Basics Professional Practice Tendering (En)
Basics Professional Practice Tendering (En)
Basics Professional Practice Tendering (En)
AUSSCHREIBUNG
zuletzt die Zeitplanung eine wichtige Tim Brandt, Sebastian Th. Franssen
Rolle spielen.
ENTWERFEN
DARSTELLUNGSGRUNDLAGEN
KONSTRUKTION
BERUFSPRAXIS BERUFSPRAXIS
BAUPHYSIK UND HAUSTECHNIK
BAUSTOFFKUNDE
LANDSCHAFTSARCHITEKTUR
STÄDTEBAU
THEORIE
BASICS
www.birkhauser.com
Tim Brandt –
Sebastian Th. Franssen
Tendering
Tim Brandt –
Sebastian Th. -Franssen
Bert Bielefeld Sebastian El Khouli
Entwurfsidee
Tendering
Birkhäuser
BIRKHÄUSER
Basel
BASEL
Contents
Foreword _7
Introduction _9
Tendering requirements _10
Tender items _18
In conclusion _81
Appendix _82
Literature _82
Standards _83
Further sources of information _83
Picture credits _84
The authors _84
Foreword
Architectural quality does not derive from good and creative designs
alone, it must also be reflected in the built reality. So in architecture qual-
ity is a continual concern, from the first sketch via design and final plan-
ning to built structures and surfaces. Tendering is the link between plan-
ning and realization, defining the project requirements. The responsible
contractors use the tender specifications to familiarize themselves with
the details of the commission and can then submit a tender to carry out
the work described, which then forms the basis for the contract and the
actual building programme. In this way the tender specification, as the
final design development stage before building starts, is an important
planning component. It should therefore be compiled with the same pre-
cision and faithfulness to the concept as a design or working plan.
7
8
Introduction
Planners – this includes architects, civil engineers and specialist en- From planning
gineers – have to involve another group of people by the end of the plan to realization
All the information needed for realizing the project is provided to Tender content
building firms as part of an invitation to tender, in the form of descrip-
tions or drawings of the work to be done and services needed. The invi-
tation to tender must contain all the information the bidding firms need
to perform the necessary services and to submit a bid for the contract
and, where appropriate, for planning the work. ◯
Establishing fundamentals
Design plans
Planning
Planning permission
Working plans
INVITATION TO TENDER
Award
Realization
Building
Documentation
9
Outcome of the The tendering process aims to attract as many appropriate bids as
tendering process needed to form a broad view of the market. The invitation to tender is
compiled by the planner and submitted to suitable contractors, who then
calculate prices and submit a bid, which is binding. This is then examined
by the planner and compared with other bids. The comparison gives the
planner an insight into current prices and enables the client to commis-
sion the work from the bidder who has submitted the most reasonable
offer for the particular project.
Tendering requirements
The invitation to tender collects all the requirements that have come
to light in the planning phase. These requirements are essentially laid
down by the client, but they may also relate to legal or technical matters.
They can be categorized as follows: > Fig. 2
—— Costs
—— Deadlines
—— Function
—— Scope
—— Quality
Deadlines
Costs Qualities
Client
Function Scope
10
Costs Geography
Time Law
General conditions
Client’s aims
Quality Market
Function Politics
Scope ...
e.g. area,
number of jobs
Requirements
Building commission
These criteria are used to fix the realization phase and to identify any
planning services that are still required. > Fig. 3
Costs
In most cases cost is the key criterion for or against a realization bid, Cost range
or even for or against the building project itself. Planners are obliged
to spend a client’s money on the project in the client’s best interest.
Planners generally have a prescribed budget, and must set all the costs
arising from the building work against this. This will mean drawing up
separate budgets for the various service packages or award units. > Chapter
Organizing the tender, Fixing bid units
11
Fig. 4: Range of prices as an aid to choosing a firm
12
An overview of the individual budgets makes it possible for planners Cost control
to control costs. If the bid for a particular unit is above the budget allo-
cated to it, planners will have to cut the budget for other units and take
this into consideration when drawing up invitations to tender, for exam-
ple by reducing quality standards or the scope of the work required. Con-
versely, if an item comes in under budget, planners can, for example,
include clients’ requirements that had previously fallen outside the cost
framework.
Clients can best ensure that costs are firmly fixed by attempting to Cost guarantees
eliminate all cost risks arising from unpredictable events during building,
from market developments, and from submitting a series of individual
tenders. One possible way of doing this is for a single contractor to take
on the whole operation, which guarantees completion costs and dead-
lines. > Chapter Organizing the tender, Fixing bid units, Package awards
Deadlines
Clients will generally set firm deadlines, or at least express their
wishes about them. Once deadlines are agreed, they are binding. ◼
Constraints on deadlines arise mainly from the planned use of the Deadline
building concerned. For example, completion dates, and thus possible constraints
moving-in dates, are crucially important for private clients building their
own home, who need to give appropriate notice on their previous, rented
accommodation. Renovation work in schools can often be carried out
only in the school holidays. Here both the starting and completion dates
are deciding factors.
13
Fig. 5: Example of a deadline plan as a bar chart
Effects on tendering Deadline requirements also affect the way planners submit their ten-
ders. Robust and detailed planning involves investing a great deal of time,
so planners have to consider whether they will be able to submit such
plans at the appropriate time. If they cannot do so, they can transfer some
of the planning services to the contractor, by defining some aspects in
terms of functions, rather than in full detail. > Chapter Organizing the tender,
Tendering style, Tendering by function
Function
Realization range The client’s requirements establish the extent and bandwidth of the
realization variants. For example, if a private client wants to buy land and
build a home on it, this can be a terraced house, a semi-detached house
or a detached house. Function is thus one of the factors determining the
form the building will take. It is also possible to decide on particular build-
ing methods from a function description. When building a warehouse with
14
Fig. 6: Various functions
The more strongly clients identify themselves with a commission, the Client profile
more influence they will wish to exert on planning the invitation to ten-
der. If the project is their dream house, the client could well wish to be
involved in every last detail of the planning process. The invitation to
tender will thus have to be correspondingly detailed, so that the client’s
ideas can be implemented in full. > Chapter Organizing the tender, Tendering style,
Detailed tendering
15
Fig. 7: There are various ways of meeting requirements for a building.
Range of services
Minimum scope The range of services derives from clients’ wishes. For example, when
building an office block, clients can state how many office workstations
are intended and what other spaces are needed to serve the desired func-
tion (foyer, conference rooms, server areas, etc.). The more precise the
requirements, the more precisely the minimum project range can be
determined.
Factors open As well as the scope set by minimum standards, there are also vari-
to influence able quantities that affect the quality of the building as a rule. For exam-
ple, planners can minimize the window area, which is more expensive
than a closed facade, at the expense of user comfort, or reduce the num-
ber of workstations at the expense of subsequent flexibility.
16
Fig. 8: The relationship between function and quality
Quality
Function also affects the quality expected. Here we can speak of
technical and aesthetic criteria. > Fig. 9 Technical requirements include
building law provisions (e.g. statutes relating to assembly of persons
or the fire prevention concept), or health aspects (e.g. ventilation or
hygiene); aesthetic requirements relate to the visual impact, form and
characteristics of the building as a whole, down to individual details such
as door handles.
