Project Engineering Slides (Recommended)
Project Engineering Slides (Recommended)
Introduction
`
Project definition
• A project is time-framed efforts which is within a program as an undertaking
with a scheduled beginning and end and which normally involves some
primary purpose.
• Rapid expenditure
projects come up in the form of investment for better return. Hence, the level of expenditure is very high compared to the plan or program of
permanent nature.
Breakeven
sanction
conceive completion
Project life cycle
• Demand
• Identification
• Feasibility studies and appraisal
• Negotiation and sanctions
• Design
• Implementation – construction
• Commission
• Operation
• Monitoring and evaluation
• Decommission
Project Environment
The project environment is made up of internal and external factors that
influence a project. When managing a project, the project manager must
consider more than just the project itself. Proactively managing a project
involves understanding the environment in which the project must function.
• Internal – Project Team (roles and responsibility) and project owner
• External – end users, customers, social groups, suppliers (manage –
communicate benefit, involve in planning, identify need and expectations and
try to meet them)
Project Management –
introduction of the subject
field
Planning for effective use of 3Ms (Manpower,
Chapter 2: Project Appraisal and Formulation
Concept of project appraisal
Project proposal (technical and financial)
Procedures for developing project proposal
Techniques of project formulation
Feasibility studies
Cost benefit analysis
Input analysis
Environmental analysis – IEE, EIA
2.1 Concept of Project Appraisal
Knowledge
• Technical
• Financial analysis
• Social analysis
Executive summary. Short and to the point, the executive summary is essentially the project’s elevator pitch. It states the
problem clearly, addresses how your proposed project intends to solve the problem, and discusses what a successful
project looks like.
Background or history. This section outlines both successful and unsuccessful previous projects, including how the latter
could have been handled better, with the goal of showing how the proposed project will be more successful based on the
lessons of the past.
Requirements. This section briefly summarizes what’s needed throughout the project life cycle in terms of resources,
tools, project schedule, etc.
Solution. The solution section explains how you intend to approach the project and bring it to completion. It covers the
project management steps, techniques, and skills needed to get things done more efficiently, as well as how to manage
problems.
Authorization. This section states explicitly who the project’s decision-makers are and the stakeholders authorized by the
client to make approval/sign-off decisions.
Appendix. Any information not included in the actual proposal should be in the appendix, such as materials and resources
that team members and stakeholders can use to learn more about the project.
If you’re not sure where to start, know that some of the best project management software applications offer project
proposal templates you can use for free from their tools library.
Project proposal (technical and financial)
Fixed capital normally called ‘fixed assets’ are those tangible and
material facilities which purchased once are used again and again. Land
and buildings, plants and machinery, and equipment’s are the familiar
examples of fixed assets/fixed capital.
Financial appraisal
• Fund source – sound capital structure
• Working capital requirement
• Cash flow to cover debt service liability
• Realistic cost estimate
• profit level
• Break even point
• Pay back period
• IRR, B/C Ratio
Environmental impact analysis
• Environmental impacts of the project
• Positive/negative and degree of impacts – identify them
• Project should meet regulatory environmental concerns
• Environmental impact mitigation measures – cost and social
acceptability
ENVIRONMENTAL APPRAISAL OF PROJECTS (EAP)
is defined as: Identification Prediction Interpretation,
Communication of information about the impact of
a project on man's health and well being. Study of
changes in socio-economic and bio-physical traits of
the environment , which may result from the project.
Basically it includes:
In case of a medium sized project the owner still holds the rein for the project management but prefers to carry out the
implementation with the help of a project manager. The situation is different for complex and large projects.
(ii) Experience suggests that the project organisation should have an overall in-charge as project manager with the quality of
strong leadership and effective communicating ability besides the required theoretical and technical skill.
(iii) The organisation structure should be interlaced so that the project work is carried out in a unified way.
(iv) The managerial personnel heading the different functions should be duly skilled in their respective functions to carry out the
project implementation and operation. The appraisal is to ensure that the key managerial personnel have been fixed before the
start of the work; it is also desirable to appraise the backgrounds of such personnel.
As a matter of practice, the financial institutions in the process of project appraisal also look out for the background of the key
managerial personnel in the relevant project management.
(v) Organisation takes care of the technical training required for the production process.
Outcome of feasibility studies
• Whether the project is technically viable or not
• Whether the project is environment friendly and viable in terms of
social acceptance or not.
• Whether the project is economically and or financially feasible
considering commercial aspects or not.
• Overall ranking of the project for its implementation priority if many
such projects are under consideration.
•
Cost benefit analysis
• A cost benefit analysis is a tool to evaluate cost versus benefits of a
project. All project expenses and tangible benefits are calculated in
order to derive at internal rate of return (IRR), Net Present Value
(NPV) and pay back period.
• The objective of CBA is to determine if the project is justifiable or
feasible in terms of benefits outweighing costs and to compare which
project more benefits than its cost.
• CBA need to consider - Project goals, alternatives, stakeholders,
outcome of cost and benefits, currency, discount rate, NPV, sensitivity
analysis,
Input analysis
• Consideration/identification of project inputs
• Input characteristics
• Its assesses the input requirements during the construction and
operation of the project •
• It defines the inputs required for each activity •
• Inputs include materials, equipment, machines, software, human
resources etc.
• Cost estimations and etc.
Input ………Processs……….output
Environmental analysis – IEE, EIA
18-Aug-21 5
Reasons for planning?
• To eliminate or reduce uncertainty
• To improve efficiency of the operations
• To obtain better understanding of the objectives
• To provide basis for monitoring and controlling the work – to monitor
performance in terms of output, time and money
• To keep the plan under constant review and make action when necessary to
correct the situation
• Wild enthusiasm
• Disillusionment
• Search for scapegoat
• Punishment of innocent
• Promotion of non-participants
• Chaos
Steps to Create a Construction Project Plan:
Project Plan Step 1 – Defining the Scope (?) Defining the scope involves gaining
agreement on the metric that the sponsor (the boss, executive or customer) will use
to measure the end result of the project. Install 2MW of hydropower Plant/
Construction 5 story Building.
Project Plan Step 2 – Breaking Down the Scope into Major Deliverables: If
Building Construction is a Project Specific Deliverables are Buying of Land, Map
approval from Municipality, Contractor Selection, Construction etc are deliverables.
Project Plan Step 3 – Breaking Down the Major Deliverables: Eg. For Buying of
Land – advertisement, visit the seller, visit the Land, Negotiation, Check all the
Documents, Transfer the ownership etc…
Project Plan Step 4 – Estimating: Each of the tasks/Activities will have an estimate
of the amount of work and the duration. This is finalize the Budget and Schedule
(Duration)
Project Plan Step 5 – Final Approval By the Sponsor: The last step in developing
the project plan is to secure the sponsor’s final approval on the project scope, major
Work Breakdown Structure
What Is Work Breakdown Structure in Project Management?
