Wcms Asist 127
Wcms Asist 127
Wcms Asist 127
Contents
Summary
G Volume Calculations
H Construction Details
J Maintenance Details
K Project Information
The design of the trickle tube and outlet pipe is covered in Annex
E. During the wettest month of the year (January) a daily average
of 1315m3 of water will enter the storage area. This is easily coped
with by the 0.15m deep pondage, and will be discharged by the
trickle tube whose capacity is 2600m³ day–1.
The present design incorporates a 50mm outlet pipe, but this can
be changed to a 75mm diameter pipe if the subsequent pumping,
storage and distribution arrangements require it. It is very
important that neither the trickle tube nor the outlet pipe should
be routed through the embankment; they must be sunk into their
own trenches under it. The casting of the staunching rings should
be closely supervised. On no account should any kind of valve be
attached to the trickle tube.
The borrow pit (see Annex F) has been designed in such a way
that many labourers can excavate it simultaneously. Although it is
expected that an excavation of 0.5m should suffice, the pit can
easily be made deeper if more material is required during
construction. The berm of 10m is that recommended by the
Rhodesian Handbook.
Storage
Purpose: domestic and stock
Reliability: 95%
Demand: 4300m³ yr–1
Residual: 500m³
Seepage: 50mm month–1
Evaporation: 1901mm yr–1
NES: 2501mm yr–1
Total Storage: 19000m3
Critical Period: 12 months
Max Depth of Water: 5.4m
Water Surface Area: 10700m²
Embankment
Type: homogeneous
Material: coarse sand / sandy
clay loam
Batters: 2½:1
Crest Width: 2m
Settlement Allowance: 0.075m
m–1
Total Length: 140m
Cut-off Trench Bottom Width:
2m
Cut-off Trench Batters: 2½:1
Cut-off Trench Depth: 1.5m
Height:
clearance: 0.5m
surcharge: 0.73m
wave action: 0.17m
freeboard (total of above):
1.4m
1 STORAGE DESIGN
Purpose of Storage
Domestic supply and stock water.
Reliability Required
95%
Water Demand
Type
Since, with losses, the total water stored will exceed 5000m3, this
will rate as a Major Storage Design.
Storage Requirements
The soil classification map for the area shows the soils to be a
mixture of 5G, 6G and 11 types. These comprise coarse-grained
sands, loamy sands, sandy clay loams, and sandy clays. Seepage
losses were estimated at 50mm month–1. Climatological data for
the area shows the annual evaporation to be 1901mm. The net
evapo-seepage loss is therefore calculated as:
2 CATCHMENT YIELD
Catchment Area
The boundaries of the catchment were delineated using stereo
photo-interpretation and are shown on the attached aerial
photograph (Handout LS5). Comparison with a 1:50000 Ordnance
Map of the area yielded a photo scale of 1:23,786. The area of the
catchment was then measured on the aerial photo with a
planimeter and found to be 302ha.
Catchment Yield
Using the Rhodesian Handbook tables, a catchment of 302ha with
a mean annual rainfall of 936mm should give a minimum annual
yield of 178000m³.
3 FLOOD RUNOFF
Catchment Coefficient
The maximum length of the catchment was measured as 2450m
with a drop of 100m from top to bottom. This represents an
approximate average gradient of 4%. The cover was interpreted
from the aerial photograph as mainly cultivated land with some
natural grassland. The soils have already been described. There
Rainfall Intensity
The climatological data given in the attached handout (LS3B) was
used to plot a graph of log intensity vs. log duration for a 50yr
return period (see Figure 3.1). The time of concentration is given
by:
Calculation of Runoff
The Rational Formula was used3. In the metric form this is:
Q = CIA / 360
1 FLOOD ESTIMATION
The 50yr flood, estimated by the Rational Method, was 34 cumecs.
2 OUTFALL CALCULATIONS
Gradient
The outfall water has to drop about 5.5m to the streambed. The
route to be taken by this water was mapped out on the contoured
site plan. It was difficult to achieve a gradient of less than 6%,
although the final drawings have managed to bring this nearer to
1981.
Cover
It is essential that a good stand of resilient grass should cover the
spillway and its banks. Couch grass was chosen, as recommended
by the Rhodesian Handbook. A stand 250 – 600mm high should
give a roughness factor ‘n’ of 0.05.
Discharge Velocity
The maximum velocity of flow down a grassed spillway should not
exceed 2.5m s–1 if erosion is to be avoided.
