSO to implement an automatic load shedding scheme to
provide for load disconnection when system frequency decays.
12.5.9 The operations of the AFLS scheme as provided in sub-section 9.14.5 shall be defined
from time to time by the TSO in consultation with other GCPs.
136
12.7.4 Subject to reporting requirements under section 14.11, the TSO shall compile and submit
to the GCAC and the LERC every quarter and annually a System Reliability Performance
Report for the LITS, giving details of the actual levels achieved in respect of the
performance and reliability indices defined in this Sub-Code.
12.7.5 A copy of the System Reliability Performance Report shall be published or posted at the
TSO’s Website for access by all GCPs.
12.7.6 The performance of the LITS shall be evaluated by the TSO at quarterly, half-yearly and
annual intervals, to compare the actual performance of the LITS with the benchmarks set
by the LERC for that period.
Reliability performance indices
12.7.7 The LERC in consultation with the GCAC shall prescribe indices and benchmarks that
shall be used to evaluate the performance of the LITS. Historical data for the past two
years may be used to derive performance benchmarks to be specified for the reliability
indices.
12.7.8 The following indices shall, at the minimum, be monitored and calculated for the purposes
of assessing the performance of the LITS:
(a) System Average Interruption Duration Index (SAIDI) - Total duration of connection
point interruptions in a period divided by the number of connection points in the
system;
(b) System Average Interruption Frequency Index (SAIFI) - The average interruptions
per connection point which is calculated by dividing the total number of
interruptions at all system connection points by the number of connection points
in the system;
(c) Unavailability - Percentage of time the entire transmission system (or a particular
class or circuit) is not available for the transmission of electricity, and it shall be
calculated as the sum of planned, unplanned, and disturbance outage durations
divided by the total hours that the system or the relevant circuit should have been
available in a given period; [Availability = 1 – Unavailability]
(d) Loss of Supply - A sustained disturbance on the transmission system, that results
in the loss of electricity supply service to one or more customers. The cause of
this disturbance can be initiated either by a distribution or transmission event, with
the cause being noted, tracked and reported;
(e) System Minutes Lost - This index is calculated by dividing the amount of energy
not supplied by the system peak demand for that year and expressing the value
in minutes;
(f) Index of Transmission Reliability (ITR) - Represents the percentage of time that
transmission circuits are available for the transmission of electricity from one
terminal to another or others (ITR is a measure of unplanned unavailability of the
transmission system. It is deduced by using outage time due to unplanned
outages or disturbances on the system and excludes outage time due to planned
outages); and
(g) Transmission Line Faults - Number of faults per 100 km of circuit lines.
137
Quality performance indices
Voltage & Power factor
12.7.9 The TSO shall report on the following for each LITS Node with respect to voltage and
power factor deviations outside the limits stipulated for the Normal state:
(a) the number of occurrences of deviation incidents;
(b) the total duration of deviation incidents;
(c) the maximum continuous period of deviation; and
(d) the maximum and minimum values recorded indicating the time and date of
occurrence.
Frequency
12.7.10 The TSO shall report on the following with respect to frequency deviations from both the
normal and emergency limits stipulated:
(a) the number of occurrences of deviation incidents;
(b) the total duration of deviation incidents;
(c) the maximum continuous period of deviation; and
(d) the maximum and minimum values recorded indicating the time and date of
occurrence.
Efficiency performance indices
12.7.11 The TSO shall report on the following with respect to energy balance within the LITS:
(a) total energy received, supplied and net energy at each LITS Node;
(b) energy used at each LITS Node; and
(c) Transmission Loss Ratio (TLR) which is calculated as the total transmission
system losses divided by the total energy entering the LITS expressed in
percentages.
Equipment loading reporting
12.7.12 The TSO shall identify the transmission circuits and power transformers that are loaded
over 85% of their nameplate rating for more than 10% of total operating time each year
and shall report this to the GCAC and LERC annually as part of the System Reliability
Performance Report along with the plans to relieve such loading problems.
Event inclusions and exclusions for performance reporting
12.7.13 A power interruption shall include any outage which may be due to the tripping action of
protective devices during faults or the failure of transmission lines and/or power
transformers and which results in the loss of service to a GCP or a group of GCPs.
12.7.14 For the purpose of reporting on LITS reliability, the following shall be reported
separately and excluded from calculations of indices:
(a) planned outages where GCPs have been notified in accordance with the relevant
notification provisions contained in the Operations Sub-Code;
(b) outages caused by Force Majeure conditions; and
(c) outages due to fundamental shortage of generation capacity.
138
SECTION 13: METERING SUB-CODE
13.1 Background, Purpose and Scope
13.1.1 Section 13 of the LEGC sets out the requirements for standards, procedures and
guidelines in respect of metering at a Connection Point within the LITS, to ensure accurate
and transparent accounting, billing and settlement for power and energy transactions over
the LITS from generation and trading sources, through transmission up to the points of
bulk off-take of power and energy for distribution and consumption.
Purpose
13.1.2 The purpose of the Metering Sub-code includes the following:
(a) definition of the minimum acceptable accuracy and minimum standards for
metering at the connection points of the LITS to facilitate energy accounting,
billing and settlement which all constitute commercial transactions;
(b) setting out the provisions relating to design, specifications, installation,
maintenance, testing and certification of metering facilities and equipment;
(c) description of the provisions relating to security and rights of access to metering
data, settlement and auditing;
(d) specification of responsibilities and rights of:
(i) the TSO as both market operator and responsible for system operations,
(ii) GCPs in relation to ownership and management of metering systems,
(iii) provision and use of metering data; and
(e) definition of procedures for resolution of metering disputes.
Scope
13.1.3 The Metering Sub-code covers transactions relating to interchange of power and energy
that is:
(a) entering or exiting from the transmission system; and
(b) entering or exiting from a GCP’s facility or network at the Connection Point.
13.1.4 The Metering Sub-code applies to:
(a) the Market Operator (MO)
(b) the TSO and
(c) GCPs, which in this Part includes the following:
(i) Transmission GCPs,
(ii) Generation GCPs directly connected to the transmission network,
(iii) Distribution GCPs,
(iv) Large Consumers directly connected to the transmission network, and
(v) Traders (Import /Export Licensees) that engage in PPA/PSA transactions
over the international interconnected tie lines.
139
13.2.3 Active and reactive energy and power demand shall be measured at all such Connection
Points in the LITS to determine both the input and output quantities.
13.2.4 Two revenue metering facilities, Main Meter and a Check Meter, are required at the
Connection Point.
13.2.5 Each metering facility shall measure power and energy flow and shall be arranged to
ensure continuous recording even in the event of failure of one of the metering facilities.
13.2.6 The Main Meter shall be the revenue meter and the Check Meter shall be used to provide
metering data when a revenue meter or its current transformer or voltage transformer is
out of service as provided for under section 13.6.
13.2.7 The revenue metering facilities shall be located as close as practicable to the Connection
Point.
13.2.8 The Transmission GCP or other relevant GCP shall provide adequate space in panels and
rooms at substations or Connection Points for installation of the meters.
13.2.9 The Check Meter installation shall involve the provision of a separate metering facility
using separate current transformer cores and separately fused voltage transformer
secondary circuits, preferably from separate secondary windings.
13.2.10 The metering facility shall comply with the prescribed standards and equipment shall be
manufactured to prescribed and internationally recognized quality standards.
13.2.11 A metering facility shall be:
(a) secure,
(b) registered with the TSO/MO, and
(c) capable of providing data for electronic transfer to a metering database
maintained by the TSO/MO.
13.2.12 Energy meter data shall be based on units of watt-hours (for active energy) and var-
hours (for reactive energy) and shall be collated at defined metering intervals.
13.2.13 A GCP is entitled to access the metering database in respect of its own production,
demand or consumption of power and energy.
13.2.14 Historical data shall be maintained in the metering database for thirteen (13) months in
accessible format and for six (6) years in archive.
13.2.15 The owner of a metering facility may replace its metering facility at any time after it has
been installed, subject to the provisions of this Metering Sub-code.
141
13.4 Ownership of Metering Systems & Associated Responsibilities
13.4.1 With the exception of metering systems for Generation GCPs, unless something different
is agreed and authorized by the MO/TSO, all Main Metering systems and Redundant
Check metering systems shall be owned by the Transmission GCP, and Verification
Metering systems owned and provided by the other relevant GCP.
13.4.2 For Generation GCPs with generating units or plant directly connected to the LITS, Main
Metering System and Redundant metering system shall be owned by the relevant
Generation GCP, and the Verification Check metering systems owned by the
Transmission GCP.
13.4.3 The Main and Redundant metering systems accounting for Generation GCP consumption
from the LITS through an auxiliary transformer shall be owned by the Transmission GCP.
A Verification Metering system shall be owned and provided by the relevant Generation
GCP when required.
13.4.4 For International Interconnections with the LITS, Main Metering System shall be owned
by the Transmission GCP (the NGC), unless something different is agreed in the relevant
Interconnection Agreements. Ownership of Check Metering Systems shall be governed
by the relevant Interconnection Agreement.
13.4.5 Owners of metering systems shall be responsible for investment, installation,
maintenance, repair and replacement of metering equipment and the management of
metering data collection at the Connection Point and transmission to the MO/TSO’s
Central Coordination Metering Database.
13.4.6 A Central Coordination Metering Database of all metering installations on the LITS shall
be kept by the MO/TSO. It is the sole responsibility of the MO/TSO to ensure that this
Central Coordination Metering Database is kept up to date. The MO/TSO shall formulate
the appropriate processes to ensure this occurs by detailing procedures, timing of data
collection from the GCP metering databases and general formatting as well as input fields
of the database.
13.4.7 An owner may also have its own metering database that it keeps and tracks its local
metering information and may utilize the services of any Metering Services Provider
accredited by LERC for these purposes including installation, site inspections, technical
audits and maintenance of the metering systems.
13.4.8 Regardless of ownership, the MO/TSO shall be responsible for approving the initial
design, the testing, commissioning and sealing of any commercial metering system in the
LITS.
13.4.9 A GCP who owns the substation where a metering equipment is located shall provide the
MO/TSO with:
(a) 24-hour unrestricted access to the facilities where the metering system is
located;
(b) adequate space for installing communications devices; and
(c) reliable power supplies.
142
13.4.10 Any remote communications to the metering equipment, meters, data registers, and
databases will be the responsibility of the TSO including the operation and maintenance
of the communication equipment, as well as the services associated with remote reading.
143
simple calculations that eliminate the effect of the network element that could exist
between them.
13.6.3 Check metering data shall be used for validation, substitution in the event of the failure of
the Main Meter and account estimation of revenue metering data.
13.6.4 Energy consumed at a generating station and drawn from the LITS shall be measured by
using a revenue meter and the Generation GCP shall pay for this energy.
144
13.7.11 Where a combined active energy and reactive energy meters are provided, a separate
record shall be provided for each measured quantity and direction.
13.7.12 The loss of auxiliary supply to the meter shall not erase the cumulative records.
13.7.13 A metering facility shall provide a pulse output for each measured quantity. The pulse
output shall have the following characteristics:
(a) it shall be for a three-wire terminal with pulse duration in the range from 40 to 80
milliseconds, preferably selectable and with selective pulse frequency or rate;
(b) it shall have a minimum pulse frequency that complies with the IEC 60044
Standard or its equivalent national standard for the shortest integration period and
the accuracy class of the meter; and
(c) it shall be galvanically isolated from the VTs and CTs being measured, and from
the auxiliary supply input terminals.
13.7.14 A metering equipment shall be of proven quality, fully type tested, individually tested and
accepted by the TSO/MO. Appropriate test certificates shall be kept by the TSO/MO or
the Transmission GCP. All metering equipment shall be supported with evidence of
approval from an accredited laboratory recognized under the International Certification
Scheme.
Integrating Pulse recorders
13.7.15 Integrating pulse recorders of a metering facility equipment shall be capable of recording
integrated demand periods adjustable between fifteen (15) minutes and sixty (60) minutes.
13.7.16 Each recorder shall be capable of transferring the data through communication channels
to be provided to the metering database by the TSO. A RTU shall be installed at the meter
location that can be interrogated by the data acquisition computer at the Dispatch Center.
13.7.17 The integrating pulse recorder shall provide a record for reference at a future time. The
record shall be suitable for reference for a period of at least one (1) year after it is
generated. The integrating pulse recorder shall be regularly interrogated and the
(interrogation) record shall be maintained by the recorder for sixty (60) days.
13.7.18 The recorder’s time and the meter’s time shall be based on the UTC Standard time. The
time reference used with the recorder shall ensure that the accuracy of the integrating
pulse recorder is with a time error of no more than plus-or-minus one (±1) second.
13.7.19 Reprogramming of an integrating pulse recorder shall be done as soon as possible,
within one billing cycle, if there is a time error.
145
(b) verification of compliance with the LEGC; and
(c) auditable control of changes to the registered information.
13.9.2 The content of the metering register will include, but not be limited to the following:
(a) a unique meter identification/serial number;
(b) location of the commercial meters and metering systems;
(c) the owner of each commercial meter;
(d) the identification of the GCP(s) concerned;
(e) meter manufacturer, type and model;
(f) specifications of the metering equipment including accuracy;
(g) the adjustment factors including circuit losses to be applied;
(h) metering system function (main, check, redundant or verification, export, import
etc);
(i) organization which issued the certification of the meter and metering equipment;
and
(j) the calibration and tests performed on the meters and/or the metering equipment
at least during the last 5 years.
13.9.3 The TSO/MO shall update the metering register from time to time, to ensure that accuracy
of the register is maintained.
13.9.4 Where the data/information in the metering register indicates that the meters or metering
equipment do not comply with the requirements of this Sub-code, the MO/TSO will advise
the owner of the non-compliance, and the owner will rectify the situation forthwith unless
a derogation is granted under Section 4 of the LEGC.
146
minimum required calibration tests and their frequency to maintain its validity during the
period.
13.10.7 The minimum set of tests a manufacturer or an authorized Metering Test Station shall
perform to verify compliance with this Metering Sub-code and issue the corresponding
certification shall be in accordance with Appendix B of the LEGC.
13.10.8 The TSO/MO shall be granted access to such metering equipment upon reasonable
notice and at reasonable times, in order to make or inspect any adjustments thereto and
to witness any tests or participate in any inspection thereof required pursuant to this Sub-
code.
147
Request for tests
13.11.11 A GCP may request the TSO/MO to arrange for a test of any metering equipment where
it has cause to believe that the performance of the equipment is not within the accuracy
limits specified in the LEGC.
13.11.12The requested test shall be carried out by an independent accredited agent appointed by
the TSO/MO and approved by the parties. The test may be witnessed by the concerned
parties if they so wish.
13.11.13 Where the metering equipment fails the requested test, the owner shall pay for the cost
of the test; but where the meter equipment passes the test, the party who requested the
test shall pay for the cost of the test.
Test failure
13.11.14 Where, following a test, the accuracy of the metering system is shown not to comply with
the requirements of the LEGC, the certification issued for the meter or metering equipment
which has failed the test will automatically expire, and a new one will be required.
13.11.15 The owner will at its own cost:
(a) consult with the TSO/MO and the relevant affected GCP regarding the errors
found and the possible duration of the existence of the errors; and
(b) make repairs or replacements to the metering system to restore the accuracy to
the required standards.
13.11.16 Where a metering system is found to be faulty, or non-compliant or outside the accuracy
stated in section 13.7, then the owner shall inform the TSO/MO and GCPs that have an
interest in this metering system of the failure. Such notification shall include the plans by
the owner to restore the metering system to compliance with the LEGC and the procedures
to be followed to determine any estimated readings during the restoration period, including
any revised readings that were provided during the period that the metering system was
faulty or non-compliant.
