BITS Pilani Energy Environment Green Assessment Report 2022 23
BITS Pilani Energy Environment Green Assessment Report 2022 23
BITS Pilani Energy Environment Green Assessment Report 2022 23
IV IRQS:FORM:GEE:03:00 Page 1 of 48
Energy, Environment and Green
Effective Date 2 Nov. 2022
Assessment Report Developed by NR Approved by HEAD-IRQS
TABLE OF CONTENT
2
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 3 of 48
1. Executive Summary
The Birla Institute of Technology & Science, (BITS) Pilani, Pilani Campus has been planned
and designed to meet sustainable environmental standards. With growing awareness of environmental
pollution and its hazards it has become necessary to take measures to make the campus an Eco campus.
The Environment, Energy and Green Assessment of the campus was carried out to assess if measures
taken by university are sufficient to make the campus environment friendly. This is the first attempt to
conduct such Assessment of the Institute’s Pilani campus .
This Assessment is mainly focused on Energy Savings, Water Management, Waste Management,
Renewable Energy, Carbon Accounting , Green Belt / Landscaping/ Gardening.
To start with a Data Collection / Survey was done through a Questionnaire. Then On Site Assessment was
carried out.
Site Rounds to assess and understand the Set ups, Operations, Monitoring etc.
Interactions with the Process Owners
Obtaining Data related to Water, Energy, Waste, Plantations, Vehicle movements etc.
Energy Efficiency measurements of High Power Consuming Machineries
Compilation & Analysis of Data
Evaluation of findings for Positive Points and identifying improvement areas.
Campus is steadily moving towards sustainability in electricity, water & uses of natural resources. Water
conservation and systematic distribution of portable water supply is managed and monitored efficiently. Water
used by campus residents is treated scientifically and recycled back to use in the campus, whereas the
recycled water is being reused in flushing systems & in horticulture work. Our aim is to make it zero discharge
campus.
Campus had also aimed to reduce its dependence on conventional power. In this regard, solar power plants
and energy saving fixtures have been introduced and installed in the campus.
Usage of transport in the campus is very limited, whereas Battery operated vehicles are being introduced in
campus for transportation. 5000+ students residing in the campus are not permitted to use their private
transport inside the campus and are encouraged to use bicycles for their local movement inside the campus &
public transportation for outside the campus.
3
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 4 of 48
2. Introduction
The Birla Institute of Technology & Science, BITS Pilani is an all-India Institute for higher
education. The primary motive of BITS is to "train young men and women able and eager to
create and put into action such ideas, methods, techniques and information". The Institute is a
dream come true of its founder late Mr G.D. Birla - an eminent industrialist, a participant in
Indian freedom struggle and a close associate of the Father of Indian Nation late Mr. Mohandas
Karamchand Gandhi (Mahatma Gandhi). What started in early 1900s as a small school,
blossomed into a set of colleges for higher education, ranging from the Humanities to
Engineering until 1964 when all these colleges amalgamated to culminate into a unique Indian
University of International standing. This university was christened as the Birla Institute of
Technology and Science, Pilani, known to many as BITS, Pilani.
Over the years, BITS has provided the highest quality technical education to students from all
over India admitted on the basis of merit. Its graduates may be found throughout the world in
all areas of engineering, science and commerce. BITS symbolizes the maturing of Indian
technical ability and "can-do" entrepreneurial spirit, especially as derived from the private
sector. BITS is located in the Vidya Vihar campus adjacent to the town of Pilani in Rajasthan
BITS mission is to advance knowledge and educate students in science, technology, and other
areas of scholarship that will best serve the nation and the world in the 21st century.
ACADEMICS:
4
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 5 of 48
Objectives in brief:
• To ensure that the performance of the institution with respect to environmental activities they
are involved in, is in compliance with existing laws and regulations.
• To check the functionality and their operating success including water supply, energy related
matters and other similar matters that are related to green operations in the campus
• To measure the environmental impact of operational process related to green activities in the
campus.
• To measure the performance of each green related operations and actions in the campus.
• To generate a database of green activities for continuous monitoring to assess the success of each
of them.
• to identify future potential liabilities.
• to align the institution’s developmental and day to day activities with the stated vision, mission,
strategies, etc.
• to identify possible ways to reduce expenditure and running costs on equipment’s, appliances,
etc. or try enhance revenue income.
to improve process and materials efficiency, and in response to stakeholder requests for
increased disclosure.