• Work breakdown structure (WBS) in project management is a method for
completing a complex, multi-step project. It's a way to divide and conquer
large projects to get things done faster and more efficiently.
• The goal of a WBS is to make a large project more manageable. Breaking it
down into smaller chunks means work can be done simultaneously by
different team members, leading to better team productivity and easier
project management.
• A Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical
decomposition of the work to be executed by the project team to
accomplish the project objectives and create the required deliverables.
A WBS is the cornerstone of effective project planning, execution,
controlling, monitoring, and reporting.
Use of WBS
• it facilitates the quick development of a schedule by allocating effort
estimates to specific sections of the WBS. it can be used to identify
potential scope risks if it has a branch that is not well defined. it
provides a visual of entire scope. it can be used to identify
communication points.
• Used for planning, monitoring, controlling
• Used for estimate and cash flow
• Calculation of resourses
• Etc.
Work breakdown structure
WBS
Factory construction project
• Survey
• Design
• Concept design
• Preliminary design
• Final design
• Architectural
• Design
• Drawings
• Plan
• Elevation
• Section
• details
• Prospective view
• model
• Structural
• Plumbing
• Electrical
• Foundation
• Fabrication
• Installation
• Handover
Project scheduling with bar chart, CPM and PERT
How to Estimate time for Activity?
Suppose Activity is EW in Excavation – 20 m^3 from Drawing
Civil Engineering Norms ?
The bar spans may overlap, as, for example, you may conduct Research before
completion of Planning and similarly you may start Design before completion
of the Research.
a. Predecessor
b. Successor
c. Both
d. None
Event (Node):
The beginning or end of the activity is known as event. It represents specific point
in time and does not consume time, manpower, material and other resources.
12 days
7 days
B- 3d
Logical Dummy
A. – Wait delivery of new machine
Grammatical Dummy B. – Install new machine
C. – Remove existing machine
D. – Dispose of existing machine
A. – Wait delivery of new machine
B. – Install new machine
C. – Remove existing machine
D. – Dispose of existing machine
Logical Dummy
B-4 3
5
E-6
There are three Paths from First Event 1 to Last Event 5
Path Description Duration Remarks
1 1-2-4-5 (A-C-F) 2+1+3 = 6
2 1-3-4-5 (B-D-F) 4+5+3 =12 Longest
3 1-3-5 (B-E) 4+6= 10
• Longest path in the network is called Critical Path – Path 2 (1-3-4-5 (B-D-F)
• Activities Lying on critical Path are Critical Activities B, D and F
• Time required to travel longest path is Project Duration - 12
FIND CRITICAL PATH, CRITICAL ACTIVITIES
AND PROJECT DURATION
There are three paths:
Paths DESCRIPTION DURATION REMARKS
1 10-30-40-50 3+1+3 = 7 mo Maximum
2 10-30-50 3+3 = 6 mo
3 10 -20-50 4+3 = 7 mo Maximum
A 2 - C
B 4 - D, E
C 1 A F
D 5 B F
E 6 B -
F 3 C and D -
Solution
A- 2 c- 1
A- 2 c- 1
D- 4
B- 4 D- 4
B- 4
E- 6
E- 6
A- 2 c- 1
A- 2 c- 1
D- 4
B- 4 D- 4
B- 4
E- 6
E- 6
WRONG RIGHT
c- 1 F- 3 F- 3
c- 2
D- 4 F- 3 D- 4
RIGHT
WRONG
E- 6 E- 6
F- 3 F- 3
WRONG RIGHT
1 A 2 - B, C
2 B 3 A D
3 C 1 A E, F
4 D 5 B G
5 E 4 C G
6 F 6 C -
7 G 2 D, E -
SN Activi Durati Predec Success
ty on essor or
1 A 2 - B, C
2 B 3 A D
3 C 1 A E, F
4 D 5 B G
5 E 4 C G
6 F 6 C -
Path 1 is 1 – 2 – 3-5-6 =2+3+5+2= 12 7 G 2 D, E -
Path 2 – 1-2-4-5-6 = 2+1+4+2 = 9
Path 3, 1-2-4-6 = 2+1+6 =9
Critical Path is 1 – 2 – 3- 5 – 6 longest with 12 duration
Critical Activities are A, B , D and G
Project Duration = 12
Draw CPM Network Find critical path Critical Activities and Project Duration
D-4 G-7
1
E-5
B-2 3 6
F-6 H-8
5
Event No. 1 2 3 4 5 6
Early 0 0+4 = 4 4+2 = 6 4+5= 6+3= 9 15 + 4=19
Event time 9 9+6=15 9+1 = 10
Late 4-4 =0 12-2=10 15- 3 =12 19-1=18 19- 4 =15 19
Event
Time 9-5=4 15-6=9
A
E-i L-i i j E-j L-j
19 19
9 9
9 9
2 B-2 3
19 19
Activity Dur E-i (EST) EFT = EST + D LST = LFT -D L-j (LFT) Total Float Remarks
A 4 0 4 0 4 0 Critical
B 2 4 6 10 12 12-6=6 Non-Cr
C 5 4 9 4 9 0 Critical
D 3 6 9 12 15 15-9=6 Non critical
E 6 9 15 9 15 0 Critical
F 1 9 10 18 19 19-10=9 Non critical
G 4 15 19 15 19 0 Critical
A
E-i E-j i j L-i L-j
EST (Earliest Start Time): It is the earliest possible time an activity or operation can
be started. It is equal to earliest occurrence time of tail event of that activity. E-i
EFT (Earliest Finish Time): It is the earliest possible time for completion of an
activity or operation without delaying the project completion time. It can be computed
by adding by activity duration by EST. EFT = EST + duration
LFT (Latest Finish Time): It is the latest time the activity or operation must be
completed so that scheduled completion date of the work can be achieved. It is equal to
latest occurrence time of head event. = L-j
LST (Latest Start Time): It is the latest possible time; an activity can be started
without delaying the project. LST = LFT-Duration
The free time available for the activity is called ‘Float’ or ‘Slack’. An activity has
four types of floats.
1. Total Float 2. Free Float and 3. Independent Float 4. Interfering Float
1. Total Float (TF): Late Start Time – Early Start Time or = Late Finish Time –
Early Finish Time
Total Float represents the maximum time by which the completion of the activity can
be delayed without affecting the project completion time. If an activity is delayed by
a time equal to its total float, that activity and all other subsequent activities in that
path become critical.
1. Free Float (FF): It is the delay that can be permitted in an activity so that
succeeding activities in the path are not affected. If the succeeding activities are to
remain un-affected by the delay in a particular activity the earliest start Time of
the head event of that activity shall not be exceeded.
2. Independent Float (IF): It is the spare time available for the activity, if preceding
activity is started as late as possible and succeeding activities are finished as early
as possible.