13.11.17 In the event that a GCP (who is the owner of the faulty metering equipment) cannot or
does not comply with its obligations to repair, adjust or replace or renew a defective
component, the TSO/MO or the relevant affected GCP shall have the right to carry out
such repair, adjustment, replacement or renewal and to recover its own costs, expenses
and profit thereon from the owner forthwith on demand (such profit to be based on a
reasonable rate of return which shall be approved by LERC).
148
13.12.4 A meter shall be considered faulty only if it is determined that the meter does not comply
with the prescribed accuracy standards.
13.12.5 Upon any observation by a GCP or the TSO that a meter may not be operating properly,
the other party shall be notified, as soon as reasonably practicable of the existence of a
fault and the length of time the fault may have existed.
13.12.6 The meter owner shall ensure that checks and appropriate repairs are made to the
metering facility as soon as reasonably practicable after becoming aware of the fault or
malfunction.
13.12.7 Until any meter or metering equipment affected by an outage, defect or malfunction is
repaired, adjusted or replaced, the affected GCPs and the TSO/MO shall ensure that
suitable proxy data is obtained or estimated and recorded for the period that the fault
condition persists.
13.13 Metering Equipment Security, Meter Reading and Metering Data Access
13.13.1 The TSO/MO and the relevant GCPs shall provide seals and other appropriate devices
to prevent or detect unauthorized interference with the metering facility equipment.
Sealing
13.13.2 Following the Effective Date of the LEGC, or following any test or inspection carried out
according to section 13.11, all meters and metering equipment shall be sealed by or on
behalf of the TSO/MO and, if necessary, the relevant affected GCP, except where sealing
is impossible or impractical having regard to the physical and electrical configuration at
each Connection Point.
13.13.3 Sealing shall be in accordance with the procedures stated in Appendix C.
13.13.4 No seal applied pursuant to this Sub-code shall be broken or removed except in the
presence of, or with the prior consent, of the owner, the TSO/MO and, if appropriate, the
affected GCP affixing the seal, or on whose behalf the seal has been affixed, unless it is
necessary to do so in circumstances where:
(a) both Main and Check meters are malfunctioning or there occurs a fire or other
similar hazard and such removal is essential and such consent cannot
immediately be obtained (in which case the person that has affixed the seal and
has not given such consent shall be informed immediately thereafter); or
(b) such action is required for the purposes of sub-section 13.11.17.
13.13.5 Where verbal consent is given under sub-section 13.13.4, it must be confirmed in writing
forthwith.
13.13.6 All relevant GCPs shall ensure that physical access to meters and metering equipment
is, where practicable, restricted to personnel who are required to have such access for the
proper performance of their duties and have received permission for such access.
13.13.7 A record of any such access in sub-section 13.13.6 shall be maintained by the TSO/MO
and the GCP on whose premises the meter and metering equipment are located, and
copies of such records shall be provided to the relevant affected GCP upon request.
149
13.13.8 In addition all meters and metering equipment, where practicable, must be made secure,
if necessary, by making the lock and keys subject to access restrictions similar to those in
sub-sections 13.13.6 and 13.13.7.
13.13.9 Each GCP or TSO/MO shall control the issue of its own seals and sealing pliers bearing
a distinctive mark and shall keep an accurate register of all such pliers and the authorized
persons to whom they are issued.
Meter reading and access to metering data
13.13.10 The TSO/MO shall download integrating pulse metering data for each Connection Point
at pre-defined intervals for billing and settlement purposes. Each GCP shall be provided
full access to the data for its Connection Point.
13.13.11 The pulses from two or more meters may be combined into one integrating pulse
recorder provided all the other requirements of this Sub-code are met.
13.13.12 The meter pulses that need to be integrated into the recorder are:
(a) active energy and active power demand, imported to and exported from the
LITS; and
(b) reactive energy and reactive power demand imported to and exported from the
LITS.
On-Site meter reading
13.13.13 Provision shall be made by the TSO/MO and GCPs to permit on-site as well as remote
interrogation of the integrating pulse recorder.
13.13.14 Where on-site meter reading is necessary, it shall be witnessed by authorized
representatives of all concerned parties including the relevant GCP whose consumption
is measured by the metering system on the agreed date and time and as stipulated in the
Connection Agreement or Amended Connection Agreement.
Electronic data transfer capability
13.13.15 All metering facilities shall have the capability of electronic data transfer.
13.13.16 The TSO shall provide appropriate security against corruption of data in transmission.
Restriction of unauthorized access to metering data
13.13.17 The TSO/MO and all GCPs shall take all reasonable measures to prevent unauthorized
access and or possible alteration to settings and calibrations.
13.13.18 Only the owner of the metering system will change data and settings within its metering
equipment and in the presence of:
(a) the MO/TSO, or its authorized representative or with the written agreement of the
MO/TSO; and
(b) the relevant GCP, or its authorized representative or with written agreement of the
relevant GCP.
13.13.19 Access to metering data by any GCP, including the provision of any remote access
equipment required, will be at that GCP’s cost, unless agreed otherwise in writing by the
parties concerned.
150
Audit of Databases
13.13.20 The TSO/MO shall submit to an audit by the LERC when reasonably requested and
shall allow access by the LERC or its officially appointed agent to the central database for
the audit.
13.13.21 GCPs shall submit to an audit by the TSO/MO and/or the LERC when reasonably
requested and shall allow access to all applicable Information for the audit to the TSO/MO,
the LERC or an agent appointed by the TSO/MO or the LERC to carry out the audit.
13.16 Confidentiality
13.16.1 Metering data and associated metering database constitute confidential information and
shall always be treated as such. The TSO/MO shall ensure that metering data is protected
from access by unauthorized persons.
13.16.2 The TSO/MO shall not provide metering data from a metering facility to any person other
than the metered entity to whom the data relates except when:
(a) the data must be supplied for law enforcement purposes;
(b) for the purpose of complying with a regulatory or legal requirement; or
(c) it is otherwise permitted by the LEGC.
151
SECTION 14: DATA AND INFORMATION EXCHANGE SUB-CODE
14.1 Background, Purpose and Scope
14.1.1 The TSO has an obligation to ensure that the LITS is operated in a safe, reliable and
secure manner. To achieve this, the TSO shall obtain from and provide to GCPs power
system data and information needed for the maintenance of system security. The
exchange of data and information will enable GCPs to carry out their obligations and to
meet statutory reporting requirements.
Purpose
14.1.2 The Data and Information Exchange Sub-code is based on the requirements of the LEGC
and other statutory requirements. The Sub-code defines the reciprocal obligations of the
TSO and GCPs regarding the provision of information and exchange of data for the
implementation of the LEGC.
Scope
14.1.3 The TSO shall obtain from GCPs, the technical and operational information needed for
the discharge of the TSO’s responsibilities to provide open, fair and non-discriminatory
access to the LITS for all GCPs.
14.1.4 The requirements of this Sub-code are complementary to any data and information
exchange requirements defined or prescribed in other Sections of the LEGC.
152
14.3.3 The TSO shall make available critical data to allow a GCP to make rational and informed
decisions regarding the operations of the LITS.
14.3.4 The TSO will provide open and timely exchange of relevant information among GCPs, to
facilitate the secure and reliable operation of the LITS.
14.3.5 The TSO shall publish all relevant non-confidential information in a timely manner, or make
them accessible by all GCPs, in an open and non-discriminatory manner.
14.3.6 In the case of electronic data sharing, access to LITS information shall be provided on
read-only basis.
14.3.7 A GCP shall be responsible for the procurement and maintenance of the required
communication systems as well as the data communication costs of its systems used for
the purpose of data and information exchange.
153
14.5.2 The planning information to be provided to the TSO shall be as specified in the Planning
Sub-code and any other information which may from time to time be required.
14.5.3 The Transmission GCP shall provide other relevant GCPs with information about
equipment and systems installed at HV transmission substations.
14.5.4 The TSO shall keep an updated technical database of the LITS for purposes of modelling
and studies on the LITS.
14.5.5 The TSO shall provide Distribution GCPs and other Demand GCPs with any information
that may be reasonably required for the proper planning and design of their networks to
enable them to comply with their obligations under the Connection Sub-code.
14.5.6 A Distribution GCP or any other Demand GCP shall, upon a request to upgrade an existing
connection or when applying for a new connection, provide the requisite information
specified in the Connection Sub-code.
14.5.7 A Generation GCP shall submit to the TSO all maintenance planning information regarding
each unit at each power station, as specified in the Operations Sub-code.
154
SCADA infrastructure
14.6.9 The information exchange shall support data from the SCADA system.
14.6.10 Each LITS node shall be accessible to the SCADA system which shall be used for
storage, display and processing of operational data.
14.6.11 All GCPs shall make available outputs of their respective operational equipment to the
SCADA system.
14.6.12 SCADA RTUs shall be installed in accordance with sub-sections 8.21.1 and 8.21.2 for
the transmission of signals and indications to and from the TSO. The signals and
indications which must be provided by GCPs for transmission by installed SCADA
equipment are those specified in sub-section 8.21.5 of the Connection Code, together with
such other data or information as the TSO may reasonably request, from time to time, by
notice to GCPs.
14.6.13 All SCADA, metering, computer and communications equipment and the data or
information carried by the LITS shall be secure from unauthorized access. Procedures
governing security and access shall be agreed with GCPs but shall allow for adequate
access to the equipment and information by the relevant GCP and TSO for the purposes
of maintenance, repair, testing and recording of measurements.
155
14.8 Time Standard
14.8.1 The time standard used shall be the UTC Standard and all information relating to time
shall be referenced to it.
14.8.2 To maintain synchronization, each LITS node shall be provided with a connection to GPS
satellite receivers that enable all relevant devices to maintain time synchronization.
156
recognizable benefit in quality, reliability and features and to do so would be reasonable
in the circumstances.
Telephone/fax
14.10.5 Each GCP shall be responsible for the provision and maintenance of telephone and
facsimile equipment as required.
14.10.6 A GCP shall provide no fewer than two separate Public Switched Telephone Network
circuits to its control room.
14.10.7 A GCP shall provide no fewer than one facsimile unit, connected to a dedicated Public
Switched Telephone Network at its Control facility.
14.10.8 The TSO may provide one or more telephone extensions to be connected to the TSO’s
private operational telephone system. This facility shall be reserved for operational
purposes only and shall be attended by an authorized person and answered without delay.
GCPs shall be responsible for optimizing the reliability and security of this telephone
service.
14.10.9 The TSO shall install and operate a system for recording of all operational voice
communication with GCPs. The historical archives of these voice recordings shall be
available for at least six (6) months and shall be made available to authorized persons
when required.
Computer equipment
14.10.10 A GCP shall provide appropriate Information Technology (IT) and data networking
equipment to allow data exchange such as electronic mail, dispatch instructions, etc
between the TSO and the GCP. The equipment shall only be used by the GCP for
operational communications with the TSO.
File Transfers
14.10.11 The structure and format for data transfer shall be negotiated and defined by the supplier
and receiver of the information.
14.10.12 The transfer media shall be mutually agreed by the parties involved.
14.10.13 The parties shall make adequate arrangements for data backup purposes to enable the
recovery of information in the event of equipment or communication failure.
157
(i) Energy balance indicating internal generation, imports, exports, energy
available for sale and transmission losses;
(ii) Generating plant Availability;
(iii) Number and total duration of frequency excursions outside statutory limits;
(iv) Number and total duration of voltage excursions outside statutory limits;
and
(v) Outage time at each LITS Node.
(c) Annually:
(i) Annual energy balance for the year;
(ii) Annual peak demand in MW, date and time;
(iii) Annual minimum demand in MW, date and time; and
(iv) Outage time at each LITS Node.
14.11.2 A Transmission GCP shall make available all information collected via recorders installed
at substations to the TSO for analysis. The TSO shall make this information available to
affected GCPs on request.
14.11.3 The TSO shall publish weekly in accordance with Technical Schedule TS– T, a report
on the power system performance for the previous week, including a report on Significant
Incidents and operating conditions relevant to the operation of the LITS.
158
14.13.3 A GCP shall not:
(a) disclose confidential information to any third party without the written consent of
the owner or provider of the information.
(b) use or reproduce confidential information for any purpose other than that for which
it was disclosed or for purposes contemplated by the LEGC; and
(c) permit unauthorized persons to have access to confidential information.
14.13.4 A GCP shall use all reasonable endeavors to prevent unauthorized access to confidential
information which is in the possession or control of that GCP.
14.13.5 A GCP shall ensure that any person to whom it discloses confidential information
observes the provisions for confidentiality in relation to that information.
14.13.6 A GCP shall report any unauthorized disclosure of information that is governed by a
confidentiality agreement as soon as practicable after it has become aware of the
unauthorized disclosure and shall provide all reasonable assistance to ensure recovery or
destruction of that confidential information as may be deemed appropriate by the
information owner or provider.
Exceptions to confidentiality of information
14.13.7 The confidentiality provisions in this section 14.13 of the LEGC do not prevent the
disclosure, use or reproduction of information:
(a) if the relevant information is at the time generally and publicly available other than
as a result of breach of confidentiality by a GCP or any person to whom the GCP
has disclosed the information;
(b) by a GCP for the use of an employee or officer of the GCP or a related body
corporate of the GCP, or a legal or other professional adviser, auditor or other
consultant which require the information for the purposes of the LEGC, or for the
purpose of advising the GCP;
(c) with the consent of the person or persons who provided the relevant information
under the Code;
(d) to the extent required by law or by a lawful requirement of any government or
governmental body, authority or agency having jurisdiction over a GCP or its
related bodies corporate;
(e) if required in connection with legal proceedings, arbitration, expert determination
or other dispute resolution mechanism relating to the LEGC;
(f) if required to protect the safety of personnel or equipment; or
(g) of an historical nature in connection with the preparation and submission of
reports under the LEGC.
Disclosure of confidential information
14.13.8 A GCP who needs to disclose confidential information shall consult with the provider of
the information prior to its release and inform those affected by the information disclosure.
159
PART E: RENEWABLE ENERGY PROVISIONS
Part E constitutes the Renewable Energy Sub-code which provides the basic technical
performance requirements that a VRPP needs to comply with in order to connect its generating
facility to the LITS in the Republic of Liberia. This Part defines the rules and minimum standards
that the TSO and the Transmission GCP shall consider when connecting a VRPP to the LITS to
ensure safe, reliable and secure operation of all facilities connected to the LITS.
160
SECTION 15: RENEWABLE ENERGY SUB-CODE
15.1 Background, Purpose and Scope
15.1.1 The ELL provides for the policy to promote the development of renewable energy
resources in the electricity generation mix of the country using appropriate RETs.
However, some RETs such as wind and solar PV present variable resource availability
that should be harnessed. This requires the establishment of guidelines to facilitate the
connection and dispatch of output from variable renewable energy sources to the LITS
without degrading system operation, performance and security.
15.1.2 Significant deployment of these variable RETs can decrease total inertia on the system,
thus increasing the need for frequency regulation but reducing the total regulation
capability available.
15.1.3 The capability to withstand disturbances on the network which result in temporarily
depressed voltages is critical in maintaining power system stability and in preventing
exacerbation of disturbances leading to the risk of cascading outages. It is in this area that
more stringent requirements have been applied for these RETs (Wind power and solar
PV).