There are fixed minimum standards for most building services, Standards of quality
intended to guarantee the use of appropriate materials and professional
execution. Clients will have requirements for their property that go be-
yond minimum quality. As soon as the planned finish deviates from the
standard quality, planners must mention this expressly in their service
description and describe the finish or the desired result.
17
Quality
Technical Aesthetic
Structural Formal
Statical Tactile
Legal ...
...
tender items
Building The building process involves choosing and coordinating an enor-
services and mous range of structural elements. Here, planners have a very wide range
construction products
of prefabricated items at their disposal (e.g. doors and door frames), but
can also work with individually manufactured elements (e.g. hand-crafted
door fittings). A building can be planned down to the position of the last
screw, and the shape of its head. Invitations to tender for building ser
vices relate both to parts of the planning process and also to the whole
realization process. They summarize all the services needed. The scope
of the invitation to tender will vary according to the scope of the building
project and the nature of the tender. > Chapter Organizing the tender, Tendering style
For example, if tenders are being invited for a complete building project,
starting from scratch to the very end, they can include all construction
services from digging the foundations to cleaning at the end of the con-
struction phase and handing the key over to the client. Invitations to ten-
der may also be issued for replacing a single window.
18
Fig. 10: Everything can be built into an invitation to tender
Complementary planning and services can also be included in an Planning and other
invitation to tender, as well as classical construction work or products. services
19
20
Organizing the tender
The possible scope of the project, and the diversity and complexity Fundamentals
of the invitation to tender, mean that it makes sense to divide the build- of organization
ject. A timetable for the planner’s and the bidding companies’ work on
the tender can be drawn up with reference to the realization deadlines,
bearing possible preliminary planning periods for specialist firms and for
the awarding procedure in mind.
Start of
tender process
Drawing up
and dispatch
Processing
and return
Assessment,
award
Preliminary
period
Realization
Completion
of work
Time to be allowed for
21
Time invested by participants
Time invested Planners need sufficient time to draw up an invitation to tender. > Fig.11
by planner Once they have compiled a list of all the client’s wishes and requirements,
they must take time to organize the invitation to tender and think how to
convey the requirements in such a way that the invitation can be formu-
lated meaningfully. Planners must establish quantities needed, to define
the scope of the services required. Any question arising must be cleared
up with manufacturers, specialist organizations or other appropriate con-
tacts. It is often necessary to provide any experts approached with doc-
uments about the general conditions, and drawings, to ensure that re-
sponses are robust and appropriate for describing the services required.
If difficult installations or complex construction processes are involved
it often makes sense for planners to cover themselves by asking manu-
facturers for written statements or opinions.
Award
Dimensioning
on site
Workshop
planning
Approval
by planner
Materials
ordered
Pre-
production
Assembly
on site
Completion
of work
Trade preparation period
22
Construction companies submitting bids who receive a description Time needed
of the services required have to familiarize themselves with a new build- for processing the bid
ing project, and thus need an appropriate period to work on the invita-
tion to tender. In some cases, the nature and scope of the tender may re-
quire additional planning work before the price can finally be calculated;
manufacturers or other firms and their internal price enquires may need
to be considered in their turn. The calculation must take wages, materi-
als, equipment and outside services into account. As well as these fac-
tors relating directly to the building commission, general overheads and
possible profit have to be built into the bid price. Preparing the bid can
take anything from a day to several weeks, according to the complexity
and scope of the tender. The necessary processing period is extended
correspondingly if the invitation to tender also covers planning services
or technical tests.
The time span from commissioning to the actual delivery of the ser- Preliminary planning
vices (start of building work) on the building site is the preliminary plan- period for trades
ning period for specialist firms. > Fig. 12 During this period, the firms being
commissioned can construct working plans or samples and submit them
to the planner for approval. Construction elements are often modified or
assembled in advance in the factory by the firms involved. Measurements
Start of construction
Preparatory
measures
Shell
Building
envelope
Interior
finishing
Domestic
services
Final work
Building
completed
Building period
Bauzeit
Fig. 13: Sequence of building work
23
for prefabrication may need to be made on site, which adds another fac-
tor for meeting completion deadlines, for example if masonry with aper-
tures has to be completed before fixing the dimensions of the windows
that have to be prefabricated.
Time needed When timetabling tenders it is important to know how long it will take
for realization to complete a particular piece of work, given that a possible completion
deadline has to be fixed. > Fig. 13 There is only limited scope for shorten-
ing such an individual completion time. The length of time needed can
be affected by the number of people working on the job, working hours
and the use of machines. There are natural restrictions on speeding up
work, for example the time that certain building materials take to dry or
harden (e.g. screed). Space on the building site may be at a premium, so
increasing the workforce could mean people getting in each other’s way
while working.
... ...
Fig. 14: Sequential planning when awarding by trade (award by specialist lot)
24
entail a preparatory period lasting several months, which must be taken
into consideration when drawing up the invitation to tender.
The sequence described here relates to invitations to tender issued Invitations to tender
while building is in progress. > Fig. 14 For tendering in this way, all the ser while building is in
progress
vices required are drawn up in sequence, and invitations to tender issued.
For example, the interior is planned and invitations to tender are issued
after the shell has already been completed. In comparison with a blan-
ket invitation to tender > Chapter Organizing the tender, Fixing bid units, Package awards
this approach offers the advantage that an appropriate response can be
made to unexpected cost developments. > Introduction, Tendering requirements,
Costs It is also possible to accommodate changes that have occurred dur-
ing the completed building phases. For example, if the ceiling slab thick-
nesses have had to be changed for practical reasons, they can be com-
pensated for in the finished floor height. However, it is impossible to be
certain about costs until the last invitation to tender, because of the
difficulty in predicting the effect market fluctuations and other eventu-
alities could have on services offered.
Awarding to a main contractor offers greater cost security. > Chapter Blanket
Here, all the services have to
Organizing the tender, Fixing bid units, Package awards tendering
Planner Contractor
Planning Realization
Planner Contractor
25
Total package award
Award by lot
completed before the first ground is dug. > Fig. 15 If there is not enough
time available for a detailed invitation to tender, planners must concen-
trate on requirements that are important to the client and describe only
these in detail > Chapter Organizing the tender, Tender style, Detailed tendering and the
rest merely functionally. > Chapter Organizing the tender, Tendering style, Tendering by
function Sometimes the pressure of time can be so great that a purely func-
tional invitation model has to be considered, giving no detail at all.
Tendering by trade
Trade (specialist lots) Subdivision by trades (trade or specialist lots) is based on craft and
technical skills traditionally delivered by an individual or a firm (e.g. craft
trades such as stonemason, carpenter or screed layer). This is generally
the smallest bid unit. > Fig. 17
26
Total package award All work
Trade lot 1
Trade lot 1
Trade lot 2
Trade lot 2
Trade lot 2
…
= bid unit
another for steel staircases and banisters. The smallest possible bid unit
is a single service. > Fig. 18
◯ Note: The term trade is also generally applied to less ● Example: A construction company that produces and
traditional work such as structural engineering, media assembles stairs every day can offer this service more
planning or sign-making. Although these are not tradi- professionally and possibly more cheaply than a metal-
tional trades, the important feature here is that the worker who specializes in facades but theoretically
services form a unit. covers all aspects of that trade.