4 5 6 12
E-i L-i A E-j L-j
B-2 j
2 3 Predecessor
i
Successor
Activity TF= (L-j)-(E-i) – D FF = (E-j) – (E-i) -D Int F = TF-FF IndF- (E-j) - (L-i) – D Remark
s
B =12-4-2=6 =6-4-2=0 =6-0=6
Total Float (TF) = [ (L-j) – (E-i) – D ] or LFT – EFT or LST – EST
Free Float (FF) = (Ej) – (Ei) – D < TF = EST of Succ – EST of Act – Dur
FF = EST of Successor – EFT of the Activity (EFT = EST + dur)
Independent Float (IF) = (Ej) – (Li) – D = EST of Suc – LFT of Act – dur = < FF or FF –
tail event slack
Interfering float = TF – FF = (Lj- Ei –d)- (Ej-Ei-d) =(Lj) - (Ej) = LFT of Act – EST of
Suucessor
6 12 E-i L-i E-j L-j
15 15
4 4 A
i j
0 0
4 4 6 12
9 9
2 B-2 3
19 19
Activity TF =(L-j) –(E-i) -d FF = (E-j) –(E-i) -d intF = TF-FF IndF =(E-j) –(L-i) - d Remarks
A 4-0-4 = 0 4-0-4=0 0-0=0 4-0-4=0 Critical
B 12-4-2=6 6-4-2=0 6-0=6 6-4-2=0
C 9-4-5 =0 9-4-5=0 0-0=0 9-4-9=0 Critical
D 15-6-3 =6 15-6-3=6 6-6=0 15-12-3=0
E 15-9-6=0 15-9-6=0 0-0=0 15-9-6=0 Critical
F 19-9-1=9 19-9-1=9 9-9=0 19-9-1=9
G 19-15-4 19-15-4=0 0-0=0 19-15-4=0 Critical
E-i L-i E-j L-j
A-3 E-i = 4 A
1 2
L-i = 5 i j
E-i=4 L-i=5 E-j= 8 L-j= 12 4 5 8 12
E-j = 8
L-j = 12 3
2 B-2
Activity TF =(L-j) –(E-i) -d FF = (E-j) –(E-i) -d intF = TF-FF IndF =(E-j) –(L-i) - d Remarks
A 12-4-3 =5 8-4-3 =1 5-1=4 8-5-3=0
B 12-4-2=6 8-4-2=2 6-2=4 8-5-2=1
9 9
2 B-2 3
19 19
0 0
4 4
19 19
9 9
EFT= LST=
SN Activity Duration EST EST+D LFT-D LFT TF FF IndF IntF Remarks
1 A 4 0 4 0 4 0 0 0 0 Critical
2 B 2 4 6 10 12 6 0 0 6
3 C 5 4 9 4 9 0 0 0 0 Critical
4 D 3 6 9 12 15 15- 6 0 0
6-
3=6
5 E 6 9 15 9 15 0 0 0 0 Critical
Draw a network with the following details. Number the events using
Fulkerson’s rule. (DUMMY …)
D
5
3
B
A dummy
1 2
6
E
4
C
SN Activity Predecessor Successor
1 A - B, C
2 B A D
3 C A E, F
4 D B F
5 E C -
6 F C, D -
SN Activity Predecessor Successor
1 A - B, C
2 B A D
3 C A E, F
4 D B F
5 E C -
6 F C, D -
Draw a CPM network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show
critical path also.
Activity A B C D E F G H
Predecessor - - A B B C,D E E, F
Duration 2 6 3 5 7 1 4 5
b. Define Total Float , Free Float and Independent flaot. Draw a CPM
network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show critical path
also.
Activity A B C D E F G H
Predecessor - - A B B C,D E E, F
Duration 2 6 3 5 7 1 4 5
11 12
2 9 13 13 Forward Pass Calculation
C-3 F-1
0 0 A-2 2 H-5
4 6
1 D-5 18 18
dummy
B-6 7
3 5
E-7 G-4
6 6 13 13
Backward Pass Calculation
Activity A B C D E F G H
Predecessor - - A B B C,D E E, F
Duration 2 6 3 5 7 1 4 5
EST (Ei) 0 0 2 6 6 11 13 13
EFT = EST + dur 2 6 5 11 13 12 17 18
LFT = L-j 9 6 12 12 13 13 18 18
2 9
11 12 13 13
C-3 F-1
0 0 A-2 2 H-5
4 6
1 D-5 18 18
dummy
B-6 7
3 5
E-7 G-4
6 6 13 13 Backward Pass Calculation
Forward Pass Calculation
Activity A B C D E F G H
Duration 2 6 3 5 7 1 4 5
2 9
11 12 13 13
C-3 F-1
0 0 A-2 2 H-5
4 6
1 D-5 18 18
dummy
B-6 7
3 5
E-7 G-4
6 6 13 13 Backward Pass Calculation
Forward Pass Calculation
Draw a CPM network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show
critical path also.
Activity A B C D E F G H
Predecessor - - A A B B C, D E D, E, F
Duration 2 6 3 5 7 1 4 5
c G
d
H
E
F
b. Define Total Float , Free Float and Independent flaot. Draw a CPM
network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show critical path
also.
Activity A B C D E F G H
Predecessor - - A A B B C, D E D, E, F
Duration 2 6 3 5 7 1 4 5
C-3
A-2
2 5 G-4
D-5
Dummy Dummy -1 from 4 to 5
1 7
4 Dummy 2, 4 to 6
E-7 Dummy
B-6
3 6 H-5
F-1
Activity A B C D E F G H I J K L M
Predecessor - - A A,B B C D D E D,F H,I H,I G,
J, K
Duration 2 6 3 5 7 1 4 5 6 2 3 4 1
C
A
Dummy
D
Dummy
B
E
Activity A B C D E F G H I J K L M
Predecessor - - A A,B B C D D E D,F H,I H,I G, J,
K
Duration 2 6 3 5 7 1 4 5 6 2 3 4 1
F-1
C-3 4 8
2 J-2
A-2 Dum-3
dum1 D-5
1 G-4
5 7 10 M-1
B-6 dum2 K-3
H-5 11
3
E-7 6 9 L-4
I-6
b. Define Total Float , Free Float and Independent flaot. Draw a CPM
network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show critical path
also.
Activity A B C D E F G H I J K L M
Predecessor - - A A,B B C D D E D,F H,I H,I
Duration 2 6 3 5 7 1 4 5 6 2 3 4 1
C E
A
dummy dummy
B
D F
. Draw a CPM network and Find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show critical
path also.
