0% found this document useful (0 votes)
88 views48 pages

Ecs 2015

Uploaded by

OYAESPETAH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views48 pages

Ecs 2015

Uploaded by

OYAESPETAH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 48

Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only. No further reproduction or networking is permitted.

d. Distributed by Thomson Reuters (Scientific) LLC, www.tech


ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
ANSI/NETA ECS-2015

STANDARD FOR
ELECTRICAL COMMISSIONING
SPECIFICATIONS for Electrical Power Equipment
and Systems

No further reproduction or networking is permitted.


Secretariat
NETA (InterNational Electrical Testing Association)

Distributed by Thomson Reuters (Scientific) LLC, www.tech


Approved by
American National Standards Institute
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
Approval of an American National Standard requires verification by
American ANSI that the requirements for due process, consensus, and other
criteria for approval have been met by the standards developer.
National Consensus is established when, in the judgment of the ANSI Board of
Standard Standards Review, substantial agreement has been reached by directly
and materially affected interests. Substantial agreement means much
more than a simple majority, but not necessarily unanimity. Consensus
requires that all views and objections be considered, and that a concerted
effort be made toward their resolution.

The use of American National Standards is completely voluntary; their


existence does not in any respect preclude anyone, whether he has
approved the standards or not, from manufacturing, marketing,
purchasing, or using products, processes, or procedures not conforming
to the standards.

The American National Standards Institute does not develop standards


and will in no circumstances give an interpretation of any American
National Standard in the name of the American National Standards
Institute. Requests for interpretations should be addressed to the
secretariat or sponsor whose name appears on the title page of this

No further reproduction or networking is permitted.


standard.

Caution Notice: This American National Standard may be revised or


withdrawn at any time. The procedures of the American National
Standards Institute require that action be taken periodically to reaffirm,
revise, or withdraw this standard. Purchasers of American National
Standards may receive current information on all standards by calling or
writing the American National Standards Institute.

Published by Copyright© 2015

Distributed by Thomson Reuters (Scientific) LLC, www.tech


InterNational Electrical Testing Association InterNational Electrical Testing Association
3050 Old Centre Ave., Suite 102 All rights reserved
Portage, MI 49024 Printed in the United States of America
269.488.6382· FAX 269.488.6383
www.netaworld.org No part of this publication may be reproduced in any form, in an
electronic retrieval system or otherwise, without the prior written
[email protected] permission of the publisher.
Jayne Tanz, CMP - Executive Director

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
Copyright Information and
Alteration of Content

2015 ANSI/NETA ECS Standard for Electrical Commissioning Specifications for Electrical
Power Equipment and Systems is protected under the copyright laws of the United States, and
all rights are reserved. Further, the ANSI/NETA ECS may not be copied, modified, sold, or
used except in accordance with such laws and as follows:

Purchasers may reproduce and use all or a portion of the 2015 ANSI/NETA ECS Standard
for Electrical Commissioning Specifications for Electrical Power Equipment and Systems
provided 2015 ANSI/NETA ECS Standard for Electrical Commissioning Specifications for
Electrical Power Equipment and Systems is clearly identified in writing as the source of all
such uses or reproductions.

No further reproduction or networking is permitted.


2015 ANSI/NETA ECS Standard for Electrical Commissioning Specifications for Electrical
Power Equipment and Systems may be reproduced and used in whole or in part for the
purpose of creating project specifications, basis of design documentation, maintenance plans,
or other similar uses that purport to require compliance with the contents of this document.

The following sections of the 2015 ANSI/NETA ECS Standard for Electrical Commissioning
Specifications for Electrical Power Equipment and Systems must be incorporated by
reference as part of any subsection:

3. Qualifications
4. Division of Responsibility
5. General

The user of this document is required to include the above sections with any other section(s)
reproduced from this document.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


© Copyright 2015
InterNational Electrical Testing Association
3050 Old Centre Ave., Suite 102
Portage, MI 49024
Voice: 888.300.6382 Facsimile: 269.488.6383
E-mail: [email protected] • Web: www.netaworld.org

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
Standards Review Council

The following persons were members of the NETA Standards Review Council which approved this
document.

Timothy J. Cotter
Lorne J. Gara
Roderic L. Hageman
David Huffman
Ralph Patterson
Alan D. Peterson
Jayne Tanz
Ron Widup

Electrical Commissioning Specifications Ballot Pool Members


The following persons were members of the Ballot Pool which balloted on this document for submission
to the NETA Standards Review Council.

No further reproduction or networking is permitted.


Ken Bassett John Hauck Randall Sagan
Tom Bishop Kerry Heid Mark Siira
Scott Blizard Andrew Kobler Jeremy Smith
Brian Borst Korey Kruse Richard Sobhraj
Michael Bowers Ben Lanz Alan Turpen
John Cadick Mark Lautenschlager Wally Vahlstrom
Michel Castonguay Finley Ledbetter, III Vicki Warren
Tim Crnko Jerry Parnell Chris Werstiuck
David Geary Lee Perry John White
Paul Hartman Tony Perry Jean-Pierre Wolff
Mose Ramieh

Distributed by Thomson Reuters (Scientific) LLC, www.tech

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
NOTICE
In no event shall the InterNational Electrical Testing Association be liable to anyone for special,
collateral, incidental, or consequential damages in connection with or arising out of the use of these
materials.

This document is subject to periodic review, and users are cautioned to obtain the latest edition.
Comments and suggestions are invited from all users for consideration by the Association in connection
with such review. Any such suggestions will be fully reviewed by the Association after giving the
commenter, upon request, a reasonable opportunity to be heard.

This document should not be confused with federal, state, or municipal specifications or regulations,
insurance requirements, or national safety codes. While the Association recommends reference to or use
of this document by government agencies and others, use of this document is purely voluntary and not
binding.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

InterNational Electrical Testing Association


3050 Old Centre Ave., Suite 102 • Portage, MI 49024
Voice: 888.300.6382 Facsimile: 269.488.6383
Email: [email protected] • Web: www.netaworld.org
Jayne Tanz, CMP - Executive Director

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
FOREWORD
(This Foreword is not part of American National Standard ANSI/NETA ECS-2015)

The InterNational Electrical Testing Association (NETA) was formed in 1972 to establish uniform
testing procedures for electrical equipment and systems. NETA has been an Accredited Standards
Developer for the American National Standards Institute since 1996. NETA’s scope of standards activity
is different from that of IEEE, NECA, NEMA, and UL. In matters of testing electrical equipment and
systems NETA continues to reference other standards developers’ documents where applicable. NETA’s
review and updating of presently published standards takes into account both national and international
standards. NETA’s standards may be used internationally as well as in the United States. NETA firmly
endorses a global standardization. IEC standards as well as American consensus standards are taken into
consideration by NETA’s ballot pools and reviewing committees.

The 2015 ANSI/NETA Standard for Electrical Commissioning Specifications for Electrical Power
Equipment and Systems is the first edition and most current revision of this document, and was approved
as an American National Standard on December 3, 2014.

The ANSI/NETA Standard for Electrical Commissioning Specifications for Electrical Power Equipment
and Systems should be used in conjunction with the most recent edition of ANSI/NETA Standard for
Acceptance Testing Specifications for Electrical Power Equipment and Systems. Together, these
standards provide the necessary specifications to test and commission electrical power equipment and
systems. Furthermore, the NETA standards should be used together with other commissioning
documents to expand the scope to include all of the applicable systems. Other systems may include

No further reproduction or networking is permitted.


mechanical, instrumentation, heating and refrigeration, and building systems.