5
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 6 of 48
In the campus total 996.4 kWp of on grid roof top solar power plant installed and commissioned to
use of renewable energy in the campus & and out of which 45 KWp roof top solar power plant was
installed in 2019 was latest
Total 26 Nos. standalone solar powered street lights are installed in the campus, which
is estimated to save around 9, 90 kW of electricity annually.
Around 80 Nos. of the street lights out of 495 in the campus are connected to off-grid
solar power plant of 18.5 kW per day. These street lights work on solar power for about eight
to ten hours every night, which is estimated to save around 6,753 kW of electricity annually.
After exhausting the solar power, these street lights function on conventional power.
6
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 7 of 48
Since 2014, hostels, residential quarters, academic and administrative blocks constructed as
part of the infrastructure expansion by Project Parivartan, replace all CFL, Metal
Hallide, Fluorescent tube lights are provided with LED fixtures to reduce consumption of energy.
Similarly existing CFL, tube lights and other electrical fixtures are being replaced with energy
saving LED fixtures in a phased manner.
In campus 28 nos. (Each carry 2 nos. of four wheelers) of car parking stand having
standalone solar powered lights, able to park 56 nos. of four wheelers.
In campus all the newly renovated hostel’s toilet lights & exhaust fans working are
controlled with motion sensor to save electricity.
In campus all street lights (Total No.495) fixtures are LED type.
In campus all street lights (Total 495 Nos.) on/off with LDR, as per sun light
intensity availability. No need to change time as seasons change.
Relating energy inputs and production output. Identifying potential areas of thermal and
To achieve and maintain optimum energy procurement and utilization, throughout the
organization
7
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 8 of 48
Process:
Electrical, Mechanical and Thermal team worked independently and an Assessment is done based on measured
energy data and historical data related to energy consumption collected from the university during the audit
8
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 9 of 48
RSEB Solar
Month KWH PF RSEB Billing KWH Solar Billing
April-21 366900 0.994 4216019 145286 636062
May-21 354720 0.996 3798964 131756 576809
June-21 467130 0.997 4812197 129587 523555
July-21 619110 0.996 6163136 120767 528722
August-21 619380 0.996 6263271 132879 581742
September-21 631140 0.997 6368798 101638 444697
October-21 681990 0.998 6729035 116986 512166
November-21 522990 0.998 5314220 92995 407133
December-21 694470 0.998 6832873 79557 348512
January-22 578550 0.998 5809059 74788 327750
February-22 439320 0.998 4569138 108778 476707
March-22 656790 0.998 6502990 138172 610375
Apr-22 960000 0.998 9250777 137749 606095
May-22 1128750 0.999 10796096 138820 610810
Jun-22 848370 0.998 8316567 135726 597197
Jul-22 857160 0.998 8414138 110344 485514
Aug-22 790380 0.998 7960795 126128 555840
Sep-22 1025280 0.997 10009653 111620 491129
Oct.-22 803370 0.999 7861859 110823 487624
Nov.-22 709740 0.998 7213931 94170 414346
9
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 10 of 48
RSEB
Month kWh PF RSEB Billing Unit Rate+ Additional Charges
21-Apr 366900 0.994 4216019 11
21-May 354720 0.996 3798964 11
21-Jun 467130 0.997 4812197 10
21-Jul 619110 0.996 6163136 10
21-Aug 619380 0.996 6263271 10
21-Sep 631140 0.997 6368798 10
21-Oct 681990 0.998 6729035 10
21-Nov 522990 0.998 5314220 10
21-Dec 694470 0.998 6832873 10
22-Jan 578550 0.998 5809059 10
22-Feb 439320 0.998 4569138 10
22-Mar 656790 0.998 6502990 10
22-Apr 960000 0.998 9250777 10
1000000 960000
800000
619110 631140 522990 578550
439320
600000
366900 467130 681990
619380 694470
400000
656790
354720
200000
10
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 11 of 48
0.996 0.996
0.996
0.996
0.995
0.994
0.994
0.993
0.992
Solar Generation
Month kWh Solar Billing Unit Rate
21-Apr 145286 636062 4.4
21-May 131756 576809 4.4
21-Jun 129587 523555 4.4
21-Jul 120767 528722 4.4
21-Aug 132879 581742 4.4
21-Sep 101638 444697 4.4
21-Oct 116986 512166 4.4
21-Nov 92995 407133 4.4
21-Dec 79557 348512 4.4
22-Jan 74788 327750 4.4
22-Feb 108778 476707 4.4
22-Mar 138172 610375 4.4
22-Apr 137749 606095 4.4
11
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 12 of 48
40000
20000
0
01-Jan 01-Feb 01-Mar 01-Apr 01-May 01-Jun 01-Jul 01-Aug 01-Sep 01-Oct 01-Nov 01-Dec
Solar KWH
160000
140000
120000
100000
80000
60000
40000
20000
12
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 13 of 48
2 Electricity Consumption
During the audit, power measurements were carried out for different equipment. The electricity from RSEB and
solar generation breakup is provided in below graph.