Dimensions
The width and depth of flow were calculated from Manning
formula:
u = 1 / n R2/3 S½
R2/3 = un / S½
LH = A, and L + 2H = P
Substituting for P:
L = 37.321 – 2H
3 INLET CALCULATIONS
The discharge over the spillway crest was assumed to obey a
broad-crested weir formula:
It was decided to adopt the same inlet and crest width as the
outfall width, so L = 36m. Thus:
H3/2 = 0.6291
Therefore H = 0.73m
4 TRAINING WALL
To maintain uniform flow down the spillway, it was necessary to
design a training wall. From the site plan the length of this wall
was found to be 116m. A crest width of 1m was chosen with
batters of 1½:1.
2 DIMENSIONS
Clearance
The standard minimum dimension for a dam of this size was
chosen, i.e. 0.5m.
Surcharge
This was calculated under Spillway: Inlet Calculations and found
to be 0.73m.
Wave Action
This was calculated from the Hawksley formula:
Pondage
A depth equal to the trickle tube diameter was chosen, i.e. 0.15m.
Storage
This had already been worked out during the hydrologic design.
The maximum depth of water was 5.4m.
Freeboard
This is the sum of clearance, surcharge, and wave action. In this
case these total 1.4m.
Total Height
Adding the above, the total height of the embankment is 6.95m.
Crest Width
This was calculated from the formula:
≅2m.
Batters
For the soil group SM, and for stored water depths between 3m
and 7m, the recommended batters for the upstream and
downstream slopes are 2½:1.
Settlement Allowance
The Rhodesian Handbook recommends a settlement allowance of
0.075m m–1
Cut-off Trench
A bottom width of 2m was chosen to allow easy passage for both a
tractor and an ox-team. Batters of 2½:1 were chosen. Owing to the
subsoil material not being the ideal type for an embankment core
it was thought advisable to take the cut-off trench to a depth of
1.5m.
1 TRICKLE TUBE
Diameter
The estimated runoff of the catchment in any one year was
estimated at 178000m³, of which 19000m³ was to be stored in the
dam. This leaves 159000m³, which is approximately equivalent to
0.005 cumecs. A 150mm diameter pipe, which is a common size
and easy to obtain, will cope with a flow of 0.03 cumecs, six times
the average catchment excess.
Inlet
For a 150mm diameter pipe the Rhodesian Handbook
recommends a drop inlet chamber of 300mm x 500mm by 750mm
deep. The top of the inlet chamber should be 0.15m below
maximum water level.
Position
The trickle tube should be laid in a trench perpendicular to the
centre line of the embankment 1m below high water level on the
opposite side to the spillway. The tube should be encased in
150mm concrete with 1m diameter concrete rings 4m from the
embankment centre, and with a 1.5m diameter collar at the cut-
off trench.
2 OUTLET PIPE
Diameter
A standard 50mm diameter pipe should be sufficient for a peak
flow of twice the June daily average demand (i.e. 0.00039 cumecs).
Inlet
Since the water is for direct animal consumption and indirect (viz.
a chlorination plant is envisaged) human consumption, the water
quality should be as high as possible. The inlet should therefore
incorporate a 1m x 1m x 1m box sand filter.
Position
The outlet pipe should be laid in a trench below the highest part of
the embankment. The pipe should be encased in 250mm diameter
concrete with 850mm diameter staunching rings (also of concrete)
every 3m, and a curtain concrete wall 1.25m wide set on the
centre of the cut-off trench floor.
Location
The downstream edge of the borrow pit should be 10m away from
the upstream toe of the embankment, within the storage basin.
Size
Trapezoidal with parallel sides of 35m and 75m separated by a
distance of 40m. A depth of 0.5m will provide approximately
1000m3 of material. Batters 2½:1.
1 EMBANKMENT
The trapezoidal formula was used to calculate the volume of
material in the embankment itself (not including the cut-off
trench). This formula is:
v = d / 6 (A1 + 4M + A2)
where V = volume in m³
d = perpendicular distance between the end faces in m
A1= area of one face in m2
M = area of midsection in m2
A2 = area of second face in m2
2 CUT-OFF TRENCH
The volume was calculated by multiplying the cross-sectional area
(8.625m2) by the total length (140m). The result is shown in
Figure 3.5.