Activity A B C D E F G H I J K L M
Successor D E,G,H,I,J F G,H L,M I,J K L,M L,M M - - -
Duration– 6 3 4 2 3 1 5 2 4 3 2 1 5
Days
Chapter 4: Project
Implementation and controlling
,
4. Project Implementation and controlling
• Introduction to monitoring, evaluation and controlling
• Project Control
• Project Control Cycle
• Elements of project control (Time, Cost, Quality)
• Project schedule control
• Project cost control: methods and procedure (EVA)
• Project Quality Control
• Introduction to PMIS
4.1 Introduction to monitoring, evaluation and
controlling
M&C, M&E
Monitoring and control processes continually track, review, adjust and
report on the project's performance. It's important to find out how
a project's performing and whether it's on time. This ensures
the project remains on track, on budget and on time
Monitoring is the collection and analysis of information about
a project or programme, undertaken while the project/programme is
ongoing. Evaluation is the periodic, retrospective assessment of an
organisation, project or programme that might be conducted internally
or by external independent evaluators.
Monitoring and controlling
• Monitoring and controlling is the management function of comparing
the actual achievements with the planned ones at every stage and
taking necessary action, if required, to ensure the attainment of the
planned goal.
Project Monitoring
• Regular observation and recording of project activities. Gathering
information on project how it is moving on.
• To check how project activities are progressing
• Giving feed back for making decisions for improving project
performances.
Project evaluation
• Project evaluation is a systematic and objective assessment of an
ongoing or completed project. The aim is to determine the relevance
and level of achievement of project objectives, development
effectiveness, efficiency, impact and sustainability. Evaluation is
periodic: mid term, initial evaluation, yearly evaluation, ex-post
evaluation
Types
• Internal
• External
4.2 Project control
System
Control Sensor
Device
Feedback
Types of control system
• Closed control system – like thermostat – automatic and does not depend on
outer environment
• Open control system – like country’s economy – external environment would be
considered for decision
• Open control loops is on with random disturbances. For example, human control
element etc.
Evaluation
Decision making
Project Control
4.3 Project control cycle
7 step control cycle
1. Project
Implementation
2. Establish
datum
7. Take corrective
actions if deviation is 3. Collect data during
not acceptable implementation
Evaluating
Correcting Determining cause of and
Taking control action to correct
possible deviations from
an unfavorable trend or to take
planned performance
advantage of an unusually
favorable trend.
1 - Planning the Project Budget. You would need to ideally make a budget at the beginning
of the planning session with regard to the project at hand.
2 - Keeping a Track of Costs.
3 - Effective Time Management.
4 - Project Change Control.
5 - Use of Earned Value.
Earned Value Analysis (EVA)
• EVA compares the value of work done with the value of work that should
have been done.
• Many of the project control systems assume a direct relationship between
lapsed time, work performed and incurred costs. EVA system analyses each
of these components independently comparing actual data to base line
plan set at the beginning of the project.
• EVA is often presented in the form of progress, productivity, or S- curve
diagrams.
• Actual and estimated costs are made available to determine the progress
factors at any stage of the project. Progress and cost factors are used to
monitor variance and trends for individual activities.
Earn value analysis
•.
Terms used in EVA
• Budgeted cost of work scheduled (BCWS) - is the value of work that should have been done at a
given point of time.
• Budgeted cost of work performed (BCWP) – is the value of the work done at a point of time. This
takes the work that has been done and the budget for each task, indicating what potion of the
budget ought to have used to achieve it.
• Actual cost of work performed (ACWP) – is the actual cost of the work done.
• Schedule variance (SV) – is the value of the work done minus the value to the work that should
have done (BCWP-BCWS). A negative number implies that work is behind schedule.
• Cost Variance (CV) – is the budgeted cost of the work done to date minus the actual cost of the
work done to date (BCWP-ACWP). A negative number implies a current budget overrun.
• Schedule performance index (SPI) – is (BCWP/BCWS) x 100. Values under 100 indicate that the
project is behind schedule.
• Cost performance index (CPI) – is (BCWP/ACWP) x 100. Values under 100 indicate that the project
is over budget.
EVA
BCWS, BCWP, ACWP
• 10000 m3 of concrete was planned to be completed in six month
@10,000/m3 = 1,000,000,00 - -------- BCWS
• 8000 m3 of concrete could be casted in six month @ 10,000/m3 that
equals to 800,000,00---------------------BCWP
• 8000m3 of concrete could be casted in six month at actual cost
@15,000/m3 that equals 1,200,000,00 ----ACWP
EVA
.
EVA
EVA
Comparison of project as per CPI and SPI
• Project A
• CPI = 70%
• SPI = 95%
• Project B
• CPI = 96%
• SPI = 93%
• Project C
• CPI= 102%
• SPI = 101%
4.7 Quality Control
Quality definitions
• Degree of goodness – oxford dictionary
• Conformance to requirements.
• Zero defects
• Doing things right first time
• Quality is the totality of characteristics of an entity that bear on its
ability to satisfy stated and implied needs.
Facts and Misconceptions
• Quality is not grade.
• Quality costs more, but lack of quality costs even more.
• Quality is means of achieving project success. It is not the goal in
itself.
• Process quality is more than product quality.
• Quality standards does not demand the best quality, they establish
the minimum requirements to be achieved.
Quality Management
• Quality Control
• Quality Assurance
• Total Quality Management
Quality Control
QC concerns the operational means to fulfill the quality requirements.
• Detection of non-conformity
• Verification of conformity
Stages of QC
• Input - Incoming goods, services and information
• In-process
• Output - End product
Quality Assurance
• QA aims at providing confidence in fulfilling the requirements both within
the organization and externally to customers and authorities.
• A systematic way of ensuring those organized activities happen in a way
that they are planned.
• QA is concerned with anticipating problems and with creating the attitudes
and controls that prevent problems arising. It is a logical extension of good
management practice.
• QA firstly, it aims to impart confidence to the client assuring that his needs
will be consistently met (external quality assurance). Secondly, it aims to
achieve quality through systematic and planned actions avoiding ‘fire-
fighting or crisis management’ (internal quality assurance).
Quality management and TQM
• QM includes QA and QC as well as other concepts of quality
planning, quality policy and quality improvement.
• TQM develops these concepts as a long-term global management
strategy and the participation of all members of the organization for
the benefits of the organization itself, its members, its customers and
society as a whole.
4.8 Project Management Information System
• Project
• Management – marketing, accounting, finance, production and R and D are
coordinated by management hierarchy. Top, middle and supervisory
management level. Top managers need information highly summarized
supported primarily by decision support system for strategic planning. Middle
managers need summarized information with detail for tactical planning and
control. Supervisory mangers should be supported by transactional processing
information system for operational control.
• Information - data that have been shaped or formed by humans into a
meaningful and useful form
• System - is a group of elements either human or non-human that is organized and
arranged in such a way that the elements can act as a whole towards achieving
some common goal, objective or end. System exists on continuous basis.
Communication - PMIS
• One of the major contributors of project success is good communication system
and set up of information system for effective communication. PMIS is employed
for effective communication. Software can be developed and communication
logistic can be added for better information system.
• An idea, no matter how great, is useless until it is transmitted and understood by
others.
• Communication is transference (imparting) and understanding of meaning.