17%
83%
Observations:
It can be seen from the above figure that the percentage share of electricity from RSEB is 83% and the
solar generation is of 17%.
Cluster 1 Transformer
Total three number of transformer is installed in cluster 1 and power quality analysis of two transformers is
carried using power analyzer, however third transformer analysis is not carried out due to connectivity issue of
Instrument.
13
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 14 of 48
Transformer details
Parameters Maximum Average Minimum
Voltage (V)
U12 rms 429 417.6 404.3
U23 rms 427.8 416.7 403.5
U31 rms 424 413.1 400.7
Current
L1 (A) 325.8 226.7 157.1
L2 (A) 330.5 223.0 150.7
L3 (A) 330.1 220.9 152.3
Active Power
Total (KW) 228 143 55.45
Apparent Power
Total (KVA) 233 160 110
Power Factor
Total 0.998 0.9 0.38
Harmonics
Voltage THD % 2.4 1.8 1.4
Current THD% 26.75 16.2 9.6
Observations:
There is no voltage variation in three phases; voltage level is maintained at 424 V which is acceptable
range.
The current harmonics (ITHD %) is 26.75 %, which is higher than the limits as specified in the IEEE
519-2014 standard i.e. 8 %.
Capacitor bank is installed at each transformer but still the power factor is observed at 0.996 to 0.998
which can be maintain near to 0.99 by fine tuning of APFC.
Percentage loading of transformer 1000 kVA is 23% which is lower side.
Oil leakage observed at 1600 kVA transformer, it is recommended that to repair it immediately or
shut down the transformer as early as possible
14
0
50
100
150
200
250
380
390
400
410
420
430
440
12:15:00
12:15:00
12:18:00
15
12:18:00
12:21:00
12:21:00
12:24:00
12:24:00
12:27:00
12:27:00
12:30:00
12:30:00
12:33:00
R phase
12:33:00
12:36:00
12:36:00
12:39:00
12:39:00
12:42:00
12:42:00
12:45:00
12:45:00
12:48:00
12:48:00
Y phase
Transformer
Green, Environmental and Energy Audit Report
12:51:00
Transformer
12:51:00
12:54:00
12:54:00
12:57:00
12:57:00
13:00:00
13:00:00
13:03:00
Voltage profile of 1000 kVA
13:03:00
0
1
0.2
0.4
0.6
0.8
1.2
12:15:00
0
100
200
300
400
12:17:37 12:15:00
12:20:14 12:17:44
12:22:51 12:20:28
12:25:28 12:23:12
12:28:05 12:25:56
12:30:42 12:28:40
12:35:56 12:34:08
IV IRQS:FORM:GEE:03:00
12:38:33 12:36:52
12:41:10 12:39:36
12:43:47 12:42:20
12:46:24 12:45:04
12:49:01 12:47:48
Y phase
transformer
transformer
12:51:38 12:50:32
12:54:15 12:53:16
12:56:52 12:56:00
12:59:29 12:58:44
Current Profile of 1000 kVA
13:02:06 13:01:28
Power Factor profile of 1000 kVA
13:04:12
B phase
13:04:43
13:07:20 13:06:56
Page 15 of 48
13:09:57 13:09:40
13:12:34 13:12:24
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 16 of 48
1.5
0.5
0
H3 H5 H7 H9 H11 H13 H15 H17 H19
16
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 17 of 48
Observations:
It is observed from the above figure that the power consumption of the 1000 kVA transformer
is varied tremendously between minimum values of 55 kW to a maximum value of 228 kW.
Due to this high variation and inductive load, there is a generation of high amount of harmonics.
The harmonics generated on the LT side of the transformer is approximately 18% in current.
It is also seen that in Voltage Harmonics, 5th, 7th and 11th Harmonics dominated the total
harmonics generation.
17
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 18 of 48
Transformer 1250
The performance analysis of 1250 kVA transformer is carried out and presented in below table.
