Manual 6-Project Time Management-Book 1
Manual 6-Project Time Management-Book 1
Book 1 of 3
Introduction to Project Time Management
Manual 6: Project Time Management
Contents
Topic 1: Project Time Management 3
Section A: Introducing Project Time Management 3
Project Time Management 3
Section B: An Overview of Project Time Management 6
Introduction to Project Time Management 6
The Five Processes of Project Time Management 6
Activity Definition – identifying the specific schedule activities that need to be performed to produce the
various project deliverables.
Activity Resource Estimating – estimating the type and quantities of resources required to perform each
schedule activity.
Activity Duration Estimating – estimating the number of work periods that will be needed to complete
individual schedule activities.
Schedule Development – analyzing activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule.
These processes interact with each other and with processes in the other Knowledge Areas as well. Each
process can involve effort from one or more persons or groups of persons, based on the needs of the
project. Each process occurs at least once in every project and occurs in one or more project phases, if the
project is divided into phases. Although the processes are presented here as discrete components with
well-defined interfaces, in practice they can overlap and interact in ways not detailed here.
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating,
activity duration estimating, and schedule development are so tightly linked that they are viewed as a
single process that can be performed by a person over a relatively short period of time. These processes
are presented here as distinct processes because the tools and techniques for each are different.
Although not shown here as a discrete process, the work involved in performing the six processes of
Project Time Management is preceded by a planning effort by the project management team. This
planning effort is part of the Develop Project Management Plan process, which produces a schedule
management plan that sets the format and establishes criteria for developing and controlling the project
schedule.
The project time management processes, and their associated tools and techniques, vary by application
area, are usually defined as part of the project life cycle, and are documented in the schedule
management plan. The schedule management plan is contained in, or is a subsidiary plan of, the project
management plan, and may be formal or informal, highly detailed or broadly framed, based upon the
needs of the project.
PROJECT SCOPE
MANAGEMENT
3. Outputs 3. Outputs
3. Outputs
1. Activity list 1 Project schedule network diagrams
1. Activity resource requirements
2. Activity attributes 2. Activity list (updates)
2. Activity attributes (updates)
3. Milestone list 3. Activity attributes (updates)
3. Resource breakdown structure
4. Requested changes 4. Requested changes
4. Resource calendars (updates)
5. Requested changes
Requested changes
Enterprise
Resource availability
Environmental Activity Requested changes
Factors Sequencing Project management plan (updates)
6.2
(3.2.2.6)
Organizational policies Project schedule network diagrams
Organizational
Historical information
Process Assets
Project calendar
Note: Not all process interactions and data flow among the processes are shown
Process Group
Initiating Planning Executing Controlling Closing
Knowledge Area
Project Time 6.1. Activity Definition 6.5. Schedule
Management Control
6.2. Activity
Sequencing
6.4 Schedule
Development
• Activity definition involves identifying specific activities that the project team members and
stakeholders must perform in order to produce the project deliverables. An activity or task is an
element of work normally found on the work breakdown structure (WBS) that has an expected
duration, cost, and resource requirements.
• Activity sequencing involves identifying and documenting the relationships between project activities.
• Activity duration estimating involves estimating the number of work periods that are needed to
complete individual activities. Resource planning, part of the project cost management knowledge
area, is an important process that is closely tied to estimating activity durations, and will also be
discussed in detail in this course.
• Schedule development involves analyzing activity sequences, activity duration estimates, and
resource requirements to create the project schedule.
• Schedule control involves controlling and managing changes to the project schedule.
Cost Schedule
Control
Cost
Estimating
Time
Schedule
Development
The main purpose of the time management processes is to create the project network diagram, which
will evolve into a project schedule.
Once the team finishes the final iteration of the network diagram, dates are assigned and approved. It is
then that the network diagram officially becomes the project schedule.
The schedule is also used to help the project manager to determine in the planning phase of the project
whether the project is feasible, given the scope of work, resources, time, labor, budget, planned quality,
and stakeholder expectations.
The project schedule is the agreed upon set of tasks/activities and due dates used to guide and monitor
the project to completion. The project schedule is a comprehensive calendar, which may depict:
All projects can be broken down into a number of activities that must be performed. In order to create the
project schedule, you must first decompose the WBS to determine what these activities are. You can then
determine how long they will take, what resources they require, and in what order they should be
performed. Each of these elements has a direct bearing on the schedule.
For example, if you fail to identify a task or omit a task altogether, the project won’t be completed. If you
underestimate the length of time or the resources required for the task, you could miss your completion
date as well as underestimate the project budget. The schedule can also be set back if you make a
mistake in the sequencing of the tasks, or fail to respond to identified risk.
The following steps are necessary in the development of the project schedule.
Once the schedule is created, it must be controlled. The schedule and budget are interrelated in that if you
fail to meet the project schedule, you will probably exceed the project budget as well. Meeting the project
schedule will not guarantee that you will meet the project budget, but it may significantly increase your
chances.