27
Preparatory Shell Building
measures envelope
Bundling trades It can sometimes make sense to bundle a number of trades. It seems
logical to commission a single firm to take on all the work relating to a
roof, and avoid having to coordinate a number of firms. Thus, carpentry
28
(constructing the roof truss), roof-covering work (roof construction from
insulation to the pantiles), and some metal-fitting work (fitting gutters,
protective leading) can all be done by the same firm. Many firms have
adapted to the clients’ desire to deal with a single contact person, and
advertise as providing a complete service. Note here that some firms that
seem quite large simply “buy in” services and often cannot offer them at
particularly reasonable prices. The client is then buying convenience by
paying an additional price for in-house subcontractor organization by the
firm commissioned. > Chapter Organizing the tender, Fixing bid units, Invitation to tender ◯
by part lot
In public commissions, this can take place with the intention of Subdividing services
involving as many firms as possible in the bidding process, as the scope
of services required will then be based on the capacities of essentially
average companies.
Another sensible reason for structuring in part lots is when planning Building phases
work over a long period with possible interruptions. Building phases are
often fixed for larger building projects so that some parts of the building
can be used while others are completed at a later stage. > Fig. 19
Package awards
Bundling several trades, with only one contact person on the reali- Main contractor
zation side, as mentioned above, is pursued further in awards to a main tendering
contractor. > Chapter Organizing the tender, Fixing bid units, Invitation to tender by part lot
29
Phase 1
Phase 3
Phase 2
Fig. 19: Bidding for part lots is possible if buildings are constructed in various phases.
Here, the client commissions a single building firm to provide all the ser-
vices needed to complete the building work. A single contract is agreed,
rather than a large number of them.
Meeting deadlines It is easier for a main contractor to fix completion dates because
such a firm will be able to compensate for delays in parts of the project
by pushing the work ahead in other areas, as part of the overall coordi-
nation process. It is more difficult to set binding deadlines when com-
missioning a number of individual firms because of the large number of
mutual dependencies: individual building firms are not contractually
obliged to each other.
Main contractor A main contractor is responsible for all this, and will generally exact
supplement payment for this often voluminous coordination work, and sometimes
also risk coverage for guarantees undertaken, by building supplements
into the bid. In practice there are few firms that can cover all the services
required using in-house workers. In fact, they tend to tender the services
out to other firms, which then – if they are commissioned – work as sub-
contractors. A main contractor’s bid concludes in a guaranteed price for
which the services must be delivered by a contractually fixed deadline.
30
tendering style
A distinction is made between functional and detailed tendering, but
these are rarely separated consistently in practice. Any detailed invita-
tion to tender will always contain functional elements. For example, even
a meticulously detailed description of a plasterboard stud wall will not
contain precise information about fixing the plasterboard panels. It is
assumed that the workmen will have the appropriate technical knowl-
edge and will know the correct screws to use for fixing the panels to the
frame. A functional invitation to tender can work without detailed ele-
ments, but here, too, there will in practice be areas where the require-
ments are formulated in greater detail. The more questions the planner
asks the client about requirements, the longer the list of detailed require-
ments within the actual functional invitation will become.
Tendering by function
Functional tendering does not describe how the work is to be done
or the precise building process, but focuses on the required outcome.
The bidder takes responsibility for planning the work and thus also car-
ries the risk of achieving the required result even if there were omissions
in the original bid. As well as being responsible for possible planning
errors, the contracted firm also carries the quantity surveying risks.
Bidders are able to determine how the work is done by choosing pro-
cedures in the light of their expertise and experience. They can optimize
the entire range of services offered in terms of their own resources, as
the contract offers room for manoeuvre.
The criteria for assessing bids include price, and the way the set Assessing bids
r equirements are addressed. The bidder will have spent time and effort
on the bid, and the planner now has to assess it in some depth. Conse-
quently, clients or planners have no further influence in principle on the
subsequent execution of the process. This loss of control, which applies
to detailed planning in particular, may lead to a loss of design quality.
Functional tendering is often chosen through lack of time. > Introduc- Choosing
It thus clearly reduces the extensive plan-
tion, Tendering requirements, Deadlines functional
tendering
ning process that would have to precede award to a main contractor.
Lower client demands on the realization details may lie behind a func-
tional invitation to tender, especially as the firm to which the contract is
awarded takes on a large number of risks as well. Another reason for
choosing a functional style may be simply that the planner has no idea
how to achieve the required aims by means of a detailed invitation to
31
tender. Thus, planners will not invite tenders for the individual compo-
nents of an air-conditioning plant or the way they are assembled, but will
simply describe cooling or ventilation rate requirements.
Detailed tendering
Detailed tendering requires every detail of the work required to have
been planned in advance to the greatest possible extent. Planners do not
simply describe the required result, but also how it is to be achieved. They
thus accept the risk that the finished work will not meet demands, or that
there will be errors and omissions in the tender invitation, or it will not
be completely clear. This can lead to additional costs for additional work
(services that are needed but were not included in the original invitation
to tender).
Assessing the bids It is much simpler to assess a detailed invitation to tender, as the
choice of procedure is fixed, and only the prices have to be compared.
Choosing a detailed It always makes sense to opt for a detailed invitation to tender if the
invitation to tender client wishes to remain in control of the building process. This is the only
way of checking every detail of the realization work, and avoids disagree-
able surprises.
Depth of tender
It is fundamentally possible to mix functional and detailed tendering.
This opens up considerable creative possibilities for planners. They will
be able to submit detailed final working plans for all the areas that are
important to clients, and to describe the realization process with equal
precision. In areas that do not require so much detail they can confine
themselves to describing requirements and choose the contractor who
offers the best possible solution.
Detailed or If planners put out detailed invitations to tender they must have the
f unctional? appropriate knowledge at their fingertips. They will be responsible for
any mistakes in their description of the services they are offering. It
is therefore advisable to tender on the basis of function, bearing the
desired result in mind, for any elements about which they are not thor-
oughly informed.
Completeness Planners must always ask themselves whether the invitation to ten-
of the bid der they have prepared is complete, in other words whether the informa-
tion they have provided is unambiguous, and that there are no omissions.
For example, if they ask for an “orderly and symmetrical” pattern of
screws for securing the facade elements, they must add a diagram show-
ing the pattern of screws, to avoid contentious interpretations of this
32
requirement. As a rule, only detailed descriptions allow control of the way
the work is ultimately done. This is very time-consuming, and cannot
always be managed for every aspect of the building. Planners should
always consider carefully what degree of detailing is necessary and
appropriate. For example, requirements about formwork for an exposed
concrete wall must be much more carefully formulated than those relat-
ing to formwork for foundations that will not be visible when the building
is completed.