The ANSI/NETA Standard for Electrical Commissioning Specifications for Electrical Power Equipment
and Systems was developed for use by those responsible for testing and commissioning newly installed
or retrofitted electrical power systems and equipment to guide them in specifying and performing the
necessary inspections, tests, measurements, and system performance verifications to commission an
electrical power system infrastructure. This document aids in ensuring safe, reliable operation of the
electrical power equipment and systems. It is essential to commission newly installed and retrofitted
electrical power equipment and systems. Additionally, acceptance testing of the equipment provides the
baseline test results for maintenance programs and equipment trending, while commissioning verifies
the electrical equipment and system meets the owner’s project requirements and basis of design.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
PREFACE
(This Preface is not part of American National Standard ANSI/NETA ECS-2015)

It is recognized by the Association that the tem "commissioning: is not well defined in the industry.
Although there are documents that exist in reference to commissioning, no standards exist that
specifically address commissioning electrical power systems. It is the intent of this document to better
define and specifically address the critical elements and requirements necessary in the commissioning of
low-, medium-, and high-voltage electrical power systems.

The ANSI/NETA ECS Standard for Electrical Commissioning Specifications for Electrical Power
Equipment and Systems is intended for use in all industries, whether it is a data center, a utility
substation, and industrial facility, or any location that requires a comprehensive electrical power system
commissioning process.

Suggestions for improvement of this standard are welcome. They should be sent to the InterNational
Electrical Testing Association, 3050 Old Centre Avenue, Suite 102, Portage, MI 49024.

To help the user better understand and navigate more efficiently through this document, the following
information is offered:

Notation of Changes
Since the 2015 edition of the ANSI/NETA ECS is the first of its kind, there are no changes noted in this

No further reproduction or networking is permitted.


document.

Document Structure
The ANSI/NETA ECS is divided into twelve separate and defined sections.

Section 1 General Scope


Section 2 Applicable References
Section 3 Qualifications
Section 4 Division of Responsibility
Section 5 General
Section 6 Commissioning Process
Section 7 Inspection and Commissioning Procedures
Section 8 Prime, Emergency, and Standby Power Systems (reserved)
Section 9 Thermographic Survey
Section 10 Transfer to Owner/Operator
Appendices Various Informational Documents

Distributed by Thomson Reuters (Scientific) LLC, www.tech


Section 7 Structure
Section 7 is the main body of the document with specific information on what to do relative to the
inspection and commissioning of electrical power equipment and systems. It is not intended that this
document explain how to test specific pieces of equipment or systems, but rather, to detail the required
steps and procedures for comprehensive commissioning of electrical power systems at a given voltage
class.

Section 7 is divided into three subsections (7.1, Low-; 7.2, Medium-; and 7.3, High- and Extra-High
Voltage Systems), which are in turn divided again into three subsections (A. Pre-Energization, B.
Energization, and C. Post Energization).

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
PREFACE (Continued)
If/When Applicable
The phrases "if applicable", "when applicable", and any variation thereof do not occur in this standard.
This standard assumes that if devices or pieces of equipment are not present, they will not be subject to
testing or verification.

Manufacturer's Instruction Manuals


It is important to follow the recommendations contained in the manufacturer's published data. Many of
the details of a complete and effective testing and commissioning procedure can be obtained from this
source.

Summary
The guidance of an experienced commissioning professional should be sought to develop a
commissioning plan and lead the commissioning team. It is necessary to make an informed judgment for
each particular system regarding how extensive a procedure is justified and required. The approach
taken in these specifications is to present a comprehensive series of inspections, tests, and verifications
applicable to most electrical systems. It is likely that in smaller electrical systems some of the
inspections, tests, and verifications can be omitted.

Likewise, guidance of an experienced commissioning professional should also be sought when making
decisions concerning the results of test data and performance results and their significance to the overall
analysis of the device or system under test. Careful consideration of all aspects of test data, including

No further reproduction or networking is permitted.


manufacturer’s published data and recommendations, must be included in the overall assessment of the
equipment or systems being commissioned.

The Association encourages comment from users of this document. Please contact the NETA office or
your local NETA Accredited Company.

Standards Review Council


InterNational Electrical Testing Association

Timothy J. Cotter
Lorne Gara
Diane W. Hageman
Roderic L. Hageman
David Huffman
Ralph Patterson
Alan D. Peterson

Distributed by Thomson Reuters (Scientific) LLC, www.tech


Jayne Tanz
Ron Widup

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
CONTENTS

1. GENERAL SCOPE .................................................................................................................. 1


2. APPLICABLE REFERENCES ................................................................................................ 2
2.1 Codes, Standards, and Specifications ..................................................................... 2
2.2 Other Publications ................................................................................................... 3
2.3 Contact Information ................................................................................................ 3
3. QUALIFICATIONS ................................................................................................................. 5
3.1 Commissioning Organization ................................................................................. 5
3.2 Commissioning Personnel ...................................................................................... 5
4. DIVISION OF RESPONSIBILITY .......................................................................................... 6
4.1 The Owner’s Representative ................................................................................... 6
4.2 The Commissioning Organization .......................................................................... 6
5. GENERAL ................................................................................................................................ 7
5.1 Safety and Precautions ............................................................................................ 7
5.2 Suitability of Test Equipment ................................................................................. 7
5.3 Test Instrument Calibration .................................................................................... 8
5.4 Documentation ........................................................................................................ 9
6. COMMISSIONING PROCESS................................................................................................ 10
6.1 Commissioning Intent ............................................................................................. 10
6.2 Owner’s Project Requirements ............................................................................... 10
6.3 Basis of Design ....................................................................................................... 10

No further reproduction or networking is permitted.


6.4 Commissioning Plan ............................................................................................... 10
7. INSPECTION AND COMMISSIONING PROCEDURES ..................................................... 13
7.1 Low-Voltage Systems (< 1 kV) .............................................................................. 13
7.2 Medium Voltage Systems (> 1 kV and < 100 kV) ................................................. 17
7.3 High-Voltage and Extra-High Voltage Systems (> 100 kV and < 1,000 kV) ........ 21
8. PRIME, EMERGENCY, AND STANDBY POWER SYSTEMS - RESERVED ................... 25
9. THERMOGRAPHIC SURVEY ............................................................................................... 26
9.1 Visual and Mechanical Inspection .......................................................................... 26
9.2 Report...................................................................................................................... 26
9.3 Test Parameters ....................................................................................................... 26
9.4 Test Results ............................................................................................................. 26
10. TRANSFER TO OWNER/OPERATOR .................................................................................. 27

APPENDICES
Appendix A – Definitions ..................................................................................................................... 28
Appendix B – Acronyms ......................................................................................................................

Distributed by Thomson Reuters (Scientific) LLC, www.tech


31
Appendix C – About the InterNational Electrical Testing Association ................................................ 33
Appendix D – Form for Comments ...................................................................................................... 35
Appendix E – Form for Proposals ........................................................................................................ 36

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only. No further reproduction or networking is permitted. Distributed by Thomson Reuters (Scientific) LLC, www.tech
– This page intentionally left blank –

ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
1. GENERAL SCOPE

1.1 Electrical Commissioning Specifications


1. These specifications describe the systematic process of documenting, and placing into
service newly–installed, or retrofitted electrical power equipment and systems. This
document shall be used in conjunction with the most recent edition of the ANSI/NETA
Standard for Acceptance Testing Specifications for Electrical Power Equipment and
Systems (ANSI/NETA ATS). The individual electrical components shall be subjected to
factory and field tests, as required, to validate the individual components.