• Barrier of communication
• Perception
• Filtration
• Environmental disturbance
• language
Knowledge - PMIS
Difference among Knowledge, information and data
• Data – raw facts that can be shaped and formed to create information
• Information - data that have been shaped or formed by humans into a
meaningful and useful form
• Knowledge – the stock of conceptual tools and categories used by human
to create, collect, store and share information
• Information system – it can be defined as a set of interrelated components
working together to collect, retrieve, process, store and disseminate
information for the purpose of facilitating planning , control, co-ordination,
and decision making in business and other organizations
•
Three basic activities of IS
• Input – collection of raw data resources from within a business or
from its external environment
• Processing – the conversion of raw input into more appropriate and
useful form
• Output – the transfer of processed information to the people or
business activities that will use it.
• Feedback – output that is returned to appropriate members of the
organization to help them refine or correct the input phase.
•
Activities of IS
Environment
Organization
Feedback
• Initial and urgent responses are also identified Secondary risk are also
to be identified that may arise in mitigating on category of risk.
Risk analysis matrix
Probalility of occurance Impacts Prioritization
1People's obstruction Y y 3
2Material scarcity y y 5
3Earthquake y y 6
4Funding arrangment y y 1
5cashflow y y 4
6labor scarcity y y 2
8
.
b) Quantitative analysis
Quantitative analysis
• Often involves sophisticated techniques requiring level of efforts ranging
from modest to extensively thorough, usually requiring computer use.
• Quantitative analysis includes measurement of uncertainty in cost and time
estimates and probabilistic combination of individual uncertainties
• Avoid or remove
• Reduce
• Transfer
• Accept
Risk management – risk response
Management of risk can be done by adopting some of the following
ways
• Identify preventive measures to avoid a risk or to reduce its effect
• Establish contingency plans to deal with risks if they should occur.
• Initiating further investigations to reduce uncertainty through better
information
• Consider risk transfer to risk insurers
• Consider risk allocation in contracts
• Set contingencies in cost estimates, float in programs and tolerances
in performance specifications
Risk monitoring and controlling
• Controlling - intervention
.
Chapter 6: Introduction to
project financing
,
Introduction to project financing
• Project finance
• Capital structure planning
• Capital budgeting decision
Project Finance
• Project finance is the long-term financing of infrastructure and industrial
projects based upon the projected cash flows of the project rather than the
balance sheets of its sponsors. Usually, a project financing structure
involves a number of equity investors, known as 'sponsors', and a
'syndicate' of banks or other lending institutions that provide loans to the
operation. They are most commonly non-recourse loans, which
are secured by the project assets and paid entirely from project cash flow,
rather than from the general assets or creditworthiness of the project
sponsors, a decision in part supported by financial modeling. The financing
is typically secured by all of the project assets, including the revenue-
producing contracts. Project lenders are given a lien on all of these assets
and are able to assume control of a project if the project company has
difficulties complying with the loan terms.
Project finance
• Generally, a special purpose entity is created for each project, thereby
shielding other assets owned by a project sponsor from the
detrimental effects of a project failure. As a special purpose entity,
the project company has no assets other than the project. Capital
contribution commitments by the owners of the project company are
sometimes necessary to ensure that the project is financially sound or
to assure the lenders of the sponsors' commitment. Project finance is
often more complicated than alternative financing methods.
Traditionally, project financing has been most commonly used in the
extractive (mining), transportation,[2] telecommunications, and power
industries, as well as for sports and entertainment venues.
Project finance
• Risk identification and allocation is a key component of project finance. A
project may be subject to a number of technical, environmental, economic
and political risks, particularly in developing countries and emerging
markets. Financial institutions and project sponsors may conclude that the
risks inherent in project development and operation are unacceptable
(unfinanceable). "Several long-term contracts such as construction, supply,
off-take and concession agreements, along with a variety of joint-
ownership structures are used to align incentives and deter opportunistic
behavior by any party involved in the project. The patterns of
implementation are sometimes referred to as "project delivery methods."
The financing of these projects must be distributed among multiple parties,
so as to distribute the risk associated with the project while simultaneously
ensuring profits for each party involved. In designing such risk-allocation
mechanisms, it is more difficult to address the risks of developing
countries' infrastructure markets as their markets involve higher risks.
Project finance
Project Finance
,
Capital structure planning
No universally accepted definition of the term “project financing” --different people uses it in different
senses. Project financing refers to a financing in which lenders to a project look primarily to the cash
flow(revenues) and assets of that project as the source of payment of their loans. In other words, project
finance is the long-term financing of infrastructure and industrial projects based upon the projected cash
flows of the project rather than the balance sheets of the project sponsors. Usually, a project financing
structure involves a number of equity investors, known as sponsors, as well as syndicate of banks that
provide loans to the operation. The loans are most commonly non-recourse loans which are secured by
the project assets and paid entirely from project cash flow rather than from the general assets or
creditworthiness of the project sponsors a decision in part supported by financial modelling.
In conventional financing, cash flow from different assets and business are co-mingled. A
creditor makes an assessment of repayment of his loan by looking all the cash flows and
resources of the borrower. In project financing, cash flow from the project related assets alone
are considered for assessing the repaying capacity. Even if one has already established many
projects, for financing a new project promoted by him, the cash flows from the proposed new
project are alone taken into account for carrying out the viability study.
In conventional financing end use of the borrowed funds is not strictly monitored by the lenders.
In project financing, the creditors ensure proper utilization of funds and creation of assets as
envisaged in the project proposal. Funds are also released in stages as and when assets are
credited.
In conventional financing, the creditors are not interested in monitoring the performance of the
enterprise and they are interested only in their money getting repaid in one way or the other.
Capital budgeting decision is the investment decisions of a firm. It may be defined as the firms’ decision
to invest its current funds most efficiently in long term activities in anticipation of an expected flow of
future benefit over a series of years. The long-term activities are those activities which affects firm’s
operation beyond the one-year period.
Investment are of two types – investment in fixed assets and investment in current assets. Investments
in the fixed assets, which have long terms implications for the firms in terms of expenditure and benefits
is evaluated as capital budgeting decision. The capital budgeting excludes investment required for
current assets.
Thus, generally, investment decision (or capital budgeting decisions) of a firm includes following types
of investment:
All the above types of investment decisions involve comparison between different alternatives or
investment proposals. Each of these investment proposals should be evaluated on the basis of a criterion
that is compatible with the objective of maximizing the market value of the firm. Any such criterion will
involve the use of the concept of the minimum rate of return required by the investor. The market value
of the firm will increase if the investment project yields a rate higher than the minimum expected by the
investor.
The exchange of current funds for future benefit (i.e. funds are invested only for future benefits)
Funds are invested in long terms activities
The future benefits will occur to the firms over a series of years (i.e. funds are invested only if
the future benefits occur over a series of years)
Since capital budgeting decision are among the most crucial and critical business decisions, special care
should be taken in their treatment. The followings are the reasons for placing greater emphasis on the
capital budgeting decisions,
1. They have long term implications for the firm, and influence its risks complexion.
First, the effect of capital budgeting decisions will long term implications for the firm. Firms
decision to invest in long term assets has a decisive influence on the rate and direction of its growth.