33
34
Structuring an invitation to tender
The invitation to tender – functional or detailed – is made up of sev-
eral elements. > Figs. 20, 21 It includes all the documents required for award-
ing a building contract. ◯
Textual elements
Textual elements mean all the descriptions couched in words and fig-
ures that provide information about the sequence and execution of the
planned building project. An invitation to tender is drawn up using these
elements, and consists of the following components:
35
Samples, references and
examples of work realized
Description of work
Project-related conditions
Technical requirements
Contractual conditions
Building description
Preliminary letters
36
Fig. 22: Example of a cover sheet
The cover sheet is both an introduction to and a summary of the con- Cover sheet/
tents of the invitation to tender. It includes brief summary of all the in- accompanying letter
formation required for the building firm to process the tender, along with
the conditions of application. The cover sheet should contain the follow-
ing information:
37
—— Details of the sender and recipient of the documents
—— Date
—— Definition of the building project
—— Location, nature and scope of the work required
—— General conditions relating to the building project
(type of award, timescales, etc.)
—— Express invitation to tender
—— Conditions of application
—— List of documents enclosed (contractual documents)
Description of the Details about the location, nature and scope of the services required
building project are needed, along with a definition of the building project, so that it can
be clearly identified. These should be as succinct as possible. If more
information about the project is required, this should be included in the
building description. > Chapter Structuring service specifications, Approach to functional
service specifications, Functional specification with designs
Information about the The awarding procedure should be clearly defined in the cover sheet
awarding procedure and must be given by public clients. > Chapter Organizing the tender, Timetabling the
invitation to tender, Time invested by participants
Viewing dates Identifying the location is also important in relation to possible view-
ing dates. Such dates should be identified on the cover sheet, giving
location and date. The same applies to planned inspection dates in other
documents not included in the tender package.
Tendering period/ Details about the tendering period, the submission date and binding
submission dates for the tender are equally important. > Chapter Organizing the tender, Time-
tabling the invitation to tender The tendering period identifies the date by which
the bid must be submitted. The bidder will be committed to the offer made
until the date given. Bidders should be informed about the essential
award criteria (e.g. price) in the cover sheet for the tender documents.
Binding nature To avoid misunderstanding, the cover sheet should include a formu-
of the bid lation stating that the bidder will incur costs as a result of bidding. The
formulation could be:
“We request your binding bid for this building project, at no cost to us
or our client ...”
38
● Example: “The ... project relates to a three-storey This example makes it clear how little the building
office building with a gross floor area of approx. description covers. It provides important information
10,000 m2, to be constructed as a reinforced concrete about the desired building method (skeleton struc-
skeleton structure with exposed concrete. The building ture with exposed concrete), the nature of the work
plot is between ... street and … street, and can be (reinforced concrete building work), size (gross floor
accessed only by the entrance at the junction of ... area, three storeys), function (office building) and
street and ... street. The precise location of the building the location of the building site (reference to the site
site can be found in the site plan.” plan).
Planners can use a request for proof of suitability and admission cri- Proof of
teria to check whether bidding companies are qualified to carry out the suitability
For larger building projects it can make sense to include more pre-
cise information about the body of the building or the structure and
organization of individual building sections in the building description, so
that bidders can form a clearer picture of the possible building phases.
Contractual conditions
The invitation to tender aims to prepare the way for a contractual
relationship between the client and one or more companies realizing the
project. Against this backdrop, provisions governing contractual modal-
ities for carrying out the building work are important, as well a descrip-
tion of the services required. ◼
39
◼ Tip: As the regulations involved are often very com-
plicated, it is advisable to use recommended contract
texts, drawn up by professional associations, for exam-
ple, or at least to have lawyers draw up the contract
conditions for larger projects.
40
—— Settlement (details about how and in what order settlement must
take place after completion of work required, or parts of that work)
—— Work paid by the hour (provisions for dealing with remuneration
for services required that are not contained in the description of
services, for example a commitment by the firm carrying out the
work to inform the client before undertaking such work)
—— Payments (general provisions governing instalments, part-final and
final invoices, for example, timings are laid down for the duration
of the final invoice check)
—— Security (provisions governing mutual security for the contract
partners, for example in the form of guarantees or security
retentions)
—— Disputes (provisions in case of dispute, such as fixing the client’s
location as the place of jurisdiction)
Special contractual conditions can relate to the same matters as the Special
general contractual conditions and complement them in certain points. contractual
conditions
They serve as an addition to the general contractual conditions, and not
as a substitute for them. Typically, special contractual conditions are
included in the tendering documents if there is already a provision in
principle in the general contractual conditions. The following areas are
also addressed:
41
—— Subcontractors (subcontractors are used to provide services that
a company cannot itself cover. If the use of subcontractors is to be
excluded or is permissible only under certain circumstances, this
should be laid down in the special contractual conditions.)
—— Competition restriction (inadmissible competition restrictions
arise from prior agreements that are unfavorable to competition
between bidders relating to the submission or non-submission
of bids, to prices or profit supplements. Special contractual
conditions lay down the consequences of behavior that is
unfavorable to competition.)
—— Price reductions (are regularly agreed as a percentage and
deducted from all invoices appropriately)
—— Environmental protection (Normally no concrete environmental
protection measures are formulated. It is customary for the special
contractual conditions to refer to reduction of environmental
damage by the building measures.)
—— Changes to the contract (Contract alteration modalities should be
stipulated in the special contractual conditions. For example, it
◯ can be agreed that alterations to the contract must be in writing.)
Technical requirements
As a rule, planning a building project and describing the work
required to realize it end when a certain degree of detail has been
reached. Everything else is fixed by the agreement on technical require-
ments. This contains instructions about the way the work is to be carried
out. For example, planners might provide a drawing of a reinforced con-
crete wall, and possibly supplement it in the text with description con-
taining details about formwork, reinforcement and concrete. But they
will not describe in detail how the formwork should be constructed,
the reinforcing steel secured in position or the concrete compacted.
Such information forms part of the specialist knowledge of the com-
pany carrying out the work, and will be conveyed by the planners to
the building firm via the technical requirements laid down in the invita-
tion to tender.
General technical General technical requirements are standards that apply in terms of
requirements the generally acknowledged rules for a particular technology.
◯
42
Regulations are usually arranged specifically to trades and contain
information about the sphere of validity, the substances and materials
used, implementation, additional services that form part of the service
as a whole, and about financial settlement and hints for compiling a
description of the services.
Special technical requirements are regulations that are used either Special technical
to complement the general technical requirements or that apply to areas contractual
conditions
not previously regulated. For example, a special technical requirement
can relate to a building process not covered by the general regulations,
or can stipulate a higher dimension tolerance requirement to comple-
ment the existing minimum requirements.
◯ Note: If certain provisions apply to one particular ◯ Note: The generally acknowledged rules of technol-
building project, they should be addressed in the con- ogy are a set of regulations based on technologies
tractual conditions relating to the project, and not in that have proved their worth over a long period of time.
the special contractual conditions, which are usually A higher standard is set by a level of technology that
formulated to cover several building projects. represents the latest technical progress, but need not
be tried and tested. A further step upwards is offered
by a level of science and technology that takes the
most recent scientific insights into account.