2. The purpose of these specifications is to assure that tested electrical systems are safe,
reliable, and operational, are in conformance with applicable standards and manufacturers’
tolerances, and are installed in accordance with design specifications.

3. The work specified in these specifications may involve hazardous voltages, materials,
operations, and equipment. These specifications do not purport to address all of the safety
issues associated with their use. It is the responsibility of the user to review all applicable
regulatory requirements prior to the use of these specifications.

4. These specifications are specifically intended for application on electrical power equipment
and systems. It is not the intent of these specifications to provide comprehensive details on
the commissioning of mechanical equipment, mechanical instrumentation systems, and
related components.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 1
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
2. APPLICABLE REFERENCES

2.1 Codes, Standards, and Specifications


All inspections and field tests shall be in accordance with the latest edition of the following codes,
standards, and specifications except as provided otherwise herein.

1. ASHRAE Guideline 0, The Commissioning Process

2. ASHRAE Guideline 1.1, HVAC&R Technical Requirements for the Commissioning Process

3. ASHRAE 202-2013 Commissioning Process for Buildings and Systems

4. InterNational Electrical Testing Association – NETA

ANSI/NETA ETT Standard for Certification of Electrical Testing Technicians

ANSI/NETA ATS Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems

5. NECA 090-2004, Commissioning Building Electrical Systems

6. NFPA 70E, Standard for Electrical Safety in the Workplace

No further reproduction or networking is permitted.


7. Occupational Safety and Health Act 29 CFR Part 1910

8. Occupational Safety and Health Act 29 CFR Part 1926

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 2
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
2. APPLICABLE REFERENCES

2.2 Other Publications


GSA Public Buildings Service, Building Commissioning Guide

2.3 Contact Information


American Society of Heating, Refrigeration, and Air-Conditioning Engineers – ASHRAE
1791 Tullie Circle, NE
Atlanta, GA 30329
(800) 527-4723
ashrae.org

Federal Energy Regulatory Commission – FERC


88 First Street, NE
Washington, DC 20426
(866) 208-3372
ferc.gov

GSA Public Buildings Service


(202) 501-1100
gsa.gov/pbs

No further reproduction or networking is permitted.


Institute of Electrical and Electronic Engineers – IEEE
3 Park Avenue, 17th Floor
New York, NY 10016-5997
(212) 419-7900
ieee.org

InterNational Electrical Testing Association – NETA


3050 Old Centre Ave. Suite 102
Portage, MI 49024
(269) 488-6382 or (888) 300-NETA (6382)
netaworld.org

National Electrical Contractors Association – NECA


3 Bethesda Metro Centre, Suite 1100
Bethesda, MD 20814

Distributed by Thomson Reuters (Scientific) LLC, www.tech


(301) 657-3110
necanet.org

National Fire Prevention Association – NFPA


1 Battery March Park
P.O. Box 901
Quincy, MA 02269-9101
(617) 984-7247
nfpa.org

Page 3
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
2. APPLICABLE REFERENCES

2.3 Contact Information (continued)


North American Electric Reliability Corporation – NERC
1325 G. Street NW, Suite 600
Washington, DC 20005-3801
(202) 400-3000
nerc.com

National Institute of Standards and Technology – NIST


100 Bureau Drive
Gaithersburg, SD 20899
(301) 975-6478
nist.gov

Occupational Safety and Health Administration – OSHA


U.S. Department of Labor
Occupational Safety and Health Administration
Office of Public Affairs – Room N3647
200 Constitution Avenue
Washington, D.C. 20210
(202) 693-1999

No further reproduction or networking is permitted.


osha.gov

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 4
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
3. QUALIFICATIONS

3.1 Commissioning Organization


1. The commissioning organization shall be an independent, third-party entity which can
function as an unbiased authority, professionally independent of the manufacturers,
suppliers, and installers of equipment or systems being evaluated.

2. The commissioning organization shall be regularly engaged in the commissioning of


electrical equipment, devices, installations, and systems.

3. The commissioning organization shall use personnel who are regularly employed for
electrical commissioning services.

4. The commissioning organization shall submit appropriate documentation to demonstrate


that it satisfactorily complies with these requirements.

3.2 Commissioning Personnel


Personnel performing these commissioning activities shall be trained and experienced
concerning the apparatus and systems being evaluated. These individuals shall be capable
of conducting the tests in a safe manner and with complete knowledge of the hazards
involved. They must evaluate the test data and make a judgment on the serviceability of
the specific equipment.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 5
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
4. DIVISION OF RESPONSIBILITY

4.1 The Owner’s Representative


The owner’s representative shall provide the commissioning organization with the following:

1. A short-circuit analysis, a coordination study, an arc-flash hazard analysis, and a protective


device setting sheet as described in ANSI/NETA ATS, Section 6.

2. Most recent version of the electronic setting files for intelligent electronic devices and relay
logic diagrams.

3. Complete set of as built electrical plans and specifications.

4. Drawings and instruction manuals applicable to the scope of work.

5. The factory and field acceptance test reports.

6. Notification of when equipment becomes available for commissioning work. Work shall be
coordinated to expedite project scheduling.

7. Project schedule.

8. Site-specific hazard notification and safety training.

No further reproduction or networking is permitted.


9. Owner’s project requirements (OPR).

10. Basis of design (BOD) document.

11. Designated representative(s) for the project commissioning activities.

4.2 The Commissioning Organization


The commissioning organization shall provide the following:

1. All necessary services and technical expertise to conduct electrical commissioning.

2. Notification to the designated representative(s) prior to the commencement of any electrical


commissioning activity.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


3. Timely notification of deficiencies based on the results of the commissioning activities.

4. Written record of all electrical commissioning activities and a final report.

Page 6
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
5. GENERAL

5.1 Safety and Precautions


All parties involved must be cognizant of industry-standard safety procedures. This document
does not include any procedures, including specific safety procedures. It is recognized that an
overwhelming majority of the activities recommended in these specifications are potentially
hazardous. Individuals conducting these activities shall be capable of conducting them in a safe
manner and with complete knowledge of the hazards involved.

1. Safety practices shall include, but are not limited to, the following requirements:

1. All applicable provisions of the Occupational Safety and Health Act, particularly
OSHA 29CFR 1910 and 29 CFR Part 1926.

2. ANSI/NFPA 70E, Standard for Electrical Safety in the Workplace

3. Applicable state and local safety operating procedures.

4. Owner’s safety practices.

2. The commissioning organization shall have a designated safety lead person on site to
supervise operations with respect to safety.

No further reproduction or networking is permitted.


3. A job hazard analysis and a safety briefing shall be conducted prior to the commencement
of work.

4. The commissioning organization shall have a designated safety representative on the project
to supervise operations with respect to safety. This individual may be the same person
described in 5.1.2.

5.2 Suitability of Test Equipment


1. All test equipment shall meet the requirements in Section 5.3 and be in good mechanical
and electrical condition.

2. Field test metering used to check power system meter calibration must be more accurate
than the instrument being tested.

3. Accuracy of metering in test equipment shall be appropriate for the test being performed.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 7
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
5. GENERAL

5.3 Test Instrument Calibration


1. The commissioning organization shall have a calibration program which assures that all
applicable test instruments are maintained within rated accuracy for each test instrument
calibrated.