Purpose
15.1.4 This Section 15 of the LEGC specifies minimum grid connection technical and design
conditions for a Variable Renewable Power Plant (VRPP) with Wind or Solar PV resource
harnessing technology that is connected to or seeking connection to the LITS, in
accordance with international best practices and standards so that they will be able to
contribute to stability of the LITS.
Scope
15.1.5 The requirements in this Renewable Energy Sub-Code shall apply to all wind and solar
photovoltaic RETs referred to as VRPPs with a design capacity of 2 MVA or larger
connected or seeking connection to the LITS.
15.1.6 The provisions in the Sub-code constitute the basic technical performance requirements
that a VRPP GCP needs to comply with to connect its generating facility to the LITS
covering the following:
(a) the definition of rules and standards that the TSO shall follow when connecting
VRPPs to the LITS; and
(b) the provision of guidance and basis for both the TSO and the VRPP GCP to
cooperate through supply of necessary data and information about their systems
to ensure safe, reliable and secure operation of the LITS and connected VRPPs.
15.1.7 A VRPP GCP seeking connection to the LITS shall comply with this Sub-Code in addition
to all other applicable requirements in the other Sections of the LEGC.
161
other Sections of the LEGC and in accordance with its Connection Agreement with the
TSO.
Frequency range of operation
15.2.2 A VRPP shall be capable of remaining connected to the LITS within the frequency ranges
and for the specified periods in Table 1.
Table 1: Frequency Ranges of Operation
(Must remain connected conditions)
Frequency range (Hz) Minimum operation
period
47.5 ≤ F < 48.75 90 minutes
48.75 ≤ F < 51.25 Unlimited (Continuous
range)
51.25 < F ≤ 51.5 90 minutes
51.5 < F ≤ 52 15 minutes
15.2.3 A VRPP shall be allowed to disconnect from the LITS when it operates outside the
frequency and for the time ranges specified in Table 1.
15.2.4 There shall be no technical restriction regarding the delivery of active power or reactive
power within the frequency range of 49 Hz to 51 Hz and a VRPP shall be permitted
unrestricted operation within this frequency range, except that high frequency response
effects set in at frequencies >50.2Hz thus limiting active power output as shown in Figure
1 and in accordance with sub-section 15.4.7.
15.2.5 The minimum active power output that a VRPP shall be capable of delivering (at various
prevailing frequencies at the PoC) is as shown in Figure 1. The frequency dependent
power limits according to Figure 1 relate to the technical capability under the condition that
sufficient primary energy of the RET (i.e. wind speed, solar irradiation) is available.
Additional limits due to limited primary energy may apply but these limits are not frequency
dependent.
Voltage Range of Operation
15.2.6 There shall be no disconnection of any unit of a VRPP module if voltage at the PoC
remains within plus or minus ten percent (+/-10%) of the nominal voltage or within IEC-
voltage limits for continuous operation (referred to as the Continuous Voltage Range),
whichever is the narrower voltage range.
15.2.7 There shall be no restrictions regarding the provision of active or reactive power when the
VRPP is operating with voltage at the PoC between plus or minus five percent (+/-5%) of
the nominal voltage, referred to as the Unrestricted Voltage Range.
162
120
P (% of Pmax)
49, 100 50.2, 100
100
47.5, 80
80
60 51.5, 49.8
40
20
0
47 47.5 48 48.5 49 49.5 50 50.5 51 51.5 52
Frequency (Hz)
163
Flicker
15.2.14 The TSO shall apportion flicker emission limits to each VRPP using the methodology
specified in IEC 61000-3-7 and based on flicker planning levels according to:
(a) Technical Schedule TS–V of the LEGC;
(b) existing background flicker levels;
(c) possible future installations; and
(d) the total size of a VRPP to be connected.
15.2.15 In the absence of any flicker limits apportioned by the TSO, flicker caused by a VRPP
shall not exceed the emission limits (HV-EHV) of 0.3 for both Pst and Plt parameters.
Harmonics
15.2.16 The TSO shall apportion individual harmonic distortion limits to each VRPP using
methodology specified in IEC61000-3-7 and based on a planning level for THD according
to:
(a) Technical Schedule TS–V of the LEGC,
(b) existing background flicker levels,
(c) possible future installations and
(d) the total size of a VRPP to be connected.
15.2.17 In the absence of any apportioned limits issued by the TSO, harmonic voltage distortion
limits at the PoC as prescribed in Table 2 shall apply.
164
15.2.22 If voltage is outside the Unrestricted Voltage Range but within the Continuous Voltage
Range the reactive power capability limits of a VRPP shown in Figure 2 can be adjusted
to the voltage dependent limits according to Figure 3.
15.2.23 The voltage dependent limits adjustment requirement in sub-section 15.2.22 applies
once automatic tap changer(s) of the grid transformer(s) or any switched shunts in the
VRPP module have operated. In the period(s) that the automatic tap changer is not
functional the VRPP module is required to reduce active power export so that reactive
power capability can be provided.
15.2.24 In the case of operation with active power below five percent (5%) of Pn, there is no
reactive power capability requirement but, in this range, reactive power must be within the
tolerance range of plus or minus five percent (+/-5%) of Pn, specified by points A and B
in Figure 2. Point A is equivalent (in MVar) to minus five percent (–5%) of rated output and
point B is equivalent (in MVar) to plus five percent (+5%) of rated output.
P/Pn
1.2
0.8
0.4
0.2
0
-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.4 0.5
165
V(p.u.) 1.15
1.1
1.05
0.95
0.9
0.85
-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.4 0.5
Figure 3: Reactive power requirements for LITS connected VRPPs corresponding to voltage
(for different Connection Point voltages outside the Unrestricted Voltage Operation range)
166
Voltage droop control
15.3.6 Voltage Droop Control is a control function which helps to control the voltage at the PoC
based on a target and slope (droop) approach.
15.3.7 A VRPP shall be able to perform the voltage control function at the PoC within its dynamic
range and voltage target specified by the TSO in accordance with the droop-characteristic
defined in Figure 4. Droop in this context, is the percentage change in voltage from the
voltage setpoint which will cause a change in reactive power exchange from zero to a
Qmax , or zero to Qmin as appropriate.
15.3.8 When the TSO choses a “droop” characteristic, the “droop” shall be specified by the
maximum voltage change in per unit (p.u.) at maximum reactive power output (Q max ).
15.3.9 If the voltage control target is changed by the TSO, such change shall be completed within
the timescale specified in sub-section 10.17.4 after the receipt of the new set-point value.
15.3.10 The maximum permitted deviation of the actual voltage from the target voltage shall be
no greater than zero-point-five percent (0.5%) of the nominal voltage, that is 0.005 p.u.
Droop
Control
Un
Q min Q max
Figure 4: Voltage Droop Control for LITS-connected VRPP
15.3.11 When the VRPP attains its dynamic design limits, the control function shall maintain this
position (maximum or minimum reactive current) and await possible overall control from
the tap changer or other voltage control functions. A VRPP should be designed not to trip
at this time unless permitted to do so by the TSO as per section 10.17 of the LEGC.
P
Pn
167
Q(P) Control
Constant
Q-Control]
Power Factor Control
Q max
Q min
Figure 5: Reactive Power & Power Factor Control functions for the VRPP module
15.3.13 The TSO shall define the actual settings of the Q/ Q(P) control characteristic (shape of
the Q(P)-characteristic, target values) which will always start from unity power factor (i.e.
zero MVar).
15.3.14 If the control target is changed by the TSO, such change shall be completed within the
timescale specified in sub-section 10.17.4 after receipt of the new target value.
15.3.15 The maximum permitted deviation of actual reactive power from the Q-target shall be no
greater than two percent (2%) of rated power, that is 0.02 p.u., beyond which the automatic
control system should act to restore the operating point on to the characteristic within two
(2) minutes after change of Q-target during steady system conditions.
15.3.17 A VRPP shall be capable of controlling power factor at the PoC either to a constant
power factor target (cosφ-target) or an active power dependent power factor target
(cosφ(P)) as illustrated by the blue line in Figure 5.
15.3.18 The TSO shall define the actual settings of the cosφ or cosφ(P) control characteristic
[cosφ-target or the shape of cosφ(P)-characteristic].
15.3.19 If the control target is changed by the TSO, such change shall be completed within the
timescale specified in sub-section 10.17.4 after receipt of the new target value.
15.3.20 The maximum permitted deviation of actual power factor from the cosφ-target shall be
no greater than ∆cosφ=0.005, beyond which the automatic control system should act to
restore the operating point on to the characteristic set cosφ-target within the timescale
specified in Section 10.17.
168
15.4.2 A VRPP module shall be capable of setting an active power curtailment set point given in
MW to limit active power following receipt of an instruction from the TSO.
15.4.3 If the TSO issues an instruction to a VRPP GCP to set an active power curtailment set-
point, the GCP shall begin to respond to the new set-point within two (2) minutes and
should ramp to the new active power curtailment set-point at the ramp rate agreed with
the TSO within plus or minus one percent (±1%) accuracy of deviation from the rated
power set-point.
15.4.4 Any active power curtailment set-point shall apply until such times as the TSO releases
the active power curtailment set-point.
15.4.5 The type of communication between the TSO and a VRPP GCP shall be in accordance
with Section 14 of the LEGC (Data and Information Sub-code) or otherwise must be
agreed between the parties and specified as part of the Connection Agreement (as
prescribed in sub-section 15.9.4).
15.4.8 High frequency response must operate with a minimum ramp rate of 100% of rated power
per minute as provided by the primary frequency control time scales.
15.4.9 The required reduction in active power output should commence within two (2) seconds
of the frequency exceeding 50.2 Hz and be continuously and linearly proportional as far
as it is practicable to the characteristic in Figure 6.
.
Figure 6: Mandatory high frequency response for all LITS connected VRPPs
169
15.5 Behavior of VRPP During Abnormal Voltage Conditions
Fault Ride-through Requirements
15.5.1 Fault ride-through refers to the ability of a VRPP to remain connected during a system
voltage disturbance. Four main characteristics typically provide the requirements for
VRPPs in the event of a voltage disturbance:
(a) Conditions for which the VRPP must remain connected;
(b) Active power provision during a fault;
(c) Voltage support requirements during the disturbance; and
(d) Restoration of active power after the fault has been cleared.
Remain-connected voltage conditions
15.5.2 A wind or solar PV VRPP shall remain connected to the LITS for voltage disturbances on
any or all phases, where the system phase voltage measured at the connection point
remains above a specified level for a specified length of time.
15.5.3 The remain-connected requirements take the form of a ‘voltage verses time’ profile as
illustrated in Figure 7 which dictates the level of voltage drop or increase that a VRPP
must be capable of withstanding along with the time for which the voltage drop or increase
should be endured.
15.5.4 Area A shows that the VRPP shall be able to operate continuously between voltages of
0.9 p.u. and 1.1 p.u. and shall stay connected to the network and uphold normal
production.
15.5.5 Area B is the area between the LVRT Bound and the bottom of the continuous operating
range, at 0.9 p.u. In Area B the VRPP shall stay connected to the network. As illustrated
in Figure 7 the VRPP shall be able to withstand voltage drops to zero, measured at the
PoC for a minimum period of 0.15 seconds without disconnecting. Less severe voltage
drops result in an increase in the length of endurance time of the connected VRPP, and
just below 0.85 p.u. the voltage drop shall be endured for nearly two (2) seconds. At 0.85
p.u. the voltage drop shall be endured a minimum of three (3) seconds.
15.5.6 Area D is the area between the HVRT Bound and the top of the continuous operating
range, at voltage of 1.1 p.u. In Area D the VRPP shall stay connected to the network and
as illustrated in Figure 7 the VRPP shall be able to withstand voltage increases up to 1.2
p.u. for at least two (2) seconds.
15.5.7 Area C (below the LVRT Bound) and Area E (above the HVRT Bound) respectively at
voltages below 0.9 p.u and above 1.2 p.u and outside the continuous operating range, are
the areas where disconnection of the VRPP is allowed.
15.5.8 If the voltage reverts to the Continuous Voltage Range (between 0.9p.u and 1.1p.u) during
a fault sequence (e.g. resulting from reclosing), subsequent voltage drops or voltage
spikes shall be regarded as new LVRT or HVRT condition. If several successive fault
sequences occur and the voltage remains outside of the normal voltage operating range,
the successive series of faults shall be considered as one continuing fault condition.
170
Active power provision and reactive current flows during fault
15.5.9 During a voltage dip the controllable VRPP shall provide active power in proportion to
retained voltage and maximize reactive current to the LITS without exceeding its declared
limits.
15.5.10 The maximization of reactive current during a fault shall continue for at least six hundred
milliseconds (600 ms) or until the voltage recovers to within the normal operational range
of the LITS, whichever is the sooner.
1.2
0.8
0.6
LVRT
HVRT
0.4
0.2
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5
Time (s)
15.5.12 The factor of proportionality between additional reactive current and voltage deviation is
named K (ΔIq=KΔVt ) and the factor K must be settable in the range of 0≤K≤10.
15.5.13 The absolute value of current (I) in each of the three phases of the unit’s terminals may
be limited to rated current (1 p.u.).
171
15.5.14 During dynamic performance, after sixty (60) milliseconds the additional current must
have settled, meaning that it shall remain within a tolerance band of plus-or-minus twenty
percent (±20%) around the value according to Figure 8.
15.5.15 During LVRT and HVRT conditions, the active current (I P) shall be reduced in proportion
to the voltage change ΔVt .
Figure 8: Reactive current support ΔIq during LVRT and HVRT situations at the unit’s terminals
Notes:
1. Voltages and currents in this section 15.5 are defined to be positive sequence
components of fundamental frequency value of voltages and currents respectively. This
applies to pre-fault and post-fault voltages and currents.
2. The additional reactive current ΔIq shall be injected in addition to the pre -fault voltage.
3. The positive sign of ΔIq in Figure 8 is voltage supporting injection of reactive power.
4. The voltage deviation ΔV t is defined by the difference between the pre-fault and the post-
fault voltage.
5. The pre-fault current and pre-fault voltage are defined by the one-minute average of
current and voltage respectively.
15.7.3 A VRPP shall be equipped with effective detection of islanded operation in all system
configurations and shall have the capability to shut down generation of power in such
condition within two (2) seconds.
15.7.4 The islanded operation of a VRPP with part of the LITS is not allowed unless specifically
agreed with the TSO.
15.7.5 The coordination among protections at the Connection Point must be agreed between the
TSO and the VRPP GCP.
15.7.6 The circuit breaker used for connection switching of a LITS-connected VRPP shall be
equipped with a disconnection system to ensure safe operation during re-connection or
re-synchronization to the LITS.
15.7.7 The TSO may request that the set values for protection functions of a VRPP be changed
following commissioning if it is deemed to be of importance to the operation of the LITS,
except that, such a change shall not result in a VRPP being exposed to negative impacts
from the LITS falling outside of the design requirements.
15.7.8 The TSO shall inform a VRPP GCP of the highest and lowest short-circuit current that
shall be expected at the PoC as well as any other information about the LITS as may be
necessary to define the VRPP's protection functions.
15.7.9 Where a VRPP’s protection equipment is required to communicate with the TSO’s
protection equipment it must meet the communications interface requirements specified
by the TSO in accordance with this Sub-code as well as section 9.20 and other relevant
Sections of the LEGC.
15.9.6 A VRPP GCP shall install equipment necessary to automatically communicate to the TSO
the expected and real-time renewable generation output and data for the purposes of
generation forecast.
174
PART F: DEFINITIONS
Part F, the Definitions, provides meanings and definitions for special words and technical terms
used in the text to bring out the meanings in the context that they have been used in the LEGC.