43
Project-related contractual conditions
Project-related information covers the general conditions of the
building project. They cover all the regulations of a contractual and tech-
nical nature affecting the building project as such.
Apportioning general The general building site costs can be contractually apportioned to
building site costs all the contractors involved. Costs for setting up site signs, using on-site
equipment and waste disposal can also be apportioned in the project-
related contractual conditions.
Implementation Stipulations about the time available for the work are particularly im-
period/contract portant. All statements relating to this are fixed in relation to the project.
deadlines
They include statements about the beginning and end of the building work.
These periods are binding for later implementation of the building com-
mission, and if not observed they represent a breach of contract with the
possible consequence of claims for damages, or a contract penalty. Only
contractual periods that the company undertaking the work has acknowl-
edged in the project-related contract conditions are legally binding. If
intermediate deadlines other than the starting and finishing deadlines
are agreed contractually with the company undertaking the work, these
must be identified as individual fixed periods in the project-related con-
tract conditions.
44
If contract deadlines are not met, this usually means claims for dam- Contract penalty
ages by the client against the company undertaking the work. Here, only
loses that have actually resulted can be considered. If other provisions
are also made for handling breach of contract, these must be indicated
appropriately in the project-related contract conditions with reference
to a contract penalty.
Tender specification
The tender specification is the key element in an invitation to tender.
The distinction between functional and detailed tendering is based solely
on the nature of the tender specification. A directory of services is used
for a detailed tender specification, and a program of services is drawn
up for a functional tender specification. In exceptional cases, building
descriptions are used as functional tender specifications. > Fig. 23
Work description
Detailed Functional
Own Standard
text text
45
Drawing elements
The plans, drawings or sketches appended to an invitation to tender
should make it easer for the contractors to compile their bid in terms of
the services to be calculated. They will therefore need all the planning
documents necessary for general geometrical orientation, and for under-
◯ standing the services required.
Range of drawn The spectrum of drawn descriptive elements extends from simple
descriptive elements hand-drawn sketches to technical drawings, with plan content varying
from site plans to scaled implementation details. > Figs. 24, 25
References The architect can use references to particular planning details in the
tender specification to identify particular points that do not emerge
directly from the descriptive text or that are more easily conveyed by
a drawing.
46
◯ Note: Building work is done on the basis of the archi-
tect’s working plans, not of the tender specification.
The tender specification forms the basis for compiling
the tender bid. If information in the tender specification
contradicts the plans, each case should be examined
individually, following the contractually fixed hierarchy
where applicable.
It is also possible to set up show rooms in which the client can see
and assess the effect made, from surface materials to individual pieces
of furniture and fittings in context.
Reference items are particularly important when building in existing Reference items,
stock, or in the case of ensembles. For example, when designing the examples of finish
47
48
Structuring service specifications
We distinguish between three basic starting situations for functional
or detailed service specifications. > Fig. 26
1. No design is supplied
2. Plans or planning permission are available
3. The final planning stage has been reached
—— Building descriptions
—— Building programs
—— Room programs
—— List specifying all the work required
49
Building program
Without
design
Functional tender
specification
Room program
design
With
Construction room book
specification
(realization)
Detailed
working
tender
plans
With
Furnishing and fittings room book
(documentation)
50
Functional tender specifications without a design
A building program and a room allocation program, offered without
a design, simply describe requirements for the building as a whole, for
individual parts of a building or for areas intended for a particular use.
The bidder is responsible for design, technical, use-oriented and eco-
nomic planning. ◯
51
Building programs contain information about the building project in
general, supplying additional information about connections to public
services (sewerage, water, gas, electricity and telecommunications), the
transport system and access to outside areas.
Room allocation A room allocation program provides a more refined definition of the
program requirements. It will give information about rooms and use areas, and
also about how they are placed and linked together. The bandwidth of
possible information in a room allocation program depends on the plan-
ning stage reached. Sensible subdivision of the areas according to the
following criteria forms a good basis for a description system:
—— Use
—— Number
—— Size
—— Position and orientation > Fig. 29
Function scheme A function scheme shows how individual areas relate to each other with-
out illustrating the areas required. Essential links between individual
areas are indicated in order to clarify the sequence of events arising from
a particular use. > Fig. 30
Graphic room Information from a tabular room program and function scheme can
allocation be summarized in a graphic room allocation program. This can contain
program
basic elements of the architectural design that have already been deter-
mined: formal statements are presented, taking the areas and rooms
◼ required and the way they relate to each other into account. > Fig. 31
52
Use Number Size Position and orientation
2 × 50 m2
Deliveries
Stack (A) Equipment Store Staff Post
and access
Magazines
Seminar
Catalogues room (B)
Textbooks PC pool
Microfilm Staff
53
Other means of description are suitable as well as building and room
allocation programs. A building description for drawing up a functional
tender specification without a design is one of these.
Building The building description essentially provides a rough idea of the build-
description ing project as a whole, but can also convey functional details. > Chapter
Structuring an invitation to tender, Textual elements, General information about the building
project Unlike the room allocation program, which is based on spatial
rganization, a building description is structured in terms of construc-
o
tion or trades. This is also why it is only very roughly suitable as a basis
for functional tender specification. Saying “reinforced concrete hall, area
2,000 m2” is a very rough description, but it is perfectly appropriate for
use as an element in a functional description. Specifying “reinforced con-
crete” rules out alternative construction elements, such as steel girders.
Canteen
Reception 150 m2
Access …
…
25 m2
200 m2
Office Kitchen
…
80 m2
Access
30 m2
Events and seminar area
Access
30 m2
Access
50 m2
…
Access
25 m2
4 ×25 m2
1 × 200 m2 2 × 50 m2
54
The more specifically the building description addresses a particular
construction method, the more effectively unwanted elements will be
ruled out as alternatives for bidders.
A room allocation program can be addressed in greater detail by in- Room book
troducing room books at an appropriate point in the planning phase. This
is a system that makes it possible to supply information about any
planned room. A room book sums up the space required systematically
and defines use requirements. Each room book should contain the
following information to ensure unambiguous identification and simplify
further use of the information provided:
55
Room book types There are three different kinds of room book, fulfilling different pur-
poses and so requiring different planning levels:
Room book
Requirement room book Sheet: 05
Technical requirements
Area Requirement Statistics
Statics Maximum deflection f = l/300
… … …
Fire prevention as per Structural component at least
Building science DIN 4102 F30
… … …
Requirements by function
Area Requirement Statistics
… … …
Design requirements
Area Requirement Statistics
… … …
Financial requirements
Area Requirement Statistics
… … …
Ecological requirements
Area Requirement Statistics
… … …
56
A requirement room book plays a key part for a functional tender Requirement room
specification with design supplied. A sheet with a table of all the known book
A construction room book offers another form of description, pro- Construction room
viding a detailed description of the construction, but not the fittings and book
Room book
Page: 05
Approved: Ms Sanders
4 Window … … …
5 Doors … … …
6 Lighting … … …
7 Power … … …
supply
8 Heating … … …
9 Ventilation … … …
Fig. 33: Example of a furnishing and fitting and construction room book
57
◯ Note: A furnishing and fittings room book giving
detailed information about every room is suitable pri-
marily for preparing a detailed tender specification with
a complete list of technical and general requirements
for each trade. Care should be taken to ensure that the
services are listed in relation to trades, and not in
relation to rooms.