2. The firm providing calibration service shall maintain up-to-date instrument calibration
instructions and procedures for each test instrument calibrated.

3. The accuracy shall be directly traceable to the National Institute of Standards and
Technology (NIST).

4. Instruments shall be calibrated in accordance with the following frequency schedule:

1. Field instruments: Analog and digital, 12 months maximum.

2. Laboratory instruments: 12 months maximum.

3. Leased specialty equipment: 12 months maximum.

5. Dated calibration labels shall be visible on all test equipment.

No further reproduction or networking is permitted.


6. Records, which show date and results of instruments calibrated or tested, must be kept up-
to-date.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 8
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
5. GENERAL

5.4 Documentation
The commissioning organization shall furnish a copy or copies of the complete documentation as
specified in the commissioning contract. The commissioning documentation shall include
the following:

1. Report

1. Summary of project.

2. Description of electrical system.

3. The final commissioning plan and the results of the implementation of that plan.

4. A copy of the commissioning design review records and logs and submittal review
logs.

5. A complete copy of the testing and performance test forms.

6. Identification of systems or assemblies that do not meet the owner’s project


requirements.

No further reproduction or networking is permitted.


7. Analysis and recommendations.

8. Resolution plan for incomplete tasks.

9. As-left relay logic diagrams and setting files.

2. Drawing packages

1. All applicable drawing packages shall be as-built.

2. A complete as-built drawing package shall be left on site and a duplicate as-built
package shall be submitted to the owner/operator.

3. O&M Manuals

Applicable equipment manuals and operational instructions shall be readily available for the
owner and operator.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 9
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
6. COMMISSIONING PROCESS

6.1 Commissioning Intent


1. Commissioning is the systematic process of verifying, documenting, and placing into
service newly-installed, or retrofitted electrical power equipment and systems.

2. Commissioning is critical for all new or retrofit installation projects to verify the correct
system operation to the design, thus contributing to the safe and reliable operation of the
system.

3. The commissioning process involves owner’s project requirements (OPR), basis of design
(BOD), factory acceptance tests, field acceptance tests, verification of the component
interconnections, and functional testing of the system in part and in whole.

4. Acceptance tests and commissioning work provides baseline results for routine maintenance
of the system and related components.

6.2 Owner’s Project Requirements


OPR are a written document that details the functional requirements of a project and the
expectations of how it will be used and operated. This includes project goals, measureable
performance criteria, cost considerations, benchmarks, success criteria, and supporting
information. (The terms project intent or design intent are used by some owners for their

No further reproduction or networking is permitted.


commissioning process owner’s project requirements.) (ASHRAE Guideline 0-2005)

6.3 Basis of Design


The BOD is a document that records the concepts, calculations, decisions, and product
selections used to meet the OPR and to satisfy applicable regulatory requirements,
standards, and guidelines. The document includes both narrative descriptions and lists of
individual items that support the design process. (ASHRAE Guideline 0-2005)

6.4 Commissioning Plan


1. A commissioning plan is a document that outlines the organization, schedule, allocation of
resources, and documentation requirements of the commissioning process.

2. The commissioning plan should be developed by the commissioning authority during the

Distributed by Thomson Reuters (Scientific) LLC, www.tech


design stage of the project. The commissioning plan should be updated and expanded
during the construction, acceptance testing, and functional testing phases of the project by
the commissioning team.

3. Parties involved in the execution of the commissioning plan shall work from the most up-
to-date version of the plan.

4. The commissioning plan should include the following information:

1. Overview of the commissioning stages and activities.

Page 10
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
6. COMMISSIONING PROCESS

6.4. Commissioning Plan (continued)


2. Roles and responsibilities for the commissioning team throughout the project.

3. Documentation of the general communication channels and project hierarchy.

4. Detailed schedule of the project, including design, construction, acceptance testing,


commissioning, and energization stages and milestones.

5. General description of commissioning activities that will occur during construction,


energization, and post-energization.

6. Commissioning checklists and test forms specific to the project.

7. A process for approval by the owner and operator to allow the equipment to be
energized.

8. A process for approval by the owner and turnover of the project and equipment from
the commissioning team to the owner.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 11
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only. No further reproduction or networking is permitted. Distributed by Thomson Reuters (Scientific) LLC, www.tech
– This page intentionally left blank –

ANSI/NETA ECS-2015
Page 12
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.1 Low-Voltage Systems (< 1 kV)


A. Pre-Energization

Prior to complete system energization, verify the following pre-energization tasks are complete:

1. Review owner’s project requirements (OPR), basis of design (BOD), project specifications,
and regulatory requirements for information specifically related to the commissioning of the
electrical system.

2. Applicable equipment manuals and operational instructions shall be readily available for the
commissioning team and owner.

3. Review factory and field acceptance test data, documentation, results, and deficiencies to
verify acceptable condition and suitability for initial energization and final acceptance.
Verify all equipment has been tested according to the most recent edition of the
ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems (ANSI/NETA ATS) and the project OPR.

4. Verify nameplate and equipment ratings are documented and correct in accordance with the
most current drawings.

No further reproduction or networking is permitted.


5. Review drawings, logic diagrams, protective device settings, engineering studies, and other
pertinent information to verify accuracy and completeness.

6. Visually inspect equipment.

7. Verify equipment is clearly labeled with unique designations and match designations on all
drawings, documentation, programming, and communication protocols.

8. Verify equipment, doors, and fences are labeled with appropriate safety labeling and have
the correct information in accordance with applicable regulations.

9. Verify equipment and circuits are correctly bonded and grounded in accordance with
applicable regulations.

10. Confirm isolation points have provisions for a lock and/or tag.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


11. Confirm that correct electrical equipment clearances have been met.

12. Confirm clear working space around electrical equipment in accordance with applicable
regulations.

13. Verify correct operation of mechanical, electrical, key, and safety interlocks on electrical
power equipment. Verify duplicate interlock keys are destroyed or retained by authorized
personnel in accordance with manufacturer’s recommendations.

14. Verify correct operation of applicable limit switches.

Page 13
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.1 Low-Voltage Systems (< 1 kV) (continued)


15. Verify wiring interconnection points such as shipping splits, field-connected devices, and
SCADA interface.

16. Verify current transformer circuits are complete and do not have an open-circuit. Shorting
devices should be in the intended position.

17. Verify instrument transformer tap connections are correct and match documentation,
drawings, and protective device settings.

18. Verify protective device settings are correct and match documentation, drawings, and
engineering studies.

19. Verify arc-flash hazard warning labels in accordance with applicable regulations.

20. Verify correct field marking of maximum available fault current at service equipment in
accordance with applicable regulations.

21. Verify applicable devices, protection and control schemes, SCADA, and communication
protocol.

No further reproduction or networking is permitted.


22. Verify all intelligent electronic devices and SCADA systems correctly trigger events and
disturbance records.

23. Verify intelligent electronic devices, communication protocol, and SCADA systems display
the correct date and time.

24. Verify applicable communication points to end device(s).

25. Verify correct neutral grounding system(s).

26. Verify correct operation of zone selective interlocking systems.

27. Verify panel boards have accurate panel schedules.

28. Verify prime, emergency, and standby power systems are operational and ready for
energization.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


29. Verify correct operation of GFCI receptacles.

30. Verify correct settings of lighting controls for electrical rooms and substations.

31. Verify correct operation of emergency shutdown systems.

32. Verify current and voltage sensors were tested in accordance with manufacturer’s published
data.

Page 14
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.1 Low-Voltage Systems (< 1 kV) (continued)


33. Verify applicable transformer insulating fluid analysis was completed and results are
acceptable.

34. Verify correct liquid levels and/or gas pressures in transformers.

35. Verify gas and liquid alarm levels.

36. Verify valves on equipment are in the correct position for energization.

37. Verify transformers are in the correct tap position(s) for energization.

38. Verify pre-start-up procedures on all UPS and battery system components have been
performed and documented.

39. Confirm the initializing charge has been completed for battery systems in accordance with
manufacturer’s requirements.

