6abha09 Abha 08 MBL Ar Itp 00017
6abha09 Abha 08 MBL Ar Itp 00017
6abha09 Abha 08 MBL Ar Itp 00017
6ABHA09-INSPECTION TEST PLAN AND CHECK LIST FOR MULTIPANEL FOLDING ALUMINUM-FRAMED GLASS
DOORS
Review Sheet
Ref: 6ABHA09-ABHA-08-MBL-AR-ITP-00017 Revision 00 Date & Time 19 March 24
Client: Saudi Entertainment Ventures
Project Management Consultant and Engineer Saudi Consolidated Engineering Company - Khatib & Alami
Assistant Engineer and Supervision Consultant DAR International for Engineering Consultancy
Contractor Modern Building Leaders
Area / Location
Discipline:
☐ Civil ☐ Structural ☒ Architectural ☐ Mechanical ☐ GM ☐ Electrical ☐ HV ☐FP ☐ Plumbing ☐ Quality ☐ BIM
☐ Project Control ☐ Quality Management ☐ FLS/Safety ☐ General ☐ Other (specify if other):
Page 1 of 1
Client PMC LDC Contractor
Saudi Entertainment Ventures Khatib & Alami Dar International Engineering Consultancy Modern Building Leaders
Project name: Program 6: Abha Entertainment Complex
Location: Abha Contract No.:
Attachments 1 2 3
Date: 9-Mar-24
Remarks:
Document Status
(A) Approved As Submitted (B) Approved with Comments (C) Revise and Resubmit (D) Rejected
Has the mock-up inspection tests with frequency of the mock-up inspection tests been
2
included with Respecting W and H points?
3 Has the samples inspection tests been included with Respecting W and H points?
Are items to be inspected and tested including test stages identified and presented in a
4
logical construction order?
Are all Quality Control requirements including, pre-task quality brief, calibration, Shop
6 drawings,Redline drawing monitoring, clearance from other disciplines, and turn-over
review detailed as required?
Are acceptance criteria with a clear tolerance for each inspection and test been
7
specified?
Are verifying documents has been identified with clear reference to applicable checklists
9
and forms?
Does the ITP include notification requirements for “Work Inspection Request” (WIR)/
10 Material inspection request (MIR)?(Minimum (24) hours for site work and (1) week in
advance for inspections requested during holidays and Fridays.
Does the ITP include specific code/ standard to be used for each inspection/ test in
11
accordance with the requirements of SEVEN List of Codes & Standards?
Are the 3rd party, MBL, LDC, PMC ,and SEVEN hold, witness review points been
14
established among all parties with a clear definition in the legend?
15 Does the ITP specify the percentage of tests to be done/ sampling plan?
17 Are the reporting forms & checklist been included as an attachment to the ITP?
Has the inspection & test plan been signed off by designated competent preparer,
19
reviewer and approver?
Does the inspection & test plan format & language is as per project requirements and
20
easy to understand?
Does the inspection & test plan include the repair stage or contain a reference to a
21
separate Special Procedure for repairs?
Does the inspection and test plan require an activity for the protection of completed
22
work? If yes is the approved Method/procedure mentioned in the Reference?
Conclusion/ Remarks
Date
PRQ, Material Submittal , Shop Drawing , All used materials as per Manufacturer recommendations in data MTS & Method Statement
1.1 Each submittal N/A N/A H H R R
Methoed Statement sheet and relevant international standards and procedure of work. Approval
SEVEN Procedure
Sample for approved glazing Finishing Material Sample
0DMQL00-DLVR-00-SEV-
1.2 Sample & Mockup Each submittal & Mockup Approvals on N/A H H H R
Mockup to inspect installation & finishing quality
QM-PRO-00002 &
Approved Sample
Aconex H
2 Material Receiving
MIR
2.1 Receiving inspection Delivery and storage of Material onsite / at warehouse MTS & Approved Sample Each delivery N/A H H R R
(Checklist 1)
3 Installation
Clause 2.1 in SEVEN
Procedure WIR
3.1 Mockup - Benchmarking Mockup - Benchmarking inspection for first activity Once N/A H H H H
0DMQL00-DLVR-00-SEV- (Checklist 2)
QM-PRO-00002
3.2 Installation Including installation, adjust, cleaning, and protection Specs 08 35 13.13 Partial Checklist 2 N/A H H R S
4 Final Handover
4.1 Final Inspection Includes final handover inspection Specs 08 35 13.13 Partial WIR N/A H H R S Third party will be H if required
H
General Notes
The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Consultant may adjust the levels of SEVEN participation based upon the
Contractor’s performance.