175
In this Liberia Electricity Grid Code (LEGC), unless the context otherwise requires—
Access means the contracted right to use an electrical system to transfer electrical
energy.
acre-foot means the volume of water that will cover one acre to a depth of one foot
and is a unit for measuring the volume of water. One acre –foot equals
325,851 gallons or one million gallons equals 3.07 acre –feet.
active energy means the electrical energy produced, flowing or supplied by a electric
circuit during a time interval, being the integral with respect to time of the
instantaneous active power, measured in units of Watt-hours or standard
multiples thereof: i.e. 1000Watt-hours = 1 Kilo Watt-hour (kWh) 1000 Kilo
Watt-hour = 1 Mega Watt-hour (MWh) 1000 Mega Watt-hour = 1 Giga
Watt-hour(GWh) 1000 Giga Watt-hour = 1 Tera Watt-hour (TWh).
active power means the product of the components of the alternating current and the
voltage that equate to true power which is measured in units of watts and
standard multiples thereof, for example: 1000 Watt = 1 Kilo Watt (kW)
1000 Kilo Watt = 1 Mega Watt (MW) 1000 Mega Watt = 1 Giga Watt (GW)
1000 Giga Watt = 1 Tera Watt (TW).
adequacy means the ability of the electric system to supply the aggregate electrical
demand and energy requirements of the customers at all times, taking into
account scheduled and reasonably expected unscheduled outages of
system elements.
aerial plate means a number plate to aid the aerial observer to identify the
transmission tower.
alternating means an electric current that reverses its direction of flow at periodic
current intervals, of 50 times per second.
ammeter is an electrical instrument, with a scale usually graduated in amperes,
placed in a circuit to measure the magnitude of electric current.
ampere (amp) is a unit of measure of an electric current and is proportional to the
quantity of electrons flowing through a conductor past a given point in one
second.
ancillary service means a service necessary to support the transmission of energy from
supply sources to loads while maintaining reliable operation of the
transmission system in accordance with Prudent Utility Practice and these
services include voltage control, operating reserves, black start capability
and frequency control.
Arc is the discharge of electricity through gas occurring across a gap or set of
electrodes.
Arcing is the process of current flowing across a gap, such as fault current
flowing across an insulator string that flashed over due to a lightning
surge.
Asset Owner means a person who owns the whole or part of the LITS or any facility
connected to the LITS.
automated meter means a system capable of reading the data from a meter preparing and
reading system conditioning the data and transmitting the accumulated data from the
meter location to a central data and accumulation device.
Automatic means the regulation of the power output of electric generators within a
Generation control area in response to changes in load, system frequency, and other
Control factors to maintain the scheduled system frequency and interchanges with
other control areas.
176
Automatic means the continuously acting automatic equipment controlling the
Voltage terminal voltage of a synchronous generating unit by comparing the actual
Regulator terminal voltage with reference value and controlling by appropriate
means the output of an exciter, depending on the deviations.
availability is a measure of time a generation unit, transmission line or other facility is
capable of delivering energy to the transmission system at the delivery
point or of providing ancillary services to the transmission system.
availability means a notice that declares the availability of the relevant facility.
declaration:
availability factor means a percentage representing the number of hours an equipment or
unit is ready for or in service in a given period, compared to the number of
hours in the period.
basic insulation means a design voltage level for electrical apparatus that refers to a short
level duration (1.2x50 microseconds) crest voltage - used to measure the ability
of an insulation system to withstand high surge voltage.
black start means the ability of a generating unit to start and synchronize to theLITS
capability without using supply from the power system.
Large Consumer means a customer that purchases or receives electric power or energy of
the amount or level specified by the LERC or end users who consume
more than a threshold number of kilowatt hours as defined by the
regulations.
bus is an electrical conductor which serves as a common connection for two or
more electrical circuits and is used to interconnect equipment of the same
voltage. A bus may be in the form of rigid bars or in the form of stranded
conductor overhead cables held under tension.
capability means the maximum load a generator, piece of equipment, substation, or
system can carry under specified (standardized) conditions for a given
time interval without exceeding approved limits.
capability curve means a curve developed for generators showing the limits of reactive
and active power that a generator can produce without overheating or
becoming unstable.
capacity means the rated continuous load-carrying ability, expressed in megawatts
(MW) or megavoltamperes (MVA) of generation, transmission, or other
electrical equipment.
capacity factor means the ratio of the electrical energy produced by a generating unit for
the period of time considered to the electrical energy that could have been
produced at continuous full power operation during the same period.
cascading is the occurrence of an uncontrollable succession of outages, each of
outage which is initiated by conditions (e.g. instability or overloading) arising or
made worse as a result of the event preceding it. The tendency of a local
line fault to trigger problems elsewhere on the system and lead to a
widespread power outage.
Check Meter is a meter installed by the transmission customer which provides the
source data for comparison with the Main Meter.
circuit means a conductor or a system of conductors through which an electric
current flow or is intended to flow.
circuit breaker is a protective device located on a circuit to interrupt the flow of current at
that particular point and used to disconnect from a power system which
experiences an electrical fault or overload.
177
combined cycle means the use of a combustion turbine and a steam turbine in an
electrical generating plant so that the waste heat from the combustion
cycle provides heat energy for the steam cycle to increase its thermal
efficiency of the entire system.
combustion means a turbine that generates power from the combustion of a fuel.
turbine
commissioning means a test conducted on equipment that is being connected to the grid
test for the first time or after modification or major maintenance.
Committed means data relating to a proposed GCP development at the time that the
Project Planning GCP commits to a Connection Agreement or an Amended Connection
Data Agreement.
compensation means the use of devices like capacitors or voltage regulators to improve
performance of an electric system with respect to some specified
characteristic.
conductor is a material through which electricity is transmitted, such as an electrical
wire, or transmission or distribution line.
Connected means the data which replaces the estimated values that were assumed
Project Planning for planning purposes with validated actual values.
Data
Connection is an agreement between the TSO and a GCP that seeks connection of its
Agreement facilities to the LITS and sets out the rights, obligations and liabilities of
both parties.
Connection is an MOU between the TSO and the GCP required to be negotiated and
MOU signed prior to commencement of construction of the connection to the
LITS.
connection point is the point of physical linkage to or with the transmission network for the
purpose of enabling the flow of electricity as the boundary between the
transmission system and a facility or other equipment.
connection point means the drawings prepared for each Connection Point, which indicate
drawing the equipment layout, common protection and control, and auxiliaries at
the Connection Point.
Connection means the document required to be submitted to the TSO for the purpose
Proposal of a new connection to the LITS.
constraints means the physical and operational limitations on the transfer of electrical
power through transmission facilities.
contingency means the possibility of a fault or equipment failure in a power system.
Continuous means network frequency or voltage operating range, outside normal
Operation range of operation, within which no generating unit is allowed to
Range disconnect and where power output restrictions may exist.
control action means an action, like switching by which the Transmission System is
operated.
control area means an electric power system or a combination of electric power
systems bounded by interconnection metering and telemetry, capable of
controlling generation to maintain its interchange schedule with other such
areas and contributing to frequency regulation of the interconnection.
control center means the facility from which a power system is monitored and regulated
where dispatchers use computerized displays to match generation with
load and to respond to faults in the system.
178
control system means the method of monitoring and controlling the operation of the
power system or equipment including generating units connected to a
transmission or distribution network.
control room same meaning as in ‘control center’.
Current means an instrument transformer, with its primary winding connected with
Transformer the conductor carrying the current to be measured, which gives an
(CT) accurate low-current indication in its secondary winding of the high
amperage current in its primary winding. The low-current output is used
for relaying, metering and indication.
customer means a person that contracts for an electricity service
demand means the rate at which electric energy is delivered to or by the System or
part of the System and is the sum of both active and reactive power,
unless otherwise stated.
demand forecast means predicted demand for electric power. A forecast may be short term
(e.g., 15 minutes) for system operation purposes, long-term (e.g., five to
20 years) for generation planning purposes, or for any range in between.
A forecast may include peak demand, energy, reactive power, or demand
profile. A forecast may be made for total system demand, transmission
loading, substation/feeder loading, individual customer demand, or
appliance demand.
Demand GCP Means a distribution company or large consumer or customer that has
facilities or equipment directly connected to the LITS to offtake power and
energy.
demand profile is the hour-by-hour profiles of demand as at each Bulk Supply Point;
demand management means the instructions by the TSO for the purposes
of balancing the load with generation.
derogation Means authorized directions from the LERC exempting or relieving a TSO
or GCP from its obligation to comply with specific aspects of the
provisions of the LEGC for a specified duration.
dispatch means the operating control of an integrated electric system to
(a) assign specific generating units and other sources of supply to meet
the power demand as load rises or falls;
(b) control operations and maintenance of high voltage lines, substations
and equipment, including administration of safety procedures,
(c) operate interconnections;
(d) manage energy transactions with other interconnected control areas;
and
(e) curtail power demand to balance generations.
Dispatch Day means the day assigned on a daily basis by the TSO for the forecast
generation and dispatch of power and energy to meet demand.
dispatch means an instruction given by the Grid Company from its System Control
instruction Centre to the Generator’s approved contact person or location to change
the output, fuel or manner of operation of the Generation Unit.
Distribution means a person licensed under the ELL to distribute and sell electricity
Company without discrimination to consumers in an area or zone designated by the
LERC.
Distribution GCP means a distribution company with distribution network or facility
connected to the LITS to offtake power and energy.
distribution means a system of electric lines and associated equipment (generally at
network nominal voltage levels of 36 kV or below) , which that Distribution
179
.Company is licensed to use to distribute electricity for supply under its
distribution license excluding public lighting assets.
disturbance means an unplanned event that produces an abnormal system condition
or any occurrence that adversely affects normal power flow in a system.
dynamic means a condition that occurs when small undamped oscillations begin
instability without any apparent cause because the Grid is operating too close to an
unstable condition.
earthing means a way of providing a low impedance connection between
conductors and the earth by an earthing device which is in accordance
with the requirements of the local safety instructions.
ECOWAS means the protocol signed by the Authority of the Heads of State and
Energy Protocol Governments of the ECOWAS on January 6, 2003, which establishes a
legal framework in order to promote long term cooperation in the energy
field based on complementarities and mutual benefits with a view to
achieving increased investment in the energy sector and increased energy
trade in the West Africa Sub-Region.
electrical means a schematic representation, using standard electrical symbols,
diagram which shows the connection of equipment or power system components
to each other or to external circuits.
electrical energy means the energy loss in an electric system, consisting of transmission,
loss transformation, and distribution losses between sources of generation and
ultimate consumer.
elements of the includes generating units, transmission lines, transformers, circuit
power system breakers and switches.
embedded means production of electricity utilizing a generation facility that is
generation electrically connected directly to a distribution system and for which the
total output of the facility is distributed and utilised locally without any
requirement for use of the national interconnected transmission system.
emergency means any abnormal system condition that requires automatic or
immediate manual action to prevent or limit loss of generation supply or
transmission facilities that could adversely affect the reliability of the
electric system.
Emergency means the overall capacity of interregional or international power lines,
Transfer together with the associated electrical system facilities, to transfer power
Capability and energy from one electrical system to another under emergency
conditions.
energize is the action of connecting a component to a source of power by the
movement of an isolator, breaker or switch enabling it to transfer active
and reactive power.
energy storage means the process for storing, or converting energy from one form to
another, for later use.
Equipment means the system of numbering or nomenclature for the identification of
Identification equipment at the connection points in the LITS.
event means an unscheduled or unplanned occurrence on, or relating to, a
system including, faults, incidents and breakdowns.
event reporting is the procedure set out for reporting events.
fault is an event occurring on an electric system such as a short circuit, a
broken wire, or an intermittent connection.
feeder means an electrical supply line, either overhead or underground, which
runs from the LITS Node. It is the start of a distribution circuit, usually less
180
than 36000 volts, which carries power from the substation. Also, a line
from a generating plant or an interchange point between a transmission
system and a load or distribution system.
firm means guaranteed or assured.
flicker means a fast fluctuation in voltage leading to quick intermittent coming on,
of an appliance and gives the impression of unstable visual sensation
induced by a light stimulus with luminance or spectral distribution that
fluctuates with light.
force majeure means superior force that is unexpected or uncontrollable event and
which upsets plans or releases a person from fulfilling an obligation.
forced outage means removal of service of the temporary de-rating of, restriction of use
of, or reduction in performance of, equipment other than those specified
as a scheduled outage.
frequency is the number of alternating current cycles per second (expressed in
Hertz) at which a system is running.
frequency means the retention of the frequency on the power system within
control acceptable limits.
frequency means the automatic adjustment of active power output by a generation
regulation unit, initiated by free governor action in response to continuous minor
fluctuations of frequency on the power system.
gas turbine means a combustion turbine that converts energy of hot compressed
gases (produced by burning fuel in compressed air) into mechanical
energy that can be used to generate electricity.
generation means a wholesale supplier with electric generation facilities to produce
company power and energy.
generating unit is an equipment or plant for producing energy from other forms of energy
generation is the process of producing electric energy from other forms of energy
(electricity): expressed in watthours (Wh).
generation means a facility comprising of generating unit(s) and equipment for
facility producing electric energy from other forms of energy expressed in watt-
hours (Wh).
Generation GCP means a generation company with generation facility(ies) connected to the
LITS for production and injection of power and energy.
generation means a statement prepared by the TSO setting out which generating
schedule units are anticipated to be required to ensure, so far as practicable, that
the integrity of the Transmission System, the security and quality of supply
and that the generating units assigned are sufficient to meet demand at all
times (to extent practicable) together with an appropriate margin of
reserve.
governor control is the automatic control system which regulates the speed of the power
system turbine of a generating unit through the control of the rate of entry into the
generating unit of the primary energy input (for example, steam, gas or
water).
grid means an interconnected network of transmission lines of the LITS
including associated equipment for the transfer of electric energy between
points of supply and points of demand.
Grid Code means this code that contains the technical and operational rules of
practice and standards of performance rules developed and approved by
the LERC to facilitate the operations related to the bulk transmission of
electricity within the LITS.
181
Grid Code A Wholesale Supplier or VRPP operator, Transmission asset owner
Participant (NGC), Distribution Company or Large Consumer with facilities that are
(GCP) connected to the LITS as provided in sub-sections 1.3.2 and 1.3.3 of the
LEGC.
harmonic means a sinusoidal wave having a frequency that is an integral multiple of
a fundamental frequency.
high voltage is descriptive of transmission lines and electrical equipment with voltage
levels greater than 36 kV.
imbalance is a condition where the generation and interchange schedules do not
match demand.
impedance is a characteristic of an electric circuit that determines its hindrance to the
flow of electricity and measured in ohms.
inadvertent means the difference between a control area’s net actual interchange and
interchange net scheduled interchange.
Individual is the ratio between RMS value of the individual harmonic content and the
Harmonic RMS value of the fundamental voltage expressed in percentage.
Distortion (IHD) 𝐼𝐻𝐷 = √ (𝑉𝑖 2 / 𝑉1 2)∗ 100 %
Vi = Voltage component of harmonic order 𝑖;
V1 = Voltage component of fundamental frequency (@50 HZ).
insulator means a material usually a ceramic ,porcelain, elastic polymeric rubber, or
fiberglass when used in the transmission line and is designed to support a
conductor physically and to separate it electrically from other conductors
and supporting material.
interchange means electric power or energy that flows from one entity to another.
interchange consists of an agreement between the TSO and the GCP on the amount,
schedule start and end times, ramp rate, and degree of firmness for the purpose of
an arrangement to transfer electric power.
