Subject: SCM (03BM0405) Date: 18-Mar-2021 Total Marks: 30 Time: 1 Hours 15 Minutes

The document appears to be an exam for a Supply Chain Management course. It contains three questions testing various concepts related to SCM, including distribution network designs, trends in SCM, and issues around reverse auctions. Students are asked to define terms, identify examples, compare approaches, and discuss impacts. The exam aims to evaluate different levels of understanding around key SCM topics.

Uploaded by

kamlajshekhar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

Subject: SCM (03BM0405) Date: 18-Mar-2021 Total Marks: 30 Time: 1 Hours 15 Minutes

The document appears to be an exam for a Supply Chain Management course. It contains three questions testing various concepts related to SCM, including distribution network designs, trends in SCM, and issues around reverse auctions. Students are asked to define terms, identify examples, compare approaches, and discuss impacts. The exam aims to evaluate different levels of understanding around key SCM topics.

Uploaded by

kamlajshekhar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Enroll. No.

_________
MARWADI UNIVERSITY
MU-FOBM
MBA-FOBM1 (MU), MBA-FOBM2 (MU)
Semester 4 - Summer

Subject : SCM ( 03BM0405 ) Date : 18-Mar-2021


Total Marks : 30 Time : 1 Hours 15 Minutes
Instructions :

1. Attempt all questions.


2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.

Que.1 Answer the following questions. [5]


(A)
(1) What is Seassonal Stock ?

(2) Explain customer service and cost trade off.

(3) What is cellular technology layout?

(4) Define the term Supply Chain Management.

(5) Write down the examples of e-retailers.

Que.1 Answer the following objectives [5]


(B)
(1) The replenishment cycle occurs at the

A) customer/retailer interface.
B) retailer/distributor interface.
C) distributor/manufacturer interface.
D) manufacturer/supplier interface.

(2) The objective of the customer arrival process is to


A) get the correct orders to customers by the promised due date at the lowest possible cost.
B) maintain a record of product receipt and complete payment.
C) maximize the conversion of customer arrivals to customer orders.
D) ensure that orders are quickly and accurately entered and communicated to other affected supply chain
processes.

(3) When a customer purchases a book online from a company such as Amazon, which of the following is NOT
part of the typical supply chain operations?

A) The customer
B) Amazon's web site
C) Amazon's book supplier
D) Amazon's accounting department
(4) Which of the following would not be the result of a poor/inappropriate distribution network?

A) High profitability
B) Low level of customer service
C) High cost
D) Poor profitability
E) None of the above are true.

(5) Which of the following is not a stage within a typical supply chain?

A) Customers
B) Retailers
C) Wholesalers/Distributors
D) Merchandisers
E) Component/Raw material suppliers

Que.2
(A) Determine the six distinct distribution network designs that may be used to move products from factory to [8]
customer.

(B) In 21st century era, major trends have emerged to make supply chain management a critical success factor [4]
in most industries. Discuss those trends.
OR
(B) Discuss the impact of the product life cycle on strategic fit between implied demand uncertainty and supply [4]
chain responsiveness.

Que.3
(A) Why do you think reverse auciton does not work for all items? Should Tata motors use reverse aucitons for [8]
procuring crank shafts?
OR
(A) Compare the management of multi-plant international network with manufacturing from domestic multi [8]
plant network.

---Best of Luck---
MARWADI UNIVERSITY
MU-FOBM
MBA-FOBM1 (MU), MBA-FOBM2 (MU)
Semester 4 - Summer

Subject : SCM ( 03BM0405 ) Date : 18-Mar-2021


Total Marks : 30 Time : 1 Hours 15 Minutes
Weightage
Difficulty Level No of Question Total Marks Question List
Recommended Actual
High 20 47 6 20 1(A), 1(B), 3(A)
Low 20 16 4 7 1(A), 1(B), 2(B)
Medium 60 35 5 15 1(A), 1(B), 2(A), 2(B)

Weightage No of Total
Module Name Question List
Recommended Actual Question Marks
INTRODUCTION TO SUPPLY CHAIN 1(A), 1(B), 2(B),
50 50 8 21
MANAGEMENT: 3(A)
1(A), 1(B), 2(A),
MANAGING MATERIAL FLOW : 50 50 7 21
3(A)

Weightage
Blooms Taxonomy No of Question Total Marks Question List
Recommended Actual
Remember/Knowledge 10 9 4 4 1(A), 1(B)
Understand 20 7 3 3 1(A)
Apply 25 9 1 4 2(B)
Analyze 25 26 4 11 1(A), 1(B), 3(A)
Evaluate 10 47 3 20 2(A), 2(B), 3(A)
Higher order Thinking 10 0 0 0