A wrong decision can provide disasters for the long-term survival of the firm. For example,
unwanted expansion of assets will result in unnecessary heavy operating costs.
Secondly, the capital budgeting decisions involve large amount of funds for long period. Such
commitment may also change the risk complexions of the firm. If investment increase and the
earning are fluctuating the firm will become riskier.
Thirdly, in most of the cases capital budgeting decisions are irreversible. The reason for
irreversibility of the capital budgeting decision is that it is very difficult to find a market for such
capital goods. The only alternative available is to scrap the asset, and incur heavy loss.
Project generation
Project evaluation
Project selection
Project execution
These four steps are necessary, but more may be added to make the process more effective.
As the capital budgeting decision involve commitment of large amount of funds for longer period, often
irreversible, such decisions need to be made by the highest level of management. This means substantial
part of the process should be confined to the top management, and when some of its parts are delegated,
a system of effective control by the top management must be evolved.
Project generation
Any project needs a written material- proposal – to initiate dialogue on funding. So, project generation
is development of proposal for investment decision. The investment proposal of any type can originate
at any level – from top management level to the level of worker. The proposal may focus in adding new
equipment for increasing the rate of production, or it may focus to reduce the cost of production. There
may be several kinds of proposal. Such proposal may originate systematically or haphazardly. In view
of the fact that enough investment proposals should be generated to employ the firms fund fully and
efficiently, a systematic procedure for generating proposals most be involved. The healthy firm is one
in which there is a continuous flow of profitable investment proposals.
Project evaluation
Project evaluation is done by expert groups. It involves two steps (a) estimation of benefits and costs,
the benefits and costs must be measure in terms of cash flow, and (b) selection of appropriate criterion
to judge the viability of the project
While evaluating a project the risk associated with it should also be properly handled, and should be
taken into account in the decision process. All care must be taken in selecting criterion to judge the
projects viability. As far as possible, the criterion should be consistent with the firm’s objective of
maximizing its market value. To achieve this purpose, time value of money must be recognized.
Project selection
No standard administrative procedure can be laid down for selecting the project and approving the
investment proposal. The screening and selection procedure may vary from firm to firm. Since the
capital budgeting decisions are of considerable significance for several reasons, the final approval of the
project may generally rest on top management. However, projects are screened at multiple levels.
Sometimes the top management may delegate authority to approve certain type of investment proposals.
Project execution
After the final selection of the investment proposal the funds are appropriated for capital expenditure.
The formal plan for appropriation of funds is called capital budget. Such plans ate prepared or approved
by the project execution committee or the top management.
The project execution committee or the top management must ensure that funds are spent in accordance
with the appropriation made in the capital budget. Funds for the purpose of project execution must be
spent only after seeking formal permission from the controller. For effective control, monthly budget
reports is prepared to show clearly the amount appropriated, amount spent, and amount not spend.
As the capital budgeting decision is of utmost importance, a sound appraisal method should be adopted
to measure the economic worth of each investment project. For this a set of evaluation criteria should
be used having following characterizes.
There are a number of investment criteria. The most important criteria that are in use are grouped in to
following two categories, which are further sub categorized as below.
A. Traditional criteria.
a. Payback period
b. IRR
Different criteria may use by different firms for the investment judgement. The selection of particularly
criteria may depends on various circumstances. Large company may use more than one technique to
appraise each of its investment projects. While a small firm may use only a single technique which
involves minimum fund time. However, to avoid confusion, same method(s) should be used uniformly
for all projects.
The payback period is one of the most popular and widely recognized traditional methods of evaluating
investment proposals. It is defined as the number of years required to recover the original cash outlay
invested in a project if the project generates constant annual cash inflows, the payback period can be
computed dividing cash outlay by the annual cash inflow. That is:
i.e. C/A
if the annual cash flow is unequal, the total payback period can be found out by adding up the cash
inflow until the total is equal to the initial cash outlay
1. It fails to take account of the cash inflow earned after the payback period
2. It does not consider the entire cash inflow yielded by the project
3. Fails to consider the pattern of cash inflow in terms of magnitude and time
4. Administrative difficulties may be faced in determining the maximum acceptable payback
period
5. Payback period method is not consistent with the objective of maximizing the market value of
the firms’ share
Acceptance value
The payback period can be used as an accept or reject criterion as well as a method of ranking projects.
If the payback period calculated for a project is less than the maximum payback period set up by the
management, it would be accepted; if not, it would be rejected. As a ranking method, it gives highest
ranking to the project which has shortest payback period and lowest ranking to the project with highest
payback period. Thus, if the firm has to choose among two mutually exclusive projects, project with
shorter payback period will be selected.
Example 6.1
A project requires an outlay of Rs 50,000 and yields an annual cash flow of Rs 12,500 for 7 years.
Calculate the payback period.
Solution
Example 6.2
solution
Example 6.3
Calculate the payback period of the following projects each requires a cash outlay of Rs 10,000. Suggest
which ones are acceptable if the standard payback period is 5 years
Cash inflows
Year Project X Project Y Project Z
1 Rs 2500 Rs 4000 Rs 1000
2 Rs 2500 Rs 3000 Rs 2000
3 Rs 2500 Rs 2000 Rs 3000
4 Rs 2500 Rs 1000 Rs 4000
5 Rs 2500 0 0
Payback period:
The accounting rate of return is obtained by dividing the average income after taxes by the average
investment
𝐚𝐯𝐞𝐫𝐚𝐠𝐞 𝐢𝐧𝐜𝐨𝐦𝐞
𝐀𝐑𝐑 =
𝐚𝐯𝐞𝐫𝐚𝐠𝐞 𝐢𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭
Advantages of ARR
1. It ignores the time value of money. Profit occurring in different periods are valued equally
2. It uses accounting profit, not cash flows in appraising the project
Acceptance rule
Accept the project proposal, if ARR is more than the minimum rate established by the
management (i.e. if ARR > minimum rate)
Reject the proposal, if ARR is less than the minimum rate established by the management (i.e.
ARR < minimum rate)
Example 6.4
A project costs Rs 50,000 and has a scrap value of Rs 10,000. Its stream of income before
depreciation and taxes during first year through five years is Rs 10,000 Rs 12,000, Rs 14,000 Rs
16,000 and Rs 20,000. Assume 50% tax rate depreciation on straight line basis. Calculate ARR of
the project.
Solution
The net present value method is the classic economic method of evaluating the investment proposal.
It is one of the discounted cash flow techniques. It recognizes the time value of the money.
In this method, first the present value of the cash inflow and the present value of cash out flow are
computed separately. NPV is the difference between these two present values.