Interconnected is a system consisting of two or more individual electric systems that
System normally operate in synchronism and that have connecting tie-lines.
interconnection means the linkage of transmission lines between two utilities, enabling
transmission power to be moved in either direction.
lines
interruptible load means load which can be automatically disconnected by the use of under
frequency relay or other means.
inter-tripping means a method in which operation of a protection equipment at one end
of a circuit causes a signal to be transmitted to trip a circuit breaker at the
remote end of the circuit.
island means a portion of a power system or several power systems that is
electrically separated from the interconnection due to the disconnection of
transmission system equipment.
Isolating device means a device which ensures the disconnection of equipment from the
remainder of the network.
isolation means the disconnection of equipment from the remainder of the network
in which the equipment is situated by either of the methods specified in
sub-section 11.6.2 of the LEGC.
Liberia means an interconnected group of electric transmission lines and
Interconnected associated equipment for moving or transferring electric energy in bulk
Transmission between points of supply and points at which it is transformed for delivery
System (LITS) over the distribution system lines to consumers, or to other electric
systems.
182
line voltage means the voltage present between any two of the conductors in a three-
phase system.
load means the amount of power carried by a utility system or subsystem, or
amount of power consumed by an electric device at a specified time.
load factor is the ratio of the actual electrical energy produced/consumed to the
possible maximum electrical energy that could be produced/consumed in
any defined period.
load flow studies means computer simulations of the transmission system, with
representations of the complete electrical transmission system along with
loads and different generation schedules to meet the loads and used by
engineers to study various operating conditions and to plan future system
additions to assure reliable service to customers.
load following means an electric system’s process of regulating its generation by
selected generators to follow the changes in demand.
load forecasts means predicted demand for electric power which may be short-term like
for a duration of one hour for system operation purposes or long-term for
five to twenty years for generation planning purposes.
load methods to reduce or reshape or redistribute electrical loads to match
management available resources designed to influence the timing and amount of
electricity that customers may use and it generally attempts to shift loads
from peak periods to low use periods.
load shedding is the process of deliberately removing pre-selected loads from a power
system, usually done automatically by relays, in order to maintain the
integrity of the system under unusual conditions.
local safety means the safety instructions of the TSO or a GCP as applicable.
instructions
losses means electric energy losses in the electric system which occur principally
as energy transformation from kilowatt-hours (kWh) to waste heat in
electrical conductors and apparatus.
low voltage is descriptive of electricity supply lines and equipment with voltage levels
up to 1000V (1KV).
Main Distribution means an interface panel for process signals.
Frame (MDF)
Main Meter is the meter installed by the TSO which provides source data for the
accounting and billing function for LITS supply and services.
maintenance means the removal of equipment from service availability to perform work
outage that can be deferred for a while, but requires the equipment be removed
from service before the next planned outage.
Market means the rules for operation of the electricity wholesale (supply) market
Operation Rules as provided for in regulation 50(3) of the ELR, as amended from time to
(MOR) time, and approved by the LERC.
major means any forced outage, malfunction or fault of an equipment or
event/incident apparatus that results in 10% or more customers losing electricity supply
from the LITS.
medium voltage is descriptive of electricity supply lines and equipment with voltage levels
above 1000V (1KV) up to 36KV.
merit-order is the ranking in order of which generating plant should be used, based on
ascending order of price together with amount of electricity that will be
generated.
183
merit-order means the allocation of demand to individual generating units to effect the
dispatch least cost production of electricity for customers. The process of
determining the desired generation level for each of the generating units in
a system in order to meet consumer demand at the lowest possible
production cost given the operational constraints on the system.
meter is a device for measuring and recording units of electrical quantities.
metering is the method of applying devices to measure and record the amount and
direction of electrical quantities with respect to time.
metering data means the data associated with a metering point.
metering is the system for the storage of data for meters and associated equipment
database in the LITS to facilitate easy retrieval.
metering includes meters, time switches, measurement transformers ,metering
equipment protection and isolation equipment, circuitry and their associated data
storage and data communications equipment and wiring which are part of
the active energy and reactive energy measuring equipment at or related
to a metering point.
metering facility means a combination of metering equipment.
metering means the time between electricity meter consumption recordings.
intervals
metering means data related to a metering facility that is prescribed by the TSO for
information record in the metering register.
metering point means a point in the LITS at which a meter and its accessories are
physically located, where electrical energy is measured and defined.
Metering has the meaning assigned to it under sub-section 13.9.1.
Register
metering system includes metering equipment, processes associated with metering, roles
and activities related to metering.
Metering Site: means overall metering location associated with metering a connection
point, and includes main and back up metering points.
Metering Test means entity that has functions of monitoring, testing, inspecting and
Service Provider adjusting the metering equipment and metering systems of the generator.
(MTSP):
Meter Test means a certified test laboratory which has the technical and infrastructure
Station capability to perform accuracy tests for meters and metering equipment.
multiple means the failure or outage of an element of the power system and the
contingency coincidental unexpected failure or outage of any other related element of
the power system.
nameplate rating means a manufacturer’s guaranteed performance of an equipment in the
power system under standardized conditions and is usually expressed in
amperes, volts, kilovolt-amperes, kilowatts or other appropriate units
usually indicated on a nameplate attached to the individual machine or
device.
network means the plant and equipment used to convey, and control the
conveyance of, electricity to customers.
NITS node see substation.
node means a point in the LITS where active or reactive power or energy can
be injected or withdrawn.
nominal voltage means the voltage by which the system is designated and to which certain
operating characteristics are related, and the voltage at which the system
184
operates and is normally about 5 to 10 percent below the maximum
system voltage for which system components are designed.
non-spinning means slow reserve.
reserve
N-1 contingency means that the system is sufficiently reliable if it is able to operate
criterion acceptably under any unplanned outage of equipment as the result of a
single cause.
off-peak means the hours or other periods defined by contract or other agreements
or guide as the periods of lower electrical demand. Off- peak normally
refers to a period of relatively low demand on an electric system and is
typical to occur in the middle of the night.
on-peak means the hours or other periods defined by contract or other agreements
or guide as the periods of higher electrical demand. On- peak normally
refers to a period of relatively high demand on an electric system.
open access means the equal right or non-discriminatory provision to connect or use a
system to transfer electrical energy provided established requirements are
met.
operating criteria means the fundamental principles of reliable interconnected systems
operation.
operating means a set of policies, practices, or system adjustments that may be
procedures automatically or manually implemented by the TSO within a specified time
frame to maintain the operational integrity of the interconnected electric
systems.
operating means the additional megawatt output required from a generation unit or
reserve demand reduction which must be realizable in real time operation to
contain and correct any potential power system frequency deviation to an
acceptable level.
operating means the established measurable criteria for determining the
standards performance of obligation within a control area or a power system.
operational data means the data required by the TSO for the purpose of satisfactorily
operating, planning and managing the LITS.
operational means planning through various time scales, the matching of Generation
planning Output with forecast Demand together with a reserve of Generation to
provide a Margin, taking into account Outages of certain Generation Units
and of parts of the Transmission System carried out to achieve as far as
possible, the required level of System Security.
outage means a scheduled or unexpected period in a power system, during which
a facility or component ceases to provide its full functioned capability and
in relation to a generation unit, a total or partial reduction in availability
such that the generation unit is unavailable to achieve its full registered
megawatts capacity in accordance with its registered operating
characteristics.
outage needs means the time and periods specified by the GCP for planned and
maintenance outage.
overload means operation of equipment in excess of its normal, full load rating or
operation of a conductor in excess of ampacity, which if continued for a
sufficient length of time, would cause damage or overheating.
peak demand means the maximum load during a specified period of time; performance
standard: is a set of standards for the purpose of monitoring the
performance of the TSO and the GCPs in the delivery of their services.
185
performance means a set of standards for the purpose of monitoring the performance
standard of the TSO and the GCPs in the delivery of their services.
planned outage means the removal of the equipment from service availability for
inspection or the general overhaul of a major equipment and is usually
scheduled well in advance.
Point of means the point on a public power supply system where the installation
Connection under consideration is or can be connected. [Note: A supply system is
(PoC) considered as being public in relation to its use, and not its ownership].
power factor means the ratio of the active power to the reactive power at a metering
point.
power flows See ‘load flow studies’.
power line means power-line communication data carried on a conductor that is also
carrier (PLC) used simultaneously for AC electric power transmission or distribution to
consumers.
power pool means two or more interconnected electric systems planned and operated
to supply power for their combined demand requirements.
Power Purchase means a commercial agreement between a Generation GCP and a
Agreement Demand GCP in which the Demand GCP agrees to purchase the
(PPA) electrical output of a Generating GCP and the Generation GCP agrees to
provide the services from its plant.
Power Supply means a commercial agreement between the Transmission GCP and
Agreement other GCP for the supply of electrical power and energy.
(PSA)
power system means the interconnected system of generation units, transmission and
distribution networks operated as an integrated arrangement for the
supply of electricity.
power system means a device that injects a supplementary signal into the AVR
stabilizer (Automatic Voltage Regulator) in order to improve power system damping;
Preliminary means data relating to a proposed GCP development at the time that the
Project Planning applicant/proposer applies for a Connection Agreement or an Amended
Data Connection Agreement.
primary reserve means reserve that is provided automatically and immediately to correct
drops in system frequency.
Prudent Utility means any generally accepted practice, method and act engaged in or
Practice approved by a significant portion of electric utility industry during a
relevant time period or any practice, method or act that in the exercise of
reasonable judgment in the light of facts known at the time of the decision,
that could have been expected to accomplish the desired result at a
reasonable cost, consistent with good business practices, reliability,
efficiency, safety and expedition.
Public switched means the aggregate of the worlds circuit-switched telephone networks
telephone that are operated by national, regional or local telephone operators.
network (PSTN)
Quick reserve means spinning reserve and comprises of primary & secondary reserve
(activated automatically), and tertiary and emergency reserve (activated
manually) per Section 9.5 of the Code.
ramp rate means the rate of change at which the power output of a generator can be
increased or decreased (for example in MW/min).
186
rated power means the rated installed power capacity of a generating unit that is
connected to the network and whose output is continuously available to
the network.
reactive energy means the integral with respect to time of the instantaneous reactive
power produced, flowing or supplied by an electric circuit during a time
interval measured in units of VARH or standard multiples thereof
reactive power means the product of voltage and current and the sine of the phase angle
between them measured in units of volt-amperes reactive and standard
multiples thereof.
reactive power means a diagram, which shows the MW and MVar capability limits within
capability curve which a generating unit will be expected to operate under steady state
conditions.
reactor means a device specifically arranged to be connected within the
transmission system during periods of low load demand or low reactive
power demand to counteract the natural capacitive effects of long
transmission lines in generating excess reactive power and so correct any
transmission voltage effects during these periods.
Regulations means the Electricity Licensing Regulations issued by the LERC.
reliability means the degree of performance of the elements of the electric power
system that results in electricity being delivered to customers within
accepted standards and in the amount desired. It is a measure of the
ability of a power system to provide uninterrupted service, even while that
system is under stress. Reliability may be measured by the frequency,
duration, and magnitude of adverse effects on the electric supply.
remedial action means special protection schemes designed to automatically perform
scheme system protection functions other than the isolation of an electrical fault.
remote terminal means a device installed in a substation f or the purpose of collecting and
unit transmitting codes and data to the Master Computer of SCADA/EMS,
SCADA/DMS system.
renewable means a type of electricity generated from an energy resource that is
energy replaced rapidly by a natural process such as from the sun (e.g. solar PV,
biomass), wind (e.g. wind power, wave power), earth’s core (e.g.
geothermal), or the moon (e.g. tidal).
Requesting Refer to definition of ‘safety coordinator’.
safety
coordinator
reserve means an ancillary service that consists of a generation capacity that is
available, or a load that can be interrupted by the Utility in the event of an
unexpected outage of a scheduled plant.
reserve margin means the difference between an electric utility’s system capability and
anticipated peak load during a specific period, measured either in
megawatts or as a percentage of peak load.
reservoir means the level of the water stored behind a dam. Also can be the
elevation reservoir’s elevation above sea level.
reservoir storage means the volume of water in a reservoir at a given time.
safety means a person appointed to be responsible in all matters concerning
coordinator safety of personnel and equipment and shall be competent to carry out the
functions set out to achieve safety on the LITS at all times as provided
under section 11.4 and can either be a “Requesting Safety Coordinator” or
an “Implementing Safety Coordinator.
187
safety means the isolation and grounding of equipment when work or testing is to
precaution be done on the LITS or GCP system.
safety means processes defined by safety rules.
procedures
safety key means a key used for locking an earthing or Isolating device.
safety log means the logbook in the relevant control room where safety precautions,
instructions and incidents are logged.
safety rules means the rules which ensures that persons working on Plant and/or
apparatus to which the rules apply are safeguarded from hazards arising
from the System.
scheduled Day means a period in the Scheduling process from 00.00 hours to 24.00
hours in the same calendar day.
secondary means the capability of a generating unit to have its generated outputs
reserve adjusted frequently (e.g. by AGC) so that any system frequency variations
can be corrected.
security means the ability of the electric system to withstand sudden disturbances
like electric short circuits or unanticipated loss of system facilities.
set point means an analog or digital signal sent by the SCADA system to a VRPP
facility representing the maximum renewable energy output required from
that facility.
shunt capacitor means an equipment connected to a network to generate reactive power.
shunt reactor means an equipment connected to a network to absorb reactive power
significant means every event or case where either or a combination of the following
incident happens:
(i) malfunctioning of equipment or apparatus connected to the
transmission network; and
(ii) a person or animal receives an electric shock, whether mild or
serious or suffers an injury or burn, directly or indirectly due to
electrical causes.
single includes the singular
contingency (a) sudden, unexpected failure or outage of a power system or of an
element like generating unit, transmission line and transformer; or
(b) removal from service of an element of the power system like
generating unit, transmission line or transformer as part of the
operation of a remedial action scheme,
the occurrence of which shall not affect the normal operation of the LITS.
single line means a drawing of electrical circuits where three phase circuits are
diagram represented by a single line rather than three lines.
Slow reserve means generating capacity that is not operating or synchronized to the
system but which is available to serve demand within specific time of
being requested as specified in sub-section 9.5.8 means non-spinning
reserve.
spinning reserve means the unloaded generation capacity, which is synchronized and
ready to automatically serve additional demand without human
intervention in order to arrest a drop of system frequency due to an
instantaneous mismatch between generation and demand.
stability means the ability of an electric system to maintain a state of equilibrium
during normal and abnormal system conditions or disturbances.
static VAR means a controllable VAR supply, that consist of a complete system of
compensation static components like capacitors, reactors and solid-state switches
188
combined in one device, to provide rapid and continuously controllable
reactive compensation.
steady state means the capability of an electric power system to maintain its initial
stability condition after a small interruption or to reach a condition very close to the
initial one when the disturbance is still present.
substation means a facility at which two or more lines are switched for operational
purposes and which may in addition have one or more transformers to
enable some connected lines operate at different nominal voltages in
relation to others.
Supervisory means a computer system that allows an electric system operator to
Control and Data remotely monitor and control elements of an electric system.
Acquisition
surge means a transient variation of current, voltage, or power flow in an electric
circuit or across an electric system.
switchgear includes the combination of various switching and interrupting devices
used in a power system like disconnecting switches circuit breakers, and
automatic circuit reclosers.
synchronize means the process of connecting two previously separated alternating
current apparatuses after matching frequency, voltage, phase angles like
paralleling a generator to the electric system.
system means any disturbance that results in localized or widespread loss of load
disturbance or resulting in one or more of the following phenomena: system instability,
cascading outages, formation of islands, or undesirable voltage or
frequency.