40. Verify that indications and records are cleared for faults, alarms, and meters.

41. Create as-left setting files.

No further reproduction or networking is permitted.


42. Create a written energization plan.

B. Energization

1. Restrict access to electrical equipment during energization and commissioning activities.


Verify emergency exits are correctly secured to prevent the entrance of an unauthorized
person from outside, while allowing free escape from inside.

2. Verify removal of temporary protective grounding equipment.

3. Verify correct position of switches, circuit breakers, and transfer switches for control
circuits, instrument transformer circuits, and power circuits. Verify test switches and
terminal block disconnects/switches are in the correct position in accordance with
energization plan.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


4. Follow and document the steps of the energization plan.

5. Verify correct current and voltage values to protective devices and metering.

6. Verify correct system phase angle and sequence.

7. Verify equipment phasing.

8. Verify correct motor rotation.

9. Verify battery and UPS systems are free of alarms and are in the specified operating mode.

Page 15
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.1 Low-Voltage Systems (< 1 kV) (continued)


10. Verify no alarms or fault indications are present.

C. Post Energization

1. Obtain post-energization oil and gas analysis on applicable devices.

2. Verify temperature monitoring and protective devices have established baseline parameters
and criteria.

3. Perform thermographic survey of equipment in accordance with Section 9.

4. The manufacturers of installed equipment should be notified of the actual energization date
for warranty purposes.

5. Monitor equipment loading and compare to design criteria.

6. Monitor loading on all panelboards to verify balanced loading and voltage levels.

7. Complete commissioning report and supply documentation in accordance with Section 5.4.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 16
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND TEST PROCEDURES

7.2 Medium-Voltage Systems, Systems Between (> 1 kV and < 100 kV)
NOTE: Refer to Section 7.3 for transmission equipment within this voltage class.

A. Pre-Energization

1. Review the owner’s project requirements (OPR), basis of design (BOD), project
specifications, and regulatory requirements for information specifically related to the
commissioning of the electrical system.

2. Applicable equipment manuals and operational instructions shall be readily available for the
commissioning team and the owner.

3. Review factory and field acceptance test data, documentation, results, and deficiencies to
verify acceptable condition and suitability for initial energization and final acceptance.
Verify all equipment has been tested according to the most recent edition of the
ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems (ANSI/NETA ATS).

4. Verify nameplate and equipment ratings are documented and correct in accordance with the
most current drawings.

No further reproduction or networking is permitted.


5. Review drawings, logic diagrams, protective device settings, engineering studies, and other
pertinent information to verify accuracy and completeness.

6. Visually inspect equipment.

7. Verify equipment is clearly labeled with unique designations and match designations on
drawings, documentation, programming, and communication protocols.

8. Verify equipment, doors, and fences are labeled with appropriate safety labeling and have
the correct information in accordance with applicable regulations.

9. Verify equipment and circuits are correctly bonded and grounded in accordance with
applicable regulations.

10. Verify medium-voltage components have adequate means for applying temporary
protective grounding equipment.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


11. Verify equipment can be safely isolated. Confirm isolation points can be visually
confirmed open and a lock and/or tag can be applied.

12. Confirm that correct electrical equipment clearances have been met.

13. Verify arc-flash hazard warning labels in accordance with applicable regulations.

Page 17
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND TEST PROCEDURES

7.2 Medium-Voltage Systems, Systems Between (> 1 kV and < 100 kV) (continued)
14. Verify mechanical, electrical, key, and safety interlocks on electrical power equipment.
Verify duplicate interlock keys are destroyed or retained by authorized personnel in
accordance with manufacturer’s recommendations.

15. Verify correct operation of applicable limit switches.

16. Verify wiring interconnection points such as shipping splits, field-connected devices, and
SCADA interface.

17. Verify current transformer circuits are complete and do not have an open-circuit. Shorting
devices should be in the intended position.

18. Verify instrument transformer tap connections are correct and match documentation, most
current drawings, and protective device settings.

19. Verify protective device settings are correct and match documentation, most current
drawings, and engineering studies.

20. Verify correct operation of applicable devices for protection and control schemes, SCADA,
and communication protocols.

No further reproduction or networking is permitted.


21. Verify intelligent electronic devices, communication protocols, and SCADA systems
properly trigger events and disturbance records.

22. Verify intelligent electronic devices, communication protocols, and SCADA systems are
connected to an adequate time synchronization source and all devices display the correct
date and time.

23. Verify applicable communication points to end device(s).

24. Verify correct neutral grounding system(s).

25. Verify communication assisted protection schemes.

26. Verify prime, emergency, and standby power systems are operational and ready for
energization.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


27. Verify correct operation of GFCI receptacles.

28. Verify correct operation of lighting controls for electrical rooms and substations.

29. Verify correct operation of emergency shutdown systems.

30. Verify current and voltage sensors were tested in accordance with manufacturer’s published
data.

31. Verify differential schemes operate in accordance with OPR.

Page 18
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND TEST PROCEDURES

7.2 Medium-Voltage Systems, Systems Between (> 1 kV and < 100 kV) (continued)
32. Verify applicable transformer and circuit breaker insulating fluid and/or gas analysis was
completed and results are acceptable.

33. Verify correct liquid levels and/or gas pressures in electrical equipment.

34. Verify valves on equipment are in the correct position for energization.

35. Verify transformers are in the correct tap position(s) for energization.

36. Verify and document correct start-up procedures on UPS and battery system components.

37. Confirm the initializing charge is completed on battery systems in accordance with
manufacturers’ requirements.

38. Verify that indications and records are cleared for faults, alarms, and meters.

39. Create as-left setting files.

40. Create a written energization plan.

B. Energization

No further reproduction or networking is permitted.


1. Restrict access to electrical equipment during energization and commissioning activities.
Verify emergency exits are correctly secured to prevent the entrance of an unauthorized
person from outside, while allowing free escape from inside.

2. Verify removal of temporary protective grounding equipment.

3. Verify correct position of switches, circuit breakers, and transfer switches for control
circuits, instrument transformer circuits, and power circuits. Verify test switches and
terminal block disconnects/switches are in the correct position in accordance with the
energization plan.

4. Follow and document the steps of the energization plan.

5. Verify correct current and voltage values to protective devices and metering.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


6. Verify correct operate and restraint values to differential protection.

7. Verify correct system phase angle and sequence.

8. Verify equipment phasing.

9. Verify correct motor rotation.

10. Verify transformer load tap changer and automatic voltage regulator operation.

Page 19
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND TEST PROCEDURES

7.2 Medium-Voltage Systems, Systems Between (> 1 kV and < 100 kV) (continued)
11. Verify battery and UPS systems are free of alarms and are in the specified operating mode.