1𝐶 2 𝐶 𝐶
3 𝐶
4 𝑛𝐶
𝑃𝑉 = [((1+𝐾)1 ) + ((1+𝐾)2 ) + ((1+𝐾)3 ) + ((1+𝐾)4 ) + ⋯ + ((1+𝐾)𝑛 )]
Where:
Advantages
Disadvantages
Acceptance
The internal rate of return (IRR) is another classic economic method of evaluating the investment
proposal. It is one of the discounted cash flow techniques. It recognizes the time value of the money.
The internal rate of return can be defined as the that rate which equates the present value of cash inflow
with the present value of cash outflow of an investment. In other words, it is that rate at which the Net
Present Value (NPV) is zero.
IRR needs to be computed following the trial and error method. In this method, first a discount rate is
assumed and the present value of both cash inflow and cash outflow are computed separately. The
differences between these two present values are noted. Accordingly, the discounted rate is adjusted in
such a way that the present value of both the cash inflow and cash outflow becomes same. This discount
rate is IRR.
So, the equation to be used here is same as that of the Net Present Value (NPV) method.
Disadvantages
Acceptance
Accept, if IRR is more than normal bank rate or investors' rate (IRR >= MARR)
Reject, if IRR is less than normal bank rate or investors’ rate. (IRR <=MARR)
Profitability index (or B/C ratio) is the ratio of the present value of the future inflow at the required rate
of return to the present value of cash outflow.
Profitability index (or B/C ratio) = (PV of the future cash inflow)/ (PV of investment)
It’s advantages and disadvantages are similar to NPV and IRR methods.
Acceptance
Example 4.5
Solution
Payback period
𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 10000
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐴 = = = 2.5 𝑦𝑒𝑎𝑟𝑠
𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 4000
𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 25000
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐵 = = = 2.5 𝑦𝑒𝑎𝑟𝑠
𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 10000
𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 30000
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐶 = = = 5 𝑦𝑒𝑎𝑟𝑠
𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 6000
𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 35000
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐷 = = = 2.91 𝑦𝑒𝑎𝑟𝑠
𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 12000
(1+𝑖)𝑁 −1 (1+0.1)12 −1
𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑏𝑒𝑛𝑒𝑓𝑖𝑡 𝑜𝑓 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐴 = 𝐴 ∗ 𝑖(1+𝑖)𝑁
= 4000 ∗ 0.1(1+0.1)12 = 𝑅𝑠 27254.76
(1+𝑖)𝑁 −1 (1+0.1)4 −1
𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑏𝑒𝑛𝑒𝑓𝑖𝑡 𝑜𝑓 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐵 = 𝐴 ∗ = 10000 ∗ = 𝑅𝑠 31698.65
𝑖(1+𝑖)𝑁 0.1(1+0.1)4
(1 + 𝑖)𝑁 − 1 (1 + 0.1)20 − 1
𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑏𝑒𝑛𝑒𝑓𝑖𝑡 𝑜𝑓 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐶 = 𝐴 ∗ = 6000 ∗
𝑖(1 + 𝑖)𝑁 0.1(1 + 0.1)20
= 𝑅𝑠 51081.38
(1+𝑖)𝑁 −1 (1+0.1)16 −1
𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑏𝑒𝑛𝑒𝑓𝑖𝑡 𝑜𝑓 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝐷 = 𝐴 ∗ 𝑖(1+𝑖)𝑁
= 4000 ∗ 0.1(1+0.1)16 = 𝑅𝑠 93884.50
(1+𝑖)12 −1
𝑃𝑊𝑖𝑛𝑓𝑙𝑜𝑤 − 𝑃𝑊𝑜𝑢𝑡𝑓𝑙𝑜𝑤 = 0 OR − 10000 = 0; 𝑖 (𝐼𝑅𝑅) = 39.24%
𝑖(1+𝑖)12
Project B
(1 + 𝑖)4 − 1
𝑃𝑊𝑖𝑛𝑓𝑙𝑜𝑤 − 𝑃𝑊𝑜𝑢𝑡𝑓𝑙𝑜𝑤 = 0; − 25000 = 0; 𝑖 (𝐼𝑅𝑅) = 21.86%
𝑖(1 + 𝑖)4
Project C
(1 + 𝑖)20 − 1
𝑃𝑊𝑖𝑛𝑓𝑙𝑜𝑤 − 𝑃𝑊𝑜𝑢𝑡𝑓𝑙𝑜𝑤 = 0; − 30000 = 0 𝑖 (𝐼𝑅𝑅) = 19.24%
𝑖(1 + 𝑖)20
Project D
(1+𝑖)16 −1
𝑃𝑊𝑖𝑛𝑓𝑙𝑜𝑤 − 𝑃𝑊𝑜𝑢𝑡𝑓𝑙𝑜𝑤 = 0; 𝑖(1+𝑖)16
− 35000 = 0; 𝑖 (𝐼𝑅𝑅) = 33.96%
Project A
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑐𝑜𝑚𝑒
𝐴𝑅𝑅 =
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
10000 + 0
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 = = 5000
2
𝟒𝟎𝟎𝟎
𝑨𝑹𝑹 = 𝟓𝟎𝟎𝟎 =0.8 (80%)
Project B
𝑖𝑛𝑐𝑜𝑚𝑒
𝐴𝑅𝑅 = 𝑎𝑣𝑒𝑟𝑎𝑔𝑒
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
25000 + 0
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 = = 12500
2
𝟏𝟎𝟎𝟎𝟎
𝑨𝑹𝑹 (𝑩) = =0.8 (80%)
𝟏𝟐𝟓𝟎𝟎
Project C
𝑖𝑛𝑐𝑜𝑚𝑒
𝐴𝑅𝑅 = 𝑎𝑣𝑒𝑟𝑎𝑔𝑒
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
30000 + 0
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 = = 15000
2
Project D
𝑖𝑛𝑐𝑜𝑚𝑒
𝐴𝑅𝑅 = 𝑎𝑣𝑒𝑟𝑎𝑔𝑒
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
35000 + 0
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 = = 17500
2
12000
𝐴𝑅𝑅 (𝐷) = 17500 =0.68 (68%)
Ranking
Project PB NPV IRR B/C ARR
A 1 3 1 1 1
B 1 4 3 4 1
C 3 2 4 3 3
D 2 1 2 2 2
1. Capital: Capital is a term describing wealth, which may be utilized to economic advantages.
Cash, land, equipment, raw material, finished products, human etc are the form of such capital.
2. Equity capital: Equity capital (common share) is supplied and used by its owner in the
expectations that a profit will be earned. There is no assurance that a profit will, in fact, be
gained or that the invested capital will be recovered. Likewise, there are no limitations placed
on the use of funds except those imposed by the owner themselves.
3. Debt capital: Debt capital is the borrowed Capital. When borrowed funds are used, fixed rate
of interest must be paid to the suppliers of the capital, and the debt must be repaid at a specified
time. The borrower of the debt does not share the profits resulting from the use of the capital.
4. Bond: A bond is essentially a long-term note given to lender by the borrower, stipulating the
terms of re- payment and other conditions. Usually, bonds are issues in unit of Rs 100 each.