System means a partial shutdown or total shutdown or any other physical
Emergency operational condition or occurrence on the power system which is
Condition (a) imminently likely to endanger life or property; or
(b) imminently likely to impair the:
(i) ETU’s ability to discharge its obligation; or
(ii) safety and reliability of the power system.
System means a measure of the ability of protection to initiate successful tripping
Protection of circuit-breakers which are associated with a faulty item of apparatus. It
Dependability is calculated using the formula:
(Dp) Dp =1- FN /Ftot Where:
Ftot = Total number of system faults
FN = Number of system faults where there was a failure to trip
a circuit breaker
tertiary reserve means quick reserve that can be manually instructed by the TSO to
replace secondary reserve, and to balance load and VRPP forecast
errors.
test procedure means a procedure that specifies the switching sequence and proposed
timing of the switching sequence, including other activities deemed
necessary and appropriate in carrying out the test.
tie-line means a circuit connecting two or more control areas or systems of an
electric system.
time error means an accumulated time difference between control area system time
and the time standard and is caused by a deviation in Interconnection
frequency from 50.0 Hz.
time error means the offset to the interconnection’s scheduled frequency to correct
correction for the time error accumulated on an electric clock.
189
Total Harmonic means the ratio of the RMS voltage of the harmonic content to the RMS
Distortion (THD) value of the fundamental voltage, expressed in percent.
𝑇𝐻𝐷 = √[∑ (𝑉𝑖 2 /𝑉1 2)]∗ 100 %
𝑉𝑖 = Voltage component of harmonic order𝑖;
V1 = Voltage component of fundamental frequency (50 HZ).
transfer means the amount of power, that can be transmitted between one system
capability and another and which power flow and stability studies can determine
under various outage, system loading and system operating conditions.
transformer means a device that consists of a magnetic core on which there are two or
more windings which can be used to transfer electrical energy from one
circuit to another by magnetic induction, usually between circuits of
different voltages.
transient stability means the ability of an electric power system to maintain synchronism
between its parts when subjected to a disturbance of a specified severity
and to regain a state of equilibrium following that disturbance OR the
ability of the system to experience a sudden change in generation, load or
system characteristics without a prolonged loss of synchronism.
transmission means the electric system consisting of (major part or the system as a
network whole) lines and cables, having design voltage of 66kV and above,
operated by the TSO and managed by the Transmission GCP to transmit
energy from a generating station to a substation or to another generating
station or inter-substations or to any interconnection system including
apparatus, equipment and metering systems owned by the Transmission
GCP and used for transmission of electrical energy.
Transmission means a person mandated and licensed under the ELL to own
GCP transmission assets and provide transmission services without
discrimination to customers within the LITS.
transmission means an interconnected group of electric transmission lines and
system associated equipment for moving or transferring electric energy in bulk
between points of supply and points at which it is transformed for delivery
over the distribution system lines to consumers, or to other electric
systems.
Transmission means a neutral operator licensed under the ELL responsible for
System Operator maintaining instantaneous balance of the LITS by controlling the dispatch
(TSO) of generating units to ensure that loads match resources available to the
system and is effected in a safe, reliable, economic and non-
discriminatory manner.
turbine means a machine to generate rotary mechanical power from the energy of
a stream of fluid like water, steam, or hot gas.
Under- means the automatic tripping of customer load by means of one or more
Frequency Load relays set to trip at specific under-frequencies which during a sudden
Shedding mismatch between Generation and customer Load attempts to prevent
system shutdown.
unit commitment means the process of determining which generator will be brought on-line
to meet load or provide ancillary services for the next generation schedule
Unrestricted means normal network frequency or voltage operating range during which
Operation no generating unit is allowed to disconnect and where there is no
Range technical restriction with regard to the delivery of active power or reactive
power.
VAR means a single unit of reactive power.
190
Variable means renewable power plant with continuously varying power output
Renewable following the availability of primary energy without any storage (Wind and
Power Plant solar PV farms.
(VRPP)
voltage means the electronic force or electric potential between two points that
gives rise to the flow of electricity.
voltage collapse means an event that occurs when an electric system does not have
adequate reactive support to maintain voltage stability and which may
result in the outage of the components of the power and the interruption in
service to customers.
voltage control means the control of transmission voltage within acceptable limits through
adjustments in generator reactive output and transformer taps, and by
switching.
voltage dip means a sudden reduction of the voltage to a value between 90% and
100% of the nominal voltage followed by a voltage recovery after a short
period of time.
voltage droop means the relationship between Voltage and Reactive Power, specified in
percent, for use in the Voltage Droop Control and which value represents
the change in Voltage which will cause a Generator’s site to move from 0
MVAr exchange to full Reactive Power exchange at the Connection Point.
voltage droop means a method of controlling the reactive power exchange from a GCP’s
control site at the Connection Point, depending on the voltage, voltage vroop and
voltage target settings.
voltage means a condition that results in Grid voltages that is beyond the level
instability where voltage control equipment can return them to the normal level
voltage stability means the condition of an electric system in which the sustained voltage
level is controllable and within predetermined limits.
VRPP Operator means an operator of a VRPP seeking connection to or already connected
to the LITS.
Watt (Electric) means the electrical measuring unit for active power.
Watt-hour (Wh) means the unit of electrical energy equal to one (1) watt of power supplied
to, or taken from, an electric circuit steadily for 1 hour.
wheeling means the use of the facilities of one transmission system to transmit
power and energy from one power system to another.
wholesale means an electricity market established by market operation rules for bulk
electricity market trading of electricity, ancillary services and any other related electricity
supply product or service.
wholesale includes electricity sales, purchase and settlements in the Wholesale
electricity trading Electricity Market between a wholesale supplier and a distribution
company or large consumer.
wholesale means a person licensed under the ELL to install and operate a facility to
supplier produce electricity or to procure electricity for sale in bulk to a large
consumer or to a distribution company for distribution and sale to
consumers.
191
PART G: TECHNICAL SCHEDULES
Part G, Technical Schedules, contains detailed technical information relevant for the
implementation of the LEGC to guide the operation of the LITS.
192
Technical Schedule TS–A: AFLS Philosophy
Introduction
1. Power system frequency is controlled mainly by the generation. Small frequency excursions
occur continually as generation is controlled to match changing loads. The frequency is stable
when generation and load match. Frequency is normally controlled by the following:
(a) generator governors;
(b) automatic generation control (AGC); and
(c) System operators/Dispatchers.
2. When these actions fail, the system is in danger of a total blackout and a final safety net is the
Automatic Frequency Load Shedding (AFLS) scheme.
Justification
3. The intent of the AFLS Program is to provide a last resort system preservation measure during
severe frequency declines that can result from an extreme disturbance or a condition where
load substantially exceeds generation. An AFLS program can minimize the risk of total or
partial system collapse, prevent damage to generation and transmission facilities, provide for
equitable load shedding, and improve the overall reliability of the power system.
Philosophy
4. An Automatic Frequency Load Shedding (AFLS) program shall be developed, coordinated,
and documented by the TSO. All Distribution Companies and large consumers are obligated
to participate in the AFLS program, in accordance with good utility practice.
5. The AFLS Program shall be coordinated between all GCPs and with interconnected utilities,
as necessary. The AFLS Program shall also be coordinated with generation protection, any
tie-line tripping schemes, etc.
6. Loads shed during AFLS operations shall not be restored except with the approval of the
TSO.
7. The AFLS Program shall be in steps, set to drop predetermined blocks of load at discreet
frequency steps and for each step, the following shall be defined:
(a) the frequency and/or rate of frequency decay settings and time delays;
(b) the substation or location of loads to be shed; and
(c) the estimated magnitude of loads/percentage of load to be shed for both peak and off-
peak periods.
8. The AFLS program shall be determined by the TSO following consultations with relevant
GCPs and published as the Demand Management Guidelines in the System Operations
Manual by November 1st each calendar year, to cover the immediately following twelve-
month period.
9. The TSO shall ensure that, as far as is practicable, the burden of load shedding is fairly
distributed among GCPs.
10. The AFLS program shall be reviewed annually or as and when necessary, by the TSO.
193
Technical Schedule TS–B: Capability and Availability Declaration
1. Capability and Availability Declarations shall contain the following information:
(a) The average active power expected to be available for each hour during the following
day (including start time and date);
(b) Estimated initial conditions (time required for notice to synchronize within the
Technical Limits and Plant Performance Characteristics), last on or off time;
(c) Generating Unit run-up rates in MW for each level of warmth (cold, warm or hot
starts);
(d) Unit run-down rates;
(e) The reactive power capability of each unit;
(f) Minimum load for each Unit; and
(g) Any maintenance which is planned during the period that could reasonably affect the
available power.
2. Definitions
(a) Cold Start: More than 96 hours since the last shutdown
(b) Warm Start: 8 hours or up to 96 hours since the last shutdown
(c) Hot Start: Less than 8 hours since the last shutdown
194
Technical Schedule TS – D: Detailed Planning Data
Generating Unit and Generating Plant Data
1. The following additional information shall be provided for the generating units at each
generating plant:
(a) Generating Unit Manufacturer;
(b) Rated power factor (over-excited and under-excited);
(c) De-rated capacity (MW) on a monthly basis if applicable;
(d) Additional capacity (MW) obtainable from the generating unit in excess of net
declared capability;
(e) Generator performance and efficiency data and curves;
(f) Minimum stable loading (MW);
(g) Reactive power capability curve;
(h) Stator armature resistance;
(i) Direct axis synchronous, transient and sub-transient reactances;
(j) Quadrature axis synchronous, transient and sub-transient reactances;
(k) Direct axis transient and sub-transient time constants;
(l) Quadrature axis transient and sub-transient time constants;
(m) Turbine and generating unit inertia constant (MWsec/MVA);
(n) Rated field current (A) at rated MW and MVar output and at rated terminal voltage;
and
(o) Short circuit and open circuit characteristic curves.
2. The following information for step-up transformers shall be provided for each generating unit:
(a) Rated MVA;
(b) Rated frequency (Hz);
(c) Rated voltage for both primary and secondary (kV);
(d) Voltage ratio;
(e) Winding connection and vector group;
(f) Positive sequence resistance (at maximum, minimum and nominal tap);
(g) Positive sequence reactance (at maximum, minimum and nominal tap);
(h) Zero sequence reactance;
(i) Magnetizing curve;
(j) Tap changer range, step size; and type (on load or off load); and
(k) Transformer test certificates from which actual technical detail can be extracted as
required are to be supplied on reasonable request.
3. The following excitation control system parameters shall be provided for each generating
unit:
(a) Voltage regulator model name;
(b) DC gain of excitation loop;
(c) Rated field voltage;
(d) Maximum field voltage;
(e) Minimum field voltage;
(f) Maximum rate of change of field voltage (rising and falling)
(g) Functional description and block diagram showing transfer function of individual
elements of the excitation system and the automatic voltage regulator;
(h) Dynamic characteristics of over excitation limiter; and
(i) Dynamic characteristics of under excitation limiter
4. The following information shall be provided for Power System Stabilizers (PSS):
195
(a) Functional description and block diagram showing transfer function of individual
elements of the PSS;
(b) Report on methodology in deriving the PSS setting, including simulation results and
tuning procedures;
(c) Commissioning tests or other filed results
5. The following speed governing system parameters shall be provided for each generating
unit:
(a) Governor dead band - Maximum setting, normal setting, minimum setting;
(b) Time constant of steam or fuel governor valve or water column inertia;
(c) Governor valve opening limits;
(d) Governor valve rate limits;
(e) Time constant of turbine; Governor block diagram showing transfer function of
individual elements including acceleration sensitive elements in accordance with IEEE
Standard Models;
(f) Detailed description of setting calculation for each of the governor system functions;
and
(g) Documents describing the performance of the overall governor system and each
governor function for which a setting is derived
6. The following plant flexibility performance data shall be submitted for each generating unit:
(a) rate of loading from a cold start-up condition;
(b) rate of loading from a warm start-up condition;
(c) rate of loading from a hot start-up condition;
(d) block load following synchronization;
(e) time from minimum stable load to full load (minutes)
(f) rate of load reduction from normal rated MW;
(g) regulating range;
(h) load rejection capability while still synchronized and able to supply load;
(i) power required for unit auxiliaries
System Data
7. The TSO and each GCP shall exchange information, including details of physical and
electrical layouts, parameter, specifications and functional description and settings of
generating unit protection and other data needed for power system studies.
8. Each GCP shall provide additional planning data that may be requested by the TSO.
[Note: All data to be provided shall be in per unit magnitude with MVA base specified. Generating
unit and generating unit’s step-up transformer data shall be provided in rated MVA capacity base]
196
(c) Auxiliary Transformers (MVA)
(d) Cables
(e) Additional reactive Equipment (e.g. STATCOM / SVC / shunt elements)
15. Voltage Control methodology (e.g. utilizing VRPP Units / STATCOM / SVC / shunt elements
etc.) 8. Earthing arrangements with earth resistance values.
18. Full description of inter-tripping of Breakers at the Connection Point(s) with the Transmission
System.
19. Most probable fault clearance time for electrical faults on the GCP's system.
C. Switchyard
21. In relation to
(a) interconnecting transformers between High Voltage Transmission System and the
PPM MV system and
(b) transformers on individual units:
(i) Rated MVA
(ii) Voltage Ratio
(iii) Vector Group
(iv) Positive sequence reactance (maximum, minimum, normal Tap(% on MVA)
(v) Positive sequence resistance (maximum, minimum, normal Tap (% on MVA)
(vi) Zero sequence reactance (% on MVA)
(vii)Tap changer Range (+ % to - %) and steps
(viii) Type of Tap changer (off-load/on-load)
22. In relation to switchgear including circuit breakers and isolators in all areas on of the VRPP
module and at the Connection Point(s):
(a) Rated Voltage (KV)
(b) Type of Breaker (MOCB/ABCB/SF6)
(c) Rated short circuit breaking current (kA) 3 Phase
(d) Rated short circuit breaking current (kA) 1 Phase
(e) Rated short circuit making current (kA) 3 Phase
(f) Rated short circuit making current (kA) 1 Phase
(g) Provisions of auto reclosing with details.
197
23. Lightning Arresters: Provide technical data.
198
Technical Schedule TS – E: LITS Security Requirement
1.0 Criteria for Normal System Conditions
1.1 Normal conditions are considered to exist if system voltages, line and equipment loadings are
within normal limits and an emergency does not exist on the system or externally.
1.2 Criteria used to define Operating Security Limits for the normal system conditions are
summarized below and must satisfy the conditions in paragraph 4.0.
(a) A permanent three-phase fault on any generation, transmission line, transformer, or
bus section excluding those bus sections contained in (e), cleared in normal time, with
due regard to reclosing facilities;
(b) Simultaneous permanent phase to ground faults on different phases on each of two
adjacent transmission circuits on a multiple transmission circuit tower, cleared in
normal time, with due regard to reclosing facilities;
(c) A permanent phase to ground fault on any generator, transmission circuit, transformer,
or bus section with delayed clearing and with due regard to reclosing facilities;
(d) Loss of any element without a fault; and
(e) A permanent phase to ground fault (between current transformers) on a circuit breaker,
cleared in normal time, and with due regard to reclosing facilities.
