0% found this document useful (0 votes)
55 views17 pages

PM Chapter 7 Part Two

Uploaded by

Anas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views17 pages

PM Chapter 7 Part Two

Uploaded by

Anas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

Eleventh Edition

Chapter 7
Project Management

Part two - CPM

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Developing the Schedule (2 of 2)
Figure 7.3 Network Diagram Showing Start and Finish
Times and Activity Slack

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (1 of 5)
Paths are the sequence of activities between a
project’s start and finish.

Path Time (wks)


A-I-K 33
A-F-K 28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (2 of 5)
Figure 7.3 Network Diagram Showing
Start and Finish Times and Activity Slack

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (3 of 5)
Figure 7.3 [continued]

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (4 of 5)
Figure 7.3 [continued]

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (5 of 5)
Figure 7.3 [continued]

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Developing a Schedule
Figure 7.4 MS Project Gantt Chart for the St. John’s Hospital Project Schedule

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Critical path method (CPM)
 How to find the critical path for
the project?
 How to find the critical activities and
non critical activities
 How to calculate the slack of
activities?
 how to find the total project
completion time?

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Estimate the project completion time by finding the
critical path.

• Identify the start and finish times for each activity for
a project schedule.

• Calculate the amount of slack time for each activity

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Equations to be used in CPM

• Earliest start time (ES) - The earliest finish time of the


immediately preceding activity.
• Earliest finish time (EF) - An activity’s earliest start time plus its
estimated duration (t).
EF = ES + t
• Latest finish time (LF) - The latest start times of the activity that
immediately follows.
• Latest start time (LS) - The latest finish time minus its
estimated duration (t)
LS = LF − t
• Activity Slack - The maximum length of time that an activity
can be delayed without delaying the entire project
S = LS − ES or S = LF − EF
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.2 (1 of 3)
Calculate the four times for each activity in order to determine
the critical path and project duration for the diagram.

Earliest Latest On the


Earliest Finish Finish (LF) Latest start Slack Critical
Activity Duration Start (ES) (EF) (LS) (LS-ES) Path?
A 7
B 2 blank blank blank
C 4 blank blank blank
D 4 blank blank blank
E 4 blank blank blank
F 3 blank blank blank
G 5 blank blank blank

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.2 (2 of 3)
Calculate the four times for each activity in order to determine
the critical path and project duration.

Earliest On the
Start Latest Latest Start Slack Critical
Activity Duration (ES) EF = ES +D Finish (LF) (LS)= LF-D (LS − ES) Path?
A 7 0 7 7 0 0−0=0 Yes
B 2 7 9 11 9 9−7=2 No
C 4 7 11 11 7 7−7=0 Yes
D 4 11 15 15 11 11 − 11 = 0 Yes
E 4 15 19 19 15 15 − 15 = 0 Yes
F 3 19 22 24 21 21 − 19 = 2 No
G 5 19 24 24 19 19 − 19 = 0 Yes

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.2 (3 of 3)
The critical path is A–C–D–E–G with a project duration
of 24 days.

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
precedence Duration ES EF LF LS slack Critical
?
A ---- 5
B A 8
C A 6
D B 9
E B, C 6
F C 3
G D, E, F 1

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
precedence Duration ES EF LF LS slack Critical
?
A ---- 5 0 5 5 0 0 Yes
B A 8 5 13 13 5 0 yes
C A 6 5 11 16 10 5 no
D B 9 13 22 22 13 0 yes
E B, C 6 13 19 22 16 3 no
F C 3 11 14 22 19 8 no
G D, E, F 1 22 23 23 22 0 yes

Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Total completion time = 23 days
• Critical path: A, B, D, G