Transformer details
Parameters Minimum Average Maximum
Voltage (V)
U12 rms 430.8 421.7 406.1
U23 rms 429.3 420.6 405
U31 rms 427.8 417.7 402
Current
L1 (A) 152.2 89.0 57.9
L2 (A) 200.8 106.9 60.8
L3 (A) 150.6 92.0 38.6
Active Power
Total (KW) 107.248 46.1 -4.3026
Apparent Power
Total (KVA) 118.672 69.9 45.901
Power Factor
Total 0.94 0.6 -0.063
Harmonics
Voltage THD % 2 1.3 0.53
Current THD% 60.2 28.1 12.6
Observations:
There is no voltage variation in three phases; voltage level is maintained at 430 V which is acceptable
range.
The current harmonics (ITHD %) is 60 %, which is higher than the limits as specified in the IEEE 519-2014
standard i.e. 8 %.
Capacitor bank is installed at each transformer but still the power factor is observed at 0.996 to 0.998
which can be maintain near to 0.99 by fine tuning of APFC.
Percentage loading of 1250 kVA transformer is 9% which is lower side.
11:45:18
11:48:15
11:51:12
11:54:09
11:57:06
12:00:03
11:45:18
11:04:00
11:06:57
11:09:54
11:12:51
11:15:48
11:18:45
11:21:42
11:24:39
11:27:36
11:30:33
11:33:30
11:36:27
11:39:24
11:42:21
11:48:15
11:51:12
11:54:09
11:57:06
12:00:03
18
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 19 of 48
11:45:18
11:39:24
11:45:18
11:51:12
11:04:00
11:06:57
11:09:54
11:12:51
11:15:48
11:18:45
11:21:42
11:24:39
11:27:36
11:30:33
11:33:30
11:36:27
11:39:24
11:42:21
11:48:15
11:51:12
11:54:09
11:57:06
12:00:03
11:04:00
11:06:57
11:09:54
11:12:51
11:15:48
11:18:45
11:21:42
11:24:39
11:27:36
11:30:33
11:33:30
11:36:27
11:42:21
11:48:15
11:54:09
11:57:06
12:00:03
Figure 9. 1250 kVA Transformer Profile
2.5
1.5
0.5
0
H3 H5 H7 H9 H11 H13 H15 H17 H19
19
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 20 of 48
60
50
40
30
20
10
0
H3 H5 H7 H9 H11 H13 H15 H17 H19
Observations:
It is observed from the above figure that the power consumption of the 1000 kVA transformer is varied
tremendously between minimum values of 45 kW to a maximum value of 118 kW.
Due to this high variation and inductive load, there is a generation of high amount of harmonics. The
harmonics generated on the LT side of the transformer is approximately 50% in current.
It is also seen that in Voltage Harmonics, 5th, 7th and 11th Harmonics dominated the total harmonics
generation.
From above data it is observed that the loading on both transformer is on lower side that will lead to
increase total losses of transformer.
The efficiency of the transformers not only depends on the design, but also, on the effective
operating load. The variable losses depend on the effective operating load to the transformer. The
maximum efficiency of the transformer occurs at a condition when constant loss is equal to variable
loss. For distribution transformers, the core loss is 15 to 20% of full load copper loss. Hence, the
maximum efficiency of the distribution transformers occurs at a loading between 40 – 60%. For
power transformers, the core loss is 25 to 30% of full load copper loss. Hence, the maximum
efficiency of the power transformers occurs at a loading between 60 – 80%.