2.0 Criteria for Emergency System Conditions
2.1 Emergency conditions are considered to exit when observance of Normal Operation Limits
would require load cuts or restriction in interconnection transactions during capacity or energy
emergencies on the system or externally.
2.2 Capacity or energy emergency exists when firm loads may have to be cut due to insufficient
power or energy is available in the area.
2.3 Criteria used to define Emergency Security Limits are summarized below and must satisfy the
conditions in paragraph 4.0.
(a) A permanent three-phase fault on any generation, transmission circuit, transformer, or
bus section, cleared in normal time and with due regard to reclosing facilities.
(b) Loss of any element without a fault.
3.0 Criteria for Areas Not Affecting Interconnections
3.1 Portions of the network where instability will not significantly affect the interconnected systems
may be operating within Security Limits based on the following criteria and must satisfy the
conditions in paragraph 4.0.
(a) Loss of any element without a fault.
(b) A normally cleared phase-to-phase to ground fault on any generator, transmission
circuit, transformer or bus section, with due regard to re-closure.
4. Operating Limits
199
4.1 The system must be stable with all un-faulted elements remaining in service except those
associated with normal fault clearance and generation rejection if employed.
4.2 The post-contingency steady-state loading of system elements must be within their 15-minute
Limited Time Rating unless a pre-planned course of action exists to return the loading to
continuous rating within shorter time period. Where a pre-planned course of action exists, the
post-contingency steady-state loading must not exceed the five-minute Limited Time Rating
on any system element.
4.3 The system must be able to withstand manual energization of the faulted element without prior
readjustment of generation levels unless specific instructions to the contrary are provided.
Such instructions will be embodied in Operating Security Limits and will normally apply only
under specified conditions of loading in instances where post-contingency conditions would
present a radical departure from the normal system configuration.
4.4 The post-contingency voltage levels must be within acceptable limits.
200
Technical Schedule TS – F: Frequency Limits
1. The LITS frequency shall be maintained as follows:
(a) Between 49.8 to 50.2 Hz under Normal State of operation;
(b) Between 49.5 to 50.5 Hz for a period not exceeding ten (10) minutes under Alert
State;
(c) Between 49.0 to 51.0 Hz for a period not exceeding thirty (30) minutes under
Emergency State.
2. A generating unit must be operable within the frequency range of 48.75 Hz to 51.25 Hz
without automatically disconnecting from the LITS.
201
Technical Schedule TS–H: Accuracy Classes of Metering Equipment
Connection Capacity < 50 MVA > 50MVA International Interconnections
202
Technical Schedule TS–K: LITS Performance Benchmarks
1. Benchmarks for system performance and reliability indices shall be determined by the LERC
on the basis of computations of the 3-year record of historical operational performance data
submitted by the TSO.
2. The LERC shall, in consultations with the TSO and the relevant GCPs, determine the
benchmarks for the system performance and reliability indices defined and specified under
Section 12 and Technical Schedule TS – R of the LEGC in consideration of the following:
(a) historical performance trends,
(b) committed reliability improvement projects,
(c) system performance requirements,
(d) industry and international standards and
(e) other considerations.
3. The benchmarks shall be defined and become effective, not later than six months following
the establishment of the LEGC.
4. The performance and reliability benchmarks shall be reviewed annually by the LERC.
203
Technical Schedule TS–L: Limits for Operating Parameters
The following indices and limits shall be measured or determined and used in the monitoring and
reporting of the performance and reliability of the LITS:
3. All Demand GCPs of power shall maintain their power factor at values not less than 0.90 at
all times.
5. Phase displacement between voltages shall be within the limits stated in the System
Operations Manual of the TSO.
6. The maximum permissible voltage flicker limits shall be in accordance with IEC/TR3 61000-
3-7 standard (or IEEE Standard 519- 1992 as alternative).
7. The maximum permissible harmonic limits shall be in accordance with IEC/TR3 61000-3-7
standard (or IEEE Standard 519- 1992 as alternative).
8. All generating units shall be operable between power factors of 0.85 lagging and 0.95 leading.
204
Technical Schedule TS–M: Minimum data requirements for transmission to
SCADA system
The SCADA system shall be used for storage, display and processing of operational real time
data. All Transmission GCPs and other GCPs shall make available outputs of their respective
installed operational equipment to the data acquisition system or as specified in the Connection
Agreement.
1. State of plant/equipment SCADA Data (Digital Inputs)
A Transmission GCP and other GCPs shall provide the status information for both real time and
recording purposes in relation to the status of each equipment or plant in respect of the indications
provided as follows:
(a) Generating unit (On/Off, if available);
(b) Generation unit circuit breaker (Open/close/undefined, if available);
(c) Circuit breaker in switchyard (open/close/undefined);
(d) Disconnector (open/close); and
(e) Position of tap changer.
3. Accumulator inputs;
(a) Generation outputs (Wh, VArh) (if available);
(b) Energy transmitted in incoming and outgoing feeders (Wh/VArh);
5. Other requirements of data acquisition and transmitting equipment (if necessary) shall be
clearly described in the Connection Agreement.
205
Technical Schedule TS–O: Operating Reserve Policy
1. The TSO shall, in consultation with the GCPs, specify the Operating Reserve Policy, including
its allocation of the permissible mix of Quick Reserve and Slow Reserve, and the procedure
for applying operating reserve in practice, and the limitations, if any, upon the amount of
interruptible load which may be included.
2. The TSO shall submit the Operating Reserve Policy to the LERC for approval.
3. In developing the Operating Reserve Policy, due consideration shall be taken of relevant
factors, including, but not limited to the following:
(a) the cost of providing operating reserve at any point in time;
(b) the magnitude and number of the largest generation in-feeds to the LITS at that time,
including in-feeds over interconnections and also over single transmission feeders
(which may be single or double circuit) within the LITS;
(c) ambient weather conditions, insofar as they may affect (directly or indirectly)
generating unit and/or transmission system reliability;
(d) the predicted frequency drop on loss of the largest credible trip as determined through
simulation using a dynamic model of the LITS;
(e) constraints imposed by agreements in place with externally interconnected parties;
(f) historical availability and reliability performance of individual generating units;
(g) notified risk to the reliability of individual generating units; and
(h) imbalance power requirements resulting from –
(i) uncertainties of demand and VRPPs’ forecasts; and
(ii) continuous variation of demand and VRPPs output during a dispatch period which
impose uncertain load following requirements.
4. Unless proven to be technically impossible, or the economic burden imposed on the dispatch
cost is excessive, the precise methodology for allocating reserve shall be defined by the TSO
and agreed with LERC, and must be in-line with the following principles:
(a) Primary Reserve: the TSO shall ensure that enough Primary Reserve is available to
maintain system frequency within acceptable limits, following a contingency such as a
unit trip or a sudden surge in Load, without any Under-Frequency Load Shedding. The
requirement on the TSO is to keep the frequency above 48.75 Hz following all credible
single contingency losses. The TSO shall ensure that the same volume of Negative
Primary Reserve is available. Those generating units that are contracted for Primary
Reserve are also required to provide the same capacity for Negative Primary Reserve
for high frequencies.
(b) Secondary Reserve: sufficient Secondary Reserve shall be carried to ensure that any
decay in Primary Reserve is replaced. The same volume of Negative Secondary
Reserve shall be carried; however, this may come from other sources.
(c) Tertiary Reserve: the TSO must ensure that sufficient Tertiary Reserve is available
to restore Primary and Secondary Reserve following a contingency or to compensate
the maximum residual load variability value within any 1-hour interval (maximum
difference between instantaneous value of Load or residual Load and one hour
average value) minus the allocated Secondary Reserve. The same volume of
206
Negative Tertiary Reserve shall be carried; however this may come from other
sources.
(d) Emergency Reserve: the TSO must ensure that sufficient Emergency Reserve is
available for compensating the worst-case credible multiple contingency loss (e.g.
simultaneous outage of two large gas turbine Generating Units).
(e) Slow Reserve: The TSO must ensure that sufficient Slow Reserve is available to
restore Tertiary Reserve plus Emergency Reserve following a contingency and to
compensate for the worst-case imbalance error resulting from day-ahead forecast
errors of the available generation and Load. Slow reserve should be procured on an
hour-by-hour basis. It should predominantly be procured from hydro power plants,
operating under water management and gas turbine Generating Units that operate
under fuel management.
(f) Operating Reserve shall be considered the effective use of capacity in an emergency
and shall be dispersed throughout the system taking into account the time required to
be effective, transmission limitations, and local area requirements.
5. The TSO shall, in consultation with the other GCPs, review probable contingencies frequently
to determine the adequacy of Operating Reserve Policy and maintain it permanently under
review.
6. On an annual basis, the TSO shall submit to the LERC an amended version for approval,
taking into consideration the previous year’s frequency recovery performance.
7. Record keeping: The TSO shall keep records of significant alterations to the Operating Reserve
Policy.
207
Technical Schedule TS–P: Power Factor and Reactive Power Limits
1. Distribution GCPs and all other Demand GCPSs off-taking power from the LITS shall maintain
their power factor at values not less than 0.90.
2. All generating units shall be operable between power factors of 0.85 lagging and 0.95 leading.
208
Technical Schedule TS–R: LITS Performance Report
Information in Performance Report
A LITS Performance Report prepared by the TSO shall, in the least, provide information relating
to the performance in relation to the following:
1. System Efficiency Performance Indices
(a) Maximum System Demand
(b) Total energy received
(c) Total energy supplied
(d) Net total energy dispatched
(e) Average power dispatched
(f) Load Factor (%)
(g) Transmission losses (%)
(h) System Capacity Factor (%)
(i) Utilization Factor (%)
(j) Equipment Loading reporting > 85% of rated capacity, time of occurrence & duration
2. Availability
(a) Availability Factor for a line segment (%)
(b) Availability Factor for group of transmission line segments (%)
(c) Equivalent Availability Factor for a line segment (%)
(d) Equivalent Availability Factor for a group of line segments (%)
3. Reliability
(a) System Time error
(b) System Average Interruption Duration Index
(c) System Average Interruption Frequency Index
(d) System Minutes Lost
(e) Index of Transmission Reliability
(f) Transmission line faults/100km of circuit line.
4. Quality
209
Index Normal State Alert State Emergency
State
Frequency deviations
(a) No. of occurrences
(b) Total duration of incidents
(c) Maximum continuous period
(d) Max Value/Time/Date
(e) Min Value/Time/Date
Voltage profile
(a) No. of occurrences
(b) Total duration of incidents
(c) Maximum continuous period
(d) Maximum Value/Time/Date
(e) Minimum Value/Time/Date
5. Events reporting
(a) Planned outages - Time/Date/Duration
(b) Forced Majeure conditions
(c) Generation capacity shortage outages - Time/Date/Duration/Amount/Causes
210
Technical Schedule TS–S: Standard Planning Data
Historical Energy and Power Demand
1. A GCP shall provide its actual monthly energy and demand consumption at each Connection
Point for the immediate past year.
2. A GCP shall also provide the hourly load profiles for a typical Weekday, Saturday, Sunday and
holiday.
4. The forecast data for the first year shall include monthly forecast for energy and power
demand, while the remaining four years shall include only one annual energy and power
demand forecast.
5. The GCP shall provide the TSO with forecast hourly load profiles for typical Weekday, Saturday
and Sunday and holiday.
6. Distribution GCPs shall provide the net values of energy and power demand forecast for the
distribution system at each Connection Point, after any deductions to reflect the output of
embedded generating plants.
7. Generation GCPs shall submit to the TSO the projected energy and power to be generated by
each generating plant.
[NB: Energy and power demand forecast shall be accompanied by a short description
setting out the basis for the forecast]
9. The following information shall be provided for generating units of each generating plant:
(a) Rated capacity (MVA and MW);
(b) Rated voltage (kV);
(c) Maximum available output in MW;
(d) Minimum stable load (MW)
(e) Type of generating unit and expected running mode(s);
(f) Direct axis transient reactance (% on MVA rating);
(g) Direct axis sub-transient reactance (% on MVA rating);
(h) Frequency Response Table;
(i) Reactive Power capability (MVAr) in the range 0.95 leading and 0.85 lagging;
211
(j) Rated capacity, voltage and impedance of the generating unit’s step-up transformer;
(k) Short Circuit Ratio (% on MVA rating); and
(l) Auxiliary Power requirement.
12. The GCP shall provide the values of the following circuit parameters of overhead lines and/or
underground cables from the GCP substation to the connection point with the LITS:
(a) Rated and operating voltage (kV);
(b) Positive sequence resistance and reactance;
(c) Positive sequence shunt susceptance;
(d) Zero sequence resistance and reactance; and
(e) Zero sequence susceptance.
13. If the GCP is connected to the LITS through a transformer, the f ollowing data for the power
transformer shall be provided:
(a) Rated MVA;
(b) Rated voltages, HV, LV, Tertiary (kV);
(c) Winding arrangement;
(d) Positive sequence resistance and reactance (at maximum, minimum and nominal tap);
(e) Zero sequence reactance for three-winding core transformer;
(f) Tap changer range, step size and type (on-load or off-load); and
(g) Basic lightning impulse insulation level (kV).
14. The GCP shall provide the following information for the switchgear, including circuit breakers
and disconnect switches at the substation of the GCP:
(a) Rated voltage (kV);
(b) Rated current (A);
(c) Rated symmetrical RMS short circuit current (kA); and
(d) Basic lightning impulse insulation level (kV).
15. The GCP shall provide the details of its system grounding. This shall include the rated capacity
and impedances of the grounding equipment.
212
16. The GCP shall provide the data on reactive power compensation equipment at the connection
point and/or at the substation of the GCP. This shall include the following information:
(a) rated capacity (MVar)
(b) rated voltage (kV);
(c) type (e.g. shunt capacitor, shunt reactor, static var compensator, etc);
(d) resistance/reactance/susceptance of all components of the compensation device; and
(e) operation and control details (fixed or switched, automatic or manual)
17. If a significant portion of the GCP’s demand may be supplied from alternative connection
point(s), the relevant information on the demand transfer capability shall be provided by the
GCP, including the:
(a) alternative connection point;
(b) demand normally supplied from each alternative connection point;
(c) demand which may be transferred from or to each alternative connection point; and
(d) control (manual or automatic) arrangements for transfer including the time required to
implement the transfer for forced outage and planned maintenance conditions.
18. If a distribution or GCP system has embedded generating plants, the short circuit contribution
of the embedded generating plants shall be provided by the Distribution GCP or the Demand
GCP. The short circuit currents shall be calculated in accordance with the IEC Standards or
their equivalent national standards.
General Information
19. For each new connection from a Distribution GCP or otherDemand GCP, the following
information is required:
(a) load build-up curve (in the case of a new connection);
(b) supply date start (start of load build-up);
(c) load type (residential, commercial, factory, etc);
(d) annual load factor;
(e) power factor;
(f) special requirements (e.g. Quality of supply); and
(g) other information required to enable the TSO to provide a GCP with an appropriate
supply.
21. Site Map: (To scale) Showing area required for VRPP module, main Plant, buildings and
location of VRPP Units.
213
Connection:
25. Connection Point: Furnish Single Line Diagram of the proposed connection with the system.
Station Capacity:
27. Total VRPP module capacity (MW).
28. Ancillary Services provided - State the total installed capacity (in MW) of VRPP Units, and the
total export capacity (in MW) at the Connection Point
29. No. of VRPP Units and Unit size MW & State whether development will be carried out in
phases and if so, furnish details.