12. Verify monitoring devices are functioning correctly.

13. Verify online partial discharge monitoring devices are functioning correctly.

14. Verify temperature monitoring and protective devices have established baseline parameters
and criteria.

15. Verify no alarms or fault indications are present.

C. Post Energization

1. Obtain post-energization oil and gas analysis on applicable devices.

2. Verify temperature monitoring and protective devices have established baseline parameters
and criteria.

3. Create and submit NERC compliance and any regulatory requirement reports (NERC
requires this within 30 day of energization).

No further reproduction or networking is permitted.


4. The manufacturers of installed equipment should be notified of the actual energization date
for warranty purposes.

5. Perform corona inspection of equipment.

6. Perform thermographic survey of equipment in accordance with Section 9.

7. Monitor equipment loading and compare to design criteria.

8. Complete commissioning report and supply documentation in accordance with Section 5.4.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 20
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.3 High-Voltage and Extra-High Voltage Systems (> 100 kV and < 1,000 kV)
A. Pre-Energization

Prior to complete system energization, assure the following pre-energization tasks have been
completed.

1. Review the owner’s project requirements (OPR), basis of design (BOD), project
specifications, and regulatory requirements for information specifically related to the
commissioning of the electrical system.

2. Applicable equipment manuals and operational instructions shall be readily available for the
commissioning team and the owner.

3. Review factory and field acceptance test data, documentation, results, and deficiencies to
verify acceptable condition and suitability for initial energization and final acceptance.
Verify all equipment has been tested according to the most recent edition of the
ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems (ANSI/NETA ATS).

4. Verify nameplate and equipment ratings are documented and correct in accordance with the
most current drawings.

No further reproduction or networking is permitted.


5. Review drawings, logic diagrams, protective device settings, engineering studies, and other
pertinent information to verify accuracy and completeness.

6. Visually inspect equipment.

7. Verify equipment is clearly labeled with unique designations and match designations on
drawings, documentation, programming, and communication protocols.

8. Verify equipment, doors, and fences are labeled with appropriate safety labeling and have
the correct information in accordance with applicable regulations.

9. Verify equipment and circuits are correctly bonded and grounded in accordance with
applicable regulations.

10. Verify high-voltage components have adequate means applying temporary protective

Distributed by Thomson Reuters (Scientific) LLC, www.tech


grounding equipment.

11. Verify equipment can be safely isolated. Confirm isolation points can be visually confirmed
open and a lock and/or tag can be applied.

12. Confirm that correct electrical equipment clearances have been met.

Page 21
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.3 High-Voltage and Extra-High Voltage Systems (> 100 kV and < 1,000 kV)
(continued)
13. Verify correct operation of mechanical, electrical, and safety interlocks on electrical power
equipment. Verify duplicate keys are destroyed or retained by authorized personnel in
accordance with manufacturer’s recommendations.

14. Verify correct operation of applicable limit switches.

15. Verify wiring interconnection points such as shipping splits, field-connected devices, and
SCADA interfaces.

16. Verify current transformer circuits are complete and do not have an open-circuit. Shorting
devices should be in the intended position.

17. Verify instrument transformer tap connections are correct and match documentation, most
current drawings, and protective device settings.

18. Verify protective device settings are correct and match documentation, drawings, and
engineering studies.

19. Verify correct operation of applicable devices for protection and control schemes, SCADA,

No further reproduction or networking is permitted.


and communication protocols.

20. Verify intelligent electronic devices, communication protocols, and SCADA systems
properly trigger events and disturbance records.

21. Verify intelligent electronic devices, communication protocols, and SCADA systems are
connected to an adequate time synchronization source and all devices display the correct
date and time.

22. Verify applicable communication points to end device(s).

23. Verify correct operation of GFCI receptacles.

24. Verify correct operation of lighting controls for electrical rooms and substations.

25. Verify correct operation of end-to-end tests on line differential and distance protection

Distributed by Thomson Reuters (Scientific) LLC, www.tech


schemes.

26. Verify differential schemes operate in accordance with OPR.

27. Verify communication assisted protection schemes.

28. Verify current and voltage sensors were tested in accordance with manufacturer’s published
data.

Page 22
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.3 High-Voltage and Extra-High Voltage Systems (> 100 kV and < 1,000 kV)
(continued)
29. Verify applicable transformer and circuit breaker insulating fluid and/or gas analysis was
completed and results are acceptable.

30. Verify correct liquid levels and/or gas pressures in electrical equipment.

31. Verify correct liquid levels and/or gas pressures in electrical equipment.

32. Verify valves on equipment are in the correct position for energization.

33. Verify transformers are in the correct DETC and LTC tap position(s) for energization.

34. Verify and document correct start-up procedures on UPS and battery system components.

35. Confirm batteries have been equalized and float charged in accordance with manufacturers’
requirements.

36. Verify that indications and records are cleared for faults, alarms, and meters

37. Create as-left setting files.

No further reproduction or networking is permitted.


38. Submit test data, as built drawings and relay as left files to owner prior to energizing
equipment.

39. Create a written energization plan.

B. Energization

1. Restrict access to the substation and components during energization and commissioning
activities.

2. Verify removal of temporary protective grounding equipment.

3. Verify correct position of switches, circuit breakers, and transfer switches for control
circuits, instrument transformer circuits, and power circuits. Verify test switches and
terminal block disconnects/switches are in the correct position in accordance with

Distributed by Thomson Reuters (Scientific) LLC, www.tech


energization plan.

4. Follow and document the steps of the energization plan.

5. Verify correct current and voltage values to protective devices and metering.

6. Verify correct operate and restraint values to differential protection.

7. Verify correct system phase angle and sequence.

8. Verify equipment phasing.

Page 23
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
7. INSPECTION AND COMMISSIONING PROCEDURES

7.3 High-Voltage and Extra-High Voltage Systems (> 100 kV and < 1,000 kV)
(continued)
9. Verify correct motor rotation for motors on electrical equipment and associated equipment.

10. Verify transformer load tap changer and automatic voltage regulator operation.

11. Verify battery and UPS systems are free of alarms and are in the specified operating mode.

12. Verify monitoring devices are functioning properly.

13. Verify online partial discharge monitoring devices are functioning correctly.

14. Verify temperature monitoring and protective devices have established baseline parameters
and criteria.

15. Verify no alarms or fault indications are present.

C. Post-Energization

1. Obtain post-energization oil and gas analysis on applicable devices.

No further reproduction or networking is permitted.


2. Verify temperature monitoring and protective devices have established baseline parameters
and criteria.

3. Create and submit NERC compliance and any regulatory requirement reports (NERC
requires this within 30 day of energization).

4. The manufacturers of installed equipment should be notified of the actual energization date
for warranty purposes.

5. Perform corona inspection of equipment.

6. Perform thermographic survey of equipment in accordance with Section 9.

7. Monitor equipment loading and compare to design criteria.

8. Complete commissioning report and supply documentation in accordance with Section 5.4.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 24
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only. No further reproduction or networking is permitted. Distributed by Thomson Reuters (Scientific) LLC, www.tech
PRIME, EMERGENCY, AND STANDBY POWER SYSTEMS - RESERVED

ANSI/NETA ECS-2015
– RESERVED –

Page 25
8.
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
9. THERMOGRAPHIC SURVEY
9.1 Visual and Mechanical Inspection

1. Perform thermographic survey when load is applied to the system.

2. Remove all necessary covers prior to thermographic inspection. Use appropriate caution,
safety devices, and personal protective equipment

9.2 Report

Provide a report which contains the following:

1. Description of equipment to be tested.

2. Discrepancies.

3. Temperature difference between the area of concern and the reference area.

4. Probable cause of temperature difference.

5. Areas inspected. Identify inaccessible and unobservable areas and equipment.

6. Identify load conditions at time of inspection.

No further reproduction or networking is permitted.