Furnishing and fittings A furnishing and fittings room book simply provides a complete
room book escription of the furniture and fittings for every room. It lays down which
d
elements are to be fitted in each room, and in what quality and quantity.
Each element is listed by number and manufacturer’s description, or in
◯ comparable detail.
Part of building
Floor
Room
Part of
building
Structural
element
58
For further breakdown, a list of use or function areas should be drawn
up. At this level, it is already appropriate to provide information about
individual supply and technology elements, foundations, the loadbearing
structure, the facade and the roof. If individual uses are known or in-
tended, requirements can even be defined on the basis of structural com-
ponents, such as a non-loadbearing wall between two offices. > Fig. 34
Scale
Part of building:
loadbearing system
Design Function
Quality
Costs
Finish
Deadlines
Scale
Function
Quality
Costs
Deadlines
Scale
Finish
59
A building project needs to be broken down only to a certain extent:
it must be possible to define different requirements on the basis of the
client’s intentions and the known general conditions. If the client pre-
scribes a function specifically, it does not make sense, and it is usually
not possible, to break such a function down into its individual compo-
● nents. > Fig. 35
Rough description of It is recommended that the first step should be to allocate the
the function of a planned building project to a function group:
building
—— Housing construction
—— Office building
—— Department store
—— School, college
—— Factory
—— Hospital
Requirement catego- The use profile can be differentiated further by identifying design
ries and aspects (social and aesthetic), technical, functional, financial, and other catego-
ries if required. Each category will contain coherent requirement aspects.
For example, building science and construction are both requirement
aspects within the technical requirement category.
60
Individual
Requirement category Requirement aspect requirement Statistics
e.g. Technical e.g. Building science e.g. Fire prevention e.g. F60
requirements ...
... ...
...
e.g. Statics ... ...
...
... ...
...
e.g. Aesthetic ... ... ...
requirements
The individual requirements and the ratings that lie behind them can
be compiled clearly using the breakdown system shown in Fig. 36.
● Important: Considerable variations are possible in ◯ Note: Ratings provide a clear, measurable basis
the depth of analysis required to describe a client’s for individual requirements. If no ratings are given, or
intentions. It is possible that a client will simply identify if they are defined only qualitatively (e.g. enhanced
an output value for a production plant. It is then up to sound insulation), this may give undesirable scope for
the bidder to investigate all other criteria within the the bidder’s interpretation.
general conditions, which cannot be changed. If this
procedure is being followed, it is neither possible nor
appropriate to break the building project down.
61
Design The design requirement category includes both aesthetic and social
requirements aspects. The content of this category is largely a matter of the client’s
sensibilities, and includes aspects like convenience, privacy and comfort
in the social sphere, and architectural quality, elegance and prestige in
the aesthetic sphere.
Technical Technical requirements are derived directly from the function, from
requirements standards and regulations, or from the client’s express wishes. Essen-
tially, all the areas relating to loadbearing capacity, stability and building
science (e.g. heat and sound insulation, fire protection and waterproof-
ing) are defined more fully by requirements.
62
External requirements
Regulations (legal)
Guidelines and standards
(technical)
Minimum standards
General
Description and definition
Requirements arising of the building project
from design Structure of the building project
Existing planning Work limitations
Use
Functional tender
Financial requirements specification with Local conditions
Costs and prices program of work Shape and position of the plot
Operating and maintenance costs Climate
Warranty periods Soil
Profit from use Other environmental
influences
Ecological requirements
Environmental soundness Function-related
Energy concept requirements
Design requirements Recycling
Form and shape Nature of use
Appearance Nature and purpose of work
Aesthetic quality, colour Performance (performance data and
and surface structure operating energy)
Dimension tolerances Dimension tolerances
Dimensioning Flexibility and possible interchange
Privacy Technical requirements Functioning, nature of business
Comfort Statics Serviceability
Convenience Fire prevention Safety precautions
Effects of gas or air Durability
Damp protection
Heat and cold insulation
Light
Sound insulation
Electricity
Other information not contained in the program of services is Other information for
important for a functional tender specification over and above the a functional tender
specification
requirements that have already been mentioned. It includes details of
legal and technical regulations, a rough description of the building,
from which it should be possible to discover the local conditions for the
project, and establish which works do not have to be included in the
tender bid.
63
Requirements must be clearly presented in the program of works.
The presentation can be in the form of continuous prose, lists or tables.
This largely depends on the way the program of works is broken down. If
the program runs from the building as a whole to the individual room, a
table of requirements can be systematized as follows:
64
Tender specification with list of work
Lot 2
The principle behind the tender specification is that it aims to make Tender specification
a direct enquiry about prices for the smallest descriptive elements, item and unit price
contract
by item. Bidders should provide unit prices for the items, which are de-
scribed precisely by nature, quantity and quality. ◯
65
Drawing up If a description of the work required is needed with a tender specifi-
a tender cation, the information has to be systematically converted from the plans
specification
into individual subjobs arranged by trade, as plans are, by their very
nature, structured according to construction components.
The next step is to record more detail about the individual subjobs.
Here we recommend that the relevant standards, guidelines and regu
lations are summed up, to provide a frame of reference for describing
◼ Tip: A useful instrument for compiling a tender speci- ◯ Note: Information about professional execution of
fication with list of works is a room book detailing building work can be found in the trading standards.
furnishings and fittings. This gives the number of rooms These standards also contain information about classi-
with a detailed description, as well as information fying the work, the building materials and construction
about areas. Certain jobs can thus be recorded quickly components used, the units to be used as a basis, the
and systematically in terms of quality and quantity for appropriate subjobs, and for invoicing and drawing up
further description in the tender specification. the tender specification (see Appendix).
66
each subjob in detail in terms of a sound, expert source of information
about building materials, construction components for listing the works ◯
required.
The tender specification for all jobs can be drawn up stage by stage
on this basis.
Lot
The lot is a complete award unit allocated to a company. Lots are to
be seen as independent subprojects that can be defined equally on the
basis of criteria relating to spaces (part lot) or to expert services (spe-
cialist lot, trade).
Subdivision into lots by area usually only takes place for large build- Part lot
ing projects, and would allow for dividing a road-building project up into
several phases or street construction contract sections. If the client per-
haps intends to commission only part of the building work and allocate
subsequent work to other firms, he or she must draw up appropriate lots.
If the client is awarding the contract by breaking down trades, the Specialist lot
term specialist lot is used. > Chapter Structuring an invitation to tender A trade can
be split up into several specialist lots. For example, one metalworker can
be commissioned to make railings and another to work on the facade. ◯
67
of speciality or physical area provides a suitable basis for establishing
prices by placing an item within the overall context.