Surveillance: Engineer/ Inspector to monitor work in progress without notice from Construction Organization
Witness: Engineer/ Inspector shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
Hold Point: Engineer/ Inspector shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
Review A ‘Review’ point identifies an activity at which the Client and / or a third party requires to review progress to date; effecting a ‘gated review’. Review points are typically applied to documentation.
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to a consultant.
Legend
H Hold Point for QC Inspection/ Test S Surveillance
W Witness Inspection/Test R Review Documents and Reports
Page 1 of 1
Aconex Ref#6ABHA09-ABHA-08-MBL-AR-ITP-00017 Rev#00 Date: 09-Mar-24
P6 ABHA Entertainment Complex
Project Management Consultant and Engineer: Supervision Consultant & Engineer’s Assistant Contractor:
Client:
Page 1 of 2
Page 2 of 2
Page 1 of 4
INSTALLATION
Comply with Drawings, Shop Drawings, and
manufacturer's written instructions for installing
3 Specs 08 35 13.13 – 3.2 ☐ ☐ ☐
multipanel folding aluminum-framed glass doors,
hardware, accessories, and other components.
Install multipanel folding aluminum-framed glass doors
level, plumb, square, true to line; without distortion,
warp, or rack of frames and panels, and without
4 impeding thermal movement; anchored securely in Specs 08 35 13.13 – 3.2 ☐ ☐ ☐
place to structural support; and in proper relation to
wall flashing, vapor retarders, air barriers, water
/weather barriers, and other adjacent construction.
Set threshold members in bed of sealant or with gaskets,
5 Specs 08 35 13.13 – 3.2 ☐ ☐ ☐
as indicated, to provide weathertight construction.
Separate aluminum and other corrodible surfaces from
6 sources of corrosion or electrolytic action at points of Specs 08 35 13.13 – 3.2 ☐ ☐ ☐
contact with other materials.
7 Install glazing as specified in Division 8 Section "Glazing." Specs 08 35 13.13 – 3.2 ☐ ☐ ☐
ADJUSTING
Adjust hardware for proper alignment, smooth
10 operation, and proper latching without unnecessary Specs 08 35 13.13 – 3.4 ☐ ☐ ☐
force or excessive clearance.
Adjust hardware and operable panels to function
11 smoothly, and lubricate as recommended by Specs 08 35 13.13 – 3.4 ☐ ☐ ☐
manufacturer.
CLEANING
Clean exposed surfaces immediately after installation.
Avoid damaging protective coatings and finishes.
12 Specs 08 35 13.13 – 3.5 ☐ ☐ ☐
Remove non-permanent labels, excess sealants, glazing
materials, dirt, and other substances.
Remove and replace glass that has been broken,
13 chipped, cracked, abraded, or damaged during Specs 08 35 13.13 – 3.5 ☐ ☐ ☐
construction period.
PROTECTION
Protect multipanel folding aluminum-framed glass door
surfaces from contact with contaminating substances
14 resulting from construction operations. Remove Specs 08 35 13.13 – 3.6 ☐ ☐ ☐
contaminants immediately according to manufacturer's
written instructions.
Page 3 of 4
Remarks
Page 4 of 4