How To Approach The Assessment of An Existing Building
How To Approach The Assessment of An Existing Building
not claim to have all the answers, but it is hoped these can
STEPHEN FERNANDEZ
be covered in forthcoming guidance from the Institution of
CEng, FIStructE, MICE, Conservation Accredited
tr ct ra n ineers Engineer
irector and lobal uilding Retrofit Leader, Arup,
Nottingham/Birmingham, UK
NTU
Introduction
ntil recently, the appraisal and modification of
existing buildings were considered specialist
areas and not an ‘essential’ part of a structural
engineer’s training. The buildings were typically
built before the 20th century from traditional
materials, and it was generally assumed that
they had proven themselves and did not require
formal assessment.
However, events such as the collapse of
Champlain Towers South (Figure 1) in Florida
in 2021 have highlighted the risk of collapse of
existing buildings. With the new Building Safety
Act in England and Wales, there is now a legal
requirement to assess the safety of 13 000
multistorey residential buildings and a formal
NIST
10
October 2023 | thestructuralengineer.org
This was a steel-framed tower and no vertical bracing was present to provide lateral
century steel and concrete buildings, rather stability in the long direction. However, masonry walls had been built tight up against
than historic buildings. However, even these the steelwork which provided structural sti ness. Removal of these walls as part of the
modern buildings are not necessarily as safe refurbishment meant that a new system needed to be introduced to replicate this sti ness
as we might expect – nearly all were built to that the walls were providing.
old codes, which often had lower factors of
STEVE FERNANDEZ
NTU
safety and were written at a time when some
design aspects were less well understood. For
e ample, concrete code rules for fire resistance
were substantially tightened in the 1980s.
When assessing an existing building, there
are several important questions that need to
be asked:
| Can we rely on past performance?
| Is the building ‘safe enough’?
| To what extent do we need to
undertake calculations?
| How many intrusive investigations
are needed?
| What are the risks for the client compared
with new-build?
11
thestructuralengineer.org | October 2023
| Visually inspect the structure. in some cases only required that the aspect
| Postulate the likely load path, and undertake ratio of the building be less than 2:1 to satisfy
rough calculations to understand whether the lateral stability, might encourage a more critical
load path seems credible. look at the lateral stability generally.
| Undertake detailed surveys and intrusive Before specifying testing, think about what
investigations to find key missing information you will do with the results, whether favourable
and also to check any areas of concern or unfavourable. If the outcome will be the
(members are often sized for serviceability, same, then the tests may not be necessary.
but investigations should be targeted to While some non-destructive testing techniques
areas which are critical for strength and are available, they all rely on combination with
hence safety). physical testing to give definitive results.
| If the load path does not prove credible, then Remember that tests measure in situ
investigate alternative paths. This means that strengths and need to be converted to
it will typically be necessary to undertake two design strengths.
rounds of investigations, with time in between All investigations should be undertaken with
for calculations and assessment. appropriate caution and supervision, especially
where the load path is uncertain or where
How many intrusive investigations elements are potentially highly stressed, to
are needed? ensure that no damage is done which might
What and how much to investigate should be impair the safety of the building.
Second, although the Building Regulations thought about carefully:
are only triggered if there is an alteration or | Avoid asking for too much to be surveyed What are the risks for the client
change of use, this does not mean (even if too early. or e ample, it is not e ective use compared with new-build?
there is no alteration or change of use) that it is of the client’s money to ask for all timber Understandably, clients prefer the predictability
acceptable to leave a defective structure in that joists to be strength graded, if (as is usually associated with standard new-build forms of
condition. Therefore, calculations will also be the case) a simple calculation shows that construction. If we are to encourage more reuse
needed when there are signs of distress, when they are relatively lowly stressed because the of existing buildings, we need to be able to help
assessing a form of construction with known original design was governed by vibration. our clients navigate the risk and uncertainty
defects, such as LPS, or when inspection of the | Start with a dimensional survey to help associated with work on existing buildings,
building and/or drawings raises concerns. understand how hard elements are working. and this can be as important as managing the
Since the building is likely to be occupied, | Focus investigations on areas of concern, technical aspects. There are many reasons for
the investigations needed to undertake reliable such as where knowledge of the form the uncertainty.