20
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 21 of 48
Cluster Cluster
Description Cluster 1
2 4 Cluster 5 Cluster 7
Rating (kVA) 1000 1250 800 1000 750 1000 630 500
Voltage (V) 424 430 430 430 430 430 430 430
Current (A) 330 200 200 200 200 200 200 200
P.F 0.98 0.94 0.94 0.94 0.94 0.94 0.94 0.94
Active
Average 143 46 107 201 17 82 46 58
power (kW) Maximu
m
228 107 125 254 24 97 123 80
Apparent Average 160 70 127 229 21 102 56 73
power Maximu
(kVA) m
233 118 147 286 38 112 134 90
Maximu
Transforme m
23% 9% 18% 29% 5% 11% 21% 18%
r loading
Average 16% 6% 16% 23% 3% 10% 9% 15%
Make - - - - - - - -
Cooling ONAN ONAN ONAN ONAN ONAN ONAN ONAN ONAN
Frequency ( Hz) 50 50 50 50 50 50 50 50
Cluster
Location
1
Serial No. - - - - - - - -
Manufacturing Year - - - - - - - -
Transformer Rating in
1000 1250 1600 500 630 1000 1600 750
kVA
Avg.Load in KVA 160.00 69.47 140.00 229.00 21.00 56.00 280.00 73.00
Present % Loading 16.00 5.56 8.75 45.80 3.33 5.60 17.50 9.73
Rated Full Load Losses of
13.50 16.40 19.80 5.70 9.50 13.50 19.80 7.50
Transformer (kW)
Total Losses of
1.70 2.10 2.50 0.80 1.08 1.70 2.50 1.15
Transformer(kW)
Operating Power Factor 0.98 0.94 0.89 0.85 0.91 0.85 0.89 0.89
No Load Loss (kVA) 1.73 2.23 2.81 0.94 1.19 2.00 2.81 1.29
Total Losses= Load
3.27 2.88 4.04 2.79 1.41 2.54 5.27 1.81
Losses+N.L. Losses
Transformer Efficiency,
97.96 95.85 97.11 98.78 93.28 95.47 98.12 97.52
%
The performance assessment of pumps includes determination of hydraulic efficiency of the pumps. The
details of the same are given below.
Zone 1
Description Units Domestic Domestic Domestic
Flush 1 Flush 2
Pump 1 Pump 2 Pump 3
Design parameters
Make - Grundfos Grundfos Grundfos Grundfos Grundfos
Model - - - - - -
Flow rate m3/hr 30 30 30 21 21
Head m 53.1 53.1 53.1 58 58
Speed rpm 2919 2919 2919 2919 2919
Motor rating kW 11 11 11 5.5 5.5
Operating Parameters
Flow rate m3/hr 37 36.0 34.9 3.9 5.0
Total head developed m 19 18.7 19 40.0 41
Motor input power kW 10.09 9.85 10.34 4.92 6.15
Motor efficiency % 92% 92% 92% 92% 92%
Combined overall efficiency % 19% 19% 18% 9% 9%
Pump efficiency % 21% 20% 19% 9% 10%
Observations:
The efficiency of zone 3 domestic pumps lies between 19% to 21% and flush pumps are lies between
9% to 19%.
VFD is installed to control the system for both domestic and flush pumps.
Out of these three pumps One pump is continuously running and two are on standby mode.
However these both set of domestic pumps and flush pumps are having VFD, the discharge line is
throttled at about 50% for both set.
22
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 23 of 48
Observations:
The efficiency of zone 2 Domestic pumps lies between 42% to 62% and for flush pump it lies between
57% to 59%.
There is no control system if requirement is fulfilled, totally controlled by manually.
Out of these four pumps two pumps are continuously running and two are on standby mode.
Only one flush pump is running and other two are on standby mode.
Domestic pump discharge line was throttled at about 30% and main header discharge line of flush
pump is throttled at about 20% as shown in photo below.
23
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 24 of 48
Zone 3
Description Units Domestic Domestic Domestic Domestic
Pump 1 Pump 2 Pump 3 Pump 4
Design parameters
Make - Grundfos Grundfos Grundfos Grundfos
Model - - - - -
Flow rate m3/hr 30 30 30 30
Head m 97.8 97.8 97.8 97.8
Speed rpm 2924 2924 2924 2924
Motor rating kW 11 11 11 11
Operating Parameters
Flow rate m3/hr 35.3 35.5 37.9 32.0
Total head developed m 22 16.0 18 21
Motor input power kW 10.46 10.39 10.38 10.49
Motor efficiency % 92% 92% 92% 92%
Combined overall efficiency % 20% 15% 18% 17%
Pump efficiency % 22% 16% 19% 19%
Observations:
The efficiency of zone 1 pumps lies between 16% to 22% , which is lower side.
The distance from main pumping station to last user end is almost 2km and the generated head at main
header line is 2 kg/cm2.
There is no control system if requirement is fulfilled, totally controlled by manually.
Out of these four pumps two pumps are continuously running and two are on stand by mode.
24
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 25 of 48
Two STP plants are installed in university, each STP plant is having Three Aeration Blowers (one is running
and Two standby mode). Measurement of these blowers are carried out during audit and presented in
below table.
Presently three transformers are installed in cluster 1, two in cluster 5 and two in cluster 7. All
transformers in these clusters are under loaded which is in the range of 6% to 46%. This will lead to
increase the losses of transformer.
So it is recommended that to shift the load of 1000 kVA transformer and 1600 kVA transformer to
1250 kVA transformer in cluster 1 which will lead to increase the percentage loading on 1250 kVA
transformer in the range of 60% to 80%.