Subtitle Individual titles can be further broken down by the use of subtitles.
For example, the reinforced concrete work required for a particular job
can be summed up under a title, and the formwork and reinforcing
material it requires in subtitles.
68
– Earthworks – Plastering and stucco
– Drilling – Ventilated curtain facades
– Preparatory work – Tiling and slab installation
– Ramming, sieving, compressing – Screed work
– Waterpipes – Poured asphalt work
– Sewerage drains – Joinery
– Draining – Parquet work
– Spray concrete – Metal fittings
– Road and path construction – Blinds
– Landscaping – Metalwork
– Injection spraying – Glazing
– Underground cabling – Painting, varnishing, coating
– Rail construction work – Corrosion prevention for steel
– Masonry – Floor coverings
– Concreting – Wallpapering
– Natural stonework – Timber flooring
– Artificial stonework – Ventilation installations
– Carpentry and woodwork – Heating and central water-heating facilities
– Steel construction – Gas, water and drainage facilities
– Sealing – Low- and medium-frequency equipment
– Roof covering and roof sealing – Lightning protection
– Plumbing – Conveyor systems, lifts, escalators
– Dry construction work – Building automation
– Composite heat insulation systems – Scaffolding
– Concrete
Fig. 39: Listmaintenance
of different trades – Demolition and dismantling
expert fields depends on the size and complexity of the individual build-
ing project and the nature of the contract relating to it. Figure 39 shows
possibilities of breakdown that are already available on the basis of spe-
cialist allocation of individual services.
Items
A single item within a tender specification is the smallest tender unit
and represents a subjob within the building work. It is made up of
individual descriptive elements defining the work to be done and the par-
ticular service required clearly and unambiguously. The descriptive ele-
ments can be formulated as required or put together from standard
catalogues.
69
No. Text Item Quantity Unit UP TP
01.02.02.0001 … Formwork Floor slab … 50 m
Components of Against this backdrop we recommend describing all the items sys-
a tender item tematically in a tender specification. In this context, the typical com
ponents of a tender item are grouped within the following categories:
—— No. number
—— Text descriptive text (short and long text)
—— ITy item type
—— Quantity the quantity worked out from the plans in terms of UQ
—— UQ unit of quantity
—— UP unit price (price for a unit)
—— TP total price per item (unit price × planned quantity)
Number The number helps to make it easier to find one’s way around a ten-
der specification. Each piece of work (subjob) in the same category in
terms of techniques and pricing is identified by a particular number
according to a defined breakdown key. This number relates directly to
the way in which the project is broken down, and reflects this in the ten-
der specification. In a relatively simple project a subjob can be identified
by number as follows.
Index The index can be used to show the relationship between a basic and
an alternative item in the numbered list.
Tender specification The tender specification text should be drawn up in long and short
text form by the planner inviting tenders.
70
01.02.01.0001 Activity 1 of title 1 in trade 2 des Loses 1
01.02.01.0002 Activity 2 of title 1 in trade 2 des Loses 1
01.02.01.0003 Activity 3 of title 1 in trade 2 des Loses 1
The short text is used essentially as a short textual summary of the Short text
service required for further use in drawing up the bid and raising the in-
voice. The short form must not lead to possible confusion between items,
each item should be identified unambiguously: “masonry 36.5 cm, cellar,”
“masonry 36.5 cm ground floor,” “masonry 17.5 cm ground floor” etc.
In contrast, the long text should describe the work required unam- Long text
biguously and exhaustively, so that all the bidders understand exactly the
same thing.
In principle, texts can be freely formulated, taking legal and tech Freely formulated or
nical regulations into consideration. But to simplify this process, plan- standard texts
ners can make use of standardized sample texts, which are generally
available.
Such standard works catalogues are collections of texts that can be Standard texts
used to described work required or subcategories of it. These are struc-
tured according to predefined patterns and contain a range of infor
mation about building work, building materials, dimensions and units of
quantity for various works. ◼
71
◼ Tip: Standardized texts are available in most coun-
tries to reduce the amount of effort needed when
drawing up tender specifications. They are arranged by
trade and constructed as modules: the descriptive text
for a required service is compiled in sequence using a
system containing several steps, with information on
building type, realization type, realization quality, struc-
tural component, type of material, quality of material
and dimensions, and possibly on the conditions of
realization as well. There is however no guarantee of
the technical correctness of the texts, as in principle
it is possible to arrive at combinations that would not
make sense.
72
Fig. 42: Biased manufacturer’s description
Formulating the text freely requires a high level of expert knowledge Freely formulated
of the work to be described. This approach is also used to distinguish texts
73
Systematization The following scheme systematizes the textual description of work,
and can be applied to any subsection of the work in this form. Modular
standard texts are based on similar patterns.
Supplementary It would also be possible to place other information about the pur-
information pose of the work on hints on invoicing or realization techniques in the de-
scriptive text. For example, if a building is to be in reinforced concrete,
the building method is directly influenced by the requirement to use pre-
fabricated elements. Equally, legal requirements can form part of a ten-
der specification, for example if material removed is to become the con-
◯ tractor’s property when the work in completed.
● Example:
Building method: masonry according to the This subservice can be further explained by comple-
standard xxxx menting the above description with information on
quality relating to the structural element (e.g. finished
Structural element: for the interior wall in section
as exposed masonry on both sides) or the building
EG XX/YY
material (e.g. salt-water-resistant finish) or on the
Building material: with calcareous sandstone building method (e.g. build with prefabricated wall
blocks yyy standard elements).
74
unambiguously the way they fit together. This means that the bidding firm
can check the completeness of the service description, and it is easier
to estimate the assembly time required.
Different types of works positions can be used in a tender specifica- Item type (ITy)
tion. Planners identify a particular item appropriately in the “Item type
(ITy) column.”
Standard items are always realized. Bidders will provide a unit price Standard item
and a total price for these in the tender specification.
◯ Note: If identical descriptions occur in different plasterboard stud wall as in preliminary note type A).
items, there are two ways of avoiding unnecessary rep- Preliminary remarks always relate to particular pieces
etitions. Planners can describe the work in full in one of work and are used exclusively in the context of
item and then refer back to this in subsequent items tender specifications listing the works in full. Funda-
(e.g. plasterboard stud wall, finish as in previous item, mentally they are the same as texts with lists of works
but with double boarding). If identical descriptions and should therefore match them in terms of content.
apply to a number of items, planners can sum them up There is no conflict with general or special contract
and identify them in their preliminary notes (e.g. finish conditions.
75
No. Text Item Quantity Unit UP TP
01.02.02.0001 ... Textile floor covering ... BI 30 m2
01.02.02.0001a ... Parkett ... AI 30 m2
Contingency items Contingency items make it possible for planners to test the market
◯ in relation to services they may wish to use additionally.
Basic and Basic items are items that are fixed for realization. Enquiries can also
alternative items be made about alternative items. Thus, a basic item is considered to be
a component of this service to be carried out, and must be provided with
a unit and a total price.