calculations will be expensive and disruptive, of construction suggests there may be Since no amount of investigation and testing
so the investigations and calculations should hidden defects. can fully determine what has been built, the
be targeted towards the potential issues | Remember to test di erent populations’ (e.g. client must always bear more risk compared
identified. his will allow a view to be taken as both columns and slabs). with new-build, where responsibility for design
to whether the factors of safety are acceptable, | Ensure that enough tests are undertaken and workmanship can be fairly passed on to
12
October 2023 | thestructuralengineer.org
ARUP
The existing building at 1 Triton Square in London was expanded significantly to enable three
additional storeys to be added over. A variety of strengthening strategies were adopted ranging
from strengthening steel plates, concrete jackets, fibre-reinforced polymer wrapping, to justifying
the structure and foundations without the need for any strengthening. All approaches required the
structural engineer to fully understand the capacity of the existing structure.
Further details:
Robertson A. and Sturel E. (2021) ‘1 Triton Square, London – low-carbon development through
reuse of an existing building’, The Structural Engineer, 99 (3), pp. 30–35; https://doi.org/10.56330/
MWVI4065
others. This will also impact insurance and Investigations and assessments will be REFERENCES
warranties. To some extent, therefore, the needed, but the amounts needed will vary on
amount of investigations will be a balance of the a case-by-case basis. The structural engineer
client’s appetite for cost and risk. must be aware of typical details and defects 1) Mayor of London (2021) The London Plan
Hidden problems are often uncovered during with the relevant form of construction, so that [Online] Available at: www.london.gov.uk/
programmes-strategies/planning/london-plan
the works. More investigations upfront can investigations and assessment can be focused.
(Accessed: September 2023)
reduce the risks if the client is prepared to pay However, the construction and condition can
for them. never be fully known. 2) London County Council (General Powers)
It is di cult to define in advance how much he engineer will then need to udge whether Act 1909 [Online] www.legislation.gov.uk/ukla/
Edw7/9/130/contents/enacted Available at:
e ort may be needed to ustify a particular the structure is adequately safe, part of which
(Accessed: September 2023)
element for a change in loads, especially when a requires them to decide on an adequate factor
structural engineer is tendering for the work at a of safety for the di erent elements. his is very 3) Matthews S. (2012) DIG 366 Part 3: Structural
time when the load path and element sizes and di erent from the prescriptive design of new appraisal of existing buildings, including for a
material change of use, Bracknell: BRE
strengths are uncertain. Typically, more analysis buildings, and will depend on many factors, e.g.
e ort will yield higher strengths and enable whether anything is changing, whether there
strengthening to be reduced or even eliminated. are any highly stressed brittle elements, and the
Thus, higher fees in the design stages of a consequence of failure, as well as the cost and Box 4. Current IStructE
pro ect will invariably lead to lower overall costs disruption of any strengthening work. resources on reuse and
for the client, but are rarely accepted. Clients need to retain more risks than is the repurposing
Given the uncertainty over both design and case for new-build, and it is important that the
strengthening requirements, the challenges client and their insurer understand these. Publications
can be even greater for design-and-build The Institution of Structural Engineers is in the | Institution of Structural Engineers
contracts. Some clients are now at least moving process of preparing training and guidance for (2010) Appraisal of existing structures
to two-stage tenders to give time for some members on the issues discussed in this article, (3rd ed.). London: IStructE Ltd
investigations and assessment to help reduce both to help them meet their obligations under | Gowler P. et al. (2023) Circular
the uncertainties before final costs are agreed. the Building Safety Act, and also to encourage economy and reuse: guidance for
owever, there can still be conflict since the adaption and reuse as much as possible to help designers, London: IStructE Ltd
investigations needed to price the work will be reduce the carbon footprint of construction.
di erent from the larger number of investigations This new guidance will address Events
needed to ensure structural safety. contemporary issues such as the safety of the | CPD course on ‘Historic timber
radical retrofits now needed to avoid demolition structures: assessment and reuse’,
Conclusions and rebuilding, how to ensure risks are as 16 November 2023
Understanding both how an existing building low as reasonably practicable, and combined | Conference on ‘Reusing existing
is working and how hard it is working is a very structural and fire risks. urther details of training buildings’, 7 December 2023
di erent skill from designing a new building and guidance will be shared in The Structural | Webinar series on ‘Analysis and
following codified rules; there are many Engineer and through other IStructE channels as strengthening of concrete buildings
additional challenges that an engineer will need they become available. (built between 1950 and 1985)’
to grapple with. Relevant current guidance is listed in Box 4.
13
thestructuralengineer.org | October 2023