In cluster 5, Shift the load of 750 kVA transformer to 1000 kVA transformer to increase the loading
on transformer and to reduce the transformer losses.
In cluster 7, Shift load of 500 kVA transformer to 630 kVA transformer to increase the loading on
transformer and to reduce the transformer losses.
The cost benefit analysis by shifting of load and reduction of losses is presented in below table.
26
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 27 of 48
Zone 2 and zone pumps are observed in throttled position for both set domestic and flush.
Throttling on the pump discharge will effect on changing the system resistance curve. This changes
the point of intersection with the pump performance curve with resultant change in flow.
In such case pump input remains same but the output of pump will reduce which will reduce the
efficiency of pump and degrades pump life.
Zone 3 pumps are having VFD for both domestic and flush pumps but still the discharge side of both
set is 50% throttled, this will nullify the purpose of VFD installation and it is running with 50Hz
frequency.
So it is recommended that to install VFD on zone 1 and zone 2 pumps and for zone 3 adjust the
frequency and remove throttling on it.
27
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 28 of 48
Sr.
Domesti Domesti Domesti
No Parameters Units Flush Flush
c Pumps c Pumps c Pumps
.
Present Zone 2 Pump Power
1 kW 20.86 8.31 19.47 9.25 15.14
Consumption
2 Daily Operating Hours hours 6 6 6 6 6
3 Annual Operating Days days 365 365 365 365 365
kWh/ye 18,19 20,25
4 Annual Electricity Consumption 45,683 42,628 33,157
ar 9 8
kWh/ye 14,55 16,20
5 Annual Energy Consumption – VFD 36,547 34,103 26,525
ar 9 6
kWh/ye
6 Annual Electricity Savings 9,137 3,640 8,526 4,052 6,631
ar
7 Electricity Tariff Rs./kWh 10 10 10 10 10
Rs.
8 Expected Annual Cost Savings 0.91 0.36 0.85 0.41 0.66
Lakhs
Rs.
9 1.28 1.26 0.66
Total Cost Savings Lakhs
10 3.20
Rs.
11 Invetsment for two VFD 2
Lakhs
12 Simple payback period Months 8
28
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 29 of 48
Thermography
During the audit, IR Thermography of Electrical Panels was also conducted as a preventive maintenance
procedure.
Location – Transformer 2 Capacitor bank 13F3 50 Temperature found on critical side need to correct
kVAR it immediately
30
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 31 of 48
31
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 32 of 48
Six groundwater recharge points are created across the campus. In this, the surface runoff water during
monsoon is directed to a designated area which then percolates in the ground resulting in groundwater
recharge. Many such recharge points are being planned across the campus in the coming years.
All overhead tanks and water coolers are fitted with floats, sensors and other mechanisms to shut the water
supply and avoid overflow.
Overhead tanks which are filled with pressurized supply of water through pumps are fitted with actuator valves
for avoiding overflow.
Insulation on water storage tank at Ram & Budh Bhawan to guard against extreme temperature.
1. VFD based hydro pneumatic system.
2. Pumps & equipments selected on ‘’best ‘energy efficiency point.
3. Use of low flow fixtures.
4. Use of treated water with BOD less than 10 ppm and COD less than 50 ppm from STP for HVAC cooling
tower make up, flushing and irrigation.
32
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 33 of 48
Capacities:
33
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 34 of 48
34
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 35 of 48
Zone-3
SrNo Description Total Domestic Flushing Water Gross Water (LPD)
Water LPD (LPD)
1 Boys Hostels 243000 97000 340000
2 Institute Area 120000 45000 165000
Total 363000 142000 505000
Irrigation water for landscape use within the campus is a domestic quality and it sourced
from in house STP and has acceptable parameter as per governing requirement, using it to
maintain lush green garden.
35
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 36 of 48
RECYCLING
Domestic waste generated in the campus at residences, hostels, messes, etc. is segregated at
source into dry, wet waste.
To maintain natural balance in the environment and make optimum utilization of waste
available, the biodegradable waste is being processed.
The two Sewage Treatment Plant (STP) with the capacity of 1 MLD & 1.5 MLD each is working
round the clock to treat sewage generated by residents of the campus.
Flushing water sourced from in-house sewage Treatment plant. The Treated Effluent for
flushing is obtained after tertiary treatment at STP. Treated effluent is odourless and shall is
acceptable chemical /bacteriological parameters as per Rajasthan pollution control boards
laws. Recently some hostels, STP treated water is supplied to flush tanks of EWC through
dedicated supply network.