3 SPILLWAY
Cross-sections were drawn at various points along the spillway
(see Figure 3.6) and the areas of these were used in the trapezoidal
formula or in a simplification of it:
V = d / 2 (A1 + A2)
5 BORROW PIT
The dimensions of the borrow pit were designed to make up the
shortfall in material required for the embankment. So far we have:
CUT m³ FILL m3
Spillway 9200 Embankment 9632
Cut-off trench 1208 Cut-off trench 1208
Training Wall 566
10408 11406
1 EQUIPMENT
Bulldozer (for the initial periods only), tractor with scraper blade,
water bowser, water pump, ramps, disc harrow or scarifier,
wheelbarrows, picks, shovels, hoes, puddling staves, levelling
equipment, marker pegs, axes, cement mixer, post augur,
hammers, wire tensioners, buckets.
2 MATERIALS REQUIRED
Sand, cement, graded aggregate (25mm), fencing posts, barbed
wire, staples, 150mm piping, 50mm piping, filter sand, 50mm gate
valve, fumigant, grass seed, fertiliser and/or kraal manure, diesel
fuel, water, large stones, bricks.
3 PERSONNEL REQUIRED
One foreman (with previous experience of earth dam building), 40
labourers, 1 bulldozer operator, 1 bricklayer/plasterer, 1 plumber,
1 surveyor and 1 staffman, 1 tractor driver, 2 herdsmen with their
cattle.
5 MARKING OUT
Establish a concrete beacon at the TBM (see Figure 3.2).
Mark out the embankment centre line with pegs and with two
strong poles some distance from either end to act as site line flags.
Remove all trees, stumps and roots (filling in the holes afterwards)
from the areas to be occupied by the embankment, training wall
and spillway, and borrow pit.
Chop down all trees to stump level from the rest of the basin area
up to the high water level mark.
Use the bulldozer to remove all the topsoil (to a depth of 250mm)
from the spillway area and training wall area and push it slightly
uphill of the spillway outer edge.
Use the bulldozer to remove all the topsoil from the borrow pit
area and push it to just beyond the southern edge of the pit. This
soil should not cover the route to be taken by the trickle tube.
Use the bulldozer to remove the topsoil (to a depth of 0.25m) from
the embankment area pushing it beyond the downstream toe of
the embankment.
Use the bulldozer tines to rip the cut-off trench and borrow pit
areas.
Excavate the cut-off trench and use the material to start building
the downstream toe of the embankment. At the same time, start
building the training wall using material excavated from the
spillway after having scarified the ground surface with a tractor
and disc harrow.
Excavate the trickle tube and outlet pipe trenches. Keep them as
narrow as possible so that the concrete may be cast straight into
the soil. The staunching rings should be cast square, again
straight into the earth, using a 4:2:1 mix. Fill up the trenches with
layers of subsoil, well puddled with 50mm staves.
Fill in the cut-off trench with 150mm layers of material taken from
the north side of the basin. Use the water if necessary to bring the
moisture content of the material to within ± 3% of the optimum for
achieving maximum dry density. Use cattle or oxteams driven
backwards and forwards to compact each layer.
When the cut-off trench has been filled, scarify the whole area to
be covered by the embankment.
Use the topsoil heaped south of the training wall to spread over
the downstream slope of the embankment and over the training
wall.
Use the borrow pit topsoil to cover the crest and top upstream face
of the embankment.
Use large stones (of not less than 25kg weight each) to stone pitch
the northern end of the embankment at the spillway crest. The
stones should be closely packed with the long axis of each stone
set at right angles to the embankment. The voids between the
stones should be filled with topsoil and planted with
rhizomoferous grass.
Inspect and check the work, and issue a maintenance form to the
headman.
DJM/ejm/4 10 78
Log duration 0.70 1.00 1.30 1.48 1.65 1.78 1.95 2.08
Log intensity 2.26 2.23 2.11 2.03 1.94 1.87 1.73 1.63
2.05
2.00
1.95
1.90
1.85
1.80
1.75
1.70
1.65
1.60
0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2
Log Duration
1 Introduction
2 Maintenance of fences
The establishment of a good grass cover over the dam wall and on
earth spillways must be achieved at all costs before the rains. This
can be done by spreading about an inch of topsoil and adding 2 to
3 bags of ammonium sulphate to the acre. Only good runner
grasses should be used, and the types recommended are as
follows:
4 Repair of erosion
5 Settlement
6 Seepage
Nearly all earth dams seep to some extent and unless it amounts
to serious leakage, or appears on the downstream face, this need
cause no alarm. There is no easy cure for a bad leak, as the
trouble lies in conditions under the wall of the dam. Seepage may,
however, be reduced over a long period by puddling the basin with
cattle as the level drops. Wood ash or cowdung distributed over
the suspect area or in the water may also help.
