0% found this document useful (0 votes)
9 views19 pages

Crashing Detailed Example 2

Uploaded by

Anas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views19 pages

Crashing Detailed Example 2

Uploaded by

Anas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

Eleventh Edition

Chapter 7

Project Management

Project crashing
example 2

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Remember that:

• Total project costs

• = direct costs + indirect cost + penalty costs

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example about crashing

Do crashing for the following project activities


considering that the indirect cost per week is $200.

Find the optimal crashed project completion time.

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Activity IPA NT CT NC CC

1-2 7 4 700 850


1-3 5 3 500 700
1-4 8 5 600 1200
2-5 9 7 800 1250
3-5 5 3 700 1000
3-6 6 5 1100 1300
4-6 7 5 1200 1450
5-7 2 1 400 500
6-7 3 2 500 850
Total

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Activity IPA NT CT NC CC Crash Cost
limit slope
1-2 7 4 700 850 3 50
1-3 5 3 500 700 2 100
1-4 8 5 600 1200 3 200
2-5 9 7 800 1250 2 225
3-5 5 3 700 1000 2 150
3-6 6 5 1100 1300 1 200
4-6 7 5 1200 1450 2 125
5-7 2 1 400 500 1 100
6-7 3 2 500 850 1 350
Total 6500

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Draw the network

9
2 5
7 2
5

1 3
5 7
6
8
4
3
6
7

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Step 1: now what is the critical path:
Path : time
1 – 2- 5- 7 18 CP

1 -3 – 5 -7 12

1- 3- 6 – 7 14
1- 4- 6-7 18 CP
(2 critical path since it has the largest duration)

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Now normal project completion time = 18 weeks
 project direct costs = $ 6500
Indirect costs = (200$ /week) * 18 weeks =
$ 3600
Penalty cost = zero

So total project cost = 6500 + 3600 = $ 10100

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
now do crashing on the activities of the critical path:
CP critical crash limit Cost slope
activity
1- 2-5-7 1-2 3 50 Min cost
You can crash
by 1 week
2-5 2 225
5-7 1 100

1-4-6-7 1-4 3 200


4-6 2 125 Min cost
You can crash
by 1 week

6-7 1 350

now go and update the table again


Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• FORM the following table

Normal 18
duration

18 17

Added cost 175

Direct cost 6500 6675

Indirect cost 3600 3400

Total cost 10100 10075

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Draw the updated network and find the C.P

9
2 5
6 2
5

1 3
5 7
6
8
4
3
6
6

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Path : time
1 – 2- 5- 7 17 CP

1 -3 – 5 -7 12

1- 3- 6 – 7 14
1- 4- 6-7 17 CP
(2 critical path since it has the largest duration)

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Again do crashing on the CP

CP critical crash limit Cost slope


activity
1- 2-5-7 1-2 2 50 Least cost
Reduce by 1
week
2-5 2 225
5-7 1 100

1-4-6-7 1-4 3 200


4-6 1 125 Least cost
Reduce by 1
week
6-7 1 350

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Update the table again
Normal 18
duration

18 17 16

Added cost 175 175

Direct cost 6500 6675 6850

Indirect cost 3600 3400 3200

Total cost 10100 10075 10050

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Draw the updated network and find the C.P

9
2 5
5 2
5

1 3
5 7
6
8
4
3
6
5

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Again find the C.P
Path : time
1 – 2- 5- 7 16 CP

1 -3 – 5 -7 12

1- 3- 6 – 7 14
1- 4- 6-7 16 CP
(2 critical path since it has the largest duration)

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Again do crashing on the CP

CP critical crash limit Cost slope


activity
1- 2-5-7 1-2 1 50 Least cost
Reduce by 1
week
2-5 2 225
5-7 1 100

1-4-6-7 1-4 3 200 Crash here,


by 1 week
4-6 125 Cannot crash
0 here as crash
limit = zero
6-7 1 350

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Update the table again
Normal 18
duration

18 17 16 15

Added cost 175 175 250

Direct cost 6500 6675 6850 7100

Indirect cost 3600 3400 3200 3000

Total cost 10100 10075 10050 10100

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Draw the updated network and find the C.P

9
2 5
4 2
5

1 3
5 7
6
7
4
3
6
5

Here total cost = 10100 > 10050 , so stop crashing as


we achieve the optimal value.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.

You might also like