The sludge generated at STP is transferred to drying bed in the vicinity of STP which is used as
manure after drying.
1. Gardening Purpose
2. Flushing Purpose
3. Cooling Tower
4. Chillers
5. Construction
6. Cleaning
Usage
36
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 37 of 48
37
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 38 of 48
38
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 39 of 48
Positives:
39
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 40 of 48
Food Waste:
Campus having total 08 Nos Mess and food preparation done in the 2 nos mess and distributed to other mess.
Mess is running by Outsource agency
1. Blue Chip Hospitalization
2. Aditya Food Management
FSSAI License verified for both.
RO water provided to all mess and Testing of the water done by external agency.
Total student appx 5000 Nos are having the meal per day (Breakfast, Lunch, Dinner)
Total food prepared appx – 3900 - 4000 Kgs/day Excluding the cutting waste
Total waste appx – 1000 – 1200 Kgs / day
Bio Gas plant not working condition, installation done in Year 2019.
Currently Food Waste is handed over to the local Municipality.
BIO WASTE:
Following Colour coding for biomedical waste management: yellow, red, white, and
blue bins
1. YELLOW
Pathological waste
Soiled (infectious) waste
Medical chemical waste
Clinical lab waste
Pharmaceutical waste (discarded/expired medicines and drugs)
2. RED
Sharps waste
Considering the nature of this hazardous medical waste, you will need containers that are puncture,
leak, AND tamper proof. As for disposal, the case is the same as with the waste falling under the red
category: you’ll need a medical waste shredder.
4. BLUE
40
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 41 of 48
The Bio Waste are disposed to Pollution Control Board Authorized Agency.
E- Waste:
E – Waste such as Computers and telecommunications equipment, Consumer electronic devices and
solar panels. TVs, monitors and screens. LED bulbs etc are under buy- back system
These are Collected separately and disposed to Pollution Control Board Authorized Agencies.
Currently no practice of segregation of Plastic & Paper Waste. All such wastes are collected by
Municipality.
41
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 42 of 48
7. GREEN MANAGEMENT
Trees play an important ecological role within the urban environment, as well as support improved
public health and provide aesthetic benefits to campuses. In one year, a single mature tree will absorb
up to 48 pounds of carbon dioxide from the atmosphere, and release it as oxygen. The amount of
oxygen released by the trees of the campus is good for the students and staff in the campus. We
need to realize the importance of trees in and around the campus as they significantly contribute
towards making the air cleaner for us. The BITS – PILANI campus sustains a luxuriant plant diversity
ranging from trees, grasses, herbs, shrubs, creepers ornamental plants, palm and seasonal flowers.
Benefits of plants
Lowers levels of anxiety. Constantly seeing and being around plants helps people feel more
calm and relaxed, thus decreasing levels of anxiety.
Increases attentiveness and memory. ...
Increases productivity. ...
Reduces stress levels and boosts mood. ...
Sparks creativity.
The ultimate benefit of plants is the air we breathe. Our ancient Earth likely contained very
little free oxygen, but scientists estimate that about 2.5 billion years ago the evolution of
photosynthesis, whose by-product was oxygen, was the ultimate cause of the rise of oxygen levels
in our atmosphere (Photo 1). Modern levels of oxygen in the atmosphere allow us to breathe easy,
thanks to photosynthesis.
42
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 43 of 48
Today, the levels of oxygen in our atmosphere are not much of a concern, but the rapid rise of
carbon dioxide is. However, another benefit of photosynthesis is the absorption of carbon dioxide
from the air which ultimately transforms into carbon (organic matter) stored in plant tissues (Photo
1). If the carbon is stored long-term, such as in trunks of long-lived trees, this process is called
“carbon sequestration.” Many scientists are looking at ways to use plants to sequester carbon in
order to mitigate or defer global warming.
The chemical formula of photosynthesis showing how six carbon dioxide molecules and six water molecules in the
presence of sunlight are converted into one molecule of organic matter and six molecules of oxygen .
43
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 44 of 48
Indoor plants are commonly used for their aesthetics benefits but they also have vital role reducing
airborne pollution. The right choice of plants can be an excellent way of improving indoor air quality
and general health. Local landscape contractor can be contacted for supply and rotation of these
plants
Aloe Vera
Formaldehyde, Paints, Plastics, Thrives under low light
Trichloroethylene Wood products conditions as well as
and Benzene etc. easy to maintain
Bamboo Plant
Benzene Paints Low maintenance
plant that prefers low
light conditions.