7. Provide photographs and/or thermograms of the deficient area.

8. Recommended action.

9.3 Test Parameters

1. Inspect distribution systems with imaging equipment capable of detecting a minimum


temperature difference of 1° C at 30° C.

2. Equipment shall detect emitted radiation and convert detected radiation to visual signal.

3. Thermographic surveys should be performed during periods of maximum possible loading.


Refer to ANSI/NFPA 70B, 2013 Edition, Section 11.17.

9.4 Test Results

Distributed by Thomson Reuters (Scientific) LLC, www.tech


4. For suggested actions based on temperature rise, refer to ANSI/NETA ATS, Table 100.18.

Page 26
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
10. TRANSFER TO OWNER/OPERATOR
1. A formal and documented turnover of the project and the facility shall be performed.

2. The operator receiving the turnover shall be informed of any outstanding deficiencies and
any abnormal operating conditions.

3. The turnover shall include all documentation, drawings, and operational responsibilities
required.

4. All contractor locks shall be removed from the facility and the operator place locks where
required.

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 27
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX A
Definitions
NETA recognizes the IEEE 100, IEEE Dictionary, as its official source for electrical definitions. The
definitions in the list provided by NETA either are not included in the IEEE reference or are more
specific to electrical testing and commissioning and to this document.

NETA defines equipment voltage ratings in accordance with ANSI/NEMA C37.84.1 American National
Standard for Electrical Power Systems and Equipment – Voltage Ratings (60 Hertz).

As-found
Condition of the equipment when taken out of service, prior to maintenance.

As-left
Condition of equipment at the completion of maintenance. As-left values refer to test values obtained
after all maintenance has been performed on the device under test.

Comment
Suggested revision, addition, or deletion in an existing section of the NETA standards.

Commissioning
The systematic process of documenting and placing into service newly-installed or retrofitted electrical
power equipment and systems.

No further reproduction or networking is permitted.


Commissioning Authority
An entity identified by the Owner who leads, plans, schedules, and coordinates the commissioning team
to implement the commissioning process.

Commissioning Plan
A document that outlines the organization, schedule, allocation of resources, and documentation
requirements of the commissioning process.

Commissioning Process
A quality-focused process for enhancing the delivery of a project. The process focuses upon verifying
and documenting that the facility and all of its systems and assemblies are planned, designed, installed,
tested, operated, and maintained to meet the owner’s project requirements.

Commissioning Team
Individuals who, through coordinated actions, are responsible for implementing the commissioning
process.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


Electrical commissioning
See definition for commissioning

Electrical tests
Electrical tests involve application of electrical signals and observation of the response. It may be, for
instance, applying a potential across an insulation system and measuring the resultant leakage current
magnitude or power factor/dissipation factor. It may also involve application of voltage and/or current to
metering and relaying equipment to check for correct response.

Page 28
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX A (continued)
Definitions
Equipment condition
Suitability of the equipment for continued operation in the intended environment as determined by
evaluation of the results of inspections and tests.

Exercise
To operate equipment in such a manner that it performs all its intended functions to allow observation,
testing, measurement, and diagnosis of its operational condition.

Extra-high voltage
A class of nominal system voltages greater than 230 kV but less than 1,000 kV

High voltage
A class of nominal system voltages equal to or greater than 100,000 volts.

Inspection
Examination or measurement to verify whether an item or activity conforms to specified requirements.

Interim amendment
An interim amendment is made by NETA’s Standards Review Council when a potential hazard is
identified with respect to the use of this document. The interim amendment is in force from the time of
its issue until the next revision of the document.

No further reproduction or networking is permitted.


Low voltage
A class of nominal system voltages 1000 volts or less.

Manufacturer’s published data


Data provided by the manufacturer concerning a specific piece of equipment.

Mechanical inspection
Observation of the mechanical operation of equipment not requiring electrical stimulation, such as
manual operation of circuit breaker trip and close functions. It may also include tightening of hardware,
cleaning, and lubricating.

Medium voltage
A class of nominal system voltages greater than 1000 volts and less than 100,000 volts.

Owners project requirements (OPR)

Distributed by Thomson Reuters (Scientific) LLC, www.tech


A written document that details the functional requirements of a project and the expectations of how it
will be used and operated. These include project goals, measurable performance criteria, cost
considerations, benchmarks, success criteria, and supporting information. (The term project intent is
used by some owners for their commissioning process owner’s project requirements.)

Proposal
Draft of a section that is currently “reserved” in one of the NETA standards.

Page 29
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX A (continued)
Definitions
Re-Commissioning
An application of the commissioning process requirements to a project that has been delivered using the
commissioning process. This may be a scheduled re-commissioning developed as part of an ongoing
commissioning process or it may be triggered by use change, operations problems, or other needs.

Ready-to-test condition
Having the equipment which is to be tested isolated, source and load disconnected, the breaker
grounded, and control and operating sources identified.

Shall
Indicates a mandatory requirement and is used when the testing firm has control over the result.

Should
Indicates that a provision is not mandatory but is recommended as good practice. This term is also used
when a value is recommended and there is no practical capability of achieving that value.

System voltage
The root-mean-square (rms) phase-to-phase voltage of a portion of an alternating-current electric
system. Each system voltage pertains to a portion of the system that is bounded by transformers or
utilization equipment.

No further reproduction or networking is permitted.


Verify
To investigate by observation or by test to determine that a particular condition exists.

Visual inspection
Qualitative observation of physical characteristics, including cleanliness, physical integrity, evidence of
overheating, lubrication, etc.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 30
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX B

Acronyms
ac – alternating current

ANSI – American National Standards Institute

ASHRAE – American Society of Heating, Refrigerating and Air Conditioning Engineers

ATS –ANSI/NETA ATS Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems

BOD – basis of design

CT – current transformer

CCVT – capacitance-coupled voltage transformer or CVT – capacitor voltage transformer

dc – direct current

DETC – deenergized tap changer

ETT – ANSI/NETA ETT Standard for Certification of Electrical Testing Technicians

No further reproduction or networking is permitted.


GFCI – ground fault circuit interrupter

HMI – human-machine interface

IEC – International Electrotechnical Commission

IED – intelligent electronic device

IEEE – Institute of Electrical and Electronics Engineers

IR – infrared

LTC – load tap changer

MTS – ANSI/NETA MTS Standard for Maintenance Testing Specifications for Electrical Power
Equipment and Systems

Distributed by Thomson Reuters (Scientific) LLC, www.tech


NEC – National Electrical Code (NFPA)

NERC – North American Electric Reliability Corporation

NETA – InterNational Electrical Testing Association

NFPA – National Fire Protection Association

NIST – National Institute of Standards and Technology

Page 31
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX B

Acronyms (continued)
O&M – operations and maintenance

OPR – owner’s project requirements

OSHA – Occupational Safety and Health Administration

PT – potential transformer

RTU – remote terminal unit

SCADA – supervisory control and data acquisition

SRC – Standards Review Council (NETA)

UPS – uninterruptible power supply

ZSI – zone selective interlocking

No further reproduction or networking is permitted.


Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 32
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX C

About the InterNational Electrical Testing Association

(This appendix is not part of American National Standard ANSI/NETA ECS-2015)

The InterNational Electrical Testing Association (NETA) is an accredited standards developer for the
American National Standards Institute (ANSI) and defines the standards by which electrical equipment
is deemed safe and reliable. NETA Certified Technicians conduct the tests that ensure this equipment
meets the Association’s stringent specifications. NETA is the leading source of specifications,
procedures, testing, and requirements, not only for commissioning new equipment but for testing the
reliability and performance of existing equipment.

CERTIFICATION
Certification of competency is particularly important in the electrical testing industry. Inherent in the
determination of the equipment’s serviceability is the prerequisite that individuals performing the tests
be capable of conducting the tests in a safe manner and with complete knowledge of the hazards
involved. They must also evaluate the test data and make an informed judgment on the continued
serviceability, deterioration, or nonserviceability of the specific equipment. NETA, a nationally-
recognized certification agency, provides recognition of four levels of competency within the electrical
testing industry in accordance with ANSI/NETA ETT Standard for Certification of Electrical Testing
Technicians.

No further reproduction or networking is permitted.


QUALIFICATIONS OF THE COMMISSIONING ORGANIZATION
An independent overview is the only method of determining the long-term usage of electrical apparatus
and its suitability for the intended purpose. NETA Accredited Companies best support the interest of the
owner, as the objectivity and competency of the commissioning firm is as important as the competency
of the individual technician. NETA Accredited Companies are part of an independent, third-party
electrical testing association dedicated to setting world standards in electrical maintenance and
acceptance testing. Hiring a NETA Accredited Company assures the customer that:

 The NETA Technician has broad-based knowledge -- this person is trained to inspect, test, maintain,
and calibrate all types of electrical equipment in all types of industries.
 NETA Technicians meet stringent educational and experience requirements in accordance with
ANSI/NETA ETT Standard for Certification of Electrical Testing Technicians.
 A Registered Professional Engineer will review all engineering reports.
 All tests will be performed objectively, according to NETA specifications, using calibrated
instruments traceable to the National Institute of Science and Technology (NIST).

Distributed by Thomson Reuters (Scientific) LLC, www.tech


 The firm is a well-established, full-service electrical testing business.

Page 33
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX C

About the InterNational Electrical Testing Association


(continued)
(This appendix is not part of American National Standard ANSI/NETA ECS-2015)

SPECIFICATIONS AND PUBLICATIONS


As a part of its service to the industry, the InterNational Electrical Testing Association provides
nationally-recognized publications:
ANSI/NETA ETT Standard for Certification of Electrical Testing Technicians
ANSI/NETA MTS Standard for Maintenance Testing Specifications for Electrical
Power Equipment and Systems
ANSI/NETA ATS Standard for Acceptance Testing Specifications for Electrical
Power Equipment and Systems
ANSI/NETA ECS Standard for Electrical Commissioning Specifications for
Electrical Power Equipment and Systems

The Association also produces a quarterly technical journal, NETA World Journal, which features
articles of interest to electrical testing and maintenance companies, consultants, engineers, architects,
and plant personnel directly involved in electrical testing and maintenance.

No further reproduction or networking is permitted.


EDUCATIONAL PROGRAMS
PowerTest, NETA's annual technical conference, draws hundreds of qualified industry professionals
from around the globe. This conference provides a forum for current industry advances, critical
informational updates, networking, and more. Regular attendees include technicians from electrical
testing and maintenance companies, consultants, engineers, architects, and plant personnel directly
involved in electrical testing and maintenance. Technical presentations from field-experienced industry
experts share practical knowledge and experience while in-depth seminars offer interactive training. At
the Trade Show attendees enjoy the highest-quality gathering of industry-specific suppliers displaying
state-of-the-art products and services directly related to the electrical testing industry. Attendance of
PowerTest is the best opportunity for interaction and input in a professional technical environment.

Distributed by Thomson Reuters (Scientific) LLC, www.tech

Page 34
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX D
Form for Comments
(This appendix is not part of American National Standard ANSI/NETA ECS-2015)

Anyone may comment on this document using this form:

Type of Comment (Check one)  Technical  Editorial


Paragraph Number
Recommend (Check One)  *New Text  *Revised Text  *Deleted Text
This Comment is original material (Note: Original material is considered to be the submitter’s own idea based
on or as a result of his/her own experience, thought, or research and to the best of his/her knowledge is not
copied from another source.)
This Comment is not original material; its source (if known) is
Please Check One: User Producer General Interest
Date
Name (please print)
Company
Address
City/State/Zip
Phone with area code Fax
Email
Organization represented, if any

No further reproduction or networking is permitted.


I hereby grant NETA the nonexclusive, royalty-free rights, including nonexclusive, royalty-free rights in
copyright, in this material; I understand that I acquire no rights in any publication of NETA in which this
proposal in this or another similar analogous form is used.

Signature (required)

*1. All comments must be relevant to the proposed standard.


*2. Suggested changes must include (1) proposed text, including the wording to be added, revised (and how
revised), or deleted, (2) a statement of the problem and substantiation for a technical change, and (3)
signature of submitter. (Note: State the problem that will be resolved by your recommendation; give the
specific reason for your comment, including copies of texts, research papers, testing experience, etc. If
more than 200 words, it may be abstracted for publication.)
*3. Editorial comments are welcome, but they cannot serve as the sole basis for a suggested change.

A comment that does not include all required information may be rejected by the Standards Review Council for

Distributed by Thomson Reuters (Scientific) LLC, www.tech


that reason. Must use separate form for each comment. All comments must be typed or printed neatly.
Illegible comments will be interpreted to the best of the staff’s ability.
This form is available electronically on NETA’s website at www.netaworld.org under Standards Activities.
Send to: Standards Review Council
3050 Old Centre Avenue, Suite 102, Portage, MI 49024
Phone: 888.300.6382 FAX: 269.488.6383 Email: [email protected]

Page 35
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only.
APPENDIX E

Form for Proposals


(This appendix is not part of American National Standard ANSI/NETA ECS-2015)

Anyone may propose a new section for this document using the following form:

When drafting a proposed section:


Use the most recent edition of the specifications as a guideline for format and wording.
Remember that NETA specifications are “what to do” documents and do not include “how to do” information.
Include references.
When applicable, use the standard base format:
1. Pre-Energization
2. Energization
3. Post Energization

Date
Name Tel No.
Company Fax No.
Address E-Mail
Please indicate organization represented (if any)
NETA document title Year

No further reproduction or networking is permitted.


Section/Number

Note 1: Type or print legibly in black ink.


Note 2: If supplementary material (photographs, diagrams, reports, etc.) is included, you may be required to
submit additional copies.

I hereby grant NETA the nonexclusive, royalty-free rights, including nonexclusive, royalty-free rights in
copyright, in this proposal. I understand that I acquire no rights in any publication of NETA in which this
proposal in this or another similar analogous form is used.

Signature (required)

This form is available electronically on NETA’s website at www.netaworld.org under Standards Activities.

Distributed by Thomson Reuters (Scientific) LLC, www.tech


Send to:
Standards Review Council
3050 Old Centre Avenue, Suite 102
Portage, MI 49024
Phone: 888.300.6382 FAX: 269.488.6383
Email: [email protected]

Page 36
ANSI/NETA ECS-2015
Copyrighted material licensed to ULVIYE COSKUN on 2015-07-21 for licensee's use only. No further reproduction or networking is permitted. Distributed by Thomson Reuters (Scientific) LLC, www.tech

You might also like