With a defined rate of interest. So, basically, this is long term debt.
5. Debentures: A debenture is a bond issued without any collateral. It is also known as unsecured
bond. Thus, debenture holders are the general creditor of the company. A company having
strong credit position and highly profitable investment, and high amount of assets issue
debenture. Bonds issued by Himalayan Bank Limited and Investment Bank Limited are example
of debenture.
6. Preference share capital: Preference share capital is that capital which has the characteristics
of both the equity capital and debt capital. Two types of dividends are provided to preference
shareholders. They are: (a) dividends based on fixed percentage (debt capital), which is paid
after tax deduction, (b) dividends based on earning (like the one paid to equity shareholders).
So, this is more like long term debt, and some time referred to as hybrid capital. Like, equity
shareholders, preference shareholders are also considered as owner of the firm, but they do not
enjoy any of the voting rights of the equity shareholders.
Capital structure, sometime known as financial plan (Capital plan or Financial Plan) refers to the
composition (makeup) of long-term sources of fund, such as debentures, long term debt, preference
share Capital, and equity share capital including reserve and surplus. Some companies do not plan their
capital structure and it develops as a result it the financial decision taken by the financial manager
without any formal planning. Such companies may prosper in short term, but ultimately will face
considerable difficulties in raising funds to finance their activities. With unplanned capital structure,
organisation may also fail to economies the use of their funds. Consequently, it is being increasingly
realized that an organisation should plan its capital structure to maximize the use of funds and to be able
to adapt more easily to the changing conditions.
While planning capital structure, one needs to decide on the following aspects:
Bond
In practise, the determination of an optimum capital structure is a formidable task, and one has to go
beyond the theory. A number of factors influence the capital structure decision. The judgement of a
person taking the capital structure decision plays the most crucial part. Thus, two similar projects can
have two different capital structure depending on the knowledge and risk-taking capacity of the decision
makers.
Planning of capital structure should be done in such way that long -term market price share should
be maximized and interest of different group of people is to be met.
In general, a capital structure is said to be appropriate when the debt- capital ratio varies between
45 and 75 (60±15%)
Profitability:
The capital structure of the company should be most advantageous. Within the constraints, maximum
use of leverage (influence on ESP caused by debt or preference share capital, and equity share) at a
minimum cost should be made
Solvency:
The use of excessive debt threatens the solvency of the company. Debt should be added only point up
to a level which does not added substantial risk to the company
Flexibility:
Flexibility means the firm’s ability to decide on its capital structure to meet its dynamic need. So, the
company capital structure should be flexible enough to meet the dynamic need of the company. Further,
the company should be able to adopt its capital structure without undue delay and cost.
Conservatism:
Conservation deals with cash flow ability of the company. To some extent the capital structure of a firm
should also be conservative in the sense that the debt capacity of the company should not be exceeded.
The debt capacity of a company of a company depends on its ability to generate future cash flow.
Control:
The capital structure should involve minimum risk of loss of control of the company. In other word
capital structure should be planned in such a way that the company should always be able to keep control
on it.
These are the general features of a sound capital structure. Sometimes depending on the characteristics
of a company, we may need to consider some additional features for a sound capital structure. Further
emphasis give to above features may vary from company to company.
A firm should plan its capital structure to maximize the use of the fund, and to be able to adopt more
easily to the changing conditions. The capital structure has to be planned initially at the time a
company is promoted. The initial capital structure should be designed very carefully. With the
improper or unplanned capital structure, firms will fail to economies the use of their funds. So, a
firm should first set a target capital structures and the subsequent financing decisions should be
made with a view to achieve the targeted capital structures.
Generally, the following factors should be considered whenever a capital structure decision has to
be taken. These are the additional factors (or features) other than that mentioned above in features
of sound capital structures.
i. Cost of debt is usually lower than the cost of preference share capital
ii. Interest paid on debt or bond is from pre tax profit. While interest (dividends paid on
the basis of fixed percentage) paid on preference share capital is from after tax profit.
Similar is the situation with the expected growth in sales. A company expected to have larger growth
of sales can employ larger debt.
3. Cost of capital
Capital structure of a firm is also shaped by the cost of the capital. This means a company may
employ cheaper capital. Usually, debt is a cheaper source of funds than equity. This is generally the
case even when taxes are considered. The tax deductibility of interest charges further reduces the
cost of debt.
It should, however, be realized that a company cannot continuously minimize its overall cost of
capital by employing debt. A point or range is reached beyond which debt becomes expensive
because of the increased risk of excessive debt to creditors increases and they demand a higher
interest rate and do not grant loan to the company at all once its debt has reached a particular level.
A large company has a greater degree of flexibility in designing its capital structure. It can obtain
loans at easy term and sell common shares; preferences share and debentures to the public.
5. Marketability
Marketability means the readiness of investors to purchase a particular type of security in a given
periods of time. Marketability does not influence the initial capital structure, but is an important
consideration to decide about the appropriate timing of security issues. The capital markets are
changing continuously. This is explained below.
If the share market is depressed, the company should not issue common shares, but issue debt and
wait to issue common shares till the share market revives.
6. Floatation costs
Floatation costs are not a very important factor influencing the capital structure of a company.
Floatation costs are incurred only when the funds are raised. Generally, the cost of floatation a
debt is less than a cost of floating an equity issue. This nay encourages a company to use debt
than issue common shares.
A firm has total capital of Rs 10,00,000 which consists of 3000 ordinary shares @ Rs 100 per shares,
Rs 200,000 preferences share at 10% interest per year and Rs 5,00,000 debts at 12% interest per year. If
firm’s earning before interest and tax are Rs 2,50,000 and tax rate applicable is 30%, determine earning
per share.
Solution
A firm has equity capital consisting of 4000 ordinary shares @Rs 100 per share and loan of Rs 8,00,000
borrowed at an interest rate of 10% per year. The firm wants to raise Rs 10,00,000 to finance its
investment and is considering two alternative methods of financing i.e. i) to issue 4,000 common shares
@100 each and to borrow Rs6,00,000 at 12% interest and ii) to issue 2000 common shares @Rs100; to
issue 3,00,000 preference share at an interest rate of 10% and to borrow Rs 5,00,000 at 12% interest. If
the firm’s earning before interest and tax is Rs 3,50,000 and the tax rate applicable is 30%, determine
earning per share to decide on the alternatives.
Solution
Option 1
Option 2
Rs 3,00,000 preference shares @10% interest per year and Rs 5,00,000 loan @12% interest per year
Rs 8,00,000 loan @10% per year and Rs 6,00,000 loan @12% interest per year
Calculation:
Loan Rs 8,00,000 loan @10% per year and Rs 5,00,000 loan @12% interest per year
Calculation:
By analysing both options, we can conclude that earning per share (EPS) is Rs 19.5 in option 2 as against
Rs 17.32 in option 1. So, the firm should choose option 2.