7 Drainage
(a) Make a hole down into the workings with an iron bar, and
push a pipe down this hole — then pour a proven fumigant down
the pipe. Alternatively, close up all visible holes with wads of
cotton wool soaked in carbon disulphide.
9 Conclusion
You should inspect your dam at least once a month during the dry
seasons and at least twice a week during the rains.
1 Introduction
2 Information Available
2.1 Location
The site is located about 7km NW of Mtoko at map reference
156,815 on sheet MTOKO 1732A3 in the Rhodesian 1:50,000
series. A section of this map with the site indicated is attached.
Aerial photography of the area (to unspecified scale) is available
(Run No. 176, photo nos. 773-6). A copy of photo no. 774 is
attached.
2.2 Climate
The attached sheet gives all the available data from the nearest
reliable climate station.
SJP
23.2.78
SOILS INFORMATION
Soil Type 5G
Mainly moderately shallow, greyish-brown, coarse-grained sands,
throughout the profile, to similar sandy loams over reddish brown
sandy clay loans; formed on granitic rocks.
Soil Type 6G
Moderately deep to deep, greyish-brown, coarse-grained sands
over pale loamy sands, to similar sandy loams over yellowish-red
sandy clay loams or, occasionally, sandy clays; clay fraction
essentially ferrallitic (no 2:1 lattice minerals), but reserves of
weatherable minerals are appreciable; base saturations range from
about 30 to 60%; E/C values lower than about 15me; formed on
granitic rocks.
Soil Type 11
Non-calcic hydromorphic group: mainly sands, which are leached
and strongly acid in reaction, with base saturation lower than
about 50%.
Period
July Aug. Sept. Oct. Nov. Dec. Jan. Feb. March April May June Year used
Rainfall (inches)
Average 0·07 0·10 0·29 1·33 4·37 7·72 8·44 7·05 5·46 1·38 0·49 0·14 36·84 1901 – 56
Greatest 1·01 1·44 4·93 7·52 11·21 23·31 19·53 14·12 16·83 5·12 7·04 1·30 71·53 1900 – 61
Year 1907 1936 1951 1922 1900 1917 1946 1907 1923 1961 1911 1941 1924 – 25 1900 – 61
Least ⎯ ⎯ ⎯ ⎯ 0·42 2·08 1·65 0·37 0·15 ⎯ ⎯ ⎯ 18·21 1900 – 61
Year Many Many Many Some 1912 1944 1922 1903 1933 Many Many Many 1923 – 24 1900 – 61
Evaporation
(inches) 4·84 5·95 6·82 7·79 6·84 6·89 6·95 6·43 6·66 5·95 5·18 4·54 74·84
Average per
month
Average per day 0·16 0·19 0·23 0·25 0·23 0·22 0·22 0·23 0·21 0·20 0·17 0·15
Maximum per day 0·21 0·25 0·30 0·32 0·33 0·33 0·33 0·33 0·29 0·26 0·22 0·20
Potential
Evapotranspiration 4·02 4·94 5·66 6·47 5·67 5·72 5·77 5·34 5·53 4·94 4·30 3·77
(inches)
Rainy season Mean date of starting 9th November Planting rains 20% probability by 20th October
Mean date of ending 16th March 40% probability by 4th November
Mean duration 128 days 60% probability by 10th November
Seasonal rainfall 33·32 in. 80% probability by 22nd
November
Effective rainfall 22·38 in.
Waterlogging rains (at least 5 in. of rain in a five-day period, followed by further raindays, number of spells in a 30-year period)
Length of spell in days 5 6 7 8 9 10 11 12 13 > Total rainfall in spell 5 in. 7 in. 9 in. 11 in. 13 in. 15 in. 17 in.
13 exceeding
Number of spells 4 7 4 2 3 ⎯ ⎯ 2 2 Number of spells 24 10 4 2 1 1 ⎯
⎯
Extracted from: Agricultural Climate of Southern Rhodesia, Rhodesian Meteorological Service, August 1962
98
97
96
Elevation (m)
95
94
93
92
0 5 10 15 20 25
Storage (m3 x 1000)
Photo 774. Top 3750’. Bottom 3550’. 49mm in 1:50,000. 103mm in 1:23,786