Developing the Schedule (2 of 2)
Figure 7.3 Network Diagram Showing Start and Finish
Times and Activity Slack
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (1 of 5)
Paths are the sequence of activities between a
project’s start and finish.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (2 of 5)
Figure 7.3 Network Diagram Showing
Start and Finish Times and Activity Slack
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (3 of 5)
Figure 7.3 [continued]
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (4 of 5)
Figure 7.3 [continued]
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (5 of 5)
Figure 7.3 [continued]
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Developing a Schedule
Figure 7.4 MS Project Gantt Chart for the St. John’s Hospital Project Schedule
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Critical path method (CPM)
How to find the critical path for
the project?
How to find the critical activities and
non critical activities
How to calculate the slack of
activities?
how to find the total project
completion time?
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Estimate the project completion time by finding the
critical path.
• Identify the start and finish times for each activity for
a project schedule.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Equations to be used in CPM
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.2 (2 of 3)
Calculate the four times for each activity in order to determine
the critical path and project duration.
Earliest On the
Start Latest Latest Start Slack Critical
Activity Duration (ES) EF = ES +D Finish (LF) (LS)= LF-D (LS − ES) Path?
A 7 0 7 7 0 0−0=0 Yes
B 2 7 9 11 9 9−7=2 No
C 4 7 11 11 7 7−7=0 Yes
D 4 11 15 15 11 11 − 11 = 0 Yes
E 4 15 19 19 15 15 − 15 = 0 Yes
F 3 19 22 24 21 21 − 19 = 2 No
G 5 19 24 24 19 19 − 19 = 0 Yes
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.2 (3 of 3)
The critical path is A–C–D–E–G with a project duration
of 24 days.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
precedence Duration ES EF LF LS slack Critical
?
A ---- 5
B A 8
C A 6
D B 9
E B, C 6
F C 3
G D, E, F 1
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
precedence Duration ES EF LF LS slack Critical
?
A ---- 5 0 5 5 0 0 Yes
B A 8 5 13 13 5 0 yes
C A 6 5 11 16 10 5 no
D B 9 13 22 22 13 0 yes
E B, C 6 13 19 22 16 3 no
F C 3 11 14 22 19 8 no
G D, E, F 1 22 23 23 22 0 yes
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Total completion time = 23 days
• Critical path: A, B, D, G