Chinese Evergreen
Formaldehyde, Wood, Paper Easy to maintain
Benzene, Air products, Air
borne fecal matter borne fecal –
particles matter particles
from pests
English Ivy
Purifies indoor air Easy to maintain
Parlor Palm
44
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 45 of 48
Fossil fuels (such as petrol, diesel) contribute significantly to environmental pollution through
emission of greenhouse gases into the atmosphere mainly as carbon dioxide. Vehicular emission is
the main source of carbon emission in the campus, hence to document the various means of
transportation that is practiced by the university members is important.
Initiatives:
Cycle movement encouraged. All students are allowed only to use the Cycles.
To minimize the traveling time and distance the hostels are within the premises only.
Every year university celebrates World Environment Day and World Water Day in the
campus. Many plants are planted on this day every year; in this way the plant count
increases every year. The main focus of these programs is to provide awareness to
the students about the importance of the environment, its conservation and
sustainable use of environmental resources.
45
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 46 of 48
8.RECOMMENDATIONS:
Energy Management
Zone 2 and 3 pumps are observed in throttled position for both set domestic and flush. Throttling
on the pump discharge will effect on changing the system resistance curve. This changes the point
of intersection with the pump performance curve with resultant change in flow. In such case pump
input remains same but the output of pump will reduce which will reduce the efficiency of pump
and degrades pump life.
Zone 1 pumps are having VFD for both domestic and flush pumps but still the discharge side of both
set is 50% throttled, this will nullify the purpose of VFD installation and it is running with 50Hz
frequency.
So it is recommended that to install VFD on zone 3 and zone 2 pumps and for zone 1 adjust the
frequency and remove throttling on it.
At present the line pressure requirement is 2 kg/ cm2 and if the line pressure goes
beyond the VFD will sense the pressure and cut off the power supply.
• LED lights are up to 80% more efficient than traditional lighting such as fluorescent and
incandescent lights. LED lights also consume much less power than traditional lighting. A
typical 84-watt fluorescent can be replaced by a 36-watt LED to give the same level of
light. Less energy use reduces the demand from grid and decreases greenhouse gas
emissions.
• LED lights contain no toxic elements. Most offices currently use fluorescent strip lights
which contain noxious chemicals such as mercury. This will contaminate the
environment when disposed of in landfill waste. Disposal has to be arranged through a
registered waste carrier so switching to LED avoids the cost and time implications
required for compliant disposal and helps to protect the environment from further toxic
waste.
• A longer life span means lower carbon emissions. LED Lights last up to six times longer
than other types of lights, reducing the requirement for frequent replacements. This
results in using fewer lights and hence fewer resources are needed for manufacturing
processes, packaging materials and transportation.
• It is reported that no Sodium/mercury Vapour Lamps are in used in the campus as on
today. It is recommended to replace Sodium/mercury Vapour Lamp light fixture with LED
Light if any.
46
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 47 of 48
• All toilet blocks and passages may be planned to put on motion sensor control in a
phased manner.
Energy Savings for Computers, Printers Scanner, Light, AC, Ceiling Fan etc.
Photocopier and printers may be “turned off”” WHEN NOT IN USE”, as even in the “sleep
mode” these consume power. Power Management features should be activated on all
copiers and printers.
Monitor and other office equipment may be plugged into power with a motion sensor.
These devices automatically turn off equipment whenever user leaves the room for more
than a few minutes that can be set by user. All Computers may be “Switched OFF” at the
end of the day.
Air conditioners temperatures can be set at optimum like for rooms may be set at 26 0 C.
Environment Management
33 KV Sub- Station:
a. 32 earth pits, renovated recently, to be painted for its number, ohmic value measured, date
of measurement, next due date etc.
b. Sand bucket is filled with soil, to be replaced with good sand
c. Material stored in battery room, may be shifted to store room
d. Electrical shock chart to be provided
47
Green, Environmental and Energy Audit Report IV IRQS:FORM:GEE:03:00 Page 48 of 48
vi. Monthly running hours, power generated, diesel consumption to be recorded and analyzed for
any possibility of saving
vii. Monthly running hours, power consumption to be recorded and analyzed for any possibility of
saving
GREEN CAMPUS
Audit Team
Name of the Client Date of Audit Date and Signature
Name Role
V. Balakrishnan Team Leader
48