Connection:
36. Report of studies of parallel operation with Transmission System:
(a) Load flow studies (including Reactive Power capability)
(b) Stability studies (Fault Ride Through)
214
(c) Short Circuit studies
215
Technical Schedule TS–T: Timetable for Data & Information Submissions
216
8.15.14 TSO Lodgment of Connection Agreement 30 days after execution
or Amended Connection Agreement
with LERC
Ref Responsible Description of submission Deadline
Section/ player
sub-
section
8.18.16 Generation Restoration of protection which was Within One (1) day
GCP bypassed by agreement to normal after the bypass
settings
8.21.9 GCPs Additional measured quantities Within seven (7) days
made available at connection point upon TSO notification
RTU
8.21.11 TSO/GCPs Verification of measured quantities Once every three (3)
& indications for functionality of RTU years
8.24.4 TSO Response to statement of readiness 14 days after receipt of
to connect the statement
8.24.12 GCP Design information of new or Four (4) months prior
replacement equipment to TSO to the planned
commissioning date
8.24.13 TSO Solicitation and compilation of GCP 20 days after receipt of
comments on newly proposed design parameter
parameter settings information from GCP
8.24.15 GCP Commissioning program including Three 3 months prior to
test procedures for new or commencement of
replacement equipment commissioning
8.24.16 TSO/Transmis Notification of GCP on decision of 15 working days after
sion GCP commissioning program receipt of the advice of
readiness to
commission
8.25.9 Transmission Revised electrical diagram of a LITS One (1) month prior to
GCP/other node in respect of connected addition or change of
relevant GCP equipment equipment
8.28.2 GCP Notice of intention to inspect a LITS At least two (2) days‘
facility not owned by that GCP notice
8.28.8 GCP Inspection report to Seven (7) days after
TSO/Transmission GCP after first entry
exercising right of entry
8.28.16 GCP’s Testing Report on any relevant tests carried Not exceeding two (2)
officer out upon a GCP’s request weeks after the test
8.27.3 (c) Generation Report on remedial actions Monthly interval report
GCP undertaken to correct detected
problems
8.31.1 GCP Notification of intention to Six (6) months prior
disconnect facility from the LITS notice
permanently
9.14.7 TSO Notification of load shedding 60 minutes after action
incident
9.15.4 TSO Review and update of LITS At least annually
Restoration Plan
217
9.16.8 (b) GCP Written notification of TSO on Within 24 hours
removal of facility or equipment from
service
9.16.14 GCP Submission of outage needs for the 15th June each year
next three years to TSO
9.16.18 TSO Circulation of Initial Outage Plan for August 15th each year
the next year and Provisional
Outage Plan for a further two years
Ref Responsible Description of submission Deadline
section/ player
sub-
section
9.16.20 TSO Issue of the Committed Outage Plan December 1st each
for the next year year
9.16.22 GCP Outage request for each month 30 days prior to start
date of planned work
9.16.30 TSO Quarterly report on outages, 15 days after the
disputes etc. quarter
9.17.5 GCP Request for carrying out proposed 14 days before the
test proposed date of test
9.18.1 TSO Periodic test of generating unit to At least 12 months
assess performance interval
9.18.2 TSO Request for carrying out annual test 14 days prior notice to
of generating unit the proposed test date
9.23.4 TSO Monthly report on LITS operations Within 15 days of the
succeeding month
9.24.2 GCP Notification through report of a Within 24 hours of
forced outage, fault or Significant occurrence
Incident
9.24.2 (a) Generation Reporting of loss of output, tripping Within 15 minutes of
GCP and loss of governor control of a event occurring
generating unit
9.24.2 (b) Demand GCP Reporting of (i) Within 15 minutes of
(i) loss of major load and event occurring and
(ii) reconnection of major load (ii)15 minutes advance
notice
9.24.2 (c) International Tie line incident As determined in
Transmission Interconnection
GCP Agreement
9.24.6 TSO Notification of forced outage, fault or Within 24 hours after
Significant Incident to LITS occurrence of incident
equipment
9.24.15 (b) TSO Preliminary report on Significant Within 3 days of
Incident investigation occurrence of incident
9.24.15 (c) TSO Final report on Significant Incident Within 3 months of
investigation occurrence
9.24.19 TSO Joint investigation of Significant Within 10 days after
Incident report to LERC receipt of report
10.6.3 GCP Forecast hourly load profiles for One (1) week in
each day of the next two weeks advance
218
10.6.5 (a) TSO Hourly day-ahead dispatch schedule As determined by MOR
10.6.5 (b) TSO Days 2-7 ahead load forecasts As determined by MOR
10.6.5 (c) TSO Weekly demand forecast for 4 As determined by MOR
weeks ahead
10.6.5 (d) TSO Monthly demand forecast for 12 As determined by MOR
months ahead
10.9.1 Generation Dispatch Day generation data One day ahead of
GCP Scheduled day
Ref Responsible Description of submission Deadline
Section/ player
sub-
section
10.9.5 (a) Demand GCP Dispatch Day hourly demand One (1) day ahead of
forecast scheduled day
10.13.2 Generation Generation unit capability and At 10:00h each
GCP availability declaration data preceding day
10.13.4 Demand GCP Requirements for power, energy, At 10:00h each
voltage and reactive power preceding day
compensation, and system or
network constraints
10.15.1 TSO Issuing of Generation schedule for At 15:00h each day
the next day
12.7.4 TSO LITS Reliability & Performance
(i) Quarterly Report 1 month after quarter
(ii) Annual Report 2 months after end of
the year
12.7.12 TSO System overload report with relief 2 months after end of
plans the year
13.11.6 GCP/TSO Notification of routine testing of Main Seven (7) days in
or Check meter advance notice
14.6.1 GCP Records of meter commissioning to Seven (7) days upon
TSO request
14.11.1 TSO Reporting requirements: –
(i) Daily (i) Mid-day of following
day
(ii) Monthly (ii) One week after end
of the month
iii) Annual Report (iii) Two months after
end of the year.
14.11.3 TSO System performance report for Monday of every week
previous week
TS-A (Par TSO AFLS program determination for the November 1st of the
8) succeeding year and publication of preceding year
the Demand Management
Guidelines in the System
Operations Manual
219
Technical Schedule TS – V: Voltage Limits
1. LITS voltage magnitudes shall be kept within the following limits:
(a) ±5% of the nominal voltage at all times under Normal State;
(b) ±10% of the nominal voltage under Alert State for a period not exceeding 10 minutes;
(c) ±10% of the nominal voltage under Emergency State for a period not exceeding 30
minutes.
3. Phase displacement between voltages shall be within the limits stated in the System
Operations Manual of the TSO.
4. The maximum permissible voltage flicker limits shall be in accordance with IEC/TR3 61000-
3-7 standard (or IEEE Standard 519- 1992 as alternative).
5. The maximum permissible harmonic limits shall be in accordance with IEC/TR3 61000-3-7
standard (or IEEE Standard 519- 1992 as alternative).
220
Technical Schedule TS–X: Additional Post-Dispatch Information
1. The TSO shall provide the following minimum operational information in near real-time and as
historic data in relation to each generating unit at each generating station:
Item no. Data description Format Size Unit
1. Unit high limit Real 999,99 MW
2. Unit high low Real 999,99 MW
3. Unit AGC mode CER/BLO Character
3
4. Unit AGC status AUT/OFF/MAN Character
3
5. Unit set-point Real 99,99 MW
6 AGC pulse Real 9,9
7. Unit sent out Real 999,99 MW
8. Unit auxiliary Real 999,99 MW
9. Unit contract Integer 999 MW
10. Unit spinning Integer 999
11. 32-bit flag on AGC settings Integer 32 bits
2. The TSO shall provide the following minimum operational information in near real-time in
relation to the overall dispatch performance:
Item no. Data description Format Size Unit
1. ACE (Area Control Error) Real 999,99 MW
2. Average ACE previous hour Real 999,99 MW
3. HZ system frequency Real 999,99 MW
4. Frequency distribution current hour Real 999,99 MW
5. Frequency distribution previous hour Real 99,99 MW
6 System total generation Integer 99999 MW
7. Control area total actual interchange Integer 999,99 MW
8. Control area total scheduled Integer 99999 MW
interchange
9. System operating reserve Integer 99999 MW
10. System sent out Integer 99999 MW
11. System spinning reserve Integer 99999 MW
12. AGC regulating up Integer 99999 MW
13. AGC regulating down Integer 99999 MW
14. AGC regulating up assist Integer 99999 MW
15. AGC regulating down assist Integer 99999 MW
16. AGC regulating up emergency Integer 99999 MW
17. AGC regulating down emergency Integer 99999 MW
18. AGC mode Character TLBC
/CFC
19. AGC status Character ON/ OFF
20. Area control error output Real 999,99 MW
21. System transmission losses Real 999,99 MW
22. Cross Border tie-line A Integer 99999 MW
23. Cross Border tie-line B Integer 99999 MW
24. AGC performance indicators
221
PART H: APPENDICES
Part H, the Appendices, contains supplementary information or additional details of information
that provide further clarification of specific provisions in certain Sections of the LEGC.
222
APPENDIX A: Connection Application Information
3. Legal documentation:
Legal documentation including copy of the following:
(a) decision of establishment
(b) business registration
(c) investment license
(d) operational licenses
(e) EPA Permit
(f) any other legal licenses required
A.3 – Demand data/Information (Apply to an applicant for Demand GCP)
1. Power and energy requirements
(a) Active power (MW)
(b) Reactive power (MVAr)
(c) Energy per day/month/year (kWh)
223
(a) Measured demand data: The existing Demand GCP is required to
provide daily load curves of all days in the latest year with clear
specification of –
(i) Active and reactive power received from TNO network;
(ii) Active and reactive power self - produced (if existing).
(iii) Monthly energy consumption and production of the latest years.
(c) The document on which above forecasts are based (if existing)
6. Load characteristics
(a) Information to be provided by Demand GCP shall include:
(i) Characteristic of the load
(ii) Power factor
(iii) Voltage sensitivity MW/kV, MVAr/kV
(iv) Frequency sensitivity MW/Hz, MVAr/Hz
(v) Maximum and average phase unbalance %
(vi) Maximum harmonic content
(vii) Long-term and short-term flicker severity
(viii) Load fluctuation
(i) Change rate of load (kW/s and kVAr/s) both increasing and
decreasing.
(ii) The shortest repetitive time interval between load fluctuations
(in seconds);
(iii) The magnitude of the largest step changes in power demand
(kW, kVAr).
1. Plant description
(a) Name of power plant
(b) Location
(c) Type of plant (hydropower, thermal power, VRPP – Wind or Solar PV
etc.)
(d) Number of generating units and rated capacity
(e) Estimated energy generation (MWh/month or year)
(f) Proposed export capacity (MW) into the LITS
(g) Proposed commercial operation time
(h) Proposed voltage level of connection point (kV)
(d) For thermal power plant, provide a functional block diagram of the main
plant components, showing boilers, alternators, any heat or steam
supplies.
4. Technical specifications
(a) For each generating unit the GCP shall provide [in per unit]
(i) Parameters Symbol and value
(ii) Direct axis synchronous reactance X d
(iii) Direct axis transient reactance X’ d
(iv) Direct axis sub-transient reactance unsaturated X’’ d
(v) Quadrature axis synchronous reactance X q
(vi) Quadrature axis transient reactance unsaturated X’ q
(vii) Quadrature axis sub-transient reactance X’’ q
(viii) Negative sequence reactance X 2
(ix) Zero sequence reactance X o
(x) Stator resistance R a
(xi) Stator leakage reactance X L
(xii) Poiter reactance X p
(xiii) Generator time constants symbol and value
(xiv) Direct axis open circuit transient Tdo ’(s)
(xv) Direct axis open circuit sub-transient Tdo ’’(s)
(xvi) Quadrature axis open circuit transient Tqo ’(s)
228
(xvii) Quadrature axis open circuit sub-transient Tqo ’’(s)
(xviii) Direct axis short-circuit transient Td’(s)
(xix) Direct axis short-circuit sub-transient Td’’(s)
(xx) Quadrature axis short-circuit transient Tq’(s)
(xxi) Quadrature axis short-circuit sub-transient Tq’’(s)
(b) Turbine generator inertia constant for entire rotating mass (MW-
sec/MVA)*
5. Excitation system
The GCP shall provide data relating to excitation system and PSS in Laplace-
domain control block diagram in accordance with IEEE standard excitation
models (or as otherwise agreed with Transmission GCP) completely
specifying all the time constants and gains.
8. Black start
The GCP shall provide information about black start system, if available.
9. Environmental impact
The GCP shall provide all information relating with gas emission (for thermal
Power Plant) parameter values as follows:
232
APPENDIX B: Certification Test for Metering Equipment
B.1. Introduction
This Appendix B sets out those tests and checks that shall be performed by a manufacturer or a
Meter Test Station to the meters and metering equipment prior to certification of compliance with
the Metering Sub-code of the LEGC.
233
(v) Power frequency withstand test between sections.
(vi) Inter-turn over-voltage test for CT.
(vii)Limits of error test.
B.3. Meters
B.3.1 Type tests
3.1.1 In accordance with the standards mentioned in this Code, samples of all meters shall
satisfactorily fulfil the requirements of type tests.
3.1.2 The type tests required to be carried out are as listed in Table AP-B1 below:
Table AP-B1: Required Type Tests for Meters
Nr Tests Electro‐ Electronic
mechanical meters
meters
1. Test of insulation properties
Impulse voltage tests X X
AC voltage tests X X
2. Tests of accuracy requirements
Test of meter constant X X
Test of starting condition X X
Test of no‐load condition X X
Test of influence quantities X X
Repeatability of error test X X
3. Tests of electrical requirements
Test of power consumption X X
Test of influence of supply voltage X X
Test influence of short‐time over‐currents X X
Test of influence of self‐heating X X
Test of influence of heating X X
Test of immunity to earth fault X X
4. Test for electromagnetic compatibility (EMC)
Radio interference suppression Fast transient burst X
test Damped oscillatory waves immunity test X
Test of immunity to conducted disturbances X
induced by radio‐frequency fields X
Test of immunity to electrostatic discharges X
Surge immunity test X
5. Tests of the effect of the climatic environments
Dry heat test X X
Cold test X X
Damp heat, cyclic test X X
Solar radiation test X X
6. Mechanical Tests
Vibration test X X
Shock test X X
Spring hammer test X X
Tests of protection against penetration of dust and X X
water X X
Test of resistance to heat and fire
234
B.3.2 Routine tests
3.2.1 Upon supply, all meters are required to fulfill requirements of routine test comprising the
following tests:
(a) A.C High Voltage Test
(b) Test of Meter Constant
(c) Test of Starting Condition
(d) Test of No-Load Condition
(e) Test of Influence Quantities
B.3.3 Acceptance tests
3.3.1 The following tests shall be conducted for meter samples for the purpose of Acceptance
Test Certification:
(a) Test of Starting Condition
(b) Test of No-Load Condition
(c) Test of Power Consumption
(d) Voltage Variation Test
(e) Frequency Variation Test
(f) Test of Influence Quantities
(g) Repeatability of Error Test
(h) Power Frequency and Impulse Voltage Withstand Tests
3.3.2 Samples of meters shall be selected from the lot (batch) using the Single Plan Method
provided in Table AP-B2:
Table AP-B2: Single Plan Method sample selection
Batch Size Sample Size Criterion
Acceptance Rejection
1-50 All No No
51-150 13 0 1
151-500 50 1 2
501-1200 80 2 3
235
APPENDIX C: Metering Equipment Sealing Procedure
236
3.4 A sealing certificate for this purpose shall contain information listed under sub-section C.3.2.6.
237