◯ Note: Contingency items should be used only for ◼ Tip: Contingency items are often not checked care-
subsidiary works that are not essential to the overall fully enough when examining the bid, as they are not
success of the building project. It would make sense included in the bid total. This can lead to accepting
to use contingency items if certain items have not been inflated unit prices that have to be kept to when order-
fixed before building starts because of insufficient ing the realization of contingency items.
information about the soil conditions on the building
site.
76
No. Text Item Quantity Unit UP TP
01.02.02.0001 ... Excavation soil class 3–5 ... 1000 m2
01.02.02.0001a ... Excavation soil class 6 ... SI 200 m2
Supplementary items are a different item type. They identify poten- Supplementary item
tial impediments or additional work needed in relation to a standard item.
Bidders provide a unit price and a total price for supplementary items in
the tender specification. The corresponding standard item then covers
something like a basic finish for the item, and the supplementary item
describes a higher standard or a special installation situation. The price
for a supplementary item is calculated from the difference between the
price for a higher standard and the basic finish. ●
The first variant shows the rendering in two standard items, sepa-
rated for the high and the low building. The other provides a tender spec-
ification with a standard item for the whole building project and a
supplement for the higher areas, for which scaffolding costs may have
to be quoted. The second variant has the advantage that a bid will not be
made for the ground floor of the high-rise building at a higher price be-
cause of additional scaffolding costs. ◼
◯ Note: An alternative item offers the possibility for ● Example: The example in Figure 44 clarifies the prin-
contractors to propose their own solution for imple- ciple behind a supplementary item. The work described
menting a basic item (e.g. “Masonry to be produced in item 01.02.02.0001 covers excavating 1000 m3 of
according to previous item, but realized according to soil in classes 3–5. The appropriate supplementary
the bidder’s choice.”) A description of the proposed item enquires about the price if the problem arises
f inish must be appended. from “excavating class 6 soil” to the extent of 200 m3.
Thus the price contains only the proportion (supple-
mentary price) for dealing with the problem, and does
not represent a price in its own right for excavating
class 6 soil. Hence the areas (200 m2) are already
included in the standard item.
77
A. B.
Quantity Quantities can be expressed in various units. But the unit of quan-
and units of quantity tity (UQ) should always relate meaningfully to a particular subservice.
Thus, it is possible to calculate reinforcement in cubic meters (m3),
although this is a disadvantage in terms of the form reinforcement bars
will take and the industry standard of calculating in tones to determine
prices. Sensible units are tones, or where applicable square meters (m2)
◯ for steel mats and meters for steel bars.
The unit of quantity fixed for an item forms the basis for quantity
s urveying and is the reference value for bidders when fixing prices for
subsections of the work.
◼ Tip: Supplementary items often differ only very ◯ Note: The general and special requirements contain
slightly from the corresponding standard positions. In guidelines for the use of units of quantity. For example,
such cases the descriptive text can be reduced to the wall areas are calculated by area (m2) for rendering
essential changes, there is no need to repeat textual work and soffits by length (m).
elements that remain unchanged. It is sufficient to
write “supplement to item xxx for double boarding.”
78
Lengths
(e.g. length of a wall)
Areas
(e.g. area of a wall) = length × height
Areas × 2
×2 (e.g. forming area or rendering on both sides)
Volume
(e.g. quantity of concrete for a wall)
= area × thickness
Tonnage
(e.g. reinforcement quantity for a wall)
= volume × proportion of steel
The unit price (UP) is calculated by unit quantity by the bidder on the Unit price (UP)
basis of the description of the subservice and built into the tender spec-
ification. As a rule the unit price is fixed and usually forms the basis for
later invoicing for the work. Unit prices are changed only if quantities vary
considerably or content deviates from the work as described.
79
Total price (TP) The total price is arrived at primarily from the product of unit price
and preliminary estimate (planned quantity). Bidders should work it out
for all items basic and supplementary items intended for realization and
include it in the tender specification in the appropriate place. The sum of
all the intermediate totals for a building project is the net final tender
price. Adding VAT at the statutory rate gives the gross price the bidder is
offering for the commission to provide the services described in the var-
ious lists. Total prices are not stated for alternative and contingent items,
as it is not clear at the point the bid is being made whether these items
will be realized or not.
Subservices are invoiced on the basis of the total prices for the indi-
vidual items and the quantities actually realized.
80
In conclusion
Tendering is not usually one of the activities planners find themselves
looking forward to with particular glee. This is understandable, as the
charms of a beautiful design, a magnificent view and even carefully
planned details seem incomparably greater. The large proportion of text
alone often detracts from the allure of the tendering process.
But planners who take the trouble to tender carefully for the ideas in
a design will gain some very sound insights into their own planning and
the necessary sequences of events needed to realize it.
81
Appendix
Literatur
Bert Bielefeld, Lars-Philip Rusch: Building projects in China, Birkhäuser
Verlag, Basel 2006
Bert Bielefeld, Falk Würfele: Building projects in the European Union,
Birkhäuser Verlag, Basel 2005
Chartered Institute of Building (ed.): Planning and Programming in
Construction, Chartered Institute of Building, London 1991
CIRIA: The Environmental Handbooks for Building and Civil Engineering:
Vol 1. Design and Specification, Thomas Telford Ltd, 1994
Sandra Christensen Weber: Scheduling Construction Projects.
Principles and Practices, Pearson Prentice Hall, Upper Saddle
River, NJ, 2005
Institution of Civil Engineers, Association of Consulting Engineers and
Civil Engineering Contractors Association: Tendering for Civil
Engineering Contracts, Thomas Telford Ltd, 2000
Richard H. Neale, David E. Neale: Construction Planning, Telford,
London 1989
Jay S. Newitt: Construction Scheduling. Principles and Practices,
Pearson Prentice Hall, Upper Saddle River, NJ, 2009
82
Sample international contracts
In addition to the above-mentioned sources, there are a number of national and international
associations and institutions that offer leaflets, examples of additional technical contractual
terms, as well as sample tender texts for certain items of work. Sample tender texts that can be
used by all types of contractors can be found on the following Internet sites:
Internet sites
http://publications.europa.eu
http://www.neccontract.co.uk
http://www.fidic.org
Tendering portal
http://ted.europa.eu
83
Picture credits
Figure 6 left: aboutpixel.de
Figure 6 center right: PixelQuelle.de
Figure 7: PixelQuelle.de
Figure 8: PixelQuelle.de
Figure 10 centre left: aboutpixel.de
Figure 10 right: aboutpixel.de
All other figures: The authors
the Authors
Tim Brandt, Dipl. Ing., is a civil engineer in Dortmund, specializing in
contract and change management; he also works in site and
project direction.
Sebastian Th. Franssen, Dipl. Ing. Architect, is proprietor of an
architectural practice in Dortmund, specializing in managing
private and public building projects.
84
Also available from Birkhäuser:
Design
Basics Design and Living Basics Modelbuilding
Jan Krebs Alexander Schilling
ISBN 978-3-7643-7647-5 ISBN 978